case study - the life-cycle of commissioning for new ... · commissioning service provider: ......
TRANSCRIPT
Owner/Facility Manager: Dan Kailey and Matt BurkholderNational Geospatial-Intelligence Agency (NGA)
Commissioning Service Provider: Mike Luffred Eaton Energy Solutions, Inc. (Eaton)
Design Professional: Charlie RowlandRTKL/KlingStubbins, Joint Venture (JV)
Construction Manager: Mike LloydClark Balfour Beatty Construction - NCE, A Joint Venture (CBB)
The Life-Cycle of Commissioning for New ConstructionA Case Study at NGA Campus East
Approved for Public Release on PA #14-091
Agenda
• NCE Project Scope• NCE Commissioning Scope• Commissioning Process• Perspectives from
– Owner– Facility Manager– Design Professional– General Contractor– Commissioning Provider
Approved for Public Release on PA #14-091
NGA Campus East (NCE) Project Scope
• New headquarters facility for the National Geospatial-Intelligence Agency
• Fort Belvoir North Area• Located in Springfield, Virginia• Largest BRAC 2005 building
project – 2.4 million ft2 - $1.7 billion
• Largest U.S. Government LEED 2.2 Gold project
• Eaton was Commissioning Authority (CxA) for all phases
– Design through warranty– LEED 2.2 Enhanced Cx
• Also provided third party QA
Approved for Public Release on PA #14-091
NGA Campus East (NCE) Project Scope
Visitor Control Center (VCC)
Parking Garage
Main Office Building (MOB)
Tech Center (TECH)
Central Utility Plant (CUP)
Remote Inspection Facility (RIF))
Approved for Public Release on PA #14-091
NCE Commissioning Scope
• Commissioning Scope of work– Commissioning Authority (CxA) for Campus
• Main Office Building• Central Utility Plant• Technology Center• Parking Garage• Visitor Control Center• Remote Inspection Facility• Water Feature Pump House
Approved for Public Release on PA #14-091
NCE Commissioning Scope
• Cx Scope of work (continued)• Implemented ASHRAE Guideline 0-2005 Commissioning• In pursuit of LEED 2.2 Credits EA 3.1 (Enhanced Cx)• Services Covered
– Mechanical, Electrical and Plumbing– Building Automation & Power Management Systems– Building Envelope Systems– Life Safety Systems– Elevators / Escalators– Data / Voice Systems– Acoustical
Approved for Public Release on PA #14-091
How well have we done?
• Commissioning Definitions• LEED Requirements• How the Cx Project Leadership Team (PLT) worked
within the project’s governance– Phases of Commissioning– Use of Metrics and “Macro” Schedule tools to manage
expectations of senior leaders not familiar with the “black box” of the Cx process
– Successes and Challenges
Approved for Public Release on PA #14-091
Definition of Commissioning
“The Commissioning Process is a quality-oriented process for achieving, verifying, and documenting that the performance of facilities, systems, and assemblies meets defined objectives and criteria.”
- ASHRAE Guideline 0-2005
• The process is performed specifically to ensure that the finished facility operates in accordance with the Owner’s Project Requirements (OPR) and the construction documents.
• To be successful the commissioning process must be integrated into all phases and major elements of the project
Approved for Public Release on PA #14-091
• Prerequisite – Fundamental Cx required for LEED– Review owner’s requirements, develop plan, create final report– Verify performance and incorporate Cx into construction documents– Counts for Energy and Atmosphere Prerequisite 1
• Point Credit – Enhanced Cx– Before Construction: Conduct design review, review submittals– After Construction: Verify training of O&M staff, review operations
after turnover– Counts for Energy and Atmosphere Credit 3
LEED – Fundamental(during construction)
LEED – Enhanced (before construction)
LEED – Enhanced(after construction)
LEED for New Construction v 2.2
Approved for Public Release on PA #14-091
Project governance
Program Board
Executive Leadership Team
Project Leadership
Team: Site
Project Leadership
Team: CUP/Tech
Project Leadership
Team: Main Bldg
Project Leadership
Team: Commissioning
Project Leadership
Team: Infrastructure
Project Leadership
Team:Ops/Deployment
Project Leadership
Team: Turnover
Stakeholders Represented at each level:USACE, NGA, DPW, Designer, Builder, IT, Security, Deployment, Facility Ops
The Commissioning project leadership team (PLT) was comprised of a cross section of members fromseveral other PLT’s and successfully integrated the Cx process into all major project facilities andelements through the resources provided by the independent third Party Commissioning Authority.
Approved for Public Release on PA #14-091
Commissioning PLT
Approved for Public Release on PA #14-091
Commissioning Process Flow
Approved for Public Release on PA #14-091
Commissioning Phases
Approved for Public Release on PA #14-091
Levels of Inspection & TestingPre Functional Inspections &
Tests
CONSTRUCTION TESTING Participants
Level 1 Factory Witness Tests - Where called for in Specifications JV, QC, QA, CxA, NGA
Level 2a On-Site Equipment Delivery Inspections QC, QA
Level 2b Installed Equipment Inspections (PFC) JV, CxA, QA, QC
Level 2c Prior to Energy or Fluid Connection Inspections CxA, QA, QC
Level 2d Manufacturers Factory Start-up and Inspections CxA, QA, QC
Level 2e As required for mechanical systems complete TAB and TAB Verification JV, CxA, QA, QC
Functional Performance Tests ACCEPTANCE TESTING Participants
Level 3 Functional Performance Tests - With Loads CxA, QA, QC, NGA
Level 3 Functional Performance Tests - Controls and External Monitoring Inspections CxA, QA, QC, NGA
Integrated Systems Testing INTEGRATED SYSTEM TESTING Participants
Level 4 Identify reliability constraints that result from normal and adverse operation tests.
All Parties
Level 4 Prove the Engineer's design for capacity and failover. All Parties
Level 4a Enhanced testing to verify monitoring and control system accuracy All Parties
Acronyms:AE – Design Professional
CxA – Eaton
QA – U.S. Army Corps of Engineers Quality Assurance
QC – CBB Quality Control and Commissioning Coordinator
Approved for Public Release on PA #14-091
Main Office Building Sequence
C
K LJ
F
North Bar
South Bar
Constructed, Commissioned & turned over by “Segment”
Approved for Public Release on PA #14-091
Metrics and “Macro” Schedule Tools
• Helped manage senior leader expectations of progress for functional (acceptance) testing
• Used during Construction Phase of Cx• Tracking Mechanisms Evolved
– Macro schedule included both electrical and mechanical functional testing activities
– Metrics included deferred testing– Cx PLT wrote two simple Cx fact sheets targeted to senior
leadership providing updates of the NCE Commissioning Program
Revised 4/14/2011Mechanical H G F E D * C * Ellipse * B* A *
Projected U&P Dates 4/22/2011 4/29/2011 5/6/2011
Segment TAB Work Completed 4/21/2011 4/22/2011
Segment TAB Report Completed by CBB/Pierce 4/26/2011 5/3/2011
Segment TAB Report Submitted to USACE 3/9/2010 4/9/2010 10/25/2010 10/27/2010 1/14/2011 3/2/2011 4/4/2011 4/27/2011 5/4/2011
RTU PFCs Completed by CBB/Pierce 4/13/2011 4/8/2011 4/22/2011 4/22/2011
RTU PFCs Submitted to USACE 7/15/2010 7/23/2010 9/3/2010 10/1/2010 3/25/2011 4/15/2011 4/10/2011 4/24/2011 4/24/2011
RTU PFCs Approved 4/1/2011 4/22/2011 4/17/2011 5/1/2011 5/1/2011
BAS Pre‐PVT Completed by CBB/Pierce/Siemens 4/12/2011 4/15/2011 4/8/2011 4/20/2011 4/20/2011
BAS Pre‐PVT Submitted 7/8/2010 7/23/2010 2/1/2011 2/1/2011 4/14/2011 4/17/2011 4/10/2011 4/22/2011 4/22/2011
BAS Pre‐PVT Approved 4/21/2011 4/24/2011 4/17/2011 4/29/2011 4/29/2011
FPT Start 5/15/2010 7/13/2010 10/5/2010 10/8/2010 11/15/2010 11/23/2010 2/21/2011 2/11/2011 4/11/2011
FPT RTU Start Date 4/4/2011 4/25/2011 4/19/2011 4/29/2011 5/2/2011
FPT Floor Level Completion (VAVs) 9/3/2010 9/3/2010 9/3/2010 9/3/2010 2/18/2011 2/27/2011 4/8/2011 4/15/2011 4/22/2011
FPT Completion RTU 4/29/2011 4/29/2011 4/29/2011 4/29/2011 4/29/2011 5/20/2011 5/14/2011 5/24/2011 5/27/2011
BAS PVT Completion 2/23/2011 2/23/2011 4/29/2011 4/29/2011 5/6/2011 5/27/2011 5/21/2011 5/31/2011 6/3/2011Deferred Water TAB & Verification Complete 440 system 4/27/2011 4/27/2011 4/27/2011 4/27/2011 4/27/2011 4/27/2011 4/27/2011 4/27/2011 4/27/2011 3/28/20011
Deferred Water TAB & Verification Complete Hot Water system 4/30/2011 4/30/2011 4/30/2011 4/30/2011 4/30/2011 4/30/2011 4/30/2011 4/30/2011 4/30/2011 4/12/2011Deferred Water TAB & Verfi cation Complete 520 system 7/8/2011 7/8/2011 7/8/2011 7/8/2011 7/8/2011 7/8/2011 7/8/2011 7/8/2011 7/8/2011 5/2/2011
Deferred Air TAB Verification Complete 5/16/2011 5/23/2011 5/30/2011 6/6/2011 6/13/2011 6/20/2011 5/27/2011 6/3/2011 6/10/2011 5/9/2011
Deferred Air FPT Requirements Complete 5/23/2011 5/30/2011 6/6/2011 6/13/2011 6/20/2011 6/27/2011 6/3/2011 6/10/2011 6/17/2011 5/16/2011
ElectricalU&P PFCs Approved 10/1/2010 9/14/2010 10/1/2010 10/1/2010 9/23/2010 9/23/2010 9/23/2010 10/7/2010 9/23/2010
FPT Completion (less lighting) 10/5/2010 10/5/2010 10/11/2010 11/12/2010 11/12/2010 12/10/2010 11/12/2010 12/6/2010 11/12/2010
PMS PVT Complete 1/12/2010 1/13/2010 7/23/2010 8/6/2010 12/23/2010 12/23/2010 12/23/2010 12/23/2010 12/23/2010
S. Bar Cx Completion vs. APT E Float: ‐105 APT E 1/14/2011 4/29/2011
N. Bar Cx Completion vs. APT F Float: ‐63 APT F 4/1/2011 6/3/2011
Deferred Cx Completion vs. APT F Float: ‐98 7/8/2011
General Notes1. Deferred water TAB i s expected to be completed by 4/29/2011 in the CUP and 7/8/2011 i n the MOB (~100 work days)
2. Deferred Water TAB Verifi cati on wil l be completed immediately fol lowing Deferred TAB of each indivi dual system.
3. **Start Date for Deferred a ir TAB Va l idation and Rooftop Unit FPTs i s based upon the removal of ALL partitions in the MOB on approximatel y 5/9/2011 a fter fi re ala rm tes ting i s completed.
4. Deferred air TAB cons is ts of rooftop AHUs , toi let exhaus t, s ta irwel l pressuri zati on fans , miscel laneous exhaus t; 5 work days per segment.
5. Deferred FPT Requirements (rooftop AHUs , toi l et exhaus t, miscel laneous exhaus t) wil l most l ikel y occur during off‐hours ; 5 work days per segment.
6. RTU FPTs are projected to take about 5 weeks to complete per segment minus deferred i tems.
7. Firs t floor of the North Bar along with the el l ipse may not be completed and turned over unti l 4/25/2011; this wil l impact completion of fi rs t floor TAB, Mechanical FPTs and Mechanica l PVTs .
8. PFCs wil l be tracked as completed once they are s igned off by both EMC and USACE.
9. *The dates shown above for the north bar compl eti on do NOT incl ude the work associa ted with the amenities areas on the 1s t floor.
LEGENDWORKING ITEM U&P Deferred COMPLETE Sub. Comp.
MOB Commissioning ScheduleSegment
Complete
U&P
Complete
Complete
Complete
Complete
Complete
Complete
Sub. Comp.
**Deferred Start Date
Complete
Deferred
Sub. Comp.
CompletionS. Bar Cx CompleteN. Bar Cx Complete
Deferred Cx Complete
Approved for Public Release on PA #14-091
Successes & ChallengesSuccesses
• Complied with LEED v2.2 CxCredits
• Independent 3rd Party CxA: – Helped lead a fully integrated
project team to ensured the Cxprocess was integrated into all major project facilities and elements
– Enforced compliance of acceptance testing
– Developed clear metrics for functional and integrated system testing which helped managed expectations of owner
– Captured lessons learned – Was contracted to provide post
construction Cx services during warranty period
Challenges• Phased construction presented
several challenges – Operations contractor not fully
mobilized during first major project turnover
– Major facilities were not functionally tested under load and permanent power before turnover
– Final TAB report not yet complete
• CxA was not selected until mid-design phase
• Final Report not yet completed
Approved for Public Release on PA #14-091
Owner Perspective – Design & Construction
Successes• Provided valuable experience
and lessons learned for application in future construction projects
• Thorough testing of mission-critical power and cooling systems provided a very high level of confidence in their reliability (subsequently proved by unexpected utility power losses – June 2012 Derecho)
• Provided a treasure trove of information for ongoing O&M of the Facility
Challenges• Had to overcome USACE’s
concern of managing a third party CxA – not their typical approach
• Speed and complexity of the project created inevitable schedule crunch –commissioning wasn’t on the construction contractor’s schedule in enough detail
• The last 5% of a project takes 95% of the effort – we’re not quite finished yet
Approved for Public Release on PA #14-091
Owner Perspective – Operations & Maintenance
Successes• Base operations support
contractor attained invaluable training and experience through participation in Cxactivities
• Provided opportunity to move into continuous CX
Challenges• How do we take the mountain
of data provided from the Construction CX task and translate that into a Continuous CX process?
• The delay in completing CX makes the transition to continuous CX more challenging
Approved for Public Release on PA #14-091
Design Professional Perspective
Successes
• Innovative Systems– Chilled Beams– Dual Temperature Chilled
Water System– “Pond” Standby Water
Storage– ETFE Roof System
• False Loading– Modified boiler/chiller
systems
Challenges
• Phased Turnover– Balancing Issues– System Turndown Issues
• Late Changes to the Program
Approved for Public Release on PA #14-091
General Contractor Perspectives
• Requirements for Successful Commissioning– Schedule
• Early development of construction schedule• Must incorporate ALL Cx activities with realistic
durations– Need to know the scope of the Cx process– Must have all the test scripts early
• Use the schedule to manage the commissioning process
– Review and update the schedule weekly
Approved for Public Release on PA #14-091
General Contractor Perspectives
• Requirements for Successful Commissioning– Early Involvement of All Stakeholders
• Owner, Design Team, Construction Manager, General Contractor, Subcontractors, Commissioning Authority
– Clearly defined roles and responsibilities » Who documents the process» Who has authority to make changes» Who has authority to sign off on items
– Accountability between stakeholders– Develop relationships with all stakeholders
» Know each members’ goals and risks
Approved for Public Release on PA #14-091
General Contractor Perspectives
• Requirements for Successful Commissioning– Subcontractor Management
• Demand a dedicated commissioning team from appropriate subcontractors
• Meet regularly with principals of the subcontractors– Hold each sub accountable for their
responsibilities– Listen to their ideas and welcome their input
Approved for Public Release on PA #14-091
General Contractor Perspectives
• Requirements for Successful Commissioning– Staffing
• Incorporate appropriate staffing into all budgets and cost proposals
• Evaluate the requirements for each staff position– Select the “Right” person for each position– Delicate balance between project management,
field supervision, and engineering
Approved for Public Release on PA #14-091
General Contractor Perspectives
• Takeaways– Commissioning begins prior to proposal submission– Early collaboration of all stakeholders– Develop a realistic construction schedule that
incorporates all commissioning activities– Manage the subcontractors and hold them accountable– Drive the schedule
Approved for Public Release on PA #14-091
Commissioning Provider Perspective
Successes
• Many Potential Show Stoppers Issues were Identified Early
• Warranty Issues Seem Minimal
• Results of Post Construction Occupancy Survey Favorable
• BRAC Mission was Accomplished
Challenges
• Security Requirements• Multiple Tracking Tools Used• Scale of Project• Overcoming Contractors
Preconceived Notions of Cx
Approved for Public Release on PA #14-091
Wrapping UpLessons Learned• Cx is a defined process that needs to be followed.• Clearly defined Cx expectations early to all. In particular the
definition of DONE.• Cx is only as effective as the commitment of the owner’s
representative.• UFGS master specs need to be updated to reflect current
Cx standards.• Increase facility management engineering capabilities to
address increase in complexity of facilities.• Partnering works.• “Quality is a victim of schedule”.
Approved for Public Release on PA #14-091
Questions
Approved for Public Release on PA #14-091
References
• ASHRAE Guideline 0-2005 – The Commissioning Process
• USGBC LEED® for New Construction & Major Renovations version 2.2 – October 2005
Approved for Public Release on PA #14-091
Approved for Public Release on PA #14-091