case study cieloazul jan2009

Upload: gaston-landa

Post on 14-Apr-2018

215 views

Category:

Documents


0 download

TRANSCRIPT

  • 7/30/2019 Case Study CieloAzul Jan2009

    1/13

    J ulie Walleisa and Caryn Grosse prepared this case study on behalf of Dekker/Perich/Sabatini and using information provided byRio Rancho Public Schools, Bridgers +Paxton, David Bend, and Bradbury Stamm.

    Copyright 2008 by Dekker/Perich/Sabatini. To order copies, contact D/P/S at (505) 761-9700. No part of this publication maybe reproduced, stored in a retrieval system, or transmitted in any form or by any means without the permission ofDekker/Perich/Sabatini. USGBC has been granted permission to post and reproduce this case.

    Cielo Azul Elementary School

    Rio Rancho, NM

    Project Overview

    Cielo Azul Elementary School is a new 85,000sf school built for Rio Rancho Public Schools (RRPS). It

    opened in Fall 2008 to serve 800 students in grades K-5 in Rio Rancho, New Mexico. Cielo Azul is a

    publicly funded project, with funds provided through both RRPS and the New Mexico Public Schools

    Capital Outlay Council (PSCOC). The school was designed and constructed using the traditional design,

    bid, build method in which a general contractor is selected through an open bid based on lowest price

    after construction documents are complete.

    While this school was intended to achieve LEED certification from the start, the true beginning of the

    projects story is tied to three other elementary schools in the same district. In 2005, 2 elementary schools

  • 7/30/2019 Case Study CieloAzul Jan2009

    2/13

    Dekker/Perich/Sabatini Cielo Azul LEED Case Study

    Page 2 of 13

    known as Stapleton Elementary and Maggie Cordova Elementary opened in Rio Rancho. This was the

    start of a number of prototype schools: the original design created for Stapleton was adapted to the site of

    Cordova Elementary. The schools were bid together and built concurrently by the same general

    contractor. These first two schools were designed responsibly to meet current codes, but did not

    incorporate any true sustainable features and did not pursue LEED certification.

    In early 2007, design began on 2 additional prototype elementary schools (Sandia Vista and Cielo Azul)

    based on the Stapleton design. As prototypes, the projects had a compressed schedule for creation of

    construction documents which allowed for little variation from the original design. Some changes were

    required in order to address changes in building code (from 1997 UBC to 2003 IBC), changes in state

    adequacy standards for public schools, need for 9 additional classrooms, and different site conditions. In

    addition to this, RRPS directed the team to incorporate sustainable features as feasible and pursue LEED

    certification, at the Certified or possibly Silver level. Both schools pursued certification under LEED for

    New Construction (LEED-NC) rather than LEED for Schools (LEED-S), because LEED-S was still beingballoted at the time the schools were registered with USGBC.

    Design began in J anuary 2007, and construction spanned from October 2007 to September 2008. Cielo

    Azul is anticipating LEED Silver certification in late 2008 or early 2009.

    Environmental Goals

    The design effort focused on incorporating meaningful sustainable features within the constraints of the

    prototype schedule and budget. The main priorities within LEED are to achieve significant reductions in

    energy and water use, and emphasize indoor environmental quality. Additional goals determined duringdesign, which formed part of the Owners Program Requirements, included:

    y The aesthetic of the building exterior should relate simultaneously to the natural environment

    of the land and the high-tech imagery of the industries which helped to create Rio Rancho.

    Thus the building uses a combination of natural materials like split-face concrete masonry

    walls and stucco to relate to the environment, while introducing metals, glass and fabricated

    canopy elements in accent locations such as the entrance to create a high-tech image.

    y The building floor-plate should remain narrow to encourage daylighting.

    y Energy efficiency should be maximized through envelope and systems design, as feasible

    within the project budget.

    y As part of the goal to create a great learning environment for students, the building should

    provide sufficient and well-controlled daylighting, flexible lighting, and views to the

    surrounding landscape and playgrounds. Faculty/staff are able to control their own

    environment through features such as operable windows, temperature controls, and suitable

    window coverings. Interior finishes should be low-emitting.

  • 7/30/2019 Case Study CieloAzul Jan2009

    3/13

    Dekker/Perich/Sabatini Cielo Azul LEED Case Study

    Page 3 of 13

    y All building systems should be of appropriate quality and maintenance requirements for a

    school.

    y The building management system should be tied to a central interface that provides for

    system simulation, monitoring, trending, set-point and sequence modification. A separate

    display should indicate real time energy consumption.

    Owner and Occupancy

    The building is owned by Rio Rancho Public Schools, and will operate on the typical 9 month school year

    schedule. The school will be occupied by approximately 800 students in grades K-5 and 100 faculty/staff.

    The basic design of the single-story school consists of a central zone housing shared functions such as

    administration, cafeteria, and gymnasium, with 2 wings of classroom spaces. The design of the project

    has evolved from the previous prototypes to reflect differences in the site, input from administrators,

    teachers, parents, and community members, lessons learned from the previous two schools, and the

    desire to achieve LEED certification.

    Floor Plan

  • 7/30/2019 Case Study CieloAzul Jan2009

    4/13

    Dekker/Perich/Sabatini Cielo Azul LEED Case Study

    Page 4 of 13

    LEED Scorecard

    The design team was directed to achieve LEED Certification, and target Silver certification, if feasible.

    The scorecard below shows the credits submitted as part of the application:

  • 7/30/2019 Case Study CieloAzul Jan2009

    5/13

    Dekker/Perich/Sabatini Cielo Azul LEED Case Study

    Page 5 of 13

  • 7/30/2019 Case Study CieloAzul Jan2009

    6/13

    Dekker/Perich/Sabatini Cielo Azul LEED Case Study

    Page 6 of 13

    Team and Process

    Dekker/Perich/Sabatini designed the building (as well as the previous prototypes) and is managing the

    LEED certification process. Bridgers +Paxton provided mechanical, electrical, and plumbing engineering,

    and Huitt Zollars provided civil engineering services. LEED issues were discussed with the team from the

    beginning of the process and closely monitored during construction. A LEED credit matrix was regularly

    updated and distributed amongst the team during the design phases to communicate about LEED action

    items and the overall LEED credit status.

    Primary Design Team:

    ArchitectDekker/Perich/Sabatini

    InteriorsDekker/Perich/Sabatini

    LandscapeDekker/Perich/Sabatini

    Structural EngineerDekker/Perich/Sabatini

    LEED ManagerDekker/Perich/Sabatini

    Mechanical, Electrical and Plumbing EngineerBridgers +Paxton

    Civil EngineerHuitt Zollars

    Primary Construction Team:

    General ContractorBradbury Stamm

    Mechanical ContractorAshcraft Mechanical

    Electrical ContractorTheco

    Commissioning AgentWHPacific

    Site Strategies

    An erosion and sedimentation control plan was implemented that included both the construction activities

    described in the Storm Water Pollution Prevention Plan and the permanent site and landscape features.

    During construction, silt fences were installed around the property and check dams provided along

    roadside swales to provide regular trapping points for localized runoff during construction. Diversion

    swales and berms were constructed and maintained to divert flows through the check dams. The site was

    stabilized with regular watering and compaction. Permanent measures included seeding disturbed areas

    of the site and providing vegetation along the perimeter of the project, providing curbs, gutters and

    stormwater sewer system for stormwater drainage Together, these procedures help to prevent erosion

    and reduce negative impacts on water and air quality.

    Some of the LEED credits for siting strategies were not achievable due to the location of the site in Rio

    Rancho. The site is not a brownfield, is not in an area of high density development, and does not have

  • 7/30/2019 Case Study CieloAzul Jan2009

    7/13

    Dekker/Perich/Sabatini Cielo Azul LEED Case Study

    Page 7 of 13

    access to public transportation. The project is located within biking distance of several residential areas,

    so bike racks and showers/changing rooms were provided. Parking was restricted to the amount required

    by state standards for public schools, and preferred parking was provided for carpools and low-emitting

    vehicles.

    A large amount of vegetated open space, equal to nearly 5 times the building footprint, was provided to

    provide habitat and achieve the credit for maximizing open space as well as an innovation credit for

    exemplary performance. The buildings entire roof is a highly reflective roof membrane that limits heat

    gain. The roof is a fully adhered Carlisle Sure Weld thermoplastic polyolefin (TPO) membrane roof with a

    solar reflectance index (SRI) of 110.

    The site was designed to capture water into 3 drainage basins to reduce site runoff rate and quantity.

    The largest drainage basin occurs at the athletic fields; recurring storm flows will assist in turf irrigation. In

    addition to reducing stormwater quantity, the ponds will also provide stormwater quality control byallowing sediments to settle out.

  • 7/30/2019 Case Study CieloAzul Jan2009

    8/13

    Dekker/Perich/Sabatini Cielo Azul LEED Case Study

    Page 8 of 13

    Water Strategies

    The site and landscaping was designed to reduce water consumption by 83% through a variety of

    methods. The planting plan utilizes a regionally appropriate plant palette while providing shade areas

    where the school children will be active. The plant palette extensively uses low water plant material that

    will also withstand the extreme winds on the site. A biological soil amendment was used in all planting

    beds. Revegetative seeding, which will not require irrigation, is being applied to the whole site to help

    mitigate construction disturbances.

    Inside the building, low-flow plumbing fixtures were installed to reduce water use by 44%. The following

    fixtures were used:

    Fixture Usage

    Dual-flush toilets 1.1/1.6 gpf

    Waterless urinals 0.0 gpf

    Low-flow showers 1.8 gpmLow-flow, sensored lavatories 0.5 gpm

    Low-flow kitchen sinks 1.8 gpm

    Energy Strategies

    This school was designed to use 31% less energy than a baseline building, based on modeling

    comparisons using ASHRAE 90.1 standards and Trane Trace software. Energy efficiency begins with the

    building envelope, and continues through the selected mechanical systems. The exterior design uses the

    same juxtaposition of natural materials like split-face concrete masonry walls and metal and glass

    storefront panels and canopies as the original prototype schools. However, changes were made to thedesign of the wall and roof assemblies to increase thermal performance to R-24 and R-38, respectively

    through use of continuous insulation and thermal breaks. The originally selected glazing was upgraded to

    a higher performing low-e insulated glass unit with an improved Solar Heat Gain Coefficient (SHGC), and

    windows remain shaded by horizontal overhangs as designed in the original prototypes.

    The original prototype school design was based on simple rooftop mechanical units with overhead duct

    distribution and constant air volume. Due to the accelerated design schedule, these basic conditions of

    rooftop units and overhead distribution needed to form the basis of design. However, the system was

    upgraded to high efficiency packaged rooftop units with constant volume rooftop direct expansion cooling

    with natural gas furnace. These supply all spaces except the electrical and data equipment rooms, which

    are served by ductless split systems. The systems serving occupied areas have economizer controls and

    demand-controlled ventilation for additional energy efficiency. A commissioning agent was hired to

    provide fundamental commissioning services for this school and other schools under construction in the

    district.

  • 7/30/2019 Case Study CieloAzul Jan2009

    9/13

    Dekker/Perich/Sabatini Cielo Azul LEED Case Study

    Page 9 of 13

    Occupancy sensors were used in classrooms to turn off lighting when the rooms are unoccupied. Multi-

    level manual switching was also provided so that occupants can adjust lighting as necessary for the time

    of day and task at hand. Cafeteria and gymnasium use multi-ballasted compact fluorescent hi-bay fixtures

    with multi-level manual switching so that light levels can be adjusted throughout the day, or for special

    events.

    Material Strategies

    Recycling played a large role in the design and construction of the building. Construction waste

    requirements were included in the project specification, and the contractor submitted a Construction

    Waste Management Plan prior to the start of construction. Over 73% of construction waste materials were

    reused or recycled rather than disposed of in a landfill. This translates to almost 563 tons of materials

    diverted from landfill.

    A target list of recycled and regional materials was developed during Design Development, and refined

    during the Construction Documents phase. Key materials that contributed to these credits included:

    Material Supplier Recycled Content RegionalManufacture

    RegionalExtraction

    Aluminumstorefront/curtainwall

    Tubelite 10% pc, 65% pi No No

    Concrete La Farge 20% cementreplaced with flyashCCBC

    Yes Yes

    Structural steel Various Varies No No

    Metal studs Dietrich 24.6% pc, 6.6% pi No No

    CMU Utility BlockCompany

    None Yes Yes

    Gypsum board AmericanGypsum

    6% pi Yes Yes

    Acoustic ceilingpanels

    USG Varies No No

    The use of renewable materials and certified wood was not pursued on this project.

  • 7/30/2019 Case Study CieloAzul Jan2009

    10/13

    Dekker/Perich/Sabatini Cielo Azul LEED Case Study

    Page 10 of 13

    Indoor Environmental Quality Strategies

    The individual rooftop units utilize CO2 sensors for ventilation monitoring. If the CO2 level rises above

    600 ppm, alarms will sound. For units serving multiple spaces, field installed airflow measuring devices

    monitor fresh air intake to the zone.

    The contractor implemented a Construction IAQ Management Plan that included a number of proven

    strategies for protecting the HVAC system and porous materials from contamination, ensuring proper

    housekeeping and ventilation procedures, and generally protecting indoor air quality. The contractor also

    conducted a flushout by introducing fresh outside air to the school via the mechanical systems. Part of the

    flushout was conducted after construction was completed and before students began occupancy, with the

    remained conducted during occupancy.

    Construction photos showing how the ductwork and materials were protected from contamination

    Low-emitting materials were specified and used throughout the project. The contractors did a great job of

    buying and using the correct products, which included Kwal paints, Interface carpet, Marshfield doors,

    SkyBlend particleboard, and a variety of compliant adhesives and sealants. To further protect indoor air

    quality, entry walk off mats were provided at the building entries, and the janitors closets were exhausted

    in compliance with LEED guidelines.

    The faade of the building incorporates the natural look of block punctuated with the high tech look of

    aluminum and glass. In order to maintain the construction budget, a very regular and comparatively less

    expensive design aesthetic was utilized for the exterior walls of the classroom wings, and the use of

    accent materials and other design elements was focused around the more public entry areas. The

    majority of the exterior walls are load-bearing concrete masonry units (CMU), with accent areas of glass

    and aluminum storefront system at office areas. The length of the classroom wings are broken down and

    made more interesting by stepping in the wall at the window areas of each classroom, and changing to a

    glass and aluminum storefront system with metal panel fascias above the windows in these recesses.

    The color palette is intended to be subtle and sophisticated overall, with a small amount of stronger color

    used in accent areas only.

  • 7/30/2019 Case Study CieloAzul Jan2009

    11/13

    Dekker/Perich/Sabatini Cielo Azul LEED Case Study

    Page 11 of 13

    Operable windows Curtain wall Recessed windows with shades

    Innovation and Design Process

    The project team anticipates two innovation credits for exemplary performance, based on the

    achievement of 44% water use reduction, and maximizing open space by providing nearly 5 times the

    required open space. Two additional innovation credits include an educational program to demonstrate

    the green features of the building to the occupants and public, and a green housekeeping program.

    A LEED accredited professional was involved with the project at every stage. Her involvement in the

    project included:

    - Initial feasibility discussions using the LEED scorecard

    - Design feedback and evaluation of alternative systems, strategies, and materials throughout the

    design process

    - Coordination with the engineers and consultants

    - Specification of LEED products and methods

    - Review of LEED submittals and management of LEED documentation

    Project Cost

    The construction of nearly identical schools pursuing LEED certification, which were based on previous

    non-LEED prototypes, presented a unique opportunity for an apples-to-apples study of the costs and

    benefits of green/LEED school construction. USGBC expressed interest in studying these projects, and

    helped the design team connect with a Masters student at J ohns Hopkins University. David Bend studiedthe school projects and wrote about them for his masters thesis for the Environmental Science and Policy

    degree program.

    The conclusion of this study was that the green features added approximately 1.3% to the cost of

    construction, but would pay back within about 2 years due to direct energy and water savings. David

    Bend used information provided by RRPS, Dekker/Perich/Sabatini, and Bradbury Stamm, as well as

  • 7/30/2019 Case Study CieloAzul Jan2009

    12/13

    Dekker/Perich/Sabatini Cielo Azul LEED Case Study

    Page 12 of 13

    interviews with key team members and broader industry data, to reach these conclusions. The study

    compared the construction costs per square foot of the new and older schools, to normalize for the

    differences in building size. While the construction cost of the new schools are higher than the existing

    non-LEED schools, several contributing factors needed to be considered in order to isolate the green

    premium. Costs were adjusted to account for escalation in construction costs between the construction of

    the original prototypes and the new schools, and to normalize for the differences in site preparation costs

    due to differing site conditions, which is unrelated to the projects green features. With these factors

    accounted for, the average cost per square foot for the non-LEED prototypes was $160.22, compared to

    $162.31 for the new LEED-registered schools. These represents a 1.3% green premium for the new

    schools, lower than the 2% green premium often cited in national studies.

    In reality, the green premium may be even lower, due to a couple of additional factors which impacted

    construction cost but could not be reliably isolated from other costs. The two new schools are being

    constructed on an expedited schedule, which may have increased construction cost. And, the locally-adopted building code was changed from the Uniform Building Code used for the original prototypes to

    the International Building code for the new schools, which resulted in a significant increase in the number

    of required plumbing fixtures for the new schools.

    Energy and water savings projections were based on actual usage from the existing schools, and energy

    models and water calculations for the new schools provided by the design team. Cost comparisions

    showed the following potential savings:

    Stapleton Cordova Sandia Vista Cielo Azul Savings

    Electricity $0.92/sf $0.84/sf $0.34/sf $0.33/sf $0.54/sf/yrGas $0.38/sf $0.31/sf $0.01/sf $0.01/sf $0.30/sf/yr

    Water 8.6g/sf 8.6g/sf 6g/sf 6g/sf $0.03/sf/yr

    These potential savings from the high performance features of the new schools total $0.87/sf/yr, or

    approximately $73,500 per school annually. This would result in a payback period of just over 2 years for

    the green premium.

    Lessons Learned

    Since the LEED certification process is still new to many contractors in New Mexico, it is important for the

    LEED manager to ensure that the contractor is not only tracking construction waste from the beginning,

    but looking at the trends to see if project goals will be met. Although a Construction Waste Management

    plan was developed at the beginning of construction, and reports were generated every month, these

    reports did not provide a cumulative total of waste diversion rates to date. When the numbers were tallied

    into a single tracking spreadsheet near the end of construction, the project team became aware that goal

  • 7/30/2019 Case Study CieloAzul Jan2009

    13/13

    Dekker/Perich/Sabatini Cielo Azul LEED Case Study

    Page 13 of 13

    of recycling at least 75% of the construction waste was unattainable, and that achievement of even the

    50% level might be in jeopardy.

    Also, the inclusion of Division 2 costs when calculating the default material value can have a dramatic

    impact from one project to the next. As mentioned in the introduction, this project was one of two schools

    based on the same prototype. While the buildings are virtually identical, the required sitework was quite

    different, resulting in nearly a million dollars of additional costs for Cielo Azul. This difference resulted in

    significantly lower percentages of recycled content and regional materials for Cielo Azul than for Sandia

    Vista, even though the material specifications were the same.

    Learning More

    RRPS, Dekker/Perich/Sabatini, and USGBC intend to continue learning from these projects over the

    coming years. RRPS intends to track actual water and energy use and operating costs to continue the

    analysis of cost and payback. They also plan to track human-impact measures such as teacherabsenteeism and turnover, student absenteeism and performance, and student health and behavior. Data

    will be collected from all 4 schools for analysis.

    For more information on the project, or to arrange a tour of the building or find out if additional data is

    available, please contact:

    Dekker/Perich/Sabatini

    7601 J efferson NE, Suite 100

    Albuquerque, NM 87109(505) 761-9700

    or visithttp://www.dpsdesign.org