case study - hi-level mezzanines · 2012-10-01 · case study teccon and hi-level mezzanines help...
TRANSCRIPT
CASE STUDY
Teccon and Hi-Level Mezzanines help major logistics company
to deliver
Introduction
Teccon is a leading industrial equipment supplier and one
of the UK’s most successful Dexion centres. Products
and services range from the design and installation of
mezzanine floors, racking & shelving systems and office
partitioning to various storage systems and a host of
industrial products.
Based in Nuneaton, Warwickshire, Teccon has over 20
years’ experience in supplying some of the UK’s leading
companies including BT, Sainsburys, Caterpillar, Exel,
Panasonic, Rolls Royce and Bookers, to name but a few.
The Challenge
The Technology Division of a major logistics company
based in Milton Keynes took the decision to close a
200,000 ft² warehouse facility, from which it had been
running an important software supplier contract.
It needed to relocate this part of the business to another
existing technology distribution facility in the same town.
In order to accommodate the increased business, this
facility needed to increase its capacity substantially.
When the logistics company weighed up the options it
became clear that a mezzanine floor within the existing
facility would: provide the capacity required, would be
cost-effective to install, would improve the productivity of
the site and, importantly, the upgraded facilities could be
brought on-stream very quickly.
The real challenge however, was to accomplish both the
installation of the new mezzanine and the relocation of
the warehouse stock to the new facility without disrupting
either the existing warehouse operation or the service
levels agreed under the software company’s contract.
The Requirement
It was decided to install a two-tier mezzanine to allow for
further expansion in the future. This would provide an
additional 37,000 ft² of floor area with a loading rating of
5.0kN/m² allowing for storage and light industrial use.
The floors had to incorporate seven staircases and six
pallet gates together with full safety protection systems.
Before the final specification could be agreed the con-
crete floor needed to be tested for strength and suitability
How a new multi-tier mezzanine floor is providing a cost-effective alternative to relocating and helping
to improve productivity
and then detailed plans would be needed for Building
Regulations approval.
In addition to the mezzanine, the main contractor was to
be responsible for the efficient installation of all other
services including ducting, fresh air, all electrics, fabrica-
tion of offices and a Board Room, 560 bays of shelving
and fire protection including a sprinkler system.
Initially, the project was scheduled to start in January
2007, with a target date for completion of July 2007. The
timescale was very tight for a project of this complexity
but it was driven by the need to close the existing
warehouse facility by the end of July 2007 at the latest.
The Solution
The logistics company invited three businesses to tender
for the project. Given the complexity of the project and
the very tight deadline, Teccon needed to partner with a
mezzanine manufacturing company that was technically
competent, reliable and able to react very quickly.
Richard Bentall, Senior Account
Manager at Teccon comments, “In
the end it wasn’t a difficult decision
to go with Hi-Level. We’ve worked
successfully with them in the past
so we knew we could rely on them
to provide the design and technical
support we needed. And, as a
leading manufacturer, we also
knew that they could handle a
project of this scale.”
Teccon and Hi-Level were
ultimately successful in the
selection process due to their
proactive approach, innovative
thinking and flexibility. “It was their
willingness to engage with us to
identify the project requirements
and to make positive suggestions
which finally convinced us that
they were the right partner for this
“It wasn’t a difficult decision to go with Hi-Level. We’ve worked
successfully with them in the past so we knew we could rely on
them to provide the design and technical support we needed.”
“The flexibility and excellent understanding built up between our teams ensured that the project
was delivered on budget and ahead of schedule”.
critical project,” comments the logistics company’s
Project Manager.
By the time the selection process had been completed
and the necessary guarantees and warranties put in
place for the landlord, the maximum site time available
before the immovable deadline was just 16 weeks.
In addition to the original project requirements, tests on
the concrete floor revealed the need to strengthen it
considerably to take the weight of the double floor
mezzanine concentrated on columns spaced at 6m
intervals. This meant that 16m piles beneath each
column were needed to take the weight of the mezza-
nine and all this additional work had to be completed
within the 16 week period.
Using its unique QD3 Pro mezzanine design manage-
ment system, Hi-Level developed a programme of work
that detailed precisely which elements of the build would
be completed by when, and co-ordinated this plan with
Teccon to ensure that the work could be done without
undue disruption to the warehouse, which needed to
continue normal operations during the construction of the
new mezzanine.
The Implementation
Due to the very tight deadlines, channels of communica-
tion were kept short with senior level, decision-maker
contacts established to ensure that complex issues were
identified and dealt with without delay.
Hi-Level took responsibility for producing detailed plans
for the mezzanine and then handled all Building Regula-
tions applications and approvals while Teccon coordinat-
ed all associated services.
Hi-Level Mezzanines Ltd, Unit 6, Petersfield Business Park, Bedford Road, Petersfield, Hampshire, GU32 3QA
T: +44 (0)1730 233223 | F: +44 (0)1730 231311 | E: [email protected] | W: www.hi-level.co.uk
About Hi-Level Mezzanines
Founded in 1991, Hi-Level Mezzanines is a leading supplier
of mezzanine flooring. The company’s mezzanine floors
incorporate high specification components as standard and
comply with BRE Digest 437 and other relevant kite marks.
Hi-Level’s unique, mezzanine production system manages
projects from start to finish, automatically calculating the best
floor design and the precise amount of materials required -
ensuring the most cost-effective use of materials to keep
build costs down.
In order to comply with strict Health & Safety require-
ments at the warehouse and out of consideration for
neighbouring businesses, the whole work area was
protected with barriers, and sheeting was erected to limit
the spread of dust from the site works.
All drilling of the concrete slab and piling work was
completed by specialist contractors working overnight to
limit the impact of noise, vibration and dust and Hi-
Level’s installation teams worked in shifts around the
clock to ensure that the project progressed according to
the schedule.
As soon as the piling was completed at one end of the
site, Hi-Level’s mezzanine floor installation teams
started the build process working with teams of special-
ists installing all the other services.
Regular site meetings with all key personnel ensured
that as issues were identified they were quickly resolved
and, throughout the whole build process, delays were
kept to an absolute minimum.
The logistics company Project Manager was delighted
with the way the project progressed, “Without the direct
lines of communication at all levels from the top down
and the willingness to find solutions as issues arose or
changes to specifications were needed, this project
simply couldn’t have been delivered on time. The
flexibility and excellent understanding built up between
our teams ensured that the project was delivered on
budget and ahead of schedule”.
The Results
The whole project from initial order to completion was
delivered in just under 16 weeks. The logistics company
has been able to relocate its software contract business
in its entirety without any negative impact on service
levels for this or any of its other technology contracts.
The consolidation of its technology distribution facilities
has produced very significant operational and financial
benefits. The relatively low cost of the installation
combined with the efficiency gains from greatly increas-
ing the usable space within an existing facility mean that
the pay-back period on the investment will be extremely
short.