Westmead Millennium Institute
Transition Planning
July 14
Overview
• Transition Planning is the planned and sequenced preparation of a facility and its staff for commencement of operations.
• The Westmead Millennium Institute relocated 11 Research Centres plus executive and administration staff in July 2014, a total of 350 staff with capacity to grow to 600 staff.
Project Overview
• 17,500m2 comprising 8 levels with Levels 2 and 8 being plant rooms
• 6 x PC2 Laboratories, a PC3 Laboratory, Biological Services unit and a Human Applications Laboratory
• $110m Budget (combination of Federal and State Government and private sector investment funds )
Transition Implementation Program
The journey
July 1996Westmead Millennium
Institute founded
Federation of four centres
2000First building
opened
2001Westmead
Research Hub founded (WMI
founding member)
2003-2005Seven new
centres joined
2001 -09 Rapid growth (quadrupled)
2010Westmead Millennium
Institute becomes
independent company
2014All Institute in one new
building
Objectives of the New Institute’s Transition Process
• Develop a One Institute Organisation• Implement new business and operating processes • Integrate research centres to support collaborative
research opportunities• Provide training to operate in the new facility and
minimise business disruption• Shared communication
Our role
• Change management• Transition planning and implementation
– Building completion information critical to the commissioning activities
– Building and Engineering Service readiness– Human Resources activities– Knowledge management including ongoing governance and
operational policies– ICT integration– FF&E access dates– Back of house operations– Communication activities to internal and external stakeholders– Move Planning including the decant and relocation of staff and
equipment
Challenges
• “If they cant agree amongst themselves it could be done by ballot. We will have to appoint proxies for absent souls.”
• If they still can’t agree we could ask someone sensible from another floor to adjudicate a meeting with post docs listed above (to make sure the dynamic inside the group is fair) if even this approach to the group is not acceptable to everyone we have one of two methods:– Royal decree– decide how to approach this by a majority vote of seniors
• What do you think? My team is fiercely independent (just how I like it) and would like to decide for themselves
• I am just hoping they won’t vote me out of the building
Learnt Lessons
• Adaptive project management delivery• Understanding the organisations culture• Communication of Capital Insight’s project role • Listening to client feedback• A dedicated project leader for the transition phase• Key personnel to be the right balance
Reward
• “Thank you as without your positive attitude I would not have been convinced to move. You helped me a lot to clear the way to come over.”
Our Opportunities
• Organisational change• Identification of resourcing shortfalls• Timely introduction of complimentary advisory
services• Define integration from building completion and
handover to transition planning• Relocation planning