case study: successfully designing, installing, and

25
Case Study: Successfully Designing, Installing, and Testing a Microgrid Scott Manson, Technology Director Schweitzer Engineering Laboratories, Inc.

Upload: others

Post on 02-Oct-2021

3 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Case Study: Successfully Designing, Installing, and

Case Study: Successfully

Designing, Installing, and

Testing a Microgrid

Scott Manson,

Technology Director Schweitzer Engineering Laboratories, Inc.

Page 2: Case Study: Successfully Designing, Installing, and

• Microgrid projects

• Lessons learned

• Technology advancements

• Remaining challenges

Chronological History of Microgrids

Page 3: Case Study: Successfully Designing, Installing, and

• Multifunction protection

• Remote I/O

• Metering

• Power quality monitoring

• Programmable logic

controller

• IEC 61850

• Sequence of Events records

• High-speed

communications

• Continuous

self-diagnostics

• Synchrophasors

• DC battery monitoring

• Human interface displays

• Trip and close controls

• Oscillography recorder

1984–2004 Microgrid Intelligence Multifunction Microprocessor Relays

Evolve Rapidly

Page 4: Case Study: Successfully Designing, Installing, and

2002 – Motor Oil Hellas Korinthos, Greece

Centralized

Microgrid

ControlsFront-End

Processing

Relay Relay Relay Relay Relay

2,500

Relays

Utility

Loads

Front-End

Processing

Page 5: Case Study: Successfully Designing, Installing, and

• Front-end processing facilitates scaled

architecture and subcycle communications

• Crosspoint switch enables subcycle

load shedding

• Subcycle load shedding allows seamless

islanding

2002 – Motor Oil Hellas Speed Is Essential for Seamless Islanding!

Page 6: Case Study: Successfully Designing, Installing, and

2002 – Motor Oil Hellas Lessons Learned

Crosspoint Switch

Trigger

Inputs

Contingency Loads Selected to Shed

1 2 3 4 5 6

G1 Trip X X

G2 Trip X X

G3 Trip X X

G4 Trip X X X

Bus Tie Trip X X X

f

t CB Opens

Load-

Shedding

Outputs

Quantity of IEDs1 10 100 1,000 10,000

0

20

402002 2015

Closed Loop

Load-Shedding

Time (ms)

Page 7: Case Study: Successfully Designing, Installing, and

2006 – Saudi Aramco Shaybah, Saudi Arabia

Plant 3

(69 kV AIS)

Plant 2

(115 kV GIS)

Plant 2

(230 kV GIS)

Plant 1

(230 kV GIS)

Page 8: Case Study: Successfully Designing, Installing, and

2006 – Saudi Aramco Factory Acceptance Tests Improved With

Hardware-in-the-Loop Testing

Controller

Inputs

ControllerStatus

Controls

Dynamic

Simulation

System

Outputs

Page 9: Case Study: Successfully Designing, Installing, and

Generation Runback Making Turbine Respond at Speed of Inverter

MW

t

Contingency Detected (breaker trips)60 MW (actual load)

30 MW (runback target MW load)

Signal Sent by Generation-Shedding System

Maximum Runback MW Setpoint

Speed

Reference

Speed Feedback

Speed ControlValve

Control

Runback Reference

Runback

Selector

Valve

Page 10: Case Study: Successfully Designing, Installing, and

Dynamic Behavior Requires

Modeling Mechanical and

Electrical Systems

0.96

1.0

Power (pu)

Frequency (pu)

1.0

Steady-State

Droop Line

3

21

Transient Governor

Behavior

Governor

Frequency

Set Point

Page 11: Case Study: Successfully Designing, Installing, and

System Synchronization Safely Reconnecting Islanded Grids

Page 12: Case Study: Successfully Designing, Installing, and

Graphical Interfaces Teach Operators to Dispatch Grid Differently

Page 13: Case Study: Successfully Designing, Installing, and

Battery

CFE

(Mexico)

AEP

(U.S.A.)

Local Distribution

Inverter

Google®

2008 – Presidio, Texas 4 MW NaS Battery Microgrid Controls

Page 14: Case Study: Successfully Designing, Installing, and

Short-Term

Capacity Limit

Long-Term

Capacity Limit

Inverter-Based

Generation

Q

P

Q

P

Rotating

Generators

2008 – Presidio, Texas Inverters Are Not as Robust as

Rotating Machinery

Page 15: Case Study: Successfully Designing, Installing, and

Google®

2010 – BHP Worsley Alumina Collie, Australia

Electric Utility

STG-A STG-B STG-C STG-D

15 MW

STG-C Grid Island

Page 16: Case Study: Successfully Designing, Installing, and

55

54

53

52

51

50

49

48

47

Fre

qu

en

cy (

Hz)

Time (ms relative)

120,000 140,000 160,000 180,000 200,000 220,000

47

48

49

50

51

52

53

54

55

120000 140000 160000 180000 200000 220000

Fre

qu

en

cy (

Hz)

Time ( ms relative)

Steam turbine and boiler

control scheme changed

under islanded conditions

2010 – BHP Worsley Alumina Islanded Steam Turbines and Electronic

Loads May Not Mix!

Fre

qu

en

cy (

Hz)

47

48

49

50

51

52

53

54

55

0 50 100 150 200 250 300

Time (seconds)

10:17:35.701

Circuit Breaker

Open

10:18:43

Automatic

Synchronization Start

10:19:10.928

Underfrequency Level 1

Shed 0.93 MW

10:19:25

Oscillation

Start Governor

10:21:38

Isochronous Mode

10:21:46.929

Generator Trip

Page 17: Case Study: Successfully Designing, Installing, and

2010 – BHP Worsley Alumina Intentional Disconnecting at PCC

Increases Reliability

df/dt (Hz/s)

X1 X2

Y1

Y2

–X1–X2

–Y1

–Y2

Δf (Hz)

Trip

Region 1

Trip

Region 2

Page 18: Case Study: Successfully Designing, Installing, and

• Large system designs

were scaled down in

cost and complexity

• Early participation in

designs reduced costs

Protective

Relays

Local

Visualization

Engineering

Applications

Thin Clients

IO modules

Microgrid Controller

Layer 1 – Protection

Layer 2 – Controls

Layer 3 – Visualization

Layer 3.5 – DMZ

Physical Security Perimeter

Firewalls

Firewalls

Layer 3.5 – Business Networks

Firewalls

In-Depth Cybersecurity Is Required!

2012 – Chevron Jack

and St. Malo Offshore Platforms

Complexity Required to Be

Scaled Down for Remote Facility

Page 19: Case Study: Successfully Designing, Installing, and

• User inputs

System inertia

Load composition factors

• Live relay measurements

Loads and source metering (kW)

Frequency and df/dt triggers

Inertia Compensation and

Load Tracking (ICLT) Balances Power Mismatch for

Underfrequency Events!

98

0

97

96

95

94

93

92

91

Po

we

r (M

W)

5 10 15 20Time (seconds)

Electrical Power

Mechanical Power

Speed

Page 20: Case Study: Successfully Designing, Installing, and

Outside

Networks

Security GatewayVisualization, Economic

Optimization, Engineering Tools

Central Controllers

Communications Equipment

Current and

Voltage TransformersCircuit Breakers

Power Generation

Controllers

Protective

RelaysRemote I/O

Metering and

Power Quality

Layer 4

Layer 3

Layer 2

Layer 1

Layer 0

Tier 2 and 3

MGCS

Tier 1

MGCS

Microgrid

2014 – University of California

San Diego, California

Industrial and utility technology,

procedures, modeling, testing, and

commissioning methods were a perfect fit!

Page 21: Case Study: Successfully Designing, Installing, and

21 3 4 5

1.8 MW

12 kV

69 kV

Phase 2

CS CS

Relay Relay

Phase 3

RelayV RelayV

V

Relay

V

Relay

V

Relay

Phase 1

V

Relay

1.8 MW

Automation

Controller

G2

Relay

G1

Relay

Relay

500 kW

Battery

System

Relay

Phase 2

1 MW

Battery

System

Relay

2015 – Borrego Microgrid 2.0 PCC Is Protection Challenge

Page 22: Case Study: Successfully Designing, Installing, and

Protection

Meter and I/O

Protection

Meter and I/O

Tesla

Battery

Synchronous Condenser

and Flywheel

Protection

Meter and I/O

RTAC

Computer

HMI

HMISecurity

Gateway

WAN

Relay

Relay

Computer

Relay

Clamp-On

CTs for

Monitoring

Key Points

of Grid

Microgrid

Controls

Serial

Data

Diode

Portable Control Center

Utility PCC Diesel

GeneratorsWind TurbinesPhotovoltaic

Solar Cells

Monitoring

and

DispatchMonitoring

and

Dispatch

Communication

Three-Phase Power

CT and PT

Relay Relay

Relay

Portable Control Center Protection Panels in Portable Control Center

Synchronous

Condenser and Flywheel

Tesla Battery

2, 250 kW, 4 hour

RTAC

Computer

HMI

HMISecurity

Gateway

WAN

Computer

Microgrid

Controls

Serial

Data

Diode

2016 – Navy Seabees Microgrid Controls, Protection, and

Security Can Be Small and Portable

Page 23: Case Study: Successfully Designing, Installing, and

Modern Microgrids Automatically

Separate, Survive, and Synchronize

Islanded

Operation

Synchronization

Reintegration Reconfiguration

Separation

Grid-Tied

Operation

Page 24: Case Study: Successfully Designing, Installing, and

Questions?

Page 25: Case Study: Successfully Designing, Installing, and

References

[1] E. R. Hamilton, J. Undrill, P. S. Hamer, and S. Manson, “Considerations for Generation in an Islanded Operation,” proceedings of the 56th Annual Petroleum and Chemical Industry Conference, Anaheim, CA, September 2009.

[2] A. Al-Mulla, K. Garg, S. Manson, and A. El-Hamaky, “Case Study: A Dual-Primary Redundant Automatic

Decoupling System for a Critical Petrochemical Process,” proceedings of the 6th Annual Petroleum &

Chemical Industry Committee Europe Conference, Barcelona, Spain, May 2009.

[3] S. Manson, A. Upreti, and M. J. Thompson, “Case Study: Smart Automatic Synchronization in Islanded Power

Systems,” proceedings of the Power and Energy Automation Conference, Spokane, WA, March 2013.

[4] S. Manson, A. Khatib, M. Checksfield, and P. Duffield, “Case Study: Simultaneous Optimization of Electrical

Grid Stability and Steam Production,” proceedings of the 61st Annual Petroleum and Chemical Industry

Technical Conference, San Francisco, CA, September 2014.

[5] S. Manson, G. Zweigle, and V. Yedidi, “Case Study: An Adaptive Underfrequency Load-Shedding System,”

proceedings of the 60th Annual Petroleum and Chemical Industry Technical Conference, Chicago, IL,

September 2013.

[6] S. Manson, B. Kennedy, M. Checksfield, “Solving Turbine Governor Instability at Low Load Conditions,”

proceedings of the 62nd Annual Petroleum and Chemical Industry Technical Conference, Houston, TX,

October 2015.