capacity of integration of wind farms within the spanish

15
1 Capacity of integration of Wind Farms within the Spanish power system: Perspectives from the TSO “Wind Barriers" Project Presentation Madrid, 7 October 2010 Juan Fran. Alonso Llorente Contents Overview of the Spanish Power System Integration of Renewable Generation (RES) in Spain: sensitive aspects of RES for the power system In System Planning and Access Defining new technical requirements In System Operation: the generation control Conclusions and Possible trends

Upload: others

Post on 10-Jul-2022

2 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Capacity of integration of Wind Farms within the Spanish

1

Capacity of integration of Wind Farms within the Spanish power system:

Perspectives from the TSO

“Wind Barriers" Project PresentationMadrid, 7 October 2010

Juan Fran. Alonso Llorente

Contents

Overview of the Spanish Power System

Integration of Renewable Generation (RES) in Spain: sensitive aspects of RES for the power system

In System Planning and Access

Defining new technical requirements

In System Operation: the generation controly p g

Conclusions and Possible trends

Page 2: Capacity of integration of Wind Farms within the Spanish

2

RED ELÉCTRICA DE ESPAÑA

Operates the system to guarantee the power supply.

Red Eléctrica de España (REE): Mission and principles.

REE, world pioneer since 1985, as independent and exclusively dedicatedto Transmission and System Operation

Since 2006 also in the extra-peninsular systems

Designs, builds and maintains the transmission network.

Since 2007 as exclusive transmission company

It has proved fundamental for the fast and secure implementation ofelectricity market and integration of RES

Wind Integration . J.F.ALONSO. Madrid. October 7th 2010

FREE-FLOAT

80%

SEPI: Spanish Stated Owned Holding Company

SEPI 20 %

SHARE CAPITAL (Closure 2009):

3

Transmission GridMain magnitudes (SPPS)

Closure 2009

REEvs.

TOT

Lines400 kV [km ct] 17 977 99,8%

220 kV [km ct] 16 777 98,4%

Subst. 220 & 400 kV [nº bays] 3 385 96,8%

Transformers 400/X kV [MVA] 66 259 98,8%

RED ELÉCTRICA DE ESPAÑA

Thinking of the challenges for integration of RES (and wind)

Do we mean system rather than grid?

Is the grid a barrier or an opportunity?Is the grid a barrier or an opportunity?

The challenges are not solely located in the grid, but in the whole

interconnected power system, including wind generation

Alth h thi d d th bj ti d l

Wind Integration . J.F.ALONSO. Madrid. October 7th 2010

Although this depends on the objective model

Page 3: Capacity of integration of Wind Farms within the Spanish

3

RED ELÉCTRICA DE ESPAÑA

There are models …No challenges for the InterconnectedSystem or the GridChallenges concentrate on Generation(and Demand)

Wind Integration . J.F.ALONSO. Madrid. October 7th 2010

RED ELÉCTRICA DE ESPAÑA

Installed capacity september 2010l Bi Cogeneration W T

… and modelsSR RES Generation, and specially Wind, has become a fundamental chapter of the electricity mix

Technology MW %

Hydro-power 16.657 17,6

Nuclear 7.455 7,9

Coal 10.789 11,4

Fuel-Gas 1.849 1,9

Combined cycles 24.792 26,2

Total (ordinary regime) 61.542 65,05

Wind power generation 19.390 20,5

Hydro

17,6%Nuclear

7,9%

Coal

11,4%

Fuel‐Gas2,0%

Combined cycle26,2%

Wind

20,5%

Solar PV

3,6%

Solar CSP0,5%

Mini‐hydro2,1%

Biomass

0,7%

Cogeneration

6,3%Waste Treat.

1,3%

46,6%

Wind Integration . J.F.ALONSO. Madrid. October 7th 2010

Wind power generation 9 390 20,5

Solar PV 3.372 3,6

Solar CSP 481 0,5

Biomass 684 2,1

Special regime hydro 1.965 2,1

Cogeneration 5.946 6,3

Waste treatment 1.204 1,2

Total (special regime) 33.062 34,83

Total 94.604

28,8%

Page 4: Capacity of integration of Wind Farms within the Spanish

4

RED ELÉCTRICA DE ESPAÑA

Demand supply first semester 2010Very significant contribution of RES - 42% of electric energy

production- due to high hydro and wind production in this period.

Technology GWh

Combined Cycle 28 556Combined Cycle 28.556

Hydro 24.742

Nuclear 22.791

Wind 22.089Non-renewableCHP

15.336

Coal 6.815

Mini-hydro 3.960

Solar 3 091

Hydro18,3%

Nuclear20 6%

Wind16,4%

Solar2,3%

Non-renewable

CHP11,4%

Renewable CHP1,4%

Wind Integration . J.F.ALONSO. Madrid. October 7th 2010

Solar 3.091

Renewable CHP 1.896

Fuel-gas 800

TOTAL 135.076

20,6%

Coal5,0%Fuel-Gas

0,6%

Combined Cycle21,1%

Mini-hydro2,9%

RED ELÉCTRICA DE ESPAÑA

Prospects and main challengesThe current high penetration of RES must be significantly increased due to ambitious national objectives (2020: 20% of Efinal40% Eelectric)

19.390 MW* 3.372 MW* 481MW*

For this challenge, REE is working to achieveSecure Integration of RES objectives in Power

System

Technical challenges motivated by particular features of new generation:

38.000 MW** 8.367 MW** 5.079 MW**

Wind Integration . J.F.ALONSO. Madrid. October 7th 2010

… without forgetting other organizational aspects

• Grid development• Technical Requirements• More dispatchable resources•Control by TSO

Technical challenges motivated by particular features of new generation:

Location far from load and gridVulnerability to incidents(voltage dips)Primary energy: Lack of firmness and control

* Power installed Sep 2010** NAP for 2020 submitted to EC in June10

Page 5: Capacity of integration of Wind Farms within the Spanish

5

RED ELÉCTRICA DE ESPAÑA

Managing Access and Planning the Grid

A good programming of new non-transmission facilities (e.g., generators) musttake into account decision and commissioning processes in transmission grid:

Decision on transmission facilities

Access to the gridRegulated continuous

process by which REE

assess the aceptability of

non-transmission facilities

applications

Grid Planning• REE carries out the planning studies and

proposals

• National Goverment, with the collaboration of

Regional Administrations, approve the grid

development plan

• Every 4 years, new horizon (10 y)

• Every year review with same horizon

Wind Integration . J.F.ALONSO. Madrid. October 7th 2010

9

applications• Every year, review with same horizon

Binding (unlike indicative planning for

generation)

The actual development of the grid (authorization, construction and ; from 1to more than 10 years)

RED ELÉCTRICA DE ESPAÑA

RES generation does not avoid distribution grid but requires transmissionexpansion, where the majority of Wind Power (>60%) and Solar Thermal (>80%) isexpected. RES is a relevant motivation in the current Plan:

new lines and reinforcements for avoiding constrains operation

facilities associated to physical connection

Main challenges: Grid Development

N b t ti d b

VCONEJOS

RIBARROJA

LAFORTUNA

ELBROSQUIL

SABON

MA R IN A

AGUAYO

ANLLARES

APARECIDA

BOIMENTE

CARTELLE

COMPO STIL LA

ELPALO

PESOZ

GRADO

L AL OMBA

LAROBLA

L ADA

MASGALAN

MONTEARE

NARCEA

SANZO SALAS

VELILLA

VILECHA

VILLAMECA

ALMAZAN

SENGRACIA

AZPEITIA

ARRUBAL

CASTEJONELEREBRO

LAGOAÇA

CRODRIGO

GRIJOTA

HERNANI

HERRERA

HINOJOSA

ICHASO

LASERNA

MURUARTE

OLMEDOOLMEDO

SAUCELLE

VILLARIN

VIRTUS

VITORIA

ARAGON ASCO

BE GUE S

BESCANO

CCTELNOU

C. BARBA

ESPLUGA

CALDERS

ESCATRON

MEZQUITA

LLOGAIA

S. PALLARS

MEDINACELI

OSERA

MUNIESA

PENAFLOR

PEÑALBA

GARRAF

RIUDARENES

RAMIS

P IE ROL ARUEDA

SALLENTE

GRAMANE T

TERRER

MUDEJAR TERUEL

MAIALS

VANDELLO

ALMARAZ

ANCHUEL O

ROMICA

VVA ESCUDEROS

AYORAAYORA

CASTELLON

CEDILLO

COFRENTES

COLOREJA

CORTESII

FUENTES ALCARRIA

BELINCHON

GALAP AGAR

LASTRAS

L OECHE S

MORELLASALSADELLA

LAMUELA

MINGLANILLA

MORALE J A MORAT A

OLMEDILL

T VE L ASCO

REQUENA

PINOFRANQUEADO

SEGOVIA

TORRENTE

CE REAL

TRILLO

T ORRECI LL A

GAUSA

VIL LAVE RDE

VALDECABALLEROS

LINDOSO

FALAGUEIRA

ARGIA

BAIXAS

AGUAYO

AMEIXEIRAS

ACERIASA

ALBARELL

APARECIDA

ASTILLER

A. ZINC

BELESAR

ABO ÑO

DUMBRIA

EIRIS

CARRIO

CHANTADACHANTADA

CACICEDO

CARTELLE

CAMBADOS

CASTRELO

CILLAMAYOR

CONSO

CORNATEL

CTCOMPOSTIL LA

FRIEIRA

LAGRANDA

GRELA-2

L AL OMBA

LUBIAN

MATAPORQUERA

MASGALAN

MEIRAMA

MONTEARENAS

MDCARRIO

MONTOUTO

MTESL EON

ONDINAS

P.BIBEY

CANDO

PDEMOURO

PEÑADRADA

PEREDA

PRADA

P.E.SIL

PSMIGUEL

PUERTO

QUERENO

REMOLINA

RIBADELAGO

S.AGUSTIN

CAYETANOCAYETANO

S.ESTEBAN

S.MARINA

S.PEDRO

SANABRIA

SANCOMPO

SANTIAGO

SIDEGASA

SI ERO

SNIACE

SOBRADELO

SOTO RI BERA

SOUTELO

SUIDO

TABIEL LA

TELLEDO

TIBO

TRASONA

CICERO

TRIVES

UNINSA

GUARDO

VELLE

VILLABLINO

VIMIANZO

MAZARICOARISTRAIN

ALCARAMA

ALDEADAVILA

ALI

AYALA

ELCERRO

CASTRO

ELGEA

CORDOVILLA

FORJASGAMARRA

ALCOMOLAALCOMOLA

GAROÑA-BARCINA

HERNANI

HERRERA

ICHASO

IRUN

JUNDIZ

LAGUARDIALORA

LASERNA

MAZORRAS

LOGROÑO

MERCBENZ

MEDINA

MIRANDA

MUDARRAI

ORCOYEN

OLITE

ORMAIZTEGUI

MURUARTE

PASAJES

POZASAL

QUEL

P.POZA

RENEDORICOBAYO

SANGUESA

SANTIZ

SAUCELLE

SENGRACIA

SEQUERO

TAFALLA

TORDESILLAS

TUBACEXTUBOS

TUDELA

MONDRAGON

LAOLMA

VALLEJERA

VALPARAISO

VILLALBILLA

VILLAMAYOR

VILLARINO

VITORIA

ZAMORA

ZUMARRAGA

ABRE RA

ADRALL

A.GURREA

ESCALDES

ASCO

ALMUDEVAR

AE NOE ST E

ATALAYA

BADALONA

ALBATARREC

LA SELVA

ANOI ABAYO

BELLICENS

BSONUEVO

BE GUE S

BESCANO

BIESCAS

CABEZO SR

CALAMOCHA

CANY E T

AENAE STEAENAE STE

CARTU JOS

GAVA

CAST E LL E T

CEL SA

CENTELLES

CSBI SBAL

E I XAMP L E

ELOL IVAR

ENTRERRIOS

SESUE

ERISTE

ESCALONA

ESCATRON

ESPARTAL

F OIX

F RANQUE SES

FUENDETODOS

GRADO

GUIXI ERE S

GURREA

JALON

JUIA

JUNEDA

L AROCA

LANZASAGUDAS

L E SCORT

VIENTOS

L.L EONES

LLAVORSI

LOSVISOSMANGRANERS

TORSEGRE

MAGALLON

MANF I GUE RE S

MARAGALL

MARIAMAT A

MEDIANO

MEQUINENZA

MEZQUITA

CE RVE L LO

MONCAYO

MONTBLANC

M ONTETORRERO

AVEZARAG

MONZON

CINCA

ELS AUBALS

MORALETS

NUDOVIAR

ONCALA

T ANGCAT A

P AL AU

PEÑAFLOR

PERAFORT

P IE ROL A

PL AZA

POLA

PUIGPELAT

R.CALDE S

REPSOL

RMART ORE L L

RUBI

RIOGALLEGO

RUBIO

CAN J ARDI

S . ANDRE U

VIL ADE CANS

S.BOIS .BOI

S .CUGAT

S.CELONI

S.JUST

S.F OST

SABADSUR

SABIÑANIGO

SE NT MENAT

SUBI RAT SSUBI RAT S

CERCS

BARO VIVE R

TARDIENTA

TABESCAN

CONSTANTI

TARRAGONATARRAGONA-G

T RINI TAT

TARRAPOWER

T RSNT BOI

EL VENTERRO

TREVAGO

VANDELLOS

URGE L L

VIC

P E NE DES

VIL LANUEVA

Z. FRANCAZAL

VI LANOVA

ACECA

ALBAL

AL GE TE

ALDAYA

ARANJUEZ

ALMARAZ

AÑOVER 2

AÑOVER

ARGANDA

AZUTAN

AL CO BE NDAS

ARR. VEGA

AZCA

BECHI

ALBURQUERQUE

ARAVACA

BOADIL L A

BOLARQUEAGUACATE

BENIFERRI

CERP L AT A

C.F RE GACC.F RE GAC

CACERES

R-C REAL

CE REAL

CANI L LE J AS

COSL ADA

CASATEJADA

CVALMANZ

SIDMED

ELGRAO

E LCOT O

EALMARAZ

EL IANA

ELEMPERADOR

EL P IL AR

ERVAL DEM

L AE STRE

F .S.LUIS

F .MUESTRAS

FORT UNA

F UENCARRAL

F T ECI LL A

G.GALAN

GALAP AGAR

GE T AF E

GUIJOG.

DAGANZO

EL HORNIL LO

HUELVESINGENIO

ALAMEDA

J.CABRERA

LAPALOMA

L UCE RO

MADRIDEJOS

M AJ ADAHONDA

MBE CE RRAMBE CE RRA

ME CO

MEL ANCOL

MIRASIE RRA

MORAT A

ARDOZ

NORTE

OLMEDILLA

OTERO

P RADSANT

P ARACUE L LOS 1

PATRAIX

PE RAL ES

P OL IGONC

PICON

P ROSP E RI

P ARL A OE ST E

T VE L ASCO

P RI NCESAP RI NCESA

P SF ERNANDO

QUARTPOB

PLASENCIA

RE TAMAR

RI VAS

PRAHONAL

SAGUNTO

SEGORBE

SIMANCAS

TORREJON

TORRENTE

TORRIJOS

T 3CANT OS

VALDECANVALDECANVALDECAN

VAL DEMORO

VAL DRIVA

VALL E CAS

VALLDUXO

VENT AS

VILLARES

TRILLO

BEMPOSTA

POCINHO

ARGIA

PRAGNERES

TORRVEGA

TPALENCIA

VICAL VAR

SANTURCEZIERBENA

AL ONSOTEGUI

BASAURI

GATICA

GUEÑES

NERVACERO

ORTUEL LA

SANTURCE

SIDENOR

ACEBI ZK

BABCOCK

ABANTOEL ABRA

ZAM UDIO

AMOREBIETA

ABADIANO

ALCUESCAR

CARRIO

BENICARLO

OROPESA

COSTA VERDE

VALLDIGNA

P.TABERNES

BENICULL

CATADAU

VENDRE LL

SABON

MORA

OLMEDILLA

PUENTELA

HIJAR

SOLORZANO

BENADRES

PENAGOS

PENAGOS

LAPOBLA

L APL ANA

LOURIZAN

PAZOSBORBEN

JM.ORIOLJM.ORIOL

STAPONSA

ATIOS

TOMEZA

ALUMINIO

ESQUEDAS RAMIS

MUDARRA

OTERO

ESPLUGA

ARENALES TRUJILLO

T VE LASCO 2

P ARACUE L LOS 2

CAN RIGAL T

GRAMANE T

CDIMAGE N

CASACAMPO

CORNIDO

P.G.RODRIGUEZP.G.RODRIGUEZ

VILLAGARCIA

LARACHA

MESON VENTO

VENTORRILLO

N. VIGO

BALAIDOS

S.CL AUD IO

PIELAGOS

ABERIN

LAS LLANAS

EZCABARTE

CRODRIGO

LAGUNA

CORCOS

VILLIMAR

CARDIEL

ALCIRA

ABANTO

BUE NAVIST A

TRI GALE S

V.ARCIP RE ST E

L AS MATAS

AL CALA II

CAMARMA

ME DI ODIA

RET IRO

L IST A

ARKALE

P ARL A

CAMPOMAYORSTA. TERESA VALDEPEÑAS

CARRASES

PUZOL

PQ. CABECERANOUMOLES

VIVEROS

LA TORRE

VINAROZ

FACUL TAT

LE SSEP S

CODONY E R

CE RDA

VAL DONCEL L ES

CORNE L LA

COL LBL ANC

SERRALLO

BURRIANA

MONCOFAR

MORVEDREMORVEDRE

P.SUERT

PUJALT

ARMUÑA DE TAJUÑA

EBORA

VALMOJADO

LAS ARROYADAS

TRENEDO

VILLATOROHARO

LARDERO

MATAPORQUERA

VALLE DEL NALON

S.MARCOS

VIL ADE CANS

VIL L AVE RDEVIL L AVE RDEVI L LAVE R E STE

BRIVIESCA

VILLARREAL SUR

CAN J ARDI 2

TJ ARA2TJARA1

SOLORZANO

MOT ORS

MIRANDA

TSIDMED

ZARATAN

SORIA

VILL ALL ANA

PALENCIA

P RADOLONGO

SAGRE RA

I LL E SCAS

N.S .COL OMA

S.A . BARCA

SARRI Á

TAMON

SILVOTA

LUGO

LABARCES

PTO. LAPICE

VILLAMANIN

N. DUMBRIA

ESCUCHA

S. PALLARS

HOSP I TAL ET

SANT S

CALAMOCHA

SAMA

PQ . C ENTRA L

VERNEDA

S.COLOMA

LOSCERROS

CONGOSTO

MERCAMADRIDVDCARROS

FUENLABRADA

CARPETANIA

PINTOAYUDEN

LEGANES

PINTOMORALEJA

VILLAVICIOSA PQINGENI

COLIMPICA

CAMPONACVALDEBEBAS

LAS MERCEDES

HORTALEZA

SANCHINARROAENA

PARACUELLOS

CDEPORTI

BRUNETE

SSREYESSSREYES2

VICALVAROPALAFOXMAZARRED

ARGANZUELA

LOS PRADILLOS

S.ROQUE

TALCIRA

PIÑOR

BERROCALES

LOECHES2

ANCHUELO

VILLALCASAYAGO

TURIS

SALSADELLA

ESTEPAR

BECILLA

VAL L EGON

S.FELIU

DESVERNDESVERN

N.BARRIS

RAMBLETA

PONFERRADA

BEJAR

CAÑAVERAL

TURIS

ALFORJA

TAMON

FUENTE HITO

CANTALEJO

PLATEA

DELTEBRE

LA PUEBLANUEVA

TALAVERAARAÑUELO

SESENA

L AJARA

OLVAN

S.COSTERA

CARIÑENA

MONZON II

TABIEL LA II

PIÑUEL

SAGRAJASSAGRAJAS

TAMBRE II

MONTEDERRAMOS

TORRECILLA

TAMBRE NUEVA

MONZON II

TABIEL LA II

MORELL

ELS AUBALS

SECUITASECUITA

facilities associated to physical connection

OH Circuit [km] 12.270UG Cables [km] 386Uprating lines [km] 8.308SS [nº bays *] 3.476Transformers [MVA] 52.450Reactors [Mvar] 2.800Capacitors [Mvar] 1.100

New substations and bays: Some 100 buses in 220 kV

and 50 in 400 kV

Wind Integration . J.F.ALONSO. Madrid. October 7th 2010

CASARES

ROMICA

ALANGE

ASOMADA

NESCOMBRERAS

PEÑARRUBIA

MANZANARES

TOTANA

PALMARPALMAR

PINILLA

ROCAMORA

ARCOSFRT

BRAZATORTAS

ARCHIDONA

SIBALBOA

GBRAL TAR

GUADAME

CARTAMA

BIENVENIDA

BROVALES

BAZA

HUENEJA

CARTUJA

JORDANA

ARENAL

LITORAL

SAN SERVAN

CABRA

PINARREY

CARMONA

TARIFA

PTOCRUZ

ALQUEVA

ALARCOS

BENEJAMA

R-C.REAL

CAMPOAMOR

CANTALAR

ARGAMASILLA

NOVELDA

BAJO SEGURA

ELCHE2

ESCOMBRERAS

FAUSITA

LAPALOMA

LA NAVA

HOYAMORENA

MTEBELLO

PALMAR

PALMERAL

PETREL

PICON

ROJALES

S.VICENT

SMSALINAS S.

S.P.PINATAR

SANTAPOLA

ACERINOX

ARROYOVALLE

AL CORES

AL GECIRA

ALHAURIN

ALMODOVAR

ALVARADO

ANDUJAR

ATARFE

BALBOA

BRAZATORTAS

CARTAMA

CADIZ

CARTUJA

CASARES

CASILLAS

SALTERAS

COSTASOL

COSTALUZ

ARENAL

DRODRIGO

ELCOGAS

ENCE

DOSHMNAS

GABIAS

FACINAS

CAPARACENA

FARGUE

SAN SERVAN

GUADAME

BENAHAVIS

GUILLENA

JORDANA

MONTEBAJO

MERIDA

VENTILLA

OLIVARESOLIVARES

ONUBA

PARRALEJO

ORGIVA

GAZULES

PINARREY

PALOS

PURMARIAPURMARIA

POLIGONO

PTOREAL

P.LLANO

ROCIO

SANTIPON

S.ELVIRA

CARMONA

SID ERAND

TAJOENCANTADA

PTOCRUZ

TORARENILLAS

UBEDA

VENTAINES

VNUEVREY

S.ROQUES.ROQUE

MANZANARES

N.CASARES

TALQUEVA

PALMAR

TCASARES

SAX

VAGUADAS

AZAHARA

QUINTOS

VILANOVA

CAMPANARIO

GANDIAP.TABERNES

VERGEL

TORREVIEJA

LANCHA

PUEBLA DE GUZMAN

JIJONA

N C.COLON

SANLUCAR

MONTEALEGRE

GIBALBIN

ALCOLEA

MAZUELOS

CORNISA

MONTIJO

RODANDAL

L.MONTES

EUROPACENTRO

TORREMOLINOS

ENSANCHE

URSO

PUENTE GENIL

GUADAIRA

PADUL

BENAHADUX

CORBONES

COSARIO

ULEA

BALSICASMURCIA

MAR MENOR

SUPERNORTEIL IPA

PAL ACIOS

VIRGENRO

ESPARTINASSTABARBARA

RANILL AS

EMPALME

CABO HUERTASALTET

RABASA

ALICANTE

TORREMENTORREMEN

MAIMONA

BERJA

VILLAJOYOSA

SMSALINAS N.

MONDAATANASIO

MANILVA

SALADAS

ANTEQUERA

RODANDAL

CENTENARN.CENTENAR

ARNEVA

LA RIBINA

NERJA

ANTEQUERA 2

JANDULA

LITORALTABERNASTABERNAS

UNIVERSIDAD

CASTALLAPETREL ESTE

JIJONA

MONTESA

GANDIA SUR

GUADAIRA

CRUZCAMPO

ATAL AYA

STAJUSTA

ENTRENUCL EOS

LOSRAMOS

CARRILPITAMO

SALADAS

ILLORA

M ARI SM AS

PAL OMARES

AL JARAFE

CASAQUEMADA

LA NAVA II

ALMADEN

SAGRAJAS

N.SALADAS

BARRIOS

Particular significance: Spain-France interconnection

Page 6: Capacity of integration of Wind Farms within the Spanish

6

RED ELÉCTRICA DE ESPAÑA

The development of Spain-France Interconnection with a2 1000 MW DC d d li

Development of the Spain-France Interconnection: A priority

Spain –and Portugal- form a peninsula, also electrically, with weak electricalinterconnections with the European Union.

new 2 x 1000 MW DC underground line-Prioritary EU Project with “European Coordinator”

-1st step for objective of 4.000 MW of commercialcapacity

-Necessary for building the IEM-Fundamental for RES integration in Spain (& Portugal)

Wind Integration . J.F.ALONSO. Madrid. October 7th 2010 11

RED ELÉCTRICA DE ESPAÑA

The transmission grid development in Europe

In the Ten Tear Network Development Plan (TYNDP) elaborated by ENTSO-E,

RES integration is a main motivation, representing > 25% of investment

Wind Integration . J.F.ALONSO. Madrid. October 7th 2010

Presented by ENTSO-E at Florence forum and published on www.entsoe.eu

Page 7: Capacity of integration of Wind Farms within the Spanish

7

RED ELÉCTRICA DE ESPAÑA

Access and Connection : Overview

Procedures for Access and connection are managed by REE, as SO and T

Main Features Main Perspective Object - Scope

Access System Operation System behaviour

6824

12574

12574

19398

19398

EOL_RdDr

EOL_RdTp 

EOL_RdTr

EOL_TOTp 

EOL_TOTr 22767

8245

14523

18510

27043

Connection Transmission Engineering and Physical Feasibility

Connection Contract (CC)

Wind Integration . J.F.ALONSO. Madrid. October 7th 2010

81

81

400

400

481

481

6824

0 5.000 10.000 15.000 20.000 25.000 30.000

TS_RdDp 

TS_RdDr 

TS_RdTp 

TS_RdTr

TS_TOTp

TS_TOTr 

EOL_RdDp 

MW

PES

CTA pte PES (RdT)

AutCon pte PES

AutAcc pte PES

Preasig pte PES RDL 6/2009

Acumulado PES  ÷ Aut. Acceso

Acumulado PES  ÷ Aut. Preasig.

2521

1819

702

8533

5423

4354

1069

13

RED ELÉCTRICA DE ESPAÑA

In any case a new perspective is introduced

From ¿What capacity of integration ?

SRG Integration Studies

PO12.1bRD

To ¿Which conditions and requisites

would be needed to maximize secure integration of SRG (RES) and achieve the foreseen objectives?

PO12.2bRD

Capacity

Bulk System orCoverage Studies(Single Bus SystemAdequacy Studies)

Estimation of OperationConditions

Wind Integration . J.F.ALONSO. Madrid. October 7th 2010

14

Grid Studies

CapacityStudyArea: Nodes AC

Estimation of ConstrainsStudy Area : Multi AC

Adequacy Studies)

Page 8: Capacity of integration of Wind Farms within the Spanish

8

RED ELÉCTRICA DE ESPAÑA

Demand Coverage Studies: Perspectives for H2014 - 2016

SRG: Installation according to amounts byRDL6/2009 y RD1578/2008

Load curve is basically maintained

El t i d d “d l d” 3 4

Demand Generation2014 ÷ 2016

“Single Bus” System Model oriented to assess sufficiency ofgeneration (and other) resources to guarantee Security of Supply

RDL6/2009 y RD1578/2008

ORG : Programs from agents

Electric demand “delayed” 3-4 years from last official plan (within H2016) Wind Power 26,3 ÷ 29 GW

[MW]

R R H d d ORG d t S it

SRG according to available estimated resource

Rest ORG

SPILLAGE

Wind Integration . J.F.ALONSO. Madrid. October 7th 2010

15

For ORG: Hourly power requirement very exigent for Thermal ORG (stop/start, ramps) For SRG: Spillage of primary resource is foreseen (wind estimations are shown)

very dependent of several factors

may be significant (0,7% ÷ 7 % of potential production)

-Demand (magnitude and manageability)

-Hydraulicity

-Interconnection Capacityf

[h]RoR Hydro and ORG due to Security

RED ELÉCTRICA DE ESPAÑA

Capacity Studies

Assessment of generation limits to preserve adequacy and security of power

system, according to planning and operation criteria, applied to an horizon within the

current medium term grid development plan

Adequacy: Assessment of generation limits by nodes and zones, reflecting

structural grid capacity

Steady State Behaviour (load flow contingency analysis)

Short-circuit power (5% Scc, for non dispatchable fluctuant generation)

Security: Validation of previously concluded limits by nodes and zones

Wind Integration . J.F.ALONSO. Madrid. October 7th 2010

16

Dynamic behaviour (stability after short-circuit)

Design criteria: buses with sufficient meshing, minimum magnitud for

generation, …..

Page 9: Capacity of integration of Wind Farms within the Spanish

9

RED ELÉCTRICA DE ESPAÑA

TOPOLOGICAL SCOPE NATURE OF LIMITATION Transmission node (and associated Load flow capacity

Planning and access studies for special generationThe planning and access studies are carried out with different analysisperspectives and different time horizons, resulting in connection capacitieswhich enable location optimization:

(distribution)

p y Short-circuit power (Scc) Stability

CapNode CapReg : Nodal capacities are not mutually compatible and resulting grid development needs are not coherent Electric zones (and associated distribution)

sharing constraint Load flow capacity Short-circuit power (Scc) Stability

Regional and Zonal Capacities are the “reference” for Regional Administrations (competent for AA of SRG) and for access managementThi i lid t t th i l l l d id i t t

Wind Integration . J.F.ALONSO. Madrid. October 7th 2010 17

This scenario validates up to the regional level and avoids persistentconstraints within this scope Power System Feasibility Balance P+jQ

StabilityHowever, lack of national coordination does not prevent potential constraintswhen regional plans are developed up to their limits

RED ELÉCTRICA DE ESPAÑA

Cost Allocation of New Facilities

Investment CostOperation and

Maintenance Cost

Transmission grid development implications

Maintenance Cost

TransmissionFacilities

Directly associatedto connection

Agent System

StructuralReinforcement

System

(Agent guarantees 20% of Cost)System

Connection Facilities Agent

Wind Integration . J.F.ALONSO. Madrid. October 7th 2010

New bay

New substation

as in/out of

existing line

New

bay

Existing

Substation

TransGrid

Connection Facilities (no TransGrid)

Page 10: Capacity of integration of Wind Farms within the Spanish

10

RED ELÉCTRICA DE ESPAÑA

Technological vulnerability (voltage dips which lead tosudden disconnections).

Voltage(pu)

1

start of disturbance

0,80,95 pu

Situations where generators

must remain connected

Main Technical Requirements

0,2

0,5 1 Time (sec)0 15

Clearance of the faultFault length

0,6

2 ph isolated fault

The “grid code” (PO 12.3) establishes the

required level for Low Voltage Through CapabilityReal Time Risk Assesment

Wind Integration . J.F.ALONSO. Madrid. October 7th 2010 19

q g g p y

Need to extend LVRTC to all significant generation

New requirements: specially dynamic control of voltage

Other challenges: protection equipment and philosophy

RED ELÉCTRICA DE ESPAÑA

The effects of collaboration on wind generationadaptation to technical requirements

Collaboration has been vital for implementation of technical requirements(specially Low Voltage Ride Through Capability)• Grid code improvement (PO12.3: chapter concerning LVRTC)• Elaboration of certification procedures for existing plants• Surveillance of compliance

4000

6000

8000

10000

12000

14000

16000

40

60

80

100

r o

f P

ow

er L

oss

es

• Surveillance of complianceThe fulfilment of LVRTC requirements has had a very positive evolution with an immediate consequence on registered generation trips

4.0006.0008.000

10.00012.00014.00016.00018.000

ACCUMULATED CERTIFIED POWER

Wind Integration . J.F.ALONSO. Madrid. October 7th 201020

0

2000

4000

0

20

2005 2006 2007 2008 2009

Nu

mb

er

Number of Wind Power Losses Bigger than 100 MW Wind Power NO Fulfilling PO 12.3

02.0004.000

2007

-09

2007

-11

2008

-01

2008

-03

2008

-05

2008

-07

2008

-09

2008

-11

2009

-01

2009

-03

2009

-05

2009

-07

2009

-09

2009

-11

Total adaptation except <1,000 MW within the next year

and no reductions for this reason within 2010

Page 11: Capacity of integration of Wind Farms within the Spanish

11

RED ELÉCTRICA DE ESPAÑA

Control Needs and Actions upon Special Generation

Special Generation has to be dispatched with priority over OrdinaryGeneration, what implies the actions

1. Whenever technically possible, the SO must solve the technicalt i t b i i i t ti t O di G ticonstraints by issuing instructions to Ordinary Generation:

Power Output Reduction

Disconnection of Plants

2.However, it may be necessary to issue Control Actions on SpecialGeneration, by :

a) Production Constraints (reduce or disconnect):

Taking into account additionalreserves if needed

Wind Integration . J.F.ALONSO. Madrid. October 7th 2010 21

Local zonal congestions (transmission or distribution)

System Stability (instruction depending on technical compliance of plants)

G-D balance in power and regulating reserve (specially off-peak and transitions)

b) Q/V Management: Set-point from SO substitutes reference for cos(established RD661)

RED ELÉCTRICA DE ESPAÑA

CECRE: Created by REE in 2006, is a control centre devoted to Special Regime Generation and especially to Wind Power:

Integrated in REE’s control structure

Communication with generation Control Centres (SRGCCs) for supervision and control instructions.

REE’s Solution: CECRE

According to RD661/2007 all special regime plants >10 MW must be connected to a SRGCC.

CECRE issues generation instructions through the SCADA system to the Control Centres.

CECOEL / CECORE

CECRE

Link

Direct Link CECRE‐SRG where Setpoint Instruction 

is transmitted automatically to be converted by plant

Wind Integration . J.F.ALONSO. Madrid. October 7th 2010 22

SRGCC: Special Regime Generation Control Centre

CCCONV: Control Centre for conventional generation

Link and telecommand

SRGCCnSRGCC1CCCONV …Link and 

telecommand 

Iccp L

Link and telecommand

744 WPP via 16 GCCs347 nonWPP via 21 GCCs

(Sep 2010)

in effective action, was a scenario non used

25 SRCCGs

Page 12: Capacity of integration of Wind Farms within the Spanish

12

RED ELÉCTRICA DE ESPAÑA

INTEGRATION IN CECRE OF OTHER GENERATION TECHNOLOGIES In 2009 new information and functionalities have been incorporated

Wind Integration . J.F.ALONSO. Madrid. October 7th 2010

23

RED ELÉCTRICA DE ESPAÑA

Production Mismatch over Programmed Production

Production schedules for new RES generation areimproving but are still far from conventional plants interms of firm productionTotal Mismatches are mainly concentrating in the new 2ary

Resources in Aug10

y gRES technologies and require resources (2aryRes+3ary Res + Mismatch Mech)

January 10 May 10 August 10

TECNOLOGY

Total Mismatch (%)

COST [€/MWh]

Total Mismatch (%)

COST [€/MWh]

Total Mismatch (%)

COST [€/MWh]

Wind 10 5 2 39 11 7 1 25 10 6 1 04

2ary Reg

21,7%

3ary Reg

26,2%

Mismatch

Man.52,1%

Wind Integration . J.F.ALONSO. Madrid. October 7th 2010

24

Wind 10,5 2,39 11,7 1,25 10,6 1,04

Solar PV 22,9 2,27 11,6 0,83 10,2 0,37

Solar Thermal 65,2 4,67 48,1 1,4 22,6 0,78

Hydro 2,9 0,62 4,3 0,31 3,5 0,34

Thermal RES 6,2 1,04 10 0,54 3,4 0,23Thermal non RES 1,9 0,34 2,2 0,1 3,5 0,10

Page 13: Capacity of integration of Wind Farms within the Spanish

13

RED ELÉCTRICA DE ESPAÑA

Wind Power: Aggregated hourly deviation (%)

D i ti hi hl t bili dDeviation highly stabilised:

Weighted Average Deviation: 13 - 14 %

Simple Average Deviation : 16 - 17 %

Wind Integration . J.F.ALONSO. Madrid. October 7th 2010 25

RED ELÉCTRICA DE ESPAÑA

Wind Power: Aggregated deviation (by program and hour)

Wind Integration . J.F.ALONSO. Madrid. October 7th 2010 26

No evidence that

distance to closure time

implies more accuracy

Page 14: Capacity of integration of Wind Farms within the Spanish

14

RED ELÉCTRICA DE ESPAÑA

Production Mismatch. Some comparisons (i)Wind Power Mismatch and Cogeneration Mismatch

Wind Integration . J.F.ALONSO. Madrid. October 7th 2010

27

RED ELÉCTRICA DE ESPAÑA

The many advantages of renewable energy lead to maximize installation.

In this context REE works in the solution of the challenges (technical,regulatory, organisational) in order to preserve the security and quality ofsupply in the power system.

Some conclusions and possible trends

supply in the power system.

Grid Access, Planning and Development: Significant expansion is needed

Better Controllability for System Operation, including forecast improvement

Identification of new technical requirements and regulatory proposals

However, probably the greatest challenges lay on preserving dispatchabilitywhen balancing G D, which calls for resources and sufficient control by TSO

New generation satisfying response requirements and enlarging energy storage

Wind Integration . J.F.ALONSO. Madrid. October 7th 2010

New generation satisfying response requirements and enlarging energy storagepossibilities

More active participation of the demand side, including the incorporation to the

electric sector energy consumption currently in other sectors: Electric Vehicles

For this aim, fruitful coordination of involved stakeholders and Adminstrationsis necessary

Page 15: Capacity of integration of Wind Farms within the Spanish

15

RED ELÉCTRICA DE ESPAÑA

Thanks for your attention!

Juan Francisco Alonso Llorente

www.ree.es

Wind Integration . J.F.ALONSO. Madrid. October 7th 2010

www.ree.es