cba final project 2002 gyorgyi cicas ; jose l. aguirre; po-hsin lin cba of operating photovoltaic...

18
CBA FINAL PROJECT 2002 Gyorgyi Cicas ; Jose L. Aguirre; Po-Hsin Lin CBA OF OPERATING PHOTOVOLTAIC SYSTEM IN PITTSBURGH

Post on 18-Dec-2015

213 views

Category:

Documents


1 download

TRANSCRIPT

Page 1: CBA FINAL PROJECT 2002 Gyorgyi Cicas ; Jose L. Aguirre; Po-Hsin Lin CBA OF OPERATING PHOTOVOLTAIC SYSTEM IN PITTSBURGH

CBA FINAL PROJECT 2002 Gyorgyi Cicas ; Jose L. Aguirre; Po-Hsin Lin

CBA OF OPERATING PHOTOVOLTAIC SYSTEM IN

PITTSBURGH

Page 2: CBA FINAL PROJECT 2002 Gyorgyi Cicas ; Jose L. Aguirre; Po-Hsin Lin CBA OF OPERATING PHOTOVOLTAIC SYSTEM IN PITTSBURGH

CBA FINAL PROJECT 2002 Gyorgyi Cicas ; Jose L. Aguirre; Po-Hsin Lin

Abstract

•Objective and Motivation

•Introduction

•Description of the Model

•Results

•Conclusions and Future Plans

Page 3: CBA FINAL PROJECT 2002 Gyorgyi Cicas ; Jose L. Aguirre; Po-Hsin Lin CBA OF OPERATING PHOTOVOLTAIC SYSTEM IN PITTSBURGH

CBA FINAL PROJECT 2002

Objective & Motivation

•Monetary Cost

•Efficiency

•Availability

•Feasibility

•Environmental Impacts

•CMU Solar House 2002

Gyorgyi Cicas ; Jose L. Aguirre; Po-Hsin Lin

Page 4: CBA FINAL PROJECT 2002 Gyorgyi Cicas ; Jose L. Aguirre; Po-Hsin Lin CBA OF OPERATING PHOTOVOLTAIC SYSTEM IN PITTSBURGH

CBA FINAL PROJECT 2002 Gyorgyi Cicas ; Jose L. Aguirre; Po-Hsin Lin

Renewable EnergyData from the U.S.

•Renewable energy 8% out of total energy

•Solar Energy 1%

Reference: Web Site: http://www.eia.doe.gov/emeu/ Main Products of the Office of Energy Markets and End Use: Annual energy review: renewable energy section 10.5

Page 5: CBA FINAL PROJECT 2002 Gyorgyi Cicas ; Jose L. Aguirre; Po-Hsin Lin CBA OF OPERATING PHOTOVOLTAIC SYSTEM IN PITTSBURGH

CBA FINAL PROJECT 2002 Gyorgyi Cicas ; Jose L. Aguirre; Po-Hsin Lin

CMU Solar House 2002

Page 6: CBA FINAL PROJECT 2002 Gyorgyi Cicas ; Jose L. Aguirre; Po-Hsin Lin CBA OF OPERATING PHOTOVOLTAIC SYSTEM IN PITTSBURGH

BP (conventional)

Combiner Boxes

Charge Controller

Batteries

AC

INV

DC

120V

Switch

PV System

Page 7: CBA FINAL PROJECT 2002 Gyorgyi Cicas ; Jose L. Aguirre; Po-Hsin Lin CBA OF OPERATING PHOTOVOLTAIC SYSTEM IN PITTSBURGH

CBA FINAL PROJECT 2002 Gyorgyi Cicas ; Jose L. Aguirre; Po-Hsin Lin

PV SystemKey components

•Conventional Solar panels has 36 cells (photovoltaic cells)

•Self regulating panels

•DC-inverter-AC

Page 8: CBA FINAL PROJECT 2002 Gyorgyi Cicas ; Jose L. Aguirre; Po-Hsin Lin CBA OF OPERATING PHOTOVOLTAIC SYSTEM IN PITTSBURGH

CBA FINAL PROJECT 2002 Gyorgyi Cicas ; Jose L. Aguirre; Po-Hsin Lin

Cost Benefit Analysis

Comparison

PV System For a Typical House In Pittsburgh

• House covered 100% by PV System

• Hybrid covering the months with highest sun irradiation and House With Classical Grid-Based System

Page 9: CBA FINAL PROJECT 2002 Gyorgyi Cicas ; Jose L. Aguirre; Po-Hsin Lin CBA OF OPERATING PHOTOVOLTAIC SYSTEM IN PITTSBURGH

CBA FINAL PROJECT 2002 Gyorgyi Cicas ; Jose L. Aguirre; Po-Hsin Lin

Maximum Sun Irradiation Factor (energy) KWh/ m2

For the Northeast of the U.S. is 6 KWh/m2

Web Site: http://www.eia.doe.gov/emeu/

Page 10: CBA FINAL PROJECT 2002 Gyorgyi Cicas ; Jose L. Aguirre; Po-Hsin Lin CBA OF OPERATING PHOTOVOLTAIC SYSTEM IN PITTSBURGH

CBA FINAL PROJECT 2002 Gyorgyi Cicas ; Jose L. Aguirre; Po-Hsin Lin

Description of ModelSelection Solar

TechnologySelection Solar

Technology

Electricity Consumption Data

Electricity Consumption Data

Characteristics of the Solar Panel

(inefficiencies, Max. Capacity)

Yearly Consumption of Avg. Household

[KWh/yr]

Monthly & Daily Consumption in the Months

of High Solar Irradiation (choice of 3 and 5) [Watts]

Requirement of Energy considering the Solar Insolation Factor for the Region [Watts]

Additional Factor from PV Panels (heating vs efficiency)

Total No. of Panels from Total Requirement of electricity (Watts) / Net Production per panel (Total Area of Solar Irradiation)

Geographical Factors

Geographical Factors

Page 11: CBA FINAL PROJECT 2002 Gyorgyi Cicas ; Jose L. Aguirre; Po-Hsin Lin CBA OF OPERATING PHOTOVOLTAIC SYSTEM IN PITTSBURGH

CBA FINAL PROJECT 2002 Gyorgyi Cicas ; Jose L. Aguirre; Po-Hsin Lin

Factors for Cost EstimatesCost of Panels [ $ / panel]

~ $ 500 USD

No. of Panels ~ 44

Approximate Cost of Panels $ 22,000 USD

Cost of Batteries [ $ / Battery]

No. of Batteries ~ 40% of No. of Panels

Total Cost of Batteries $ 8,500 USD

Additional Installation Costs

Wiring, rack for modules, connection devices, labor work

and transportation

~ $ 12,345 USD

Total Investment Cost $ 42, 850 USDYear 2002

Total Investment Cost $ 42, 850 USDYear 2002

Additional Costs

Additional Cost for Electricity from Grid $ 525 ~ $ 430 USD / yr (with no change in consumption behavior from average household in the U.S.) Compare to the $1,000 USD of yearly spending

for future O&M Activities:Replacement of Batteries Bank every 4 Years

Cleaning Activities of Panel Array ~ $ 80 USD / YearReplacement of the whole PV System (solar panels, connectors, wiring, batteries, etc.) every 20 years

Page 12: CBA FINAL PROJECT 2002 Gyorgyi Cicas ; Jose L. Aguirre; Po-Hsin Lin CBA OF OPERATING PHOTOVOLTAIC SYSTEM IN PITTSBURGH

CBA FINAL PROJECT 2002 Gyorgyi Cicas ; Jose L. Aguirre; Po-Hsin Lin

Case PV covers only in Months with major Sun IrradiationTwo Variations: • 3 Months with highest Sun Irradiation (June, July, August)• 5 Months (May, June, July, August, September)

Assumptions for Future Improvements in Technology • 20 and 40 yr period : Improved efficiency of panels, capacity of Peak

Watts per panel, $ per panel and per battery decreases

Time, [year]Purchase cost,

[$]Install.

cost, [$]Maint.

cost, [$]Total cost, [2002yr $]

Total cost, [nom. $]

0 41,245 1,600 0 43,479 43,4791 0 0 80 714 7502 0 0 80 714 7883 0 0 80 714 8274 8,500 0 80 9,214 11,2005 0 0 80 714 91248 1,035 0 80 1,750 18,19949 0 0 80 714 7,80250 0 0 80 714 8,192

Total cost of usage of grid connected PV system $165,453.65 $500,905.85

Page 13: CBA FINAL PROJECT 2002 Gyorgyi Cicas ; Jose L. Aguirre; Po-Hsin Lin CBA OF OPERATING PHOTOVOLTAIC SYSTEM IN PITTSBURGH

CBA FINAL PROJECT 2002 Gyorgyi Cicas ; Jose L. Aguirre; Po-Hsin Lin

Case 2 PV covers only in Months with major Sun Irradiation

The actual average cost of Electricity from the Grid ~ $ 0.10 / KWh

Classic System

YearCost of

UseMaintenance

Total Cost

Cost of Classic System

Final Total Cost

Nominal Values NPV

Benefit of using solar

Cost / Benefit

Cost of KWh

[$/ KWh]

1 2002 -$42,845 $0 -$42,845 -$503 -$43,348 -$45,412 $454 -$96 $5.0262 2003 $0 -$80 -$80 -$503 -$583 -$640 $454 -$1 $0.0683 2004 $0 -$80 -$80 -$503 -$583 -$671 $454 -$1 $0.0684 2005 -$8,500 -$80 -$8,580 -$503 -$9,083 -$10,940 $454 -$20 $1.05340 2041 -$15,866 $0 -$15,866 -$503 -$16,370 -$105,162 $454 -$36 $1.89841 2042 $0 -$80 -$80 -$503 -$583 -$3,925 $454 -$1 $0.06842 2043 $0 -$80 -$80 -$503 -$583 -$4,112 $454 -$1 $0.06843 2044 $0 -$80 -$80 -$503 -$583 -$4,308 $454 -$1 $0.06844 2045 -$971 -$80 -$1,051 -$503 -$1,555 -$12,029 $454 -$3 $0.18045 2046 $0 -$80 -$80 -$503 -$583 -$4,728 $454 -$1 $0.06846 2047 $0 -$80 -$80 -$503 -$583 -$4,953 $454 -$1 $0.06847 2048 $0 -$80 -$80 -$503 -$583 -$5,189 $454 -$1 $0.06848 2049 -$971 -$80 -$1,051 -$503 -$1,555 -$14,489 $454 -$3 $0.18049 2050 $0 -$80 -$80 -$503 -$583 -$5,694 $454 -$1 $0.06850 2051 $0 -$80 -$80 -$503 -$583 -$5,965 $454 -$1 $0.068

-$131,945 -$25,162.50 -$157,108 -$439,479 $22,678.00 -6.9277494 -$0.364

Solar System

Page 14: CBA FINAL PROJECT 2002 Gyorgyi Cicas ; Jose L. Aguirre; Po-Hsin Lin CBA OF OPERATING PHOTOVOLTAIC SYSTEM IN PITTSBURGH

CBA FINAL PROJECT 2002 Gyorgyi Cicas ; Jose L. Aguirre; Po-Hsin Lin

Conclusions and Further Estimations – I.

Estimated cost of electricity produced by the grid

connected PV system ~ 38¢/kWh

Data from studies: 25¢/kWh – 50¢/kWh

Conventional power plant: 11¢/kWh

Page 15: CBA FINAL PROJECT 2002 Gyorgyi Cicas ; Jose L. Aguirre; Po-Hsin Lin CBA OF OPERATING PHOTOVOLTAIC SYSTEM IN PITTSBURGH

CBA FINAL PROJECT 2002 Gyorgyi Cicas ; Jose L. Aguirre; Po-Hsin Lin

Conclusions and Further Estimations – II.

Benefits?

• Increased siting flexibility

• Decreased installation lead time

• Installations cause fewer disruptions

• Improved aesthetics

• Increased reliability

• Portability

• Progressive "green" image

Page 16: CBA FINAL PROJECT 2002 Gyorgyi Cicas ; Jose L. Aguirre; Po-Hsin Lin CBA OF OPERATING PHOTOVOLTAIC SYSTEM IN PITTSBURGH

CBA FINAL PROJECT 2002 Gyorgyi Cicas ; Jose L. Aguirre; Po-Hsin Lin

Conclusions and Further Estimations – III.

Progressive "green" image

“Low environmental impact—they are quiet and nonpolluting (no greenhouse gas emissions).”/Federal Energy Management Program/

• We can avoid the environmental impacts (e.g. GHG emission) of the estimated yearly 2,500 - 3,600 kWh electricity production

• Is this significant compared to the environmental impacts of the PV system?

Page 17: CBA FINAL PROJECT 2002 Gyorgyi Cicas ; Jose L. Aguirre; Po-Hsin Lin CBA OF OPERATING PHOTOVOLTAIC SYSTEM IN PITTSBURGH

CBA FINAL PROJECT 2002 Gyorgyi Cicas ; Jose L. Aguirre; Po-Hsin Lin

Conclusions and Further Estimations –IV.

How to make it feasible?

• Net metering

• Renewable Energy Pilot Program

• 10% federal tax credit and accelerated depreciation

on the PV system

• Continuous technology improvement

Page 18: CBA FINAL PROJECT 2002 Gyorgyi Cicas ; Jose L. Aguirre; Po-Hsin Lin CBA OF OPERATING PHOTOVOLTAIC SYSTEM IN PITTSBURGH

CBA FINAL PROJECT 2002 Gyorgyi Cicas ; Jose L. Aguirre; Po-Hsin Lin

Further Information

http://www.eren.doe.gov/sunlab

http://www.sandia.gov/pv

http://www.arc.cmu.edu/carnegie_team

http://www1.sedo.energy.wa.gov.au/renewable.asp

http://www.trfund.com/sdf

http://www.bccf.org

http://www.sustainable.energy.sa.gov.au/pages/advisory/renewables/types/solar/technologies

http://www.solarpaces.org/resources/technologies.html

http://www.solarserver.de/solarmagazin