capital budget 2

Upload: amar-g-patil

Post on 04-Apr-2018

215 views

Category:

Documents


0 download

TRANSCRIPT

  • 7/29/2019 Capital Budget 2

    1/37

    Capital Budgeting Process 9-

    ? , 1997

    Capital Budgeting Process 9-

    ? , 1997

    Capital Budgeting Process 9-Capital Budgeting Process 9-

    ? , 1997

    Capital Budgeting Process 9-

    ? , 1997

    Capital Budgeting Process 9-

    ? , 1997

    Chapter 9

    CAPITAL

    BUDGETING

  • 7/29/2019 Capital Budget 2

    2/37

    PROCESS

  • 7/29/2019 Capital Budget 2

    3/37

    Capital Budgeting Process 9-

    ? , 1997

    1 . I N T R O D U C T I O N

    # Working with the left-hand-side of a balance sheet

    # CAPITAL BUDGETING /INVESTING in Long-term Assets !Definitions

    " Capital: Fixed assets used in production

    " Budget: Plan of in- and outflows during some period

    " Capital Budget: A list of planned investment (i.e.,expenditures on fixed assets)outlays for different projects.

    " Capital Budgeting: Process of selecting viableinvestment projects.

    " Financial investment vs. economic investment

    ! In this course, investments are needed in order to:

    " Expand in existing markets.

    " Enter new markets.

    " Replace existing capital assets.

  • 7/29/2019 Capital Budget 2

    4/37

    Capital Budgeting Process 9-

    ? , 1997

    ! Where do these projects come from?

    " Suggested by managers of plants & divisions "

    Upper management

    ! Upper management approves these projects

    ! Investment and financing decisions are independent.

    ! Some common errors:" Expansion without incorporating cost of financing" Cost cutting without looking at revenue side" Ignoring alternative uses of capital

    # TOOLS CAN BE USED IN:

    ! M&As

    ! Divestitures & spin-offs

    ! Correct-sizing

    ! Other

  • 7/29/2019 Capital Budget 2

    5/37

    Capital Budgeting Process 9-

    ? , 1997

    # CAPITAL BUDGETING OUTLINE

    ! Develop tools & criteria of selecting projects (Ch. 8): Given Q

    Relevant CFsQ The required return of the project (i.e., the risk of use of

    project CFs)

    ! Determine which CFs are relevant in project analysis (Ch. 10)

    ! Introduce possibility of forecast error in CF data used inanalysis (Chapter 11)

    ! Assume that k (cost of financing) is known until Ch. 12

  • 7/29/2019 Capital Budget 2

    6/37

    Capital Budgeting Process 9-

    ? , 1997

    Type of Business

    Choose AppropriateFinancing

    Choose AppropriateWorking capital

    FINANCIAL MANAGEMENT

    PROCESS

    Given yourLine of Business

    List Potential

    Projects

    Type of

    ProjectsInternal

    Expansion

    External

    (M&A)

    Divestitures

    & Spin Offs

    Capital Budgeting

    Capital Structure

    Short-term financialManagement

    Dividend Policy

    Choose Viable

    Projects

    OptimalDividend polic

  • 7/29/2019 Capital Budget 2

    7/37

    Capital Budgeting Process 9-

    ? , 1997

    INVESTMENT

    DECISION

    CAPITAL BUDGETING &

    FINANCING

  • 7/29/2019 Capital Budget 2

    8/37

    Capital Budgeting Process 9-

    ? , 1997

    MANAGERIAL TALENT &

    IN VESTMENTS

  • 7/29/2019 Capital Budget 2

    9/37

    Capital Budgeting Process 9-

    ? , 1997

    2 . T O O L S O F I NVE S T M E NT DE S I RAB I L I T Y

    2.1 BASIC INTUITION

    1)Criteria

    How fast you re-coup initial investment?Benefits > CostsCompare PV of cash inflows & PV of cash expenditureCompare return on investment & cost of financing project

    2)A word of Caution

    A manager needs to make a decision today (t=0) givenestimated/forecasted cash flows. Obviously there is noguarantee that the decision would always turn out asanticipated. However, what is important is that the managerhas to make the best decision at t=0 given all the relevantinformation.

    2.2 INDEPENDENT vs. MUTUALLY EXCLUSIVE PROJECTS:# Independent: A project that has nothing to do with

    other projectsunder investigation.

    Example : Replace copy machine andbuild a new plant.

    # Mutually Exclusive: You only need one ofthese alternative

    projects.

    Example : Buy IBM or Apple PC?

  • 7/29/2019 Capital Budget 2

    10/37

    Capital Budgeting Process 9-

    ? , 1997

    2.3 TOOLS

    3.1 Payback Period Method:

    Criterion: For two mutually exclusive projects, choose the one thatpays you back your initial cost the sooner.

    Example: Calculating Payback Period

    Given the following CFs, and k = 10%, we get:

    Investment Initial cost CF1 CF2

    A $10,000 0 $14,400

    B 10,000 $10,000 2,400

    choose project B, since it pays back initial investment in one

    year.

    ? Is this choice optimal?

  • 7/29/2019 Capital Budget 2

    11/37

    Capital Budgeting Process 9-

    ? , 1997

    NPV ' PV of all Relevent CFs & Initial Investment

    CF1 CF2 CFn% % ...%

    (1%k)1 (1%k)2 (1%k)n

    n CFt'j & I0t'1 (1%k)t

    n CFt

    ' CF1 [PVIFk,1 ] % CF2 [PVIFk,2 ] % ... % CFn [PVIFk,n ] & I 0

    'j (1t'0 %k)t

    3.2 Net Present Value (NPV) method:

    L Payback ignores the concept of CFs. Ignores CF after payback andrisk of CFs.

    we need to look at the PV of these CFs net of any initial cost.

    where,CFt

    I0k

    /Net cash flow (inflow - outflow) at time t/ Initial cost or investment outlays/ cost of capital (financing)/ required return reflecting risk of use ofCFs

    Note: CF0/ I0

  • 7/29/2019 Capital Budget 2

    12/37

    Capital Budgeting Process 9-

    ? , 1997

    Thus,

    NPV measures the additional market value thatmanagement expects the project to create (or destroy) ifit is undertaken.

    NPV Criteria:

    Since the objective of the manager is to maximize value, then for

    Independent Projects : Choose All Projects with NPV > 0.

    Mutually Exclusive: Choose projects with the highest

    NPV.

    Note: NPV > 0 is equivalent to PV of cash inflow > PV of cashoutflow.

  • 7/29/2019 Capital Budget 2

    13/37

    Capital Budgeting Process 9-

    ? , 1997

    Example: Calculating NPV

    Given the following CFs, and k = 10%, we get:

    Investment Initial cost CF1 CF2

    A $10,000 0 $14,400

    B 10,000 $10,000 2,400

    Solution:

    NP VA '

    NPVB '

    $14,400 & 10,000 ' $1,901(1%k)2

    10,000 2,400%_______________&10,000 ' $1,074

    (1 %.1)1 (1 %.1)2

    choose A, since it has the highest NPV if mutually exclusive,or both if independent as they are both with NPV >0.

  • 7/29/2019 Capital Budget 2

    14/37

    Capital Budgeting Process 9-

    ? , 1997

    Remarks on payback method:

    With payback method, project B is selected. Thus, if you ignore

    amount, timing, and risk of CFs, then potentially you would end upwith the wrong valuation.

    Both projects would add value to shareholders. However, if youselect project "B", you would not be maximizing shareholder value,as "A" provides more value to shareholders.

    In general, if you accept a project with NPV

  • 7/29/2019 Capital Budget 2

    15/37

    Capital Budgeting Process 9-

    ? , 1997

    Value created per share '

    Example: Calculating additional Shareholder Value

    Using a project's NPV = $1,901 and assuming that there are 1,000 sharesoutstanding, then

    NPV

    # of shares outstanding

    $1,901'________ ' $1.901

    1,000

    If the project is adopted then the price of the stock should increase by$1.90.

  • 7/29/2019 Capital Budget 2

    16/37

    Capital Budgeting Process 9-

    ? , 1997

    3.3 Internal Rate of Return Method (IRR)

    # Motivation:! Internal in that it is a rate of return that depends on the CFs

    of the project.

    ! Return on investment (ROI) is a very intuitively appealingconcept; measured in % terms.

    ROI ' profit

    investment

    ! Easy to determine profit if you have single CF in future. Whatabout if we have multi-period payoffs?

    Periods

    0 1 2 3

    CF from project -100 10 60 80

    Profit would be calculated as:Ending Value - Beginning Value = $80 - $100

    But this calculation ignores the intermediate CFs, namely $10and $60 in periods 1 and 2 respectively.

  • 7/29/2019 Capital Budget 2

    17/37

    Capital Budgeting Process 9-

    ? , 1997

    CF 1 % CF2 % ...% CFN

    (1 % IRR) (1 % IRR)2 (1 % IRR)NNPV' 0 ' CF0%

    Thus, when examining the return on a project, we need anew tool that would incorporate all the cash flows of a

    project.

    # Definition of IRR : IRR is defined as that particular k, such that theproject breaks-even, i.e., when NPV = 0.Thus,

    Decision Rule:

    IRR Criterion: Choose projects with IRRhigher than cost offinancing.

    L If [the cost of financing "k"] < IRR NPV > 0 Additional value would becreated. Obviously the larger the difference between k & IRR, thehigher the NPV.

    Note: Use IRRcautiously for mutually exclusive projects!Limitations of IRR are discussed on p. 21.

  • 7/29/2019 Capital Budget 2

    18/37

    Capital Budgeting Process 9-

    ? , 1997

    Example: Calculating IRR (single future CF)

    Given:

    Period CF($)

    0 -100

    1 300

    Solution:

    300 &100%________________' 0

    (1 %IRR)

    300 ____ ' 100

    (1 %IRR)

    100(1%IRR) ' 300

    100 % 100IRR ' 300

    300&100 200IRR '____________' ' 2 ' 200%

    100 100

    The ROI is:

    ROI '$300 & $100 ' 200% $100

  • 7/29/2019 Capital Budget 2

    19/37

    Capital Budgeting Process 9-

    ? , 1997

    Example: Calculating IRR (multiple future CFs)

    Given:

    Periods

    0 1 2 3

    CF from project F -100 10 60 80

    IRRF = ?

  • 7/29/2019 Capital Budget 2

    20/37

    Capital Budgeting Process 9-

    ? , 1997

    .. .

    CFN%

    ' 0(1 %IRR)N

    Try a smaller #, say IRR =

    >0

    Solution:

    L To calculate IRR (just like YTM) there is no simple formula to use.Thus, we need to use either trial & error method or a calculator.From definition of IRR,

    ______________CF ____________1 CF 2

    CF0%___________ %__________ %

    (1%IRR) (1%IRR)2

    Guess an IRR, say IRR = 19%, then substituting in above equation

    yields:

    10 60

    &100%________%__________

    80%_________

    < 0

    You have guessed a number too high. 17%, thus

    10 60 80&100%___________%__________ %_________

    (1%.17) (1%.17)2 (1%.17)3

    If you try IRR = 18.1%, you get correct answer.

    IRRF = 18.1 % (using either trial & error or calculator)

  • 7/29/2019 Capital Budget 2

    21/37

    Capital Budgeting Process 9-

    NPV Flow Profile: Relation between NPV, IRR, and "k"

  • 7/29/2019 Capital Budget 2

    22/37

    Capital Budgeting Process 9-

    ? , 1997

    Problems With IRR for Mutually Exclusive Projects:

    Problem 1: Consider two projects such that returnA = 15%, returnB =

    50%, and k = 10%. Which would you choose?

    Now assume that they require the following initial investments:IA = $1,000,000 while IB = $100

    ? Which would you choose?

    If initial investments are not equal, IRR ranking can be

    misleading.

    Problem 2: Possible existence of multiple IRRs. Every time the CFschange sign, you would get an additional IRR. (See NPV,IRR, "k" profile)

    Problem 3: Possible conflict of ranking with NPV.

  • 7/29/2019 Capital Budget 2

    23/37

    Capital Budgeting Process 9-

    ? , 1997

    % use of each Tool

    Primary method NPV

    IRR

    payback

    AROR Secondary method

    NPV

    IRR

    payback

    AROR

    21% 49 19 8

    24% 15 35 19

    3.4 What tools does industry use?

    AROR ' Accounting Rate of Return

    j accounting profit after taxt/N

    t'1

    (initial outlays %salvage value)/2

    where t is time, and N = # of periods

    Source: Kim, Crick, and Kim, "Do executives Practice What Academics Preach?"Management Accounting (November 1986), pp. 49-52.

  • 7/29/2019 Capital Budget 2

    24/37

    Capital Budgeting Process 9-

    ? , 1997

    So Why Does Industry Still use IRR Despite Problems?

    percentage results are more intuitive than a $NPV; 50% return vs.NPV = $500,000

    Since IRR gives you break-even cost of financing:The number itself is of interest to managers; you want simplyto ask at what financing cost does project break-even?

    If a project's break-even is 100%, in a "normal" situation, you

    wouldn't need to go through the trouble of estimating all the CFs, as100% is considerably higher than a normal financing rate.

    ? Why Do Managers Use Payback with All of its

    Problems?

  • 7/29/2019 Capital Budget 2

    25/37

    Capital Budgeting Process 9-

    ? , 1997

    3. SUMMARY

    T Payback Period

    T NPV

    # Independent Projects

    # Mutually exclusive

    # NPV = sum of discounted CFs, where the discount rate isthe cost of financing the project.

    # NPV criterion is equivalent to PV of cash inflow > PV ofcash outflow

    T IRR

    # Criterion

    Two equivalent ways to look at itBreak-even or ROI > cost of financing project

    # Calculation

    ! Trial & error !

    Calculator

  • 7/29/2019 Capital Budget 2

    26/37

    Capital Budgeting Process 9-

    ? , 1997

    4. QUESTIONS

    I. True/Disagree-Explain

    1. According to the NPV criterion, you should choose all projects with NPV > 0.

    2. According to the IRR criterion, you should choose projects with IRR < cost of financing.

    3. Ignoring brokerage fees, purchasing a stock in an efficient market is a zero NPV transaction.

    4. Capital budgeting tools can be used to analyze the merits of "flextime."

    5. A NPV > 0 project might not be undertaken because of its high risk, despite the manager'sconfidence in the accuracy of the CF estimates.

    6. If a company is expanding, then it is necessarily creating additional value to shareholders.

    7. If buying stocks is a NPV = 0 transaction, then no one would profit from them as an investor'sprofits would be zero.

    II. Problems1) Given:

    Project S Project L

    Cost $10,000 25,000

    Annual Benefits $4,000 8,000

    # of years 5 5

    k 14% 14%

    Which of these mutually exclusive projects is better based on NPV and IRR?

  • 7/29/2019 Capital Budget 2

    27/37

    Capital Budgeting Process 9-

    ? , 1997

    ANSWERS TO QUESTIONS I.

    Agree/Disagree-Explain

    1. Disagree. Only if the projects are independent. If they are mutually exclusive, then youchoose the one with the highest NPV.

    2. Disagree. If IRR < cost of financing, then the project would be losing money as it costsmore to finance than to break-even. Such a project will have NPV < 0.

    3. Agree. NPV = -market price + PV of dividends. Present value of a stock would be itsAgree worth--value. If you pay (market price) exactly its worth (PV of dividends), then NPV= 0.

    4. Agree. Analyzing flextime corresponds to analyzing its impact on a firm's CFs. However,in practice it is difficult to obtain good estimates of the incremental CFs. Thus, if "flextime"makes sense, then you would be undertaking a NPV > 0 project.

    5. Disagree. The risk of CFs is reflected in the cost of capital (k). Thus, the fact that youobtain a NPV > 0, and assuming you did the correct calculation, the project should beaccepted.

    6. Disagree. Only if it is re-investing revenue at a rate higher than the required rate of return.A simple example would be a company borrowing to finance projects that are not profitable,NPV

  • 7/29/2019 Capital Budget 2

    28/37

    Capital Budgeting Process 9-

    ? , 1997

    L

    S

    II. Problems

    1)

    Step 1 Are CFs of equal length? Yes

    Step 2 Calculate NPV

    NPVS

    = -10,000 + 4,00 0(PVIFA14%,5)= 3,732 NPVL

    = -25,000 + 8,000(PVIFA14%,5)= 2,465

    Using IRR: IRRS

    = 28.6% and IRRL

    = 18%

    Since cost of capital for each = 14% < IRR. Accept S as it has a higher IRR.Obviously, you should choose both if they were independent.

  • 7/29/2019 Capital Budget 2

    29/37

    Capital Budgeting Process 9-

    ? , 1997

    ELIMINATIONS

    a . APPRO ACH E S T O CAPI T AL B UDG E T I NG

    Top Down Approach Bottom up Approach

    I NT E R-DE PE NDE NCE O F I NVE S T M E NT &

    FI NANCI NG DE CI S I O NS

    I l l u s t ra t i o n 1 :

    Project 1: ATT owes you $100, and makes you an offer of $100 today or

    $107 next year. Which would you choose? Assume that returnon similar risky investments is 6%.

    Project 2: Suppose, in addition to the ATT opportunity, you have a "greatdeal" that requires a $100 investment that is expected to payoff$300 in a year.

    Case 1: Assume: you can borrow at a cost of 10%. Action: Take both

    projects (independent)

  • 7/29/2019 Capital Budget 2

    30/37

    Capital Budgeting Process 9-

    ? , 1997

    NPVA T T ' & 100 % 100.94 ' $.94

    VA T T '$107 ' 100.94 > $100

    (1 % .06)

    choose $107 as

    PVATT 1.06

    NPV ' &100 % 300 ' $1 7 2 7

    Thus, if you borrow, in effect you would be undertaking bothprojects.

    Total NP Vindependent = NP VAT T + NP Vgreat deal

    = 0.94 + 172.7 = 173.64

    Case 2: You cannot borrow, or cost of borrowing is 400% andassume that a project with same risk as "great deal" hasa return of 12%.

    Action: Mutually exclusive projects

  • 7/29/2019 Capital Budget 2

    31/37

    Capital Budgeting Process 9-

    ? , 1997

    " "' &100 % 300

    ' &100 % 60 ' &40 < PVIRS

  • 7/29/2019 Capital Budget 2

    32/37

    Capital Budgeting Process 9-

    ? , 1997

    NPV' & 100 %

    1% .12

    Obviously, in this case you are better off taking $100 from ATT. Thus,

    Choose project with highest NPV choose "great deal".

    Notes:! You discount at 12%, since it is the return you have to forego

    if you invest in a project with same risk as ATT.NPVindependent > NPVmutually exclusive

  • 7/29/2019 Capital Budget 2

    33/37

    Capital Budgeting Process 9-

    ? , 1997

    where ROE '

    (RR) (EPS1) (ROE)

    k

    ROE.

    ( ( ( )

    b. RELATIONSHIP BETWEEN P, DIVIDENDS, g, & NPV

    p0 = PV (CF of existing business) + NPV ( dividend growth due to

    investment of future earnings)PS11

    % NPVGO k

    Let RR' Retention Ratio D1 ' (1&RR) (EPS1)

    return on retained earnings ' (RR) (EPS1) (ROE) EPS1

    book equity per share

    NPV1 ' & I0% PV of increases CFsP

    & (RR) (EPS1) %%

    (RR) (EPS1)&1 %

    NPV1, NPV2 ,.... are growing at a rate (RR) (ROE) ' g

    ______________NPV 1NPVGO '

    k& g

    EPS1

    NPV1

    D1

    p0 '________ %__________ '_________k k& g k& g

    Substitute NPVGO in (*), we get

    Conclusions:NPVGO depends on a.EPS1: current earnings size

  • 7/29/2019 Capital Budget 2

    34/37

    Capital Budgeting Process 9-

    ? , 1997

    0.Relative magnitudes of ROE and k; see equation (**) above.

    a.Growth, (RR)(ROE), does not necessarily imply NPV .

  • 7/29/2019 Capital Budget 2

    35/37

    Capital Budgeting Process 9-

    ? , 1997

    c. WHERE DO NPV> 0 PROJECTS COME FROM?

    # In long-run NPV = 0 excess economic profit = 0

    # Sources of NPV > 0 (Sources of competitive advantage)! Barriers to entry

    product differentiationeconomies of scale

    better distribution channelsluck

    INVESTMENT UNDER UNCERTAINTY

    Classical micro-economic theory

    Observations:

    # Firms use cost of capital "hurdle rate" in NPV > 3 times cost ofcapital firms invest only if price is substantially > LRAC(Summers '87)

    # Firms stay in business even after p < AVC

    . # First quarter of '85 $ started By end of '87, $ was at '78 level.But, import volume did not until 2 years later. (Krugman &Baldwin '87)

  • 7/29/2019 Capital Budget 2

    36/37

    Capital Budgeting Process 9-

    ? , 1997

    # U.S. firms abandon project earlier than Japanese (TV, VCR, semi-conductors)

    Explanation:

    Agree NPV = NPV + flexibility option

    Sources of option value:

    # sunk costs in abandonment decision! Severance pay for workers (-)

    ! scarp value (+) (Myers & Majd '85)" capital used is industry specific (eg. steel mills) Who is going

    to buy machinery when entire industry is suffering?!

    " lemon problem" stop and re-start needs additional costs (McDonald &

    Siegel '85)

    # Uncertainty: product price, operating costs, interest ratesvalue in option to wait (Pindyck '91, Ross & Ingersoll '92)

    ! parameters:

    " if uncertainly is high value of waiting" if k is low future outcomes valued more value of

    . option to wait and resolve future uncertainty

    " What happens if there are other firms in industry?"balance" between waiting and implementing(Fudenburg & Tirole '83, Stiglitz '89)

    " if k does not Investment as cost of waiting" Why did U.S. abandon color TVs, VCRs and semi-

    conductors?The value of waiting to invest is governed by downside risk. But Japanese

    government supports

  • 7/29/2019 Capital Budget 2

    37/37

    Capital Budgeting Process 9-

    firms during downside through cartelization toavoid destructive competition. (Bernake '83)

    ! Sequential investing , as in drug industry

    # Remarks

    ! If 400% (in above illustration) is the cost of borrowing, maybethat is the Agree cost of financing.

    If a project sounds "too good to be Agree," it probably is "toogood to be Agree."

    Role of market in information processing vs. personalborrowing market.