capstone 2 project collateral
TRANSCRIPT
Folio Instrument’s Social Media
Project
Project Document Binder
December 1, 2014
To Project Sponsor: Gordon Howes
To Project Supervisor: Dave Barrett
Prepared by Group 5
Sheila Kearns, Andre Yam, Lauren Ippolito, Sankalpa Dash, Ricky Thakkar
2
Table of Contents
1. Introduction:
1.1 Executive Summary … 4
2. Initiation Phase Documents:
2.1 Project Charter … 5-6
2.2 Roles and Responsibilities … 7-8
2.3 Stakeholder Analysis … 9-10
3. Planning Phase Documents:
3.1 Work Breakdown Structure … 11
3.2 Project Scope Statement … 12-14
3.3 Project Schedule … 15
3.4 Cost Baseline … 16
3.5 Risk Register … 17-19
4. Execution Phase Documents:
4.1 Progress Reports … 20-26
5. Closing Phase Documents:
5.1 Final Project Reports … 27-28.
5.2 Lessons-Learned Report … 29-30
5.3 Project Presentation … 31
5.4 Meeting Minutes … 32-48
5.5 Work Samples … 49
3
List of Tables and Figures
Figure 2-1. Key Project Roles Contact Information Table. … 6
Figure 2-2. Stakeholder Analysis Table. … 9-10
Figure 3-1. Cost Baseline Chart. … 16
Figure 3-2. Risk Registry Table. … 17-19
Figure 4-1. Activities During the week of October 27 Table. … 21
Figure 4-2. Activities for the Week of November 3 Table. … 21
Figure 4-3. Project Issues for the Week of November 3 Table. … 21
Figure 4-4. Changes to Project Plans for November 3 Table. … 21
Figure 4-5. Activities During the Week of November 3 Table. … 22
Figure 4.6. Activities for the Week of November 10 Table. … 22
Figure 4-7. Changes to Project Plans for November 10 Table. … 22
Figure 4-8. Activities During the Week of November 10 Table. … 23
Figure 4-9. Activities for the Week of November 17 Table. … 23
Figure 4-10. Project Issues for the Week of November 17 Table. … 24
Figure 4-11. Activities During the Week of November 17 Table. … 25
Figure 4-12. Activities for the Week of November 24 Table. … 25
Figure 4-13. Project Issues for the Week of November 24 Table. … 26
Figure 4-14. Changes to Project Plans for November 24 Table. … 26
Figure 5-1. Project Objective and Success Criteria Table. … 27
Figure 5-2. Completion Table. … 27
Figure 5-3. Project Spending Table. … 27
Figure 5-4. What Went Well Table. … 29
Figure 5-5. What Did Not Go Well Table. … 29
Figure 5-6. Lessons Learned Table. … 30
4
1. Introduction
1.1 Executive Summary
The following project was initiated in October of 2014 at the behest of Gordon Howes, president
of Folio Instrument. After discussing possible projects, it was decided that the project would be
to expand Folio Instrument’s online presence through three deliverables: the first was to create 3
to 5 product videos that Folio carried; the second was to strengthen the social media presence of
Folio by improving their existing LinkedIn account, while creating a Facebook and YouTube
company page; the final deliverable is the creation of an online-focused communication guide.
The project team’s working budget was zero. The project’s end date was on December 1, 2014.
The goal of this report is to compile and archive the work documents that the project
team created, in order to create a timeline that can be used to reflect upon the project’s lifecycle.
All work included has been updated after initial feedback. While there are samples of certain
planning documents included, there will not be every document used. The reason for this is
because the samples used represents the best examples created, thus reducing the frequency of
redundant and similar documents.
This post-mortem project report will include the following documents in chronological
order: project charter, roles and responsibilities, stakeholder analysis, work breakdown structure,
project scope statement, project schedule, cost baseline, risk register, progress reports, final
project report, lessons-learned, and the project presentations. Samples and meeting minutes will
be included at the end of the document. Samples will not be numbered.
Please direct any questions or inquires to the project team.
Andre Yam, Technical Writer December 1, 2014
5
2. Initiation Phase Documents
2.1 Project Charter
Project Folio Information:
Project Start Date: September 15, 2014
Project Finish Date: December 1, 2014
Budget: $0 (All labour and spending done in-house by sponsor)
Project Objectives:
The overall objective is to increase Folio Instrument’s online presence and product offering. This
will be established through three initiatives:
● Creating Folio Instrument Inc.’s social media presence through developing a
Facebook and a LinkedIn company page;
● Establishing Folio Instrument Inc.’s YouTube channel and developing up to 5
product information videos;
● Compiling social media communication guidelines and providing training to Folio
Instrument Inc.’s employee(s).
Folio Instruments has a business need to increase their social media presence because they do not
have a dedicated employee to initiate the online business presence. Folio also wanted 3 to 5
product videos created for their website because there is not anything like this currently on their
company site. Folio believes this will help customers who visit the site looking for instructions
on usage of their products.
Success Criteria:
Sponsor acceptance of deliverables as outlined above must, at a minimum, meet the baseline
scope, time, and cost expectations. Successful delivery and presentation of the videos and social
media training guidelines.
6
Key Project Roles:
The following is a contact list for some of the key project members involved.
Role Name Organization
Project Advisor Dave Barrett Conestoga College
Project Sponsor Gordon Howes Folio Instruments Inc.
Sales Engineer Neil Howard Folio Instruments Inc.
Project Coordinator Lauren Ippolito Conestoga College
Filming Director Ricky Thakkar Conestoga College
Media Specialist Sankalpa Dash Conestoga College
Sponsor Relations Lead Sheila Kearns Conestoga College
Technical Writer Andre Yam Conestoga College
Figure 2-1. Key Project Roles Contact Information Table.
7
2.2 Roles and Responsibilities
Dave Barrett – Project Advisor at Conestoga College:
Provides coaching and mentoring to the project team during class and through eConestoga email.
He is available for questions and guidance throughout the semester as the project goes through
the lifecycle. He will also provide assessment and constructive feedback on weekly deliverables
that the project team submits.
Gordon Howes – Project Sponsor and President of Folio Instruments:
Providing direction to the project and necessary approvals. He is a crucial supporter of the
project and is influential with negative and positive supporters. It is important to keep him
informed of all project progress and issues.
Neil Howard – Project Subject Matter Expert at Folio Instruments:
Provides technical and product knowledge to the project team regarding the Folio products that
will be taped. He also will provide support on equipment rental, product scripting, filming, and
editing. He is supportive of the project and will address technical product issues. He is able to
assist during the day of taping and equipment setup.
Line Bergeron – Marketing Coordinator at Folio Instruments:
Chief contact for Folio’s advertisement and marketing department. She is willing to assist in any
way that would ensure the success of this project.
Lauren Ippolito – Project Coordinator at Conestoga College:
She is the chief minute taker and progress report writer. Serves as a project coordinator and
provides task and technical leadership. She is responsible for executing tasks and producing
deliverables as outlined in the Project Plan at whatever level of effort or participation has been
defined.
As part of the team, she is responsible for ensuring that the project team completes their work.
She has helped develop the Project Plan with the team and manages the team’s performance of
project tasks. Secures acceptance and approval of deliverables from the Project Sponsor and
Stakeholders is also within her responsibilities. Lauren ensures that communication is kept open,
including status reporting, risk management, escalations of issues that the team cannot solve, and
making sure the project is delivered on schedule and within scope.
8
Ricky Thakkar – Filming Director at Conestoga College:
He serves as lead expert on videotaping and editing, while also providing his expertise for
technical leadership. Ricky is also responsible for updating the project’s schedule in Microsoft
Project and for submission of documents to the course instructor.
As part of the team, he is responsible for ensuring that the project team completes their work. He
has helped develop the Project Plan with the team and manages the team’s performance of
project tasks. Secures acceptance and approval of deliverables from the Project Sponsor and
Stakeholders is also within his responsibilities. Ricky ensures that communication is kept open,
including status reporting, risk management, escalations of issues that the team cannot solve, and
making sure the project is delivered on schedule and within scope.
Sankalpa Dash – Media Specialist at Conestoga College:
She serves as lead expert on media relations, with tasks including gathering and preparing social
media documents and compiling the training binder. Sankalpa also established the various social
media sites and resolved issues with the sponsor.
As part of the team, she is responsible for ensuring that the project team completes their work.
She has helped develop the Project Plan with the team and manages the team’s performance of
project tasks. Secures acceptance and approval of deliverables from the Project Sponsor and
Stakeholders is also within her responsibilities. Sankalpa ensures that communication is kept
open, including status reporting, risk management, escalations of issues that the team cannot
solve, and making sure the project is delivered on schedule and within scope.
Sheila Kearns – Sponsor Relations Lead at Conestoga College:
Responsible for arranging all sponsor meetings, preparing and sending agendas prior to meetings
and providing the resulting minutes to the sponsor and team.
As part of the team, she is responsible for ensuring that the project team completes their work.
She has helped develop the Project Plan with the team and manages the team’s performance of
project tasks. Secures acceptance and approval of deliverables from the Project Sponsor and
Stakeholders is also within her responsibilities. Shelia ensures that communication is kept open,
including status reporting, risk management, escalations of issues that the team cannot solve, and
making sure the project is delivered on schedule and within scope.
Andre Yam – Technical Writer at Conestoga College:
His duties include inspection of documents, compiling for the project binder, and assistance with
storyboarding and video editing. Other duties are ensuring that work on deliverables is done and
that communication on all other facets of the project remains open between all stakeholders.
9
2.3 Stakeholder Analysis
The stakeholder analysis was initially done on September 9, 2014. Since then, there has been no
variance found at the prospect of new stakeholders emerging.
Name Project Role Power / Interest General Approach Management Strategy
Dave Barrett Project Advisor High / High Manage Closely The team will manage
closely through weekly
meetings, document
submissions, and asking
for his feedback. This
will be done through
face-to-face meetings,
eConestoga, and class
lectures. If an issue has
to be escalated, the team
will contact Dave and
arrange a meeting to
discuss it.
Gordon Howes Project Sponsor High / High Manage Closely The team will manage
closely through meetings,
project status updates,
approving deliverables,
and obtain project
direction. This will be
done through face-to-
face meetings, email
correspondence, and
project documents. Vocal
and visible champion of
the project and
legitimizes the project’s
goals and objectives.
Ultimate decision-maker
for the product video and
social media sites.
Neil Howard Sales Engineer Low / High Keep Informed The team will keep him
informed through
meetings and project
deliverables. This will be
done through face-to-
face meetings, email
correspondence and
project documents. Very
10
interested in the
successful outcome of
the project and product
video content.
Folio
Customers
Consumers Low / Low Monitor The team may monitor
customer’s initial
reaction to accepted
deliverables and modify
accordingly if videos
delivered prior to
schedule milestone. This
may be done through
feedback by Folio.
Figure 2-2. Stakeholder Analysis Table.
11
3. Planning Phase Documents
3.1 Work Breakdown Structure
Project Folio
1.0 Facebook and LinkedIn
1.1 Create social media banner
1.1.1 Set up Facebook
1.1.2 Compile Folio supplier list
1.2 Add to LinkedIn page
2.0 Video Creation
2.1 Rent camera / equipment
2.2 Gather software tools for video editing
2.3 Gather product descriptions
2.3.1 Storyboard videos
2.3.2 Script videos
2.4 Record videos
2.5 Record voiceovers
2.6 Edit videos
2.6.1 Add background music
2.6.2 Format videos
3.0 YouTube
3.1 Create Folio YouTube account
3.2 Format YouTube account
3.3 Upload videos to YouTube and website
4.0 Training
4.1 Create training documents
4.2 Train Folio staff
4.3 Folio presentation
5.0 Project Management
5.1 Planning documents
5.2 Final project binder
5.3 PowerPoint class presentation
12
3.2 Project Scope Statement
Project Name: Project Folio
Project Overview:
The overall objective is to increase Folio Instrument’s online presence and product offerings.
In Scope of Project:
Creating Folio Instrument’s social media presence through developing a Facebook and a
LinkedIn company page;
Establishing Folio Instrument’s YouTube channel and developing 3 to 5 product
information videos;
Compiling social media communication guidelines and providing training to Folio
Instrument’s employee(s).
High Level Description of the End Products:
Product Videos: the length of the videos will be under 2 minutes, which will be adequate
for the purpose of providing product information that describes the features,
specifications, and use. It will also help increase Folio Instrument’s online presence by
sharing links to the company’s Facebook, YouTube, and LinkedIn pages.
Social Media Awareness: this deliverable includes creation of Facebook, YouTube, and
LinkedIn profile for the company. Its purpose is to create and expand the company’s
social media presence and its range of products offered.
Training Marketing Advisor: this includes creation of training documents, which will
help the company’s marketing advisor to maintain and update the social media profiles
and YouTube account once they are delivered.
Below is the Work Packages:
1.0 Facebook and LinkedIn
1.1 Set up Facebook
1.1.1 Folio email information is required
1.1.2 Establish Folio credentials
1.2 Compile Folio supplier list
1.2.1 Upload links to Facebook
2.0 Video Creation
2.1 Rent camera / equipment
2.1.1 Research possible suppliers
2.2 Gather software tools for video editing
2.2.1 Contact Neil for assistance on preferred video editing programs
2.3 Gather product descriptions
13
2.3.1 Storyboard videos
2.3.1.1 Review storyboards with Neil
2.3.2 Script videos
2.3.2.1 Answer five “W” when drafting script
2.3.2.2 Review scripts with Neil for approval
2.4 Record videos
2.4.1 Setup background, lighting, and filming room
2.4.2 Decide filming and setup
2.5 Record voiceovers
2.5.1 Decide who will record script
2.5.2 Decide how voiceover will be recorded
2.6 Edit videos
2.6.1 Add background music
2.6.2 Format videos
2.6.2.1 Layer video, music, and voiceover to make one cohesive video
3.0 YouTube
3.1 Create Folio YouTube account
3.1.1 Choose which Folio email to use
3.2 Format YouTube account
3.2.1 Decide on thumbnail picture, banner, and background
3.3 Upload videos to YouTube and website
3.3.1 Decide who is uploading the videos to the account and website
4.0 Training
4.1 Create training documents
4.1.1 Prepare directions on how to use and maintain Facebook, YouTube, and
LinkedIn accounts
4.2 Train Folio staff
4.2.1 Decide on the method of training (online or otherwise)
4.2.2 Decide on materials needed
4.3 Folio presentation
4.3.1 Prepare meeting agenda, PowerPoint presentation, and training documents
4.3.2 Compile documents and submit a hardcopy to Folio Instruments
5.0 Project Management
5.1 Planning documents
5.1.1 Complete documents as required by course outline
5.2 Final project binder
5.2.1 Compile and edit all planning and execution documents
5.2.2 Print and bind documents
5.3 PowerPoint class presentation
5.3.1 Create PowerPoint version of project overview
5.3.2 Include lessons learned
14
Not In Scope of Project:
No more than 5 videos.
Project team will not maintain the Facebook or LinkedIn pages.
Team will not do offline marketing, like newspaper ads, brochures, etc.
No travelling required for training. It will be provided through virtual conferencing or
training document handover in case the concerned marketing person is unavailable.
15
3.3 Project Schedule
See the adjoining page for project schedule information, as created on Microsoft Project.
16
3.4 Cost Baseline
The following is the cost baseline for Project Folio, which was created on October 27, 2014.
Week Ending
Cost Description
19
-Sep
-14
26
-Sep
-14
3-O
ct-14
10
-Oct-1
4
17
-Oct-1
4
24
-Oct-1
4
31
-Oct-1
4
7-N
ov
-14
14
-Nov
-14
21
-Nov
-14
28
-Nov
-14
5-D
ec-1
4
Total
Cost
NA. Since costs
covered by sponsor ,
Folio Instruments
$0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
$0.00
Total $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Figure 3.1 Cost Baseline Chart.
17
3.5 Risk Register
The following is the risk register, which was created on October 27, 2014.
Risk Identification Probability Impact Level
of
Risk
Risk
Response
Risk
Response
Description
Contingency Plan
Description
Sponsor unhappy with
video scripts.
High High 5 Mitigate Get script
approvals
before
recording
voiceover.
Re-script and re-
edit videos to
sponsor's
requirements.
Camera is not available for
rental on filming days.
High High 5 Mitigate Have back-
up rental
options
available.
Use the camera
that the sponsor
already owns.
Editing software issues. High High 5 Mitigate Make sure
team
members are
trained in
software
editing.
Crash schedule
for this
deliverable.
Sponsor unhappy with
completed videos.
Low High 3 Mitigate Keep sponsor
updated and
seek
approvals on
a timely
basis.
Re-edit videos to
sponsor's
requirements.
Sponsor unhappy with
number of videos
completed.
Low High 3 Accept Unable to
deliver
estimated
number of
videos due to
time
constraints.
Offer an apology
and reasoning for
why the videos
did not get done.
Sponsor unhappy with
video presentation quality.
Low High 3 Mitigate Make sure
team
members are
trained in
software
editing.
Re-edit video to
sponsor’s
requirements.
Camera is damaged while
under rental.
Low High 3 Mitigate Rental
agreement
ensures rental
Folio incurs extra
cost of damaged
equipment. Team
18
company's
responsibility
of camera.
will use a
different camera.
Loss of audio and video
due to data corruption.
Low High 3 Mitigate Have back-
ups of video
and audio
data on
Drive.
Use back-up files.
Low quality videos
submitted.
Low High 3 Mitigate Gain
approvals
from sponsor
as each video
is created.
Crash schedule
and re-edit
videos.
Marketing Advisor is
unavailable to receive
social media training.
High Low 3 Accept Have training
documents e-
mailed to
employee.
E-mail the
documents to
sponsor and
employee.
SME is unavailable for
consultation/assistance
within project timeline.
Low High 3 Mitigate Stay in touch
with SME
and work
around his
schedule.
Arrange for a
meeting with
sponsor.
Folio LinkedIn information
is not transferred to project
team.
Low High 3 Mitigate Ask for the
account
information
in a timely
manner.
Remove
deliverable from
scope.
Unable to complete all 3
videos. (Initially it was 5
videos)
High Low 3 Accept Plan to
complete
videos.
Deliver number
of completed
videos.
Actor is sick on day of
videotaping.
Low Low 1 Mitigate Have a back-
up actor
ready to
perform.
Another team
member will act
in videos or we
can re-schedule
filming day.
Camera rental price is out
of budget compared to
initial estimates.
Low Low 1 Mitigate Gain sponsor
approval
prior to
rental.
Find a different
place to rent or
find a different
camera within
budget.
Social media
banners/profile pictures are
substandard to sponsor's
requirements.
Low Low 1 Mitigate Change
picture
placement as
per sponsor
requirements.
Adjust as required
by sponsor and
update the
schedule.
19
Final presentation with
sponsor is delayed outside
of course timeline.
Low Low 1 Avoid Change date
of
presentation
to
accommodate
sponsor's
availability.
E-mail the final
presentation to
the sponsor.
Training materials are
unclear / insufficient for
Folio use.
Low Low 1 Accept Create simple
and clear
material.
Supply materials
as created.
Voiceover person becomes
sick.
Low Low 1 Mitigate Have a back-
up person to
record script.
Another team
member will
record script.
Figure 3-2. Risk Registry Table.
20
4. Executing Phase Documents
4.1 Progress Reports
The following are the status progress reports that the team produced during the weeks November
3, 2014 to November 24, 2014. The project’s overall status throughout the execution period was
considered green, or good. There were few issues and the project team overcame those. As you
will see, the progress reports will show the extent of work that the project team has put into the
development of product videos, social media pages, and communication guide.
21
Project Name: Project Folio Report Period: Week Ending November 3, 2014
Overall Status: Green
Activities During the Past Week:
Task Comments
Create Cost Baseline. Team created this during class time.
Create Risk Register. Team created this during class time.
Gather product descriptions
1. Obtain descriptions from Folio. 2. Decide on what information to use.
This was necessary to do before scripts are written. Lauren, Sheila
and Ricky worked on this.
Rent Camera/Equipment
1. Research possible suppliers.
2. Obtain pricing.
3. Obtain approval from Folio.
Ricky and Sheila were responsible for these tasks.
Figure 4-1. Activities During the Week of October 27 Table.
Activities Planned for Next Week:
Task Comments
Gather software tools for video editing
1. Determine suitability of available software.
2. Obtain software. 3. Train video editors on software use.
4. Utilize software.
Andre and Ricky are assigned to these tasks.
Add to LinkedIn page
1. Obtain Folio information for LinkedIn.
Sankalpa will obtain this information at the meeting on November
7th.
Figure 4-2. Activities for the Week of November 3 Table.
Project Issues:
Description Proposed Resolution
The Training session with Marketing Advisor Line cannot
be conducted because of her absence from November 10th-
December 1st.
The team decided on providing a soft copy of the training materials
to Line.
Figure 4-3. Project Issues for the Week of November 3 Table.
Changes to the Project Plans:
Description Reason for the Change Authorized By
‘Arrange for video conference’ and ‘complete
training session’ have been deleted from the
schedule.
We are no longer having a training session
for Line, the Folio employee. Team
Figure 4-4. Changes to Project Plans for November 3 Table.
22
Project Name: Project Folio Report Period: Week Ending November 10, 2014
Overall Status: Green
Activities During the Past Week:
Task Comments
Gather software tools for video editing
5. Determine suitability of available software.
6. Obtain software.
7. Train video editors on software use. 8. Utilize software.
Andre and Ricky obtained software and are trained on
how to use it.
Add to LinkedIn page
1. Obtain Folio information for LinkedIn.
Sankalpa received account information from Folio at the
meeting on November 7th.
Figure 4-5. Activities During the Week of November 3 Table
Activities Planned for Next Week:
Task Comments
Storyboard the videos
1. Establish template.
2. Sequence pictures.
3. Add dialogue.
4. Make revisions.
5. Re-sequence pictures.
Andre, Sankalpa and Ricky will work on this.
Rent Camera/Equipment
1. Secure equipment rental.
2. Pick up equipment.
Sheila and Ricky will secure the rental. Folio will handle
the rental contract and payment.
Record Videos
1. Set up equipment.
2. Test equipment.
3. Film videos.
Andre and Ricky will record the videos.
Add to LinkedIn page
1. Upload information to LinkedIn site. Sankalpa is assigned to this task.
Script Videos
1. Create video voiceover documents.
2. Match dialogue to storyboard.
1. Lauren and Sheila are assigned to this task.
2. Andre, Ricky, and Sankalpa are assigned to this
task.
Record Voiceover
1. Review scripts.
2. Record scripts.
Team will be recording voiceovers on filming day.
Figure 4-6. Activities for the Week of November 10 Table.
Changes to the Project Plans:
Description Reason for the Change Authorized By
Originally planned for up to 5 videos to be made;
we are now completing 3 videos.
Folio felt it was unnecessary for 5 videos to
be completed. Sponsor, SME, Team
Videos will be recorded Saturday Nov. 15th. Folio fast-tracked the date to record based
on rental dates and to allow for editing. Sponsor, SME, Team
Figure 4-7. Changes to Project Plans for November 10 Table.
23
Project Name: Project Folio Report Period: Week Ending November 17, 2014
Overall Status: Green
Activities During the Past Week:
Task Comments
Rent Camera/Equipment
3. Secure equipment rental.
4. Pick up equipment.
Folio secured the rental and set it up at their office.
Storyboard the videos
6. Establish template. 7. Sequence pictures.
8. Add dialogue.
9. Make revisions.
10. Re-sequence pictures.
Andre, Ricky, and Sankalpa completed this.
Add to LinkedIn page
1. Upload information to LinkedIn site. Sankalpa edited this account.
Script Videos
1. Create video voiceover documents.
2. Match dialogue to storyboard.
1. Lauren and Sheila created these documents.
2. Andre, Ricky, and Sankalpa completed this.
Record Videos
4. Set up equipment.
5. Test equipment.
6. Film videos.
Folio set up equipment. Team filmed the videos.
Record Voiceover
3. Review scripts.
4. Record scripts.
Sheila and Sankalpa recorded the scripts on filming day.
Figure 4-8. Activities During the Week of November 10 Table.
Activities Planned for Next Week:
Task Comments
1. Create banner.
2. Create profile picture.
3. Create account.
Sankalpa is assigned to this task.
Like supplier’s Facebook pages. Sankalpa is assigned to this task.
Edit videos
1. Transfer videos to editing software.
2. Edit video content.
3. Add background music.
Andre and Ricky are assigned to this task.
Figure 4-9. Activities for the Week of November 17 Table.
24
Project Issues:
Description Proposed Resolution
If we are unable to finish video sequencing and are unable to transfer
footage to SME (Neil) by Friday November 21st our schedule will be
delayed.
Team will have to troubleshoot editing issues on our
own. If we edit on our own the schedule will not be
delayed.
Due to the length of time the video editing will take, and between the
team’s schedule and with our sponsor’s schedule we may not have a
final presentation date for Folio.
E-mail sponsor training documentation and transfer
video files, Facebook, LinkedIn, and YouTube account
information.
Figure 4-10. Project Issues for the Week of November 17 Table.
25
Project Name: Project Folio Report Period: Week Ending November 24, 2014
Overall Status: Green
Activities During the Past Week:
Task Comments
1. Create banner.
2. Create profile picture.
Sankalpa created these.
Edit videos
4. Transfer videos to editing software.
5. Edit video content.
6. Add background music.
Andre and Ricky started the editing process.
Figure 4-11. Activities During the Week of November 17 Table.
Activities Planned for Next Week:
Task Comments
1. Create account. Sankalpa will finish creating and editing this account.
Like supplier’s Facebook pages. Sankalpa is assigned to this task.
Edit videos 1. Format video layouts.
2. Add text to videos.
Andre and Ricky will continue editing.
YouTube
1. Create YouTube account.
2. Create banner.
3. Create thumbnail picture.
4. Format YouTube account.
5. Upload videos to account.
6. Upload videos to Folio website.
Lauren is assigned to these tasks.
Training documents
1. Gather relevant information.
2. Consolidate material.
3. Print hard copy for Folio.
4. Create PDF of material.
Sankalpa is assigned to these tasks.
Train Folio staff
1. Email training material. Sankalpa is assigned to this task.
Folio presentation.
1. Arrange meeting.
2. Prepare presentation. 3. Deliver presentation.
Team will compile all necessary documents and deliver
the presentation to Folio on December 4th.
Closing
1. Create final project report.
2. Create lessons learned report.
3. Create final capstone 2 presentation.
4. Deliver presentation.
Team will create these reports and presentations.
Figure 4-12. Activities for the Week of November 24 Table.
26
Project Issues:
Description Proposed Resolution
Facebook password that Gordon provided did not work so Sankalpa
did not have access to the account.
Sankalpa has arranged for a phone meeting on
Thursday, November 27th to get access to the account.
Figure 4-13. Project Issues for the Week of November 24 Table.
Changes to the Project Plans:
Description Reason for the Change Authorized By
‘Return equipment’ activity has been deleted. Folio took responsibility for all rental needs. Gord, Team
Figure 4-14. Changes to Project Plan for November 24 Table.
27
5. Closing Phase Documents
5.1 Final Project Report
Project Name: Project Folio
Project Performance:
Project Objectives and Success Criteria Summary of Project Results
3 Product Videos 3 videos were created for Folio, including the
Thickness Gage, and the 3 and 60 Gloss Meter.
They are under 2 minutes long and utilized the
footage and audio recorded under the supervision
of Neil. The editing was completed early and are
ready to be shown to the sponsor for approval. All
baseline scope objectives were met and time
baseline was exceeded.
Social Media Pages The Facebook, YouTube, and LinkedIn social
page. They have been started and customized, as
per the sponsor’s request, and have a custom
banner created for it. There were minor delays in
gaining appropriate emails, but that has been
overcome without damage. The Facebook page
has a supplier list added to the “Like” list. They
are ready for the sponsor’s approval. The scope
and time baselines were met with little deviation.
Communication Guide The guide has been compiled, though the scope
has been adjusted: there will not be time to train
Folio Instrument’s marketing manager. Handoff
will instead be given to the sponsor. Though there
has been some changes, the majority of objectives
were met within scope and time baselines.
Figure 5-1. Project Objective and Success Criteria Table.
Completion Time:
Original Completion Date Actual Completion Date
Videos: December 1 2014 December 1 2014
Social Media Pages: December 1 2014 December 1 2014
Communication Guide: December 1 2014 December 1 2014
Figure 5-2. Completion Table.
Budget Spending:
Original Budget Actual Costs Incurred
$0 $0
Figure 5-3. Project Spending Table.
28
Project Assessment:
The project was, overall, executed fairly accurate to the project plan. Deliverables and milestones
were achieved on time or earlier than expected, and the scope quality remained consistent to
expectation. Communication remained high throughout the project, ensuring that negative risks
were avoided and that issues were pre-emptively dealt with. Some issues, such as training with
Folio’s marketing manager or delays in gaining company login credentials, would have to be
accepted, with minor deviations to the scope and schedule. The occurrences of risks were
minimal during the project, with their impact easily accommodated within the schedule.
Quality objectives that the sponsor requested was all met, specifically regarding the delivery time
and number of product videos to be created. The social media aspects were originally a
suggestion, made by the project team, that the sponsor liked and, as a result, his expectations
were aligned with our perspective of how an expanded social media This means that we were
intimately knowledgeable as to the requirements necessary for such a work deliverable. The
results are satisfying and we stand by the work we have managed to do, even if there were slight
delays in obtaining credentials that slowed down our ability to pushing the social media pages to
live servers.
Video filming and editing, a new skill that our team had to learn, was executed smoothly. There
had been some trepidation originally as to how much work would be needed in learning and
utilizing the skills to use the editing software, Lightworks. But due to a strong research during
the planning phase, learning how to use the program progressed quickly and without difficulty.
Folio Instrument’s subject matter expert, Neil Howard’s expertise allowed us to complete the
filming in under a day.
Though there has yet to be an official sponsor acceptance and handoff, the presentation for the
December 4th meeting has been prepared for and we are ready to discuss our progression with
Folio Instruments. We strongly believe that we have met all of the success criteria’s that were
originally agreed upon and planned around and look forewords to presenting the deliverables to
the sponsor, Gordon Howe.
29
5.2 Lessons Learned
Project Name: Folio
What Went Well During the Project?
Description How did this benefit the project?
The video and voice recording took 6 hours due to good
story boarding and scripting.
We were done before time, which really impressed
the sponsor.
Video editing software utilized optimally. Everything was done quickly with consistent look
and feel
In order to complete on time we had to ramp two tasks
(videos and voice-over recordings) in parallel.
This accelerated the execution process.
Sponsor provided quick responses to our emails when we
were arranging meetings with Folio
The flow of information was quick and everyone was
aware of what was going on in a timely manner.
Figure 5-4. What Went Well Table.
What Did Not Go Well During the Project?
Description How did this impact the project?
Certain videos ended up having shadow reflections. The videos might look a little distracting to the
person viewing the video.
Figure 5-5. What Did Not Go Well Table.
30
What are the Lessons you learned?
Description How would this benefit the next project?
Attention to detail is critical for excellent product quality.
Covering the table with a tablecloth could have made
the video look even more professional.
Ricky and Andre benefited from learning new technologies
like professional camera, lighting, audio and video editing
software.
Future preparedness, which will result in future,
projects getting executed faster with fewer risks.
Optimized use of social media like Facebook and Google
Drive
Makes it convenient for the team to collaborate
Requirements gathering are crucial for a successful project
Arrange a meeting to gather requirements before
making any project plans. This will ensure efficiency
and reduce the change of mistakes
Setting an agenda and sending it to the sponsor before the
meeting, ensured time was used efficiently, all questions we
wanted answered were answered and we did not waste the
sponsor’s time.
Setting an agenda will aid future project meetings so
time is not wasted, meetings have purpose, and
everyone can come prepared.
Sankalpa and Ricky learned the fundamentals of
storyboarding.
Having a direction of how the videotaping shots
should be set up and the order of the shots added to
the efficiency of videotaping on the scheduled
Saturday.
The team learned hands on experience on varied
skills, resulting in smooth execution of the project.
Establishing a central repository for team documents
ensured project success because the team knew where to
find vital information without wasting time. Our team used
Google drive for all project documents.
Since the majority of people have cell phones,
laptops or home computers with access to the
internet, future projects will improve greatly because
of the instant access to information and team
communication through the use of this social media
sites. The use of Google drive provided push pull
information whenever required. Eliminated the need
for a lot of emails.
Establishing a Facebook account for the project team
helped the team communicate quickly and efficiently. This
reduced the chances of sending team emails and accidently
forgetting to add all team members on the email thread.
Since the majority of people have cell phones,
laptops or home computers with access to Facebook,
future projects will improve greatly because of the
instant access to information and team
communication through the use of this social media
site.
Figure 5-6. Lessons Learned Table.
31
5.3 Project Presentation
The following are the slides of the PowerPoint presentation that was given on December 1, 2014,
for the end of the MGMT 8410, Capstone 2 course at Conestoga College.
32
5.5 Meeting Minutes
The following are the collected meeting minutes that were taken from September 15, 2014, to
November 24, 2014. Tables and charts will not be logged in the appendix, in order to reduce
redundancies.
33
Project Name: Unknown Date: September 15, 2014
Purpose/Name of Meeting: Project Discovery Process
Team Members Present: Andre, Lauren, Ricky, Sankalpa, and Sheila
Minute Taker: Andre
Agenda Items
List the items to discuss with the
estimated time required
Discussion Summary
Record only a summary of your discussions or decisions.
Do not record all discussion.
Decide on what upload service team will use
to store documents.
Team chose to use Google Drive.
Team to decide on how to choose a project. Team will base decision on feedback, interest, and capability
within the course time frame.
Team to decide who will be the minute taker
for the project.
Team decided that the minute taker role will rotate each
week and will be decided at the beginning of each meeting.
Project Charter Format. Team discussed if there should be a predefined template for
this and other documents or if we should create/find our
own.
Project Binder Format. Team discussed what the final binder should consist of.
Team will use Capstone 1 binder as an example.
Project Document Submissions Schedule. Team to find out when documentation is due and necessary.
Instructor gave insight and schedule during class.
Action Items
Description of Action Item Assigned To: Date required:
Create Google Drive account. Andre September 15
Create Gmail account. Lauren September 16
Have a meeting with a representative from the Library. Team September 16
Have a meeting with Folio Instruments Inc. Team September 17
Create e-mail template for securing sponsor. Sheila September 17
Finalize sponsor and project. Team September 17
34
Project Name: Folio Date: September 22, 2014
Purpose/Name of Meeting: Project Initiation
Team Members Present: Andre, Lauren, Ricky, Sankalpa, and Sheila
Minute Taker: Ricky
Agenda Items
List the items to discuss with the
estimated time required
Discussion Summary
Record only a summary of your discussions or decisions.
Do not record all discussion.
Review of previous action items:
1. Create Google Drive account.
2. Lauren to create Gmail account.
3. Have a meeting with a
representative from the Library.
4. Have a meeting with Folio
Instruments Inc.
5. Create e-mail template for securing
sponsor.
6. Finalize sponsor and project.
1. Andre created this account.
2. Lauren resolved the issue. She did not need to create
a new account.
3. Team met with library sponsor to discuss a potential
project.
4. Team met with Gord Howes, of Folio Instrument
Inc., to discuss potential projects.
5. Sheila finalized the template and uploaded it to
Google Drive.
6. Team decided to do the project with Folio
Instruments Inc.
Create Project Charter. Team will work on this in today’s class.
Team to decide on project name. Team decided to call the project “Folio”.
Set up meeting with sponsor. Team set up a meeting with the sponsor to gather
requirements.
Action Items
Description of Action Item Assigned To: Date required:
Prepare draft-meeting agenda with Gord. Team September 22
E-mail sponsor team’s contact details and set up meeting. Sheila September 22
Come up with video examples to present to Gord. Team September 26
35
Project Name: Folio Date: September 29, 2014
Purpose/Name of Meeting: Project Initiation
Team Members Present: Andre, Lauren, Ricky, Sankalpa, and Sheila
Minute Taker: Ricky
Agenda Items
List the items to discuss with the
estimated time required
Discussion Summary
Record only a summary of your discussions or decisions.
Do not record all discussion.
Review of previous action items:
7. Prepare draft-meeting agenda with
Gord.
8. E-mail sponsor team’s contact
details and set up meeting time.
9. Come up with video examples to
present to Gord.
1. Sheila prepared this and sent it to the team and to
Gord.
2. Sheila e-mailed Gord the relevant information.
3. Team came up with video examples during the week.
Create Roles and Responsibilities. Team will work on this in today’s class.
Create Stakeholder Analysis. Team will work on this in today’s class.
Action Items
Description of Action Item Assigned To: Date required:
Go through the meeting agenda and assign responsibilities
each team member.
Team September 29
Have meeting with Gord.
Team September 30
36
Project Name: Folio Date: Monday, October 6, 2014
Purpose/Name of Meeting: Scope and WBS Planning
Team Members Present: Andre, Lauren, Ricky, Sankalpa, Sheila
Minute Taker: Lauren
Agenda Items
List the items to discuss with the
estimated time required
Discussion Summary
Record only a summary of your discussions or decisions.
Do not record all discussion.
Review of previous action items:
1. Go through the meeting agenda and
assign responsibilities to the team
members.
2. Have meeting with Gord.
1. Agenda was prepared and distributed prior to the meeting.
Agenda topics were assigned to the team.
2. Team meeting held at Folio Inc. All were in attendance
except for Ricky.
Define team roles and responsibilities at a
deeper level.
Divide work and assign work packages.
Create WBS. Team will use the sticky note method.
Create Scope Statement. Team will create scope statement in today’s class.
Action Items
Description of Action Item Assigned To: Date required:
Draft templates for social media sites.
Andre Oct 14
Team will teach and explain Folio employees how to
access and use Facebook and LinkedIn upon completion
of objectives.
Team Nov 18
Team will keep the project sponsor informed on all
aspects of the project through regular status updates.
Team will cc: Gord on all communications to Folio
employees.
Team December 1
Team to update stakeholder register document.
Sankalpa Oct 6
Andre to investigate if PowerPoint can export to video.
Andre Nov 1
Team to look at the camera place in Waterloo and see if Ricky, Sheila Oct 17
37
they rent documentary quality equipment.
Follow up with Neil to investigate a place in Toronto
Queen St near the Opera House for video equipment
rental.
Ricky, Sheila Oct 17
Gord to supply password for us to access the LinkedIn site
for any revisions.
Sankalpa Nov 1
Follow up with Neil to provide us with links to Folio
suppliers so we can incorporate this into their social media
sites.
Andre Oct 17
Collect photos that Neil will send to the project team that
are currently used on the Folio website.
Andre Oct 17
Team to send Line an e-mail introducing ourselves and
explain the training that we will be conducting.
Sankalpa Oct 10
Team to find out about Light Works for video editing.
Andre to find out about other video editing software, such
as Adobe Premiere, Final Cut Pro and GIMP.
Andre Oct 17
Product knowledge and scripting for videos. Lauren, Sheila Nov 1
38
Project Name: Folio Date: Monday, October 20, 2014
Purpose/Name of Meeting: Activity List and Schedule
Team Members Present: Andre, Lauren, Ricky, Sankalpa, Sheila
Minute Taker: Sankalpa
Agenda Items
List the items to discuss with the
estimated time required
Discussion Summary
Record only a summary of your discussions or decisions.
Do not record all discussion.
Review of previous action items:
1. Team to update stakeholder register
document.
2. Andre to investigate if PowerPoint
can export to video.
3. Team to find out about Light Works
for video editing.
4. Team to look at the camera place in
Waterloo and see if they rent
documentary quality equipment.
5. Team to send Line an e-mail
introducing ourselves and explain
the training that we will be
conducting.
1. Sankalpa updated the stakeholder register with necessary
details.
2. Andre found out that PowerPoint could be converted
through Windows Movie Maker and then exported to Light
Works.
3. The team will use a combination of Light Works, GIMP
and Windows Movie Maker for editing videos.
4.Ricky and Sheila will do further investigation before the
team finalizes the vendor.
5. Sankalpa emailed Line Bergeron providing a brief
introduction about the team. Kept Gord in Cc.
Team reviewed the action items and updated
the dates.
Few action items from the previous week need some more
time to be resolved. The dates were updated for the same.
Create Activity List The team will be working on the activity list and list detailed
activities of each work package.
Create Schedule Team will be working on the Project Schedule.
Action Items
Description of Action Item Assigned To: Date required:
Team to look at the camera place in Waterloo and see if
they rent documentary quality equipment.
Ricky, Sheila Oct 24
Follow up with Neil to investigate a place in Toronto Ricky, Sheila Oct 24
39
Queen St near the Opera House for video equipment
rental.
Follow up with Neil to provide us with links to Folio
suppliers so we can incorporate this into their social media
sites.
Andre Oct 24
Collect photos that Neil will send to the project team that
are currently used on the Folio website.
Andre Oct 24
Draft templates for social media sites.
Andre Oct 25
Story Board template Sankalpa, Ricky and
Andre
Oct 31
Product knowledge and scripting for videos. Lauren, Sheila Nov 1
Gord to provide password for us to access the LinkedIn
site for any revisions.
Sankalpa Nov 1
Team will train Folio employees how to access and use
Facebook and LinkedIn upon completion of objectives.
Team Nov 18
Team will keep the project sponsor informed on all
aspects of the project through regular status updates.
Team will cc: Gord on all communications to Folio
employees.
Team December 1
40
Project Name: Folio Date: Monday, October 27, 2014
Purpose/Name of Meeting: Cost Baseline and Risk Register
Team Members Present: Andre, Lauren, Ricky, Sankalpa, Sheila
Minute Taker: Lauren
Agenda Items
List the items to discuss with the
estimated time required
Discussion Summary
Record only a summary of your discussions or decisions.
Do not record all discussion.
Review of previous action items:
1. Team to look at the camera place in
Waterloo and see if they rent
documentary quality equipment.
2. Follow up with Neil to provide us
with links to Folio suppliers so we
can incorporate this into their social
media sites.
3. Collect photos that Neil will send to
the project team that are currently
used on the Folio website.
1. Ricky looked into it and found daily and weekly
rental rates.
2. Andre received links from Neil and uploaded them
to Google Drive.
3. Andre received photos and added them to the
supplier list on Google Drive.
Create Cost Baseline The team will be working on the Cost Baseline.
Create Risk Register Team will be working on the Risk Register.
Action Items
Description of Action Item Assigned To: Date required:
Follow up with Neil to investigate a place in Toronto
Queen St near the Opera House for video equipment
rental.
Ricky, Sheila November 4
Draft templates for social media sites.
Andre October 31
Story Board template. Sankalpa, Ricky,
Andre
November 7
Product knowledge and scripting for videos. Lauren, Sheila November 4
Gord to provide password for us to access the LinkedIn
site for any revisions.
Sankalpa November 4
41
Team will keep the project sponsor informed on all
aspects of the project through regular status updates.
Team will cc: Gord on all communications to Folio
employees.
Team December 1
Team will train Folio employees how to access and use
Facebook and LinkedIn upon completion of objectives.
Team November 18
Have a meeting with Gord and Neil to approve and edit
the scripts and camera options.
Team November 4
Hold a meeting to review and edit each other’s scripts. Team October 29
Investigate audio editor. Andre November 3
42
Project Name: Folio Date: November 3, 2014
Purpose/Name of Meeting: Project Discovery Process
Team Members Present: Andre, Lauren, Ricky, Sankalpa, Sheila
Minuter Taker: Andre
Agenda Items
List the items to discuss with the
estimated time required
Discussion Summary
Record only a summary of your discussions or decisions.
Do not record all discussion.
Review of previous action items:
1. Follow up with Neil to
investigate a place in Toronto
Queen St near the Opera House
for video equipment rental.
2. Draft templates for social media
sites.
3. Story Board template.
4. Product knowledge and scripting
for videos.
5. Investigate audio editor.
1. Due to schedule constraints, will be pushed
back after the Nov 7 meeting.
2. Document done last week by Andre. Examples
document was posted to Google Drive.
3. Was completed by assigned members,
templates are up on Google Drive.
4. Information was utilized for script drafts to be
approved by Folio SME. Further iterative
processes will be utilized as feedback is given.
5. Andre has looked at the market options, settled
on Audacity as audio software.
Create Progress Reports Team will be working on this today after meeting minutes.
Presentation Preparation Andre will be doing the progress status report presentation.
Script Editing Though some work has been done before, team will work on
this as a group.
Update Schedule Team will be working on this today after progress reports.
Action Items
Description of Action Item Assigned To: Date required:
Sponsor Meeting on Nov 7 Team November 7
Storyboard Drafts Team November 10
Equipment Rental Sheila, Ricky November 10
Gord to provide password for us to access the LinkedIn Team November 10
43
site for any revisions.
Have a meeting with Gord and Neil to approve and edit
the scripts and camera options.
Team November 7
Team will train Folio employees how to access and use
Facebook and LinkedIn upon completion of objectives.
Team November 17
Team will keep the project sponsor informed on all
aspects of the project through regular status updates.
Team will cc: Gord on all communications to Folio
employees.
Team December 1
Do Lights Works Tutorial Ricky, Andre November 10
Investigate using Conestoga College resources for voice
over recordings
Sheila November 10
44
Project Name: Folio Date: November 10, 2014
Purpose/Name of Meeting: Update Schedule and Progress Report
Team Members Present: Andre, Lauren, Ricky, Sankalpa, and Sheila
Minute Taker: Sheila
Agenda Items
List the items to discuss with the
estimated time required
Discussion Summary
Record only a summary of your discussions or decisions.
Do not record all discussion.
Review of previous action items:
6. Sponsor Meeting on Nov 7
7. Equipment Rental
8. Gord to provide password for us
to access the LinkedIn site for
any revisions.
9. Have a meeting with Gord and
Neil to approve and edit the
scripts and camera options.
10. Team will train Folio employees
how to access and use Facebook
and LinkedIn upon completion of
objectives.
11. Do Lights Works Tutorial
12. Investigate using Conestoga
College resources for voice over
recordings
6. Meeting with Folio was on Nov. 7 and Andre,
Sankalpa and Ricky were able to attend.
7. During the Folio Nov. 7 meeting it was decided
that Folio will take care of equipment rentals,
reservation of equipment, tripod, lights and
equipment pick up with Henry’s Camera in
Waterloo.
8. Gord provided Sankalpa the passwords for
social media sites.
9. The scripts were reviewed at the Nov 7 with
Folio and Neil made revisions. Neil will send
the revised scripts back to the project team.
10. Folio decided that the project team will send a
soft copy to Gord and no will have one-on-one
training.
11. Andre completed Light Works Tutorial
12. Sheila contacted the Media Dept. at Conestoga
and was referred to contact the Radio Dept. to
assist with voice over recordings.
Create Progress Reports Team will be working on this today after meeting minutes.
Presentation Preparation Ricky will be doing the project status report class
presentation.
Nov. 7 Folio meeting Andre reviewed the outcomes of the Folio meeting
with the team because Sheila and Lauren were
unable to attend.
Gord decided that he wants the girls to do the
45
voice-overs and be in the videos.
It was decided that Folio would take care of all
equipment rentals since it involves money and
credit card information.
Folio reviewed the scripts and made minor
adjustments. Neil will return the scripts to the
project team by Tuesday Nov. 11.
Folio decided they want the video voiceovers
completed at the same time. Sheila will continue to
investigate options with contacts at Conestoga
College.
Folio decided, we need to fast track the schedule
and we will start videotaping the products on
Saturday Nov. 15 at 9am so there is time for
editing.
Folio decreased the scope of the project and now
the project team will only do 3 product videos
instead of 5.
Update Schedule Team will be working on this today after progress reports.
Action Items
Description of Action Item Assigned To: Date required:
Voiceover scripts
Waiting on SME - Neil to return video scripts
Andrea/Sheila November 11
Sequence Story Board Pictures
-Once scripts are returned, this action item can be
started
Andre, Sankalpa,
Ricky
November 14
Video tape 3 videos with Folio team on Saturday Nov.
15
Team November 15
Create Facebook and LinkedIn accounts Sankalpa November 13
Facebook and LinkedIn review social media sites with
Folio
Sankalpa November 15
Team will keep the project sponsor informed on all
aspects of the project through regular status updates.
Team will cc: Gord on all communications to Folio
employees.
Team December 1
Sheila to follow up with Radio Dept. contact about
helping us with voice over recordings
Sheila November 13
46
Project Name: Folio Date: November 17, 2014
Purpose/Name of Meeting: Update Schedule and Progress Report
Team Members Present: Andre, Lauren, Ricky, Sankalpa, and Sheila
Minute Taker: Lauren
Agenda Items
List the items to discuss with the
estimated time required
Discussion Summary
Record only a summary of your discussions or
decisions. Do not record all discussion.
Review of previous action items:
1. Voiceover scripts
2. Sequence Story Board Pictures
3. Video tape 3 videos with Folio
team on Saturday Nov. 15
4. Create LinkedIn Account
5. Facebook and LinkedIn review
social media sites with Folio
6. Sheila to follow up with Radio
Dept. contact about helping us
with voice over recordings
13. SME (Neil) returned edited scripts.
14. Storyboards were completed for filming day,
November 15.
15. Videos and voiceovers were filmed.
16. Sankalpa updated the Folio LinkedIn page.
17. Sankalpa spoke with sponsor (Gord) about the
format of the pages.
18. Radio Dept. did not get back to Sheila in time
and the issue was resolved by filming the
voiceovers on filming day ourselves.
Create Progress Reports Team will be working on this today after meeting minutes.
Presentation Preparation Ricky will be doing the project status report class
presentation.
Update wording on scripts and upload to
Google Drive
Sheila will update and upload the scripts.
Update Schedule Team will be working on this today after progress reports.
Action Items
Description of Action Item Assigned To: Date required:
Create Facebook account. Sankalpa November 20
Scan storyboards and upload to Google Drive. Sheila November 21
47
Team will keep the project sponsor informed on all
aspects of the project through regular status updates.
Team will cc: Gord on all communications to Folio
employees.
Team December 1
48
Project Name: Folio Date: November 24, 2014
Purpose/Name of Meeting: Update Schedule, Progress Report, and Lessons Learned Report
Team Members Present: Andre, Lauren, Ricky, Sankalpa, and Sheila
Minute Taker: Lauren
Agenda Items
List the items to discuss with the
estimated time required
Discussion Summary
Record only a summary of your discussions or
decisions. Do not record all discussion.
Review of previous action items:
1. Create Facebook account.
2. Scan storyboards and upload to
Google Drive.
1. Sankalpa created the account.
2. Sheila uploaded the storyboards to Google Drive.
Create Progress Reports Team will be working on this today after meeting minutes.
Presentation Preparation Sankalpa will be doing the project status report class
presentation.
Create Lessons Learned Report Team will work on the first draft of this document today.
Update Schedule Team will be working on this today after progress reports.
Action Items
Description of Action Item Assigned To: Date required:
Update Facebook account. Sankalpa November 27
Create YouTube account. Lauren November 28
Finish video edits. Andre, Ricky December 1
Compile Folio training binder. Sankalpa December 1
Edit project documents and compile final project binder. Team December 1
Create final presentation PowerPoint. Team December 1
Team will keep the project sponsor informed on all
aspects of the project through regular status updates.
Team will cc: Gord on all communications to Folio
employees.
Team December 1
49
5.5 Work Samples
The following includes various work package-related documents that were utilized during the
project, including scripts, storyboards, sponsor meeting agendas, and rental information. This is
not a complete list, as there may be duplicates used or non-essential, supporting documents.
50
Thickness Gage Script – Revised November 10 by Neil
Welcome to Folio Instruments product video.
C1: The Thickness Gage is a tool that can be used for various substances in a wide variety of settings. Its dual measurement technology measures non-conductive coatings over non-ferrous substrates such as aluminum and non-magnetic coatings over ferrous substrates such as steel. The gage will automatically detect the substrate and use the appropriate measuring method. (Demonstration of where it measures from and how to use it). C2: It has two measurement ranges; a magnetic range of 0-80 mils and an Eddy Current range of 0-40 mils. The gage is capable of displaying measured results in mils or microns by utilizing a sequence of button presses explained in the quick start guide. C3: The gage is an easy to use hand-held tool that only weighs 2.5 ounces and requires two triple A batteries to operate. (Demonstration of ease of use and battery location). C4: To use, press blue button to turn on gage. When display of gage shows (---) you are ready to take your measurement. Place gage onto substrate to measure. The screen will provide a reading of the sample’s thickness. “) (Demonstration of sample and blue button). C5: The gage comes with a quick start guide, certified shim and base steel used for verifying instrument functionality, operating manual, and a mobile case. (Show what it comes with and someone clipping it onto their belt). - C6: You can visit the website for more information and pricing on the Folio Thickness Gage at www.folio.com. Don't forget to LIKE us on Facebook and subscribe to our YouTube channel for more Folio informational videos! (Have Facebook URL and YouTube URL on screen)
51
Henry's Waterloo
573 King St. North
Waterloo, Ontario
N2L 5Z7 Phone: (519) 884-4035
Email: [email protected] [email protected]
Link to Henry’s Equipment Rental landing page for rental documents:
http://www.henrys.com/rentals.aspx#rentals-header-image
Product:
SONY HDR-CX700V 96GB FLASH CAMCORDER
o $60/Day - $90 on weekend and if we go for a week its $180.
Rental Details:
There is a Rental Request form that needs to be filled on and submitted online
o We have to know our Pickup and Return dates for the rental form
Rentals are available at 3pm on the day of the reservation
A Pre-Authorization form needs to be filled out online and printed
o This form is required to pick up the rented equipment
o The credit card number supplied on the Pre-Authorization form will/may be
charged a HOLD fee
o Once goods are returned and inspected the HOLD fee will be removed from the
credit card
o Charges for rentals, late fee, loss and/or damage will be charged to the credit card
number supplied
A driver’s licence is required for equipment pick up
There is a 20% Student Discount Program off rentals any time
Reservation hours are:
o Mon-Wed 8:30 – 6pm
o Thurs.-Fri 8:30 – 8pm
o Sat 10 – 5
o Sun 12 - 5
Other rental considerations:
o 10X16’ Black Muslin Background can be rented for $25/day or $37.50/week
o Tripod?
YouTube video link on the camcorder:
https://www.youtube.com/watch?v=TAho0u38T0k
52
Project Folio Meeting Agenda September 30, 2014
Team Members Sheila, Ricky, Lauren, Andre, Sankalpa
Time Item Owner
5 min What is Project Management and our plan for this project
PMBOK framework
Review previous project binder
Sheila/Andre
5min Project Charter
Distribute and read
Andre
5min Stakeholders
Are all stakeholders identified and involved?
Shelia
10 min Video Requirements
Format
o Words on a screen
o Voice recording
o Script-low music or both
o Length of video o Active or passive
o Instructional-How to Use?
o Informative-this is how it’s used?
Resources
o Video equipment
o People and availability
Andre
10 min YouTube Channel
What is required to set this up?
Sankalpa
10 min Facebook and LinkedIn
Priority
Sankalpa
10 min Facebook Requirements
Discuss information required from Folio to establish
Sankalpa
10 min LinkedIn Requirements
Discuss information required from Folio to establish
Sankalpa
10 min Social Media Training Requirements
What is the level of training material required?
Andre
10 min Questions from sponsor [Name]
10 min Topic [Name]
10 min Topic [Name]
53
1:45 pm Adjournment [Name]
Project Folio Meeting
Date: September 30th, 2014 12:30-1:45pm
Present: Gord, Neil, Sheila, Andre, Lauren, and Sankalpa
Absent: Ricky
Next Meeting: Will be arranged once planning documents are complete
Agenda Topic Discussion Outcomes Action Items and Outcomes
What is Project
Management?
Andre walked through last semester’s
Project Binder and explained Project
Management framework
Sheila walked through the Project Life
Cycle and where we currently are in the
planning and organizing stage
Project Charter
Lauren walked through the Project Charter
and read the objectives
Folio is in agreement with the goals and
objectives
Communication Plan was discussed and the
following was decided
● Conestoga College project
team will teach and explain
Folio employees how to
access and use Facebook
and LinkedIn upon
completion of objectives
● Conestoga College project
team will keep the project
sponsor informed on all
aspects of the project
through regular status
updates
● Conestoga College project
team will cc: Gord on all
communications to Folio
employees
Are all stakeholders
identified?
Add Lynn Bergeron and her contact
information is on the Folio website. Lynn is
in Montreal and is Folio’s Marketing
assistant
● Conestoga College project
team to update stakeholder
register document
Video requirements
Text on screen and voice over. Folio doesn’t
want it too wordy. Neil has some ideas and
techniques for recording and can help us
out.
● Conestoga College project
team to investigate if
PowerPoint can export to
video? Andre to talk to a
54
Neil can sit with the project team and go
through instrument demo’s and information
session’s scripts and video editing.
The requirement is to see the product
running and is a demonstration of the
product in use. This will be an active voice
video. Neil showed us an example of a
supplier YouTube video – Konica Minolta -
as a reference to what Folio is expecting.
Neil didn’t like the zoom in and zoom out
and asked us to consider this when doing
the Folio video.
Planning could include storyboarding with
Neil.
Script - Don’t use excel! Use TV or movie
scripts as an example. Folio wants the video
to show ease of use of the equipment and
more of a chat.
Suggestion – do a separate recording of
narration for the person who will be talking.
Folio has used a professional DJ for voice-
overs.
Length of video: 1 or 2 minutes. No need to
be lengthy
Close with – more information contact Folio
and give website
Equipment – may have to rent a camera
unless Folio wants to use their current
camera. There is a place in Toronto that rent
high quality equipment $70/camera for a
day. Preferably rent a documentary quality
camera (Cannon or Excel 2) and do not rent
Broadcast quality because this would be too
costly. Rental equipment comes with quality
microphones. Neil has all the microphones
in house.
couple of people he knows
regarding video editing
● Conestoga College project
team to look at the camera
place in Waterloo and see
if they rent Documentary
quality equipment.
● Neil to investigate a place
in Toronto Queen St near
the Opera House for video
equipment rental
55
YouTube channel
Folio doesn’t have anything currently set up
so we will start from the bottom up
Use Folio greyish blue colour scheme and
logo to keep things nice and simple. Keep
the look similar to the Folio website to keep
it consistent.
Banner/Logo – Andre presented examples
and explained the advantage of consistency
from a consumer advantage so they know
the product is from Folio. Provide a link to
Folio’s main webpage (hard link) from the
YouTube channel; below the video.
Do not put too much text on screen so
consumers don’t feel lost in a sea of words.
● Conestoga College project
team to provide two or
three variations of
YouTube.
Facebook and
LinkedIn priority?
Facebook is the priority over LinkedIn
There is a LinkedIn page already set up
Andre presented the Dutchie FB site as an
example
After a team discussion it was decided to
turn comments off and the site’s purpose is
more for promotion of the Folio product
line
Folio wants their Facebook to match the
look and feel to the YouTube channel
● Gord to supply password
for us to access the
LinkedIn site for any
revisions.
● Neil to provide us with
links to Folio suppliers so
we can incorporate this
into their social media
sites.
● Folio has a seminar
coming up soon and
pictures from this event
could be used to post on
the Folio site.
● Neil will send the project
team some pictures that are
currently used on the Folio
website
Social Media Training
Requirements
Social media training will be provided by
the Conestoga College project team to Folio
employee –Lynn
We will show Lynn how to maintain the site
and provide a guideline document, Social
Media binder, What to Do and What Not to
● Sankalpa to send Lynn an
email introducing the team
and explain the training.
56
Do type material
Questions
Q: Will we set up a project timeline?
A: Yes. The schedule is part of our planning
process and it will include major milestones
Q: What video editing software is available?
A: Light Works and its free open source.
Q: Do we have access to Adobe Premiere at
school? Final Cut Pro? GIMP graphics
editor open source photo edit program.
A: to be investigated
Q: What is the best day to do the
videotaping?
A: Thursday’s looks like the best day to do
this. Aim for Nov 6.
Q: Can we have a list of products to
showcase?
A: Gord will email it to us.
Neil has some PDF’s on the gloss meters
and an overview of what the product is.
This will help us with storyboarding and
scripting
Andre discussed the possibility of doing a
high level video of Folio, guarantees of
product, what they do, what services they
provide.
● Gord to email us a list of
products to showcase
● Conestoga College project
team to find out about
Light Works for video
editing
● Conestoga College project
team to find out about
other video editing
software. Such as Adobe
Premiere, Final Cut Pro
and GIMP
● Conestoga College project
team to find out if
PowerPoint can be
exported to video. The
high level information
could then be added to the
Folio FB page.