case study of productivity and yield improvement of a single part using kaizen … · 2020. 5....

5
Case Study of Productivity and Yield Improvement of a Single Part Using Kaizen and Best Practices at N S International KEYWORDS: Productivity, Yield, Slide Bolt, Traub, Cold forging, Kaizen. ABSTRACT This case study deals with a single part improvement in Yield Saving and Productivity Improvement. Problems and ideas eliminating those problems through Kaizen and best practices are described and the benefits achieved by the organization and sharing the same with customer are shown. Introduction: Productivity & Yield Improvement Productivity & Yield Improvement in SLIDE BOLT OPERATION : TROUB MODEL : BOHD018 Problem (Reason for Selection) 1. Productivity was 1200 Nos./Shift with multiple machine 2. Yield was 13.39% 3. Customer order increasing but not adhered 4. Selling price was lower than the Quotation Cost 5. High Process Cost 6. Delivery failure 7. Customer Complaints were increasing Problem Understanding Slide bolt-Focus on Process for Productivity Improvement Traub-1 Part off and Turning CLG-1 TRD Grinding Ruff Troub-2 Under Cut Milling Dia Turning CLG-2 TRD Grinding Finish Milling-1 Rolling Plating Inspection Packing End Start 1=44 Nos. 1 2 3 4 5 11 10 9 1=333 Nos. 1=145 Nos. 1=125 Nos. 1=167 Nos. 1=167 Nos. 1=417 Nos. Milling-2 Deburing = Focus in process to be improved or eliminated = Freeze Process 44 N 333N 45 25N 67N 67N 17N Productivity and Yield Improvement of a Single Part Using Kaizen and Best Practices 105

Upload: others

Post on 19-Aug-2020

1 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Case Study of Productivity and yield Improvement of a Single Part Using Kaizen … · 2020. 5. 29. · Case Study of Productivity and yield Improvement of a Single Part Using Kaizen

Case Study of Productivity and yield Improvement of a Single Part Using Kaizen and Best Practices at n S InternationalKeywords: Productivity, yield, Slide Bolt, Traub, Cold forging, Kaizen.

AbstrAct

This case study deals with a single part improvement in Yield Saving and Productivity Improvement. Problems and ideas eliminating those problems through Kaizen and best practices are described and the benefits achieved by the organization and sharing the same with customer are shown.

Introduction: Productivity & yield Improvement

Productivity & Yield Improvement inSLIDE BOLT

OPERATION : TROUBMODEL : BOHD018

Problem (Reason for Selection)

1. Productivity was 1200 Nos./Shift with multiple machine

2. Yield was 13.39%

3. customer order increasing but not adhered

4. Selling price was lower than the Quotation cost

5. High Process cost

6. Delivery failure

7. customer complaints were increasing

Problem Understanding

Slide bolt-Focus on Process for Productivity Improvement

Traub-1Part off

andTurning

CLG-1TRD

GrindingRuff

Troub-2Under CutMilling Dia

Turning

CLG-2TRD

GrindingFinish

Milling-1 Rolling

PlatingInspectionPacking

End

Start1=44 Nos.

1 2 3 4 5

11 10 9

1=333 Nos. 1=145 Nos. 1=125 Nos. 1=167 Nos. 1=167 Nos. 1=417 Nos.

Milling-2 Deburing

= Focus in process to be improved or eliminated

= Freeze Process

44 N 333 N 45 25 N 67 N 67 N 17 N

Productivity and Yield Improvement of a Single Part Using Kaizen and Best Practices 105

Page 2: Case Study of Productivity and yield Improvement of a Single Part Using Kaizen … · 2020. 5. 29. · Case Study of Productivity and yield Improvement of a Single Part Using Kaizen

Productivity-Nos./Man/Hr

44

333

125

Taub

-1 P

art

off a

nd T

urni

ng

CLG

-1 T

RDG

rindi

ng R

uff

Milli

ng-1

Milli

ng-2

Debu

rring

CLG

-2 T

RDG

rindi

ng F

inish

Machine

450400350300250200150100500

Nos.

GOOD

Nos./Man/Hr.

167 167

417

yield loss

Yield Loss

Bar used Dia 18.5 (56 g/pc), Material Cost 60 Rs./Kg.Material Cost Per pc 3.37 Rs. Yield was 13.39%

Yield% used

Yield% Loss13.39

86.61

Loss1

61

List of Kaizens Implemented

S.No. Before After Benefit Target Date1 Troub-1, CLG-1,

Troub-2, Mil-1, Mil-2, Deburing, CLG-2, Processes were very low production

Forging Developed for the part. Troub-1, Mil-2, Deburing, CLG-2, has been eliminated

32000 Nos. Produced in Single Shift. Process Cost reduce 4.4 Rs. to 1.53 Rs.

02.12.2014

2 Bar Dia 18.5 used. Raw material cost was 3.37 Rs./pc, Weight 56 gms/pc, Yield-13.39%

Wire size 8.88 used. Raw material Cost 0.82/pc., Weight 14 gms/pc, Yield-53.57%.

Yield improved 13.39% to 53.57%, where Per pc cost reduce 3.37 Rs. to 0.82 Rs.

02.12.2014

106 N S International

Page 3: Case Study of Productivity and yield Improvement of a Single Part Using Kaizen … · 2020. 5. 29. · Case Study of Productivity and yield Improvement of a Single Part Using Kaizen

Kaizen No. 01Company: Deptt.: Result: Month of Report Dec-14N.S. International Production-Troub Implemented

Subject: Productivity improvement through process change Process: Productivity Improvement

Before

Why-Why Analysis Horizontal Deployment

Benefits:

Comments: Comments:

ProductivityQuality

CostDeliverySafetyMorale

EnvironmentOthers

Saving/YearDate of Imple.Suggested by

Approved by

YesYesYesYesYes

Yes

20.1 Lac12.12.14Dayal Singh

PraveenSharma

Troub-1, CLG-1, Troub-2, Mil-1, Mil-2, Deburing, CLG-2, where the production was 1200 pcs/shift

� Production increased by 28800 Nos./shift (288000/mpnth)� Process Cost reduce 4.4 Rs. to 1.53 Rs./pc (Monthly-1435000

Forging Developed for the part. Troub-1, CLG-1, Troub-2, Mil-1, Mil-2, Deburing, CLG-2, has been eliminated, where production is 30000 Nos. per shift

Bolt Maker-1Cold Forging

1=30,000 Nos.

Traub-1Part off

andTurning

CLG-1TRD

GrindingRuff

CLG-2TRD

GrindingFinish

Milling-1

Start1=44 Nos.

11

2 4 5

1=333 Nos. 1=125 Nos. 1=167 Nos. 1=167 Nos. 1=417 Nos.

Milling-2 Deburing

44 N 333 N 25 N 67 N 67 N 17 N

After

Kaizen No. 02Company: Deptt.: Result: Month of Report Dec-14N.S. International Production-Troub Implemented

Subject: Yield improvement through process change Process: Cold Forging

Before

Why-Why Analysis Horizontal Deployment

Benefits:

Comments: Comments:

ProductivityQuality

CostDeliverySafetyMorale

EnvironmentOthers

Saving/YearDate of Imple.Suggested by

Approved by

YesYesYesYesYes

Yes

20.1 Lac12.12.14Dayal Singh

PraveenSharma

Slide Bolt fully machining at troub section by using of Bar Dia 18.5 (Slide Bolt fully machining at troub section by using of Bar Dia 18.5 (56 Grams) Operation-Part turning and total length, Groove Turning, OD Turning, Milling1 2, Deburring, CLG Threading, Plating, Inspection, Yield% 13.39, per pc cost-3.37Rs.

� Yield Saving–Rs. 2.55/pc (129000/month),� Quality Complaints reduced

Slide Bolt developed at forging process by using Bar Dia 8.88 (14 Grams) Operation-Forging, Traub, Milling, Deburring, CLG, Yield improved 53.57 Per pc cost 0.82 Rs./pc.

After

Productivity and Yield Improvement of a Single Part Using Kaizen and Best Practices 107

Page 4: Case Study of Productivity and yield Improvement of a Single Part Using Kaizen … · 2020. 5. 29. · Case Study of Productivity and yield Improvement of a Single Part Using Kaizen

Benefits and Achievements

Traub-1Part off

andTurning

CLG-1TRD

GrindingRuff

Troub-2Under CutMilling Dia

Turning

CLG-2TRD

GrindingFinish

Milling-1

Start

Start

End

1=44 Nos.

1

1 2 3

456

2 3 4 5 6 7

1=333 Nos. 1=145 Nos. 1=125 Nos. 1=167 Nos. 1=167 Nos. 1=417 Nos.

Milling-2 Deburing

444 N 333 N 455 25 N 677 N 677 N 177 N

6 Machining Processes Eliminated

Slide Bolt – Productivity Improvement – After

Bolt Maker-1Cold Forging

1=30,000 Nos.

RollingTraub-1Turning

PlatingInspection

= Process After Improvement= Freeze Process

Packing

OperationBefore After

Manpower Nos./Man/Hr.

ManPower Nos./Man/Hr.

Traub-1 Part off and Turning 1 44

1 2500

CLG-1 TRD grinding Ruff 1 333Milling-1 1 125Milling-2 1 167Deburring 1 167CLG-2 TRD Grinding Finish 1 417

Benefit – 1 Man makes 2500 Nos./Hr. instead of 5 Men where productivity was 125 Nos. to 417 Nos./Man/Hr. Max.

13.39

86.61

Yield Loss – BeforeBEFORE

AFTER Yield Improved – After

Yield% used

Yield% Loss

Yield% Loss

Bar used Dia 18.5 (56 g/pc), While finish Pc. Wt.was just 7.5 gms.

Yield was 13.39%

Wire used Dia 8.88(14g/pc), against finish Pc.Wt. 7.5 gms.

Yield was 53.53%

46.47

53.53

Yield% used

108 N S International

Page 5: Case Study of Productivity and yield Improvement of a Single Part Using Kaizen … · 2020. 5. 29. · Case Study of Productivity and yield Improvement of a Single Part Using Kaizen

1. Productivity was 1200 Nos./Shift with multiple machine – Increased by 30000/Shift with Single Machine

2.Yield was 13.39% – Increased by 53.57%

3.customer order increasing but not adhered – Adhered

4. High Process cost – Process Improvement done. Cost Reduced

5.Delivery Failure – no Delivery Failure

6. customer complaints were increasing – no. Customer Complaint after Process Improvement

Benefits Sharing with Customer

Cost

in R

s./P

c.

GOOD

Benefit Sharing with Customer

9876543210

Previous Cost/Pc. Present Cost/Pc.

5.6.

8.5

Team: Group Leader - Shri Dayal Singh, manager (operations), Team Leader – Shri rajinder Saini, In-charge (Production), Team Members – Shri Waseem ahmad, engineering (Qa), Shri Satish thakur, assistant In-charge (tool room) & Shri madan, Die Setter (Production).

s

Productivity and Yield Improvement of a Single Part Using Kaizen and Best Practices 109