capital expenditure summary project update

18
Capital Expenditure Summary Project Update Joel Melanson DIVISION MANAGER, ENGINEERING & CONSTRUCTION WATER SERVICES Water Committee, April 15, 2021 44307090 5.1 Water Committee

Upload: others

Post on 17-Oct-2021

6 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Capital Expenditure Summary Project Update

Capital Expenditure Summary Project Update

Joel MelansonDIVISION MANAGER, ENGINEERING & CONSTRUCTIONWATER SERVICESWater Committee, April 15, 202144307090

5.1

Water Committee

Page 2: Capital Expenditure Summary Project Update

SECOND NARROWS WATER SUPPLY TUNNEL

2

North shaft looking south along the tunnel Back end of the tunnel boring machine

Water Committee

Page 3: Capital Expenditure Summary Project Update

NEWTON PUMP STATION NO. 2

Architectural renderings Inside the pump station

Water Committee

Page 4: Capital Expenditure Summary Project Update

KENNEDY NEWTON MAIN & ANNACIS MAIN NO. 5 SOUTH

4

Lowering pipe into trenchTrench ready for pipe installation

Water Committee

Page 5: Capital Expenditure Summary Project Update

Phase 1CENTRAL PARK MAIN NO. 2

5

Installation of the 1.2 meter diameter pipe section

Water Committee

Page 6: Capital Expenditure Summary Project Update

SOUTH DELTA MAIN

6

South Delta Main No. 1 tie-ins

Water Committee

Page 7: Capital Expenditure Summary Project Update

SUNNYSIDE RESERVOIR

7

Corner of interior receiving water proofing membrane

Wet tapping into existing supply

Water Committee

Page 8: Capital Expenditure Summary Project Update

8

Questions

Capilano Reservoir

Water Committee

Page 9: Capital Expenditure Summary Project Update

2020 GVWD Water Quality Annual Report

Larry ChowProgram Manager, Interagency Projects and Quality Control

Water Committee April 15, 202144089915

Coquitlam Reservoir

5.2

Water Committee

Page 10: Capital Expenditure Summary Project Update

PURPOSE

2

• Required under the BC Drinking Water Protection Regulation and Metro Vancouver’s Drinking Water Management Plan

• Documents the effectiveness of the multiple barriers used to protect water quality

• Provides water quality information to local governments and the public

Water Committee

Page 11: Capital Expenditure Summary Project Update

SOURCE WATER QUALITY

3

• Turbidityo Capilano and Seymour Sources:

Delivered water <0.3 NTUo Coquitlam Source:

Greater than 1 NTU for 7 days, but never exceeded 5 NTU

• Chemical Compounds and Microbiological Parameterso Below GCDWQ

0

0.2

0.4

0.6

0.8

1

1.2

1.4

1.6

Turb

idit

y (N

TU)

Coquitlam

0

5

10

15

20

25

Capilano Seymour SCFP Finished

0

5

10

15

20

25

Turb

idit

y (N

TU)

Capilano Seymour SCFP Finished

Water Committee

Page 12: Capital Expenditure Summary Project Update

SEYMOUR CAPILANO FILTRATION PLANT

4

Seymour Capilano Filtration Plant

• Met turbidity removal objectives under the GCDWQ

• Effective removal of organics and colour resulting in:o Less chlorine required for

secondary disinfectiono Lower levels of disinfection by-

products

Water Committee

Page 13: Capital Expenditure Summary Project Update

FILTRATION REQUIREMENTS

5

Month Occurrence of IFE Turbidity Greater Than

1.0 NTU (None Allowed)

Percent of Time IFE Turbidity Less than 0.3

NTU Minimum 95% Allowed

January 0 99.99%

February 0 99.72%

March 0 99.94%

April 0 100%

May 0 100%

June 0 100%

July 0 100%

August 0 100%

September 0 99.99%

October 0 100%

November 0 100%

December 0 100%

• GCDWQ prescribes specific filtration requirements

• The turbidity leaving each individual filter (IFE) must:o Be less than 0.3 NTU

at least 95% of the time

o Never be greater than 1 NTU

Water Committee

Page 14: Capital Expenditure Summary Project Update

COQUITLAM WATER TREATMENT PLANT

6

UV Units

• Ultraviolet light provides primary treatment for Giardia and Cryptosporidium

• Meets the requirements of the GVWD Operating Permit and GCDWQ for an unfiltered source

Coquitlam Water Treatment Plant

Water Committee

Page 15: Capital Expenditure Summary Project Update

SYSTEM WATER QUALITY

7

Drinking Water Sample Analysis

GVWD Transmission System Water Mains and Reservoirs:• Approximately 7,500 samples collected and

99.6% were negative for coliform bacteria• No E. coli detectedLocal Government Distribution Systems:• Approximately 20,000 samples collected and

99.8% were negative for coliform bacteria • No E. coli detected

Water Committee

Page 16: Capital Expenditure Summary Project Update

DISINFECTION BY-PRODUCTS

8

• Disinfection by-products (DBPs) are produced by disinfectants reacting with naturally-occurring organic compounds found in the source water.

• There are two main groups:o Trihalomethanes (THMs)o Haloacetic Acids (HAAs)

2020 Average MV TTHM = 22 µg/L2020 Average Municipal TTHM = 31 µg/L

2020 Average MV THAA = 24 µg/L2020 Average Municipal THAA = 30 µg/L

THMs

HAAs

Water Committee

Page 17: Capital Expenditure Summary Project Update

CONCLUSIONS

9

• Both Water Treatment Plants servicing the GVWD region met requirements of:o Provincial GVWD Operating Permit o Federal Guidelines for Canadian Drinking

Water Quality • System wide, delivered water quality

was excellent in 2020

Water Committee

Page 18: Capital Expenditure Summary Project Update

Questions?

Seymour Falls Dam

Water Committee