case studies on abc bridge bundling
TRANSCRIPT
Case Studies on ABC Bridge Bundling
Ahmad Abu-Hawash, P.E.Chief Structural Engineer
Bridges and Structures BureauIowa Department of Transportation
ABCs of ABC SymposiumDecember 4, 2020
Outline• Bridge Bundling Definitions and Motivation• FHWA 2019 Bridge Bundling Guidebook• State of Practice: Case Studies
• Michigan DOT’s Bridge Bundling Local Agency Pilot• Washington State DOT’s Project Bundles for Fish Passages• Kentucky Transportation Cabinet’s Bridging Kentucky Program• Iowa DOT’s Bridge Bundling Experience• Other Initiatives
2
OutlineBridge Bundling Definitions and Motivation• FHWA 2019 Bridge Bundling Guidebook• State of Practice: Case Studies
• Michigan DOT’s Bridge Bundling Local Agency Pilot• Washington State DOT’s Project Bundles for Fish Passages• Kentucky Transportation Cabinet’s Bridging Kentucky Program• Iowa DOT’s Bridge Bundling Experience• Other Initiatives
3
Center for Accelerating Innovation
What is Project Bundling?Project bundling is a process by which a single contract award is used to deliver multiple preservation, rehabilitation, or replacement projects
…and so much more….
4
Source: FHWA
What is a “bridge bundling project”?
“
Source: FHWA Bridge Bundling Guidebook
Bridge Bundling ProjectA single contract award for preservation, preventative maintenance, rehabilitation, or replacement of multiple bridges.
Bridge Bundling ProgramA defined set (or bundle) of bridges that are planned for preservation, preventive maintenance, rehabilitation, or replacement in a timely and efficient manner through a series of bridge bundling projects with the support of various funding options and/or partnerships that may include a program completion time frame.
Center for Accelerating Innovation
Why Project Bundling?Bundling projects leverages design and construction expertise and achieves economies of scale.
6
Sources: FHWA; Culverts, Delaware DOT; Accessible Curb Ramp, U.S. Access Board
Center for Accelerating Innovation
Why? Address program goals! Address infrastructure asset needs/backlog
(pavements, bridges, safety hardware) Improve system performance measures
7
Reduce design and construction costs with economies of scaleImprove project and program delivery timeTake advantage of financing opportunities Utilize agency staff more efficientlyDeliver transportation benefit to public faster
Project Bundling helps to:
Bridge Bundling = ABC
Bridge bundling lends itself very well to ABC at two levels:• Macro-level (or Program-level) – Allows owners to accelerate
improvements to their bridge program by bundling bridges, funding, permitting, etc.
• Micro-level (or Project-level) – Facilitates faster bridge construction through scale, efficiency, and sequence of construction
Source: FHWA Bridge Bundling Guidebook
Goals and Objectives1. Achieve performance goals2. Save time3. Save design costs4. Save construction costs5. Take advantage of economies of scale6. Take advantage of available funding7. Take advantage of financing8. Deploy innovation9. Expedite project delivery 10.Utilize alternative contracting methods11.Coordinate construction staging – reduce public disruption
Source: FHWA Bridge Bundling Guidebook
Goals and Objectives, cont’d.12.Start construction of multiple bridges simultaneously13.Maintain bridges in good and fair condition14. Improve bridges in fair condition to good condition15.Reduce bridges in poor condition16. Improve locally owned bridge conditions17. Improve surrounding land value, economic benefits18.Partner with other agencies to achieve efficiencies19.Create jobs in the construction industry20. Increase pool of bridge contractors in a geographic area21.Create opportunities for small and disadvantaged businesses22.Create on-the-job training opportunities
Source: FHWA Bridge Bundling Guidebook
When to Use Bridge Bundling?
It is best when bridge bundling is used for:• Locations with no, or minimal, ROW acquisitions
• Locations with minimal environmental constraints
• Locations where hydraulic analysis is completed in advance
• Locations with sufficient advance geotechnical information
Source: FHWA Bridge Bundling Guidebook
Outline• Bridge Bundling Definitions and MotivationFHWA 2019 Bridge Bundling Guidebook• State of Practice: Case Studies
• Michigan DOT’s Bridge Bundling Local Agency Pilot• Washington State DOT’s Project Bundles for Fish Passages• Kentucky Transportation Cabinet’s Bridging Kentucky Program• Iowa DOT’s Bridge Bundling Experience• Other Initiatives
12
FHWA 2019 Bridge Bundling GuidebookChapter 1: Define successful bridge bundlingChapter 2: Determine goals & objectivesChapter 3: Identify funding or financingChapter 4: Build a coalition & outreachChapter 5: Perform risk assessmentChapter 6: Select bridgesChapter 7: Select delivery methodChapter 8: Determine environmental review & preliminary design considerationsChapter 9: Bundle & let contract(s)Chapter 10: Conduct quality assurance, close-out & celebrate! 13
https://www.fhwa.dot.gov/ipd/alternative_project_delivery/defined/bundled_facilities/
AppendicesA. Bridge Bundling Process Flow ChartB. Bridge Bundling Implementation ChecklistC. Case StudiesD. National Bridge Condition and Bridge Asset ManagementE. Finance MechanismsF. Risk Management Process OverviewG. Bridge Selection MatrixH. Alternative Contracting MethodsI. Alternative Technical ConceptsJ. Sample Contract DocumentsK. Other Bridge-Related InnovationL-1. Research: Capital Program Cost Optimization through Contract Aggregation ProcessL-2. Research: Quantification of Cost, Benefits, and Risks associated with ACMs and
Accelerated Performance SpecificationsSource: FHWA Bridge Bundling Guidebook
Outline• Bridge Bundling Definitions and Motivation• FHWA 2019 Bridge Bundling GuidebookState of Practice: Case StudiesMichigan DOT’s Bridge Bundling Local Agency Pilot• Washington State DOT’s Project Bundles for Fish Passages• Kentucky Transportation Cabinet’s Bridging Kentucky Program• Iowa DOT’s Bridge Bundling Experience• Other Initiatives
15
Collaboration Coordination
Background & Overview
► 2016 - FHWA ‘Fast Act’ Bridge Program Incentive to Bundle Bridges
► Policy discussions underway at MDOT
► 2017 – Internal team began reviewing network-level data
► 2018 – Statewide Feasibility Study launched
► Engaged with PennDOT, MoDOT, and contractors on previous bundles
Source: Matt Chynoweth, P.E., Michigan DOT Chief Bridge Engineer, Director, Bureau of Bridges & Structures, 10-23-2020
MDOT Bridge Bundling Local Agency Pilot
Collaboration Coordination
Background & Overview
Pilot Development:
►Preliminary Screening - December 2019
►Procurement of Consultant Team – Early 2020
►Final screening & scoping - May-July 2020
►20 bridges advanced into final pilot bundle
Preliminary Screening
Preliminary List of Bridges
Final Screening Criteria
Final List of Bridges
MDOT Bridge Bundling Local Agency Pilot
Source: Matt Chynoweth, P.E., Michigan DOT Chief Bridge Engineer, Director, Bureau of Bridges & Structures, 10-23-2020
Collaboration Coordination
Project Goals & Objectives►Reduce the number of Serious and
Critical bridges
►Require zero local agency match
►Develop Michigan experience implementing local agency bridge bundles
►Demonstrate collaborative, partnering model with participating agencies
MDOT Bridge Bundling Local Agency Pilot
Source: Matt Chynoweth, P.E., Michigan DOT Chief Bridge Engineer, Director, Bureau of Bridges & Structures, 10-23-2020
Collaboration Coordination
Project Goals & Objectives► Deliver a successful pilot to
increase buy-in for a future collaborative and coordinated Michigan Bridge Bundling Program
► Develop maintenance and lifecycle bridge asset management plans for participating agencies
► Surpass DBE Goal of 5%
MDOT Bridge Bundling Local Agency Pilot
Source: Matt Chynoweth, P.E., Michigan DOT Chief Bridge Engineer, Director, Bureau of Bridges & Structures, 10-23-2020
Collaboration Coordination
Project Schedule►Proposals Due – February 2021
►Contract Award – Expected March 2021
►Final Design – Spring/Summer 2021
►Construction Completion – November 2023
MDOT Bridge Bundling Local Agency Pilot
Source: Matt Chynoweth, P.E., Michigan DOT Chief Bridge Engineer, Director, Bureau of Bridges & Structures, 10-23-2020
Outline• Bridge Bundling Definitions and Motivation• FHWA 2019 Bridge Bundling GuidebookState of Practice: Case Studies
• Michigan DOT’s Bridge Bundling Local Agency PilotWashington State DOT’s Project Bundles for Fish Passages• Kentucky Transportation Cabinet’s Bridging Kentucky Program• Iowa DOT’s Bridge Bundling Experience• Other Initiatives
21
22
WSDOT Project Bundles for Fish Passages
Source: WSDOT Project Milestones
WSDOT US 101 & SR 109 Grays Harbor, Jefferson and Clallam Counties - Fish Barriers
This fish passage project includes 29 identified streams and culverts that cross under US 101 and State Route 109 in Grays Harbor, Jefferson and Clallam Counties needing correction to meet the project deadline of fall 2026 .
WSDOT considers to bundle multiple fish barriers each year as an efficient delivery method that will accomplish the overall project objectives with the least amount of impacts to travelers.
Washington State Project Bundling Examples
Key Advantages of Bundling for this Project:
1. Schedule: Strategy for project delivery of several elements including similar scope and geographic location, project team assignment, subject matter experts, teams to identify efficiencies, best practices and technical assistance to the project.
2. Decision-Making: The aggressive schedule will require timely communications and decision making to meet schedule commitments.
3. Tribal Communications: An integrated environmental and tribal strategy will be prepared to ensure clear and consistent communications across agencies and tribes.
4. Permitting: Expedite Permitting process that can be lengthy for projects with in-stream work.
5. Minimizing Traffic Disruption During Construction: With limited alternate routes, traffic impacts during construction are a concern to area businesses, property owners, and travelers.
Washington State Project Bundling Examples
Benefits of Kitsap Peninsula Project Bundling:Reduced Cost - Shared features leverages design expertise and achieves economies.
Coordinate NEPA Approvals - coordinating multiple locations with environmental oversight agencies.
Expedited Project Delivery - Using a single contract for several similar projects streamlines design and construction and saves procurement time.
Reduce Burden on Agency Staff - Reduce staff workload with fewer contracts to manage.
Increase Innovation Opportunities – Grouping projects creates opportunities for technical and financial innovations.
Increase Quality – Allows specialty contractors to produce quality work through repetition.
Benefit from Local Agencies - Smaller agencies can team up to form bundles of projects and enjoy the benefits.
Washington State Project Bundling Example
Outline• Bridge Bundling Definitions and Motivation• FHWA 2019 Bridge Bundling GuidebookState of Practice: Case Studies
• Michigan DOT’s Bridge Bundling Local Agency Pilot• Washington State DOT’s Project Bundles for Fish PassagesKentucky Transportation Cabinet’s Bridging Kentucky Program• Iowa DOT’s Bridge Bundling Experience• Other Initiatives
26
27Bridge Bundling Guidebook
Case Study: Bridging Kentucky
• Years: 2019-2024• Cost: $700M• Goals: To rehab, repair, or
replace 1,000 critical bridges in 6 years
• Large Project Team• Directed by KYTC• 21 Consultant Firms• Deep Expertise in key
areas• Working alongside KYTC
Source KYTC
Date:• Bridges in all regions of state• Based on structure conditions• Distributed across the
Commonwealth• Concentrations
in East/West
Statewide Initiative
Source: Royce Meredith, P.E., Bridging Kentucky Program Manager; and Dr. Tony Hunley, P.E., Consultant Team Program Manager – 08/27/2020
Date:
Typical Bridges in Program
• Average 900 crossings/day• 18.5 feet wide/ 60 feet long• 60 percent locally owned • Weight restrictions limiting School buses Emergency vehicles Commercial users
Source: Royce Meredith, P.E., Bridging Kentucky Program Manager; and Dr. Tony Hunley, P.E., Consultant Team Program Manager – 08/27/2020
Programmatic Benefits
• Large number of bridges• Ability to prioritize projects
statewide• Expedited project delivery• Significant savings (owner
cost & contractor cost)• Scalable solution to meet
short and long-term needs• Goal was efficiency
Source: Royce Meredith, P.E., Bridging Kentucky Program Manager; and Dr. Tony Hunley, P.E., Consultant Team Program Manager – 08/27/2020
Project Delivery Alternatives
Key points• Project bundling
was a tool• KYTC used a
variety of delivery methods
Source: Royce Meredith, P.E., Bridging Kentucky Program Manager; and Dr. Tony Hunley, P.E., Consultant Team Program Manager – 08/27/2020
Date:
Bundling Bridge Projects
• Type of work• Geography• No. bridges• Proximity• Contract type• Contract
amount• Scheduling
Considerations
Source: Royce Meredith, P.E., Bridging Kentucky Program Manager; and Dr. Tony Hunley, P.E., Consultant Team Program Manager – 08/27/2020
Date:
Design Standardization
Source: Royce Meredith, P.E., Bridging Kentucky Program Manager; and Dr. Tony Hunley, P.E., Consultant Team Program Manager – 08/27/2020
• Pre-designed common construction elements End bents
Abutments
Superstructures
Steel boxes
• Common design teams
• Expedited design
Date:
Summary of Lessons Learned
• Must be prepared • No one size fits all• Bundling could have
been more efficient Priority/pace dictated
initial bundling concepts Prioritized years 3-4
based on bundling but couldn’t use those due to budget
• Think of bundling beyond construction procurement
Source: Royce Meredith, P.E., Bridging Kentucky Program Manager; and Dr. Tony Hunley, P.E., Consultant Team Program Manager – 08/27/2020
NEED IMAGE
Outline• Bridge Bundling Definitions and Motivation• FHWA 2019 Bridge Bundling GuidebookState of Practice: Case Studies
• Michigan DOT’s Bridge Bundling Local Agency Pilot• Washington State DOT’s Project Bundles for Fish Passages• Kentucky Transportation Cabinet’s Bridging Kentucky ProgramIowa DOT’s Bridge Bundling Experience• Other Initiatives
35
Motivation
Category National Rank
Number of Bridges 7th
Number of Poor Bridges 1st
Number of NHS Bridges 22nd
Number of Poor NHS Bridges 40th
Owners Number of Bridges
State 4,178
Counties 18,613
Cities 1,210
Total 24,001 36
37
Need For Innovative ApproachChallenges: Each county is responsible for own
bridges 99 different jurisdictions involved Preference for local control Limited funding and resourcesSolution: Bundling across county lines Iowa DOT let/administered supply
contract Each county retains responsibility IHRB Development of design
standards AID Federal Grant and IHRB match Extensive collaboration IHRB – Iowa Highway Research Board
AID – Accelerating Innovation Deployment38
Approach
Iowa Highway Research Board (IHRB): funded a multi-phase research project to develop ABC Bridge Standards for Low Volume Roads.
HDR: Conducted a feasibility study to select bridge system in Phase I and prepared the design details in Phase II
State Transportation Innovation Council (STIC) recommended AID Grant for funding a demonstration project.
Demonstration project to utilize the ABC Standards on multiple projects across county lines.
Iowa County Engineers Association Service Bureau solicited and selected bridge candidate for demonstration project.
39
Project Location
Bridge Construction Completed in 2020
Bridge Construction To Be Completed in 2021 40Source: ontheworldmap.com
Lessons Learned
• Bundling the materials under a DOT contract to assist locals was a success.
• Challenges with traditional supplier becoming a prime contractor• Originally included UHPC labor in contract, but removed after industry
feedback on mixing labor in a supply contract• Benefit the counties, their bridge was cheaper than traditional project
because of “free beams and UHPC” through the grant• Replacing bridges in poor condition
• Bid prices similar with or w/o bundle concept• Standards were new to industry• UHPC not widely used in Iowa
• Extra coordination needed between counties, contractors, Iowa DOT, Forterra
• Need for one point person to administer project• Beam construction and delivery based on each county bridge construction
schedule• Constraints on when UHPC should be placed after beam delivery
• Contractor education using UHPC• Use of UHPC training videos• YouTube Channel to share information
41
Resources
Project Videos: Search YouTube for “ICEA Service Bureau”
https://www.youtube.com/channel/UCJvDukK2PHnPPLG8H32BNKw
Design Standards:https://iowadot.gov/bridge/bridge-and-culvert-standards/county-bridge-standards
Project Information:https://abc-utc.fiu.edu/mc-events/innovative-contracting-project-to-accelerate-replacement-of-multi-county-bridges-in-iowa/?mc_id=604
https://ideas.iowadot.gov/subdomain/news-2938/end/node/3108?qmzn=VoqGDZ
42
Outline• Bridge Bundling Definitions and Motivation• FHWA 2019 Bridge Bundling GuidebookState of Practice: Case Studies
• Michigan DOT’s Bridge Bundling Local Agency Pilot• Washington State DOT’s Project Bundles for Fish Passages• Kentucky Transportation Cabinet’s Bridging Kentucky Program• Iowa DOT’s Bridge Bundling ExperienceOther Initiatives
43
Contract Duration & Bridges per Contract Bundle
44
Agency Funding Source
D-B-B CM/GC D-B P3
Duration (Years)
Bridges (per Bundle)
Duration (Years)
Bridges (perBundle)
Duration (Years)
Bridges (per Bundle)
Duration (Years)
Bridges(per Bundle)
Delaware DOT Federal –State
- 2-20 - - - 28 - -
Erie County, NY Federal –Local
2 3-25 - - - - - -
Georgia DOT State - - - - 3 5-7 - -
Missouri DOT Federal reimbursement bonds
3 2-10 - - 5 554 - -
Nebraska DOT SIB – Local 1-2 2-7 - - - - - -
New York State DOT
Federal –State
1, 2 2-19 - 2 6-16 - -
Northampton County, PA
Private –Local
- - - - - - 12+10 33
Ohio DOT GARVEE bonds
2-3 - - 3 2-6 - -
Oregon DOT State - - 7 3 - - - -
Osceola County, FL2
Local - - 7 13 - - - -
Pennsylvania DOT
State, Private –Federal
2 7-18 - - - - 25 558
South Carolina DOT
Federal –State
3-5 - varies 3-13 - -
RANGE - 1-3 2-25 7 3-13 2-5 2-554 10-25 33-558
45Bridge Bundling Guidebook
Case Study: DelDOT Culvert Replacement Bundling Program
• Years: 2006-Present• Cost: $1M-$3M/Year• Goal: Replace hundreds of
culverts in poor condition• Bundled using D-B-B, IDIQ,
and DB• Environmental permitting
handled differently for each method
Source DelDOT
46Bridge Bundling Guidebook
Case Study: Erie County (New York) Preventative Maintenance Bridge Bundling Program
• Years: Ongoing• Cost: $1M-1.5M/year• Goals
• Extend service life• Maximize funding
• $1M steel repairs (every 2 years)
• $1M deck repairs (every 2 years)
• $250K bridge washing (every 2 years)
• $200K deck sealing (every year) The original map is the copyright property
of Google® Earth™ and can be accessed from https://www.google.com/earth.
47Bridge Bundling Guidebook
Case Study: MoDOT Safe & Sound Bridge Improvement Plan• Years: 2009-2012• Cost: $685M (Total)
$487M(DB), $198M (DBB)• Goal: 802 bridges in 4 years• 42 Days Avg. road closure• Selection Criteria
• State owned• Poor condition• Limited or no RW needs• Small bridges (147’ avg)• Available detour route• Low-volume road• No RR or Historic bridges• Minimum Env. Permits Source MoDOT
48Bridge Bundling Guidebook
Case Study: New York Works Accelerated Bridge Program
• Years: 2012-2013• Cost: $135M(DBB), $84M (DB)• Goals
• Reduce bridge decks in poor condition
• Jobs (2012 & 2013)• 116 bridge decks over 2 years
(81 DBB, 35 DB)• Bundled to maximize efficiency• Flexibility in contracts• Contractors gained efficiency
through repetitionSource Fort Miller Co., Inc NY
49Bridge Bundling Guidebook
Case Study: Ohio Bridge Partnership Program
• Years: 2014-2017• Cost: $110M• Goal: Replace 200 locally
owned bridges in 3 years• Grant Anticipation Revenue
Vehicle (GARVEE) bonds to pay for 80%
• Toll credits for 20% (No local match)
• Small bundles• Replaced 210 bridges due
to cost savingsSource ODOT
50Bridge Bundling Guidebook
Case Study: Oregon Trans. Inv. Act (TIA) III State Bridge Delivery Program
• Years: 2004-2014• Cost: $1.3B • Goal: To repair or replace 271
bridges due to load rating analysis
• Bundled by corridor• 96 Bundles (2-13 bridges)• Formal program-level risk
analysis up front• Risk assessment for each
bridge performed • Delivery Method Chosen
• 85 D-B-B, 10 D-B, 1 CM/GC
Source Oregon DOT
51Bridge Bundling Guidebook
Case Study: PennDOT Rapid Bridge Replacement Program
• Years: 2015-2018• Cost: $899M• Goal: Replace 558 bridges in
poor condition• P3 procurement (DBFM)• Consultant Program Manager• Private partner set the NEPA
impact footprint throughSpecial Experimental Program 15
• Participated in utility coordination• Outreach program to educate DBEs about program
Source PennDOT
Center for Accelerating Innovation
Nebraska County Bridge Match ProgramSmall agencies can partner for economies of scale• With one another • With their State Agency
52
Source: NDOT
NDOT County Bridge Match Program sites.
Center for Accelerating Innovation
Indiana DOT- Case Study Summary• Bundle various project types:
• bridge/culvert, road/pavement• Efficiencies in environmental approval and permitting • Standardization of design and construction methods• Shared resources: workforce, equipment, facilities • INDOT Admin. savings (e.g. contracting, letting)• Cost effective MOT• Efficiencies in contractor overhead• Scheduled accelerationCFO gives $50M back to the budget due
to expected project bundling savings53
54
• EDC web site https://www.fhwa.dot.gov/innovation/everydaycounts/edc_5/project_bundling.cfm
• Accelerated Bridge Construction webinar https://abc-utc.fiu.edu/mc-events/fhwa-bridge-bundling-guidebook-bbg/?mc_id=508
• BATIC Institute webinar Project Bundling Presentationhttp://www.financingtransportation.org/capacity_building/event_details/webinar_project_bundling_021220.aspx
Project Bundling Resources