    Structure Name Structural Part Casting DateConcrete

    Quantity (Cum)Remarks

    Floculator Base (Road Side),+1.2Level

    17-May-16 250

    Floculator Middle wall (RiverSide),+1.2 Level

    14-May-16 60

    Floculator Slope wall (RiverSide),+1.2 Level

    14-May-16 100

    Floculator North wall (RoadSide),+1.2 Level

    31-May-16 55

    Receiving Well Base,+2.7 Level 20-May-16 15

    Receiving Well Base,+3.35 Level 15-May-16 90

    Rapid Sand Filter Base Casting,Zone-2 (Road side) 22-May-16 324

    Back Wash Wast Tank Wall Casting +3.7 to +5.0 19-May-16 92

    Wall Casting +1.4 to +3.5 (RiverSide)

    10-May-16 65

    Wall Casting +1.4 to +3.5 (RoadSide)

    15-May-16 95

    Levelling Concrete10 May 2016 to

    10 June 201670

    Base Casting20 May 2016 to

    20 July 2016300

    Floculator

    Receiving Well

    Casting Date for May' 16

    CONSTRUCTION OF MODUNAGHAT WATER TREATMENT PLANT & PATENGABOOSTER PUMP STATION (CWSISP/W-1)

    Dewatering Building

    Pump House