1 The Construction Specifications Institute Audio Sessions Session 1 DOCUMENTS USED DURING CONSTRUCTION AND PROJECT DELIVERY METHODS Construction Contract Administration Education Program Certified Construction Contract Administrator (CCCA) Preparatory Course 2011 1 www.csinet.org This presentation is protected by US and International copyright laws. Reproduction, distribution, display and use of this presentation without written permission of the speaker and The Construction Specifications Institute is prohibited. © The Construction Specifications Institute 2011 The Construction Specifications Institute is a Registered Provider with The American Institute of Architects Continuing Education Systems. Credit earned on completion of this program will be reported to CES Records for AIA members. Certificates of Completion for non-AIA members available on request. This program is registered with the AIA/CES for continuing professional education. As such, it does not include content that may be deemed or construed to be an approval or endorsement by the AIA of any material of construction or any method or manner of handling, using, distributing, or dealing in any material or product. Questions related to specific materials, methods, and services will be addressed at the conclusion of this presentation. AIA 2

Upload: danganh

Post on 17-Apr-2018

214 views

Category:

Documents


1 download

TRANSCRIPT

Page 1: CCCA Session 1 - Documents Used During Construction ...eo2.commpartners.com/users/csi/downloads/CCCA_Session_1.pdfconditions and agreements in common use ( AIA Documents A101, A201,

1

The Construction Specifications Institute

Audio Sessions

Session 1

DOCUMENTS USED DURING CONSTRUCTION AND PROJECT

DELIVERY METHODS

Construction Contract Administration

Education ProgramCertified Construction Contract Administrator (CCCA)

Preparatory Course2011

1www.csinet.org

This presentation is protected by US and International copyright laws. Reproduction, distribution, display and use of this presentation without written permission of the speaker and The Construction Specifications Institute is prohibited.

© The Construction Specifications Institute 2011

The Construction Specifications Institute is a Registered Provider with The AmericanInstitute of Architects Continuing Education Systems. Credit earned on completion ofthis program will be reported to CES Records for AIA members. Certificates ofCompletion for non-AIA members available on request.

This program is registered with the AIA/CES for continuing professional education.As such, it does not include content that may be deemed or construed to be anapproval or endorsement by the AIA of any material of construction or any method ormanner of handling, using, distributing, or dealing in any material or product.Questions related to specific materials, methods, and services will be addressed atthe conclusion of this presentation.

AIA

2

Page 2: CCCA Session 1 - Documents Used During Construction ...eo2.commpartners.com/users/csi/downloads/CCCA_Session_1.pdfconditions and agreements in common use ( AIA Documents A101, A201,

2

Source Material• The CCCA examination tests candidates' knowledge and understanding of

the following source materials: • Construction Contract Administration Practice Guide • Project Delivery Practice Guide• MasterFormat™• SectionFormat/PageFormat• UniFormat™ • General Conditions of the Contract and Contract Forms

– AIA A201-2007 General Conditions of the Contract for Construction – EJCDC C-700-2007 Standard General Conditions of the Construction Contract – AIA B201 – 2007 Standard Form of Architect’s Services – EJCDC E-500 – 2002 Agreement Between Owner and Engineer for Professional

Services

• Agreement Forms – AIA A101-2007 Standard Form of Agreement Between Owner and Contractor – EJCDC C-520-2007 Suggested Form of Agreement Between Owner and

Contractor for Construction Contract (Stipulated Price)

• 3

Source Material• Exam Summary The proportion of the exam dedicated to each subject area is as follows:

• Study Unit No.1: Documents Used During Construction and Project Delivery Methods 6%

• Study Unit No. 2: Roles and Responsibilities 4%

• Study Unit No. 3: Preconstruction 5%

• Study Unit No. 4: Procurement references the PDPG 12.1 8%

• Study Unit No. 5: Meetings 5%

• Study Unit No. 6: Submittals 8%

• Study Unit No. 7: Site Visits, Observation, and Inspection 10%

• Study Unit No. 8: Quality Assurance and Quality Control 6%

• Study Unit No. 9: Interpretations and Modifications 16%

• Study Unit No. 10: Executing the Work 6%

• Study Unit No. 11: Claims and Disputes 8%

• Study Unit No. 12: Measurement and Payment 7%

• Study Unit No. 13: Project Closeout 8%

• Study Unit No. 14: Facility Management references the PDPG 14.1 3%

4

Page 3: CCCA Session 1 - Documents Used During Construction ...eo2.commpartners.com/users/csi/downloads/CCCA_Session_1.pdfconditions and agreements in common use ( AIA Documents A101, A201,

3

From the Study Guide• This can be a difficult examination for the unprepared candidate.

• The exam thoroughly tests the candidate’s knowledge and comprehension of the Construction Contract Administration Practice Guide and related CSI publications and the general conditions and agreements in common use (AIA Documents A101, A201, B201 and EJCDC C700, C-520, E-500).

• Candidates who took the CDT exam prior to 2009 will have studied different source material and should take care to review all sections of the Construction Contract Administration Practice Guide as well as the updated source materials referenced above.

5

The Construction Specifications Institute

Learning Objectives• To define construction contract administration

• To list the basic principles in each of the Contract Documents and their relationships

• To recognize Contract Document requirements for each major construction contract administration activity

• To describe the importance of feedback to improve future construction documents

• To distinguish between the various types of construction contracts, how construction contract administration is affected by each type of contract, and the roles and responsibilities change with each project delivery method

6

Page 4: CCCA Session 1 - Documents Used During Construction ...eo2.commpartners.com/users/csi/downloads/CCCA_Session_1.pdfconditions and agreements in common use ( AIA Documents A101, A201,

4

The Construction Specifications Institute

Session OutlineSTUDY GUIDE: Subject Matter Area No. 1 6%

DOCUMENTS USED DURING CONSTRUCTION AND PROJECT DELIVERY METHODS

7

A. Definition of Construction Contract Administration

B. Contractual Documents Used in Construction Contract Administration1. Owner-A/E agreements2. Owner-Contractor agreements3. Conditions of the contract4. Division 01 – General

Requirements5. Division 02-49 specifications6. Contract drawings7. Addenda

8. Modifications9. Notice to Proceed

C. Contract Documents Relationships

Continued on following slide

The Construction Specifications Institute

Session OutlineSTUDY GUIDE: Subject Matter Area No. 1

DOCUMENTS USED DURING CONSTRUCTION AND PROJECT DELIVERY METHODS

8

D. Contract Document Requirements for Each Major Construction Contract Administration Activity

1. Meetings (session 5)2. Submittals (session 6)3. Site visits, observations, and

inspection (session 7)4. Quality assurance and quality

control (session 8)5. Interpretations and modifications

(session 9)

6. Executing the work (session 10)7. Claims and disputes (session 11)8. Measurements and payment (12)9. Project closeout (session 13)

E. Project Feedback

F. Contract Administration and Project Delivery Methods

1. Single prime contract2. Multiple prime contracts3. Construction management

contracts in both advisor or agent and constructor roles

4. Design-build contract5. Owner-build contract

Continued from previous slide

Page 5: CCCA Session 1 - Documents Used During Construction ...eo2.commpartners.com/users/csi/downloads/CCCA_Session_1.pdfconditions and agreements in common use ( AIA Documents A101, A201,

5

The Construction Specifications Institute 9

DOCUMENTS USED DURING CONSTRUCTION AND PROJECT

DELIVERY METHODSSTUDY GUIDE AREA NO. 1

The Construction Specifications Institute

DEFINITION OF CONSTRUCTION CONTRACT ADMINISTRATION

STUDY GUIDE: Submit Matter Area No. 1 - A.

10

Page 6: CCCA Session 1 - Documents Used During Construction ...eo2.commpartners.com/users/csi/downloads/CCCA_Session_1.pdfconditions and agreements in common use ( AIA Documents A101, A201,

6

Construction Contract Administration• Activities necessary to

effect and determine fulfillment of contract requirements by parties to construction contract

Construction Contract Administration Practice Guide: 1 Introduction

11

The Construction Specifications Institute

CONTRACTUAL DOCUMENTS USED IN CONSTRUCTION CONTRACT

ADMINISTRATIONSTUDY GUIDE: Submit Matter Area No. 1 – B.

12

1. Owner-A/E agreement2. Owner-Contractor agreement3. Conditions of the contract4. Division 01 – General Requirements5. Divisions 02-49 – Specifications6. Contract drawings7. Addenda8. Modifications9. Notice to proceed

Page 7: CCCA Session 1 - Documents Used During Construction ...eo2.commpartners.com/users/csi/downloads/CCCA_Session_1.pdfconditions and agreements in common use ( AIA Documents A101, A201,

7

Owner-A/E Agreements• Advise and consult Owner

• Interpret contract documents

• Observe the work

• Review and certify payments to Contractor

• Review and approve submittals

• Prepare modifications

• Prepare revisions to Contractor’s initial punch list

• Inspect to determine date of– Substantial completion

– Final completion

Construction Contract Administration Practice Guide: 3.3.1.1

13

Owner-Contractor Agreements• Project delivery methods

• Number of contracts

• Basis of payment

• Contract document list

• Contract time

• Contract price/sum

• Payment procedures

Construction Contract Administration Practice Guide: 3.3.1.1

14

Page 8: CCCA Session 1 - Documents Used During Construction ...eo2.commpartners.com/users/csi/downloads/CCCA_Session_1.pdfconditions and agreements in common use ( AIA Documents A101, A201,

8

Conditions of the Contract• Includes

– General conditions are typically one of the standardized forms published by a professional association

– Supplementary conditions are typically written to modify the general conditions for the specific project

• Establishes responsibilities for– Owner

– A/E - Construction contract administration

– Contractor - Construction project management

Construction Contract Administration Practice Guide: 3.3.1.3

15

TypicalGeneral Conditions Provisions

• General provisions and definitions

• Owner’s responsibilities

• Contractor’s responsibilities

• A/E’s responsibilities

• Subcontractors (definition and relationships)

• Construction by Owner or separate contractors

16

Construction Contract Administration Practice Guide: 3.3.1.3

Continued on following slide

Page 9: CCCA Session 1 - Documents Used During Construction ...eo2.commpartners.com/users/csi/downloads/CCCA_Session_1.pdfconditions and agreements in common use ( AIA Documents A101, A201,

9

TypicalGeneral Conditions Provisions

Continued from previous slide

• Changes in the work

• Contract time

• Payments to Contractor and completion of work

• Protection of persons and property

• Insurance and bonds

• Correction, removal, or acceptance of defective work

• Miscellaneous provisions

• Suspension of work and termination of contract

• Claims and disputes

17

Construction Contract Administration Practice Guide: 3.3.1.3

Typical Supplementary Conditions Provisions

• Performance

• Responsibilities of certain parties

• Project related insurance requirements

• Progress payment arrangements

• Wage rate requirements

• Equal employment opportunity requirements

• Other project specific requirements

18

Construction Contract Administration Practice Guide: 3.3.1.3

Page 10: CCCA Session 1 - Documents Used During Construction ...eo2.commpartners.com/users/csi/downloads/CCCA_Session_1.pdfconditions and agreements in common use ( AIA Documents A101, A201,

10

Division 01 – General Requirements• Expands, amplifies and customizes following on project

specific basis– Administrative requirements

– Procedural requirements

– Temporary facilities and controls

• Governs execution of work specified in Divisions 02-49

• Basic rights and responsibilities in general conditions, including supplementary conditions

19

Construction Contract Administration Practice Guide: 3.3.1.4

Division 01 Sections• 01 00 00 GENERAL

REQUIREMENTS

• 01 10 00 SUMMARY– 01 11 00 Summary of Work

– 01 12 00 Multiple Contract Summary

– 01 14 00 Work Restrictions

– 01 18 00 Project Utility Sources

20

• 01 20 00 PRICE AND PAYMENT PROCEDURES– 01 21 00 Allowances

– 01 22 00 Unit Prices

– 01 23 00 Alternates

– 01 24 00 Value Analysis

– 01 25 00 Substitution Procedures

– 01 26 00 Contract Modification Procedures

– 01 29 00 Payment Procedures

Construction Contract Administration Practice Guide: Figure 3.3

Page 11: CCCA Session 1 - Documents Used During Construction ...eo2.commpartners.com/users/csi/downloads/CCCA_Session_1.pdfconditions and agreements in common use ( AIA Documents A101, A201,

11

Division 01 Sections

21

• 01 30 00 ADMINISTRATIVE REQUIREMENTS– 01 31 00 Project

Management and Coordination

– 01 32 00 Construction Progress Documentation

– 01 33 00 Submittal Procedures

– 01 35 00 Special Procedures

• 01 40 00 QUALITY REQUIREMENTS– 01 41 00 Regulatory

Requirements

– 01 42 00 References

– 01 43 00 Quality Assurance

– 01 45 00 Quality Control

Construction Contract Administration Practice Guide: Figure 3.3

Division 01 Sections

22

• 01 50 00 TEMPORARY FACILITIES AND CONTROLS– 01 51 00 Temporary Utilities

– 01 52 00 Construction Facilities

– 01 53 00 Temporary Construction

– 01 54 00 Construction Aids

– 01 55 00 Vehicular Access and Parking

– 01 56 00 Temporary Barriers and Enclosures

– 01 57 00 Temporary Controls

– 01 58 00 Project Identification

• 01 60 00 PRODUCT REQUIREMENTS– 00 61 00 Common Product

Requirements

– 01 62 00 Product Options

– 01 64 00 Owner Furnished Products

– 01 65 00 Product Delivery Requirements

– 01 66 00 Product Storage and Handling RequirementsConstruction Contract Administration

Practice Guide: Figure 3.3

Page 12: CCCA Session 1 - Documents Used During Construction ...eo2.commpartners.com/users/csi/downloads/CCCA_Session_1.pdfconditions and agreements in common use ( AIA Documents A101, A201,

12

Division 01 Sections

23

• 01 70 00 EXECUTION AND CLOSEOUT REQUIREMENTS– 01 71 00 Examination and

Preparation

– 01 73 00 Execution

– 01 74 00 Cleaning and Waste Management

– 01 75 00 Starting and Adjusting

– 01 76 00 Protecting Installed Construction

– 01 77 00 Closeout Procedures

– 01 78 00 Closeout Submittals

– 01 79 00 Demonstration and Training

Construction Contract Administration Practice Guide: Figure 3.3

Division 01 Sections

24

• 01 80 00 PERFORMANCE REQUIREMENTS– 01 81 00 Facility

Performance Requirements

– 01 82 00 Facility Substructure Performance Requirements

– 01 83 00 Facility Shell Performance Requirements

– 01 84 00 Interiors Performance Requirements

– 01 85 00 Conveying Equipment Performance Requirements

– 01 86 00 Facility Services Performance Requirements

– 01 87 00 Equipment and Furnishings Performance Requirements

– 01 88 00 Other Facility Construction Performance Requirements

– 01 89 00 Site Construction Performance Requirements

Construction Contract Administration Practice Guide: Figure 3.3

Page 13: CCCA Session 1 - Documents Used During Construction ...eo2.commpartners.com/users/csi/downloads/CCCA_Session_1.pdfconditions and agreements in common use ( AIA Documents A101, A201,

13

Division 01 Sections

25

• 01 90 00 LIFE CYCLE ACTIVITIES– 01 91 00 Commissioning

– 01 92 00 Facility Operation

– 01 93 00 Facility Maintenance

– 01 94 00 Facility Decommissioning

Construction Contract Administration Practice Guide: Figure 3.3

Division 02-49 – Specifications • Identifies specific requirements for each material or

systems along with relevant standards

• Indicates submittal information required

• Specify QC and QA provisions

• Indicates requirements for product storage, handling, and installation

• Indicates specific sequencing or scheduling requirements

• Specifies product warranties

• Indicates requirements for preparation, installation, and protection

• Other specifics of material or system being specified

26

Construction Contract Administration Practice Guide: 3.3.1.5

Page 14: CCCA Session 1 - Documents Used During Construction ...eo2.commpartners.com/users/csi/downloads/CCCA_Session_1.pdfconditions and agreements in common use ( AIA Documents A101, A201,

14

Contract Drawings • Graphic representations of

work

• Shows – Location

– Materials

– Dimensions

– Size

– Interrelationship of materials

• Drawings are complementary with specifications

27

Construction Contract Administration Practice Guide: 3.3.1.6

Addenda and Modifications• Written or graphic changes that clarifies, revises, adds, or

deletes information

• Addenda – In procurement documents or in previous addenda before contract is executed

• Modifications – In contract documents after contract is executed

28

Construction Contract Administration Practice Guide: 3.3.1.7 – 3.3.1.8

Page 15: CCCA Session 1 - Documents Used During Construction ...eo2.commpartners.com/users/csi/downloads/CCCA_Session_1.pdfconditions and agreements in common use ( AIA Documents A101, A201,

15

Notice to Proceed• When Owner is satisfied that pre-construction documents

have been submitted after contract is executed, Owner issues notice to proceed directing Contractor to begin work

• Lists date work is authorized to commence and establishes beginning of contract time

• Includes number of calendar days or date of substantial completion

29

Construction Contract Administration Practice Guide: 3.2

The Construction Specifications Institute

CONTRACT DOCUMENT RELATIONSHIPS

STUDY GUIDE: Submit Matter Area No. 1 - C.

30

Page 16: CCCA Session 1 - Documents Used During Construction ...eo2.commpartners.com/users/csi/downloads/CCCA_Session_1.pdfconditions and agreements in common use ( AIA Documents A101, A201,

16

Contract Documents Defined• Written and graphic documents prepared and assembled by

A/E for communicating the project design for construction and administering the construction contract

• Legal basis of the contract

• Describes the construction (work) that results from performing services, furnishing labor, and supplying and incorporating materials and equipment into the construction

31

Construction Contract Administration Practice Guide: 1.3

Contract Documents• Contracting requirements

– Agreement

– Conditions of the contract

– Revisions, clarifications, and modifications

• Specifications– Written requirements for the work

– Defines quality requirements for products, materials, and workmanship

– Establishes requirements for administering and performance

• Drawings – Graphic illustrations of the physical form of work to be performed

– Show quantitative extent and relationships of elements to one another

32

Construction Contract Administration Practice Guide: 1.3.1

Page 17: CCCA Session 1 - Documents Used During Construction ...eo2.commpartners.com/users/csi/downloads/CCCA_Session_1.pdfconditions and agreements in common use ( AIA Documents A101, A201,

17

The Construction Specifications Institute

CONTRACT DOCUMENTS REQUIREMENTS FOR EACH MAJOR

CONSTRUCTION CONTRACT ADMINISTRATION ACTIVITY

STUDY GUIDE: Submit Matter Area No. 1 – D.

33

1. Meetings 2. Submittals3. Site visits, observation, and inspection4. Quality assurance and quality control5. Interpretations and modifications6. Executing the work7. Claims and disputes8. Measurement and payment9. Project closeout

Meetings (Session 5)• Preconstruction

– Procedural

– Site mobilization

– Utility coordination

– Authorities having jurisdiction

• Progress

• Contractor/subcontractor

• Preinstallation

• Closeout

34

Construction Contract Administration Practice Guide: 4

Page 18: CCCA Session 1 - Documents Used During Construction ...eo2.commpartners.com/users/csi/downloads/CCCA_Session_1.pdfconditions and agreements in common use ( AIA Documents A101, A201,

18

Submittals (Session 6)• Administrative and procedural requirements contained in

– General conditions

- Requires Contractor to prepare, review and forward submittals to A/E

- Clarifies A/E’s role in using professional judgment to review, approve, or take other appropriate action

– Division 01 – General Requirements

- Stipulates amount of review time by A/E- Contractor should allow sufficient time for A/E’s review, rejection,

and re-review without causing delay

• Should not include requests for substitution

• Are not contract documents

• Important part of quality assurance

35

Construction Contract Administration Practice Guide: 5

Categories of Submittals• Preconstruction

• Construction– Action

– Informational

– Closeout

– Maintenance

• Project closeout

36

Construction Contract Administration Practice Guide: 5

Page 19: CCCA Session 1 - Documents Used During Construction ...eo2.commpartners.com/users/csi/downloads/CCCA_Session_1.pdfconditions and agreements in common use ( AIA Documents A101, A201,

19

Site Visits, Observations, and Inspections(Session 7)

• Basic to quality control is that participants have certain responsibilities for making observations and inspections– Observe – Perceive, notice,

see

– Inspection – Examine carefully and crucially, especially for defects

• Distinction between observation and inspection is important

37

Construction Contract Administration Practice Guide: 6

Authorities Having Jurisdiction (AHJ)• Federal, state, county, and city authorities oversee safety

and welfare of public

• Verifies that design complies with codes and ordinances before issuing permits

• Verifies that construction complies with codes and ordinances by site inspections

• Reject work not complying with codes and ordinances

38

Construction Contract Administration Practice Guide: 6

Page 20: CCCA Session 1 - Documents Used During Construction ...eo2.commpartners.com/users/csi/downloads/CCCA_Session_1.pdfconditions and agreements in common use ( AIA Documents A101, A201,

20

Quality Assurance (QA)Quality Control (QC)

(Session 8)• Construction is

process of executing requirements of contract documents

• Quality requirements established by contract documents

39

Construction Contract Administration Practice Guide: 7

Interpretations and Modifications(Session 9)

• Not a substitute for clear, concise, correct, and complete contract documents

• However, extent of design and construction process is such that modifications and changes are necessary

• Contract documents are not perfect and following required of A/E – Interpretations

– Clarifications

– Modifications

40

Construction Contract Administration Practice Guide: 8

Page 21: CCCA Session 1 - Documents Used During Construction ...eo2.commpartners.com/users/csi/downloads/CCCA_Session_1.pdfconditions and agreements in common use ( AIA Documents A101, A201,

21

Interpreting Contract Documents• Well coordinated and produced contract documents

– Reduce potential for conflicts

– Need for contract interpretations and modifications

– Information stated clearly without conflicts

– Drawings and specifications should be complementary

• Conflicts within contract documents require interpretations and modifications

41

Construction Contract Administration Practice Guide: 8

Standard Contracts• Define contract documents as complementary

• State what is required by one is required by all

• Establishes A/E (Initial Decision Maker) as impartial interpreter of contract documents

• Requires A/E (or IDM) to render decisions according to intent of contract documents

• When contract documents are interpreted, contents of drawings and specifications must be considered together

• Require modifications made according to a specified process

42

Construction Contract Administration Practice Guide: 8

Page 22: CCCA Session 1 - Documents Used During Construction ...eo2.commpartners.com/users/csi/downloads/CCCA_Session_1.pdfconditions and agreements in common use ( AIA Documents A101, A201,

22

Requests for Interpretations (RFI)• Contracts typically require A/E, as

interpreter of contract documents, to respond to requests for– An interpretation

– Information that is missing or in conflict

• Requests for interpretations should not be used to– Substitute a product for one specified

– Attempt to transfer Contractor’s responsibility for timely and thorough review

43

Construction Contract Administration Practice Guide: 8

Contract Modifications• Modifications that change

contract sum or time– Change orders

– Construction change directive

• Modifications that do not change contract sum or time– Minor changes in the work

– Architects supplemental instructions

– Field orders

44

Construction Contract Administration Practice Guide: 8

Page 23: CCCA Session 1 - Documents Used During Construction ...eo2.commpartners.com/users/csi/downloads/CCCA_Session_1.pdfconditions and agreements in common use ( AIA Documents A101, A201,

23

Executing the Work (Session 10)

• Supervision of construction– Contractor responsible for supervision of the work

– Complying with contract documents

– Quality assurance and quality control procedures

• Coordinating construction activities– Issues related to coordinating the work

– Coordination drawings

• Sequencing the work– Scheduling

• Field engineering– Surveying

– Layout

45

Construction Contract Administration Practice Guide: 9

Executing the Work• Contractor record keeping

– Daily reports

– Use of photographs and video

– Use of forms and log forms

– Filing and retrieval of documentation

– Posting modifications to the contract documents

– Record documents

46

Construction Contract Administration Practice Guide: 9

Page 24: CCCA Session 1 - Documents Used During Construction ...eo2.commpartners.com/users/csi/downloads/CCCA_Session_1.pdfconditions and agreements in common use ( AIA Documents A101, A201,

24

Projects are Successful When• Completed on time

• Within budget

• All claims resolved

47

Construction Contract Administration Practice Guide: 10

Claims and Disputes (Session 11)• Interpretation or modification may become a claim

• Unresolved claims may lead to disputes

• Claims are initially requests for adjustments in contract sum or time

48

Construction Contract Administration Practice Guide: 10

Page 25: CCCA Session 1 - Documents Used During Construction ...eo2.commpartners.com/users/csi/downloads/CCCA_Session_1.pdfconditions and agreements in common use ( AIA Documents A101, A201,

25

Contractor Claims• Conditions contrary to those indicated or shown in contract

documents may be initiated as a claim• Changed conditions include

– Active interference by Owner or A/E– Conditions beyond control of Contractor or Owner– Unknown or concealed conditions that affect extent of work– Modifications made to contract documents– Errors or omissions in contract documents

• Contractor is required to provide documentation that changed condition– Was not foreseeable at time of pricing– Resulted in demonstrable damages

• Claims may be submitted by Contractor on behalf of subcontractors and suppliers

49

Construction Contract Administration Practice Guide: 10

Owner Claims• Belief that value of work received is not commensurate with

contract sum• Increased costs because of actions or inactions by Contractor

• Claims that are grounds for withholding payment– Correction of non-conforming or defective work – Failure to clean– Repair of damages to existing property– Liquidated or compensatory damages for late performance– Ineffective management and/or control of work resulting in added costs

for- Inordinate number of submittal reviews- Reviews of substitution requests- Interferences with Owner’s operations- Additional site visit, inspections, and

related administrative time

50

Construction Contract Administration Practice Guide: 10

Page 26: CCCA Session 1 - Documents Used During Construction ...eo2.commpartners.com/users/csi/downloads/CCCA_Session_1.pdfconditions and agreements in common use ( AIA Documents A101, A201,

26

Resolving Claims• Standard Contracts typically stipulate A/E or initial decision

maker will resolve claim

• Once claim is documented and understood, A/E may generate written preliminary response summarizing– Essence of claim

– Identifies any concerns requiring reconciliation

– Establishes proposed schedule for resolving claim

• Justification often apparent from outset

• Such claims can be handled with less effort by promptly addressing issues and negotiating settlement if possible

• Claims involving adjustments in contract sum or time require support documentation

51

Construction Contract Administration Practice Guide: 10

Periodic Progress Payments(Session 12)

• Standard contracts typically establishes procedures for periodic progress payment to the Contractor

52

• Typical procedure– Contractor prepares

application for payment and forwards to A/E

– A/E reviews and executes certificate for payment and forwards to Owner

– Owner obligated to make payment on or before time established in contract documents

Construction Contract Administration Practice Guide: 11

Page 27: CCCA Session 1 - Documents Used During Construction ...eo2.commpartners.com/users/csi/downloads/CCCA_Session_1.pdfconditions and agreements in common use ( AIA Documents A101, A201,

27

Periodic Progress Payments• When payment has been made to Contractor, Owner has

discharged Owner’s payment obligation for the work completed to date

• Contracts typically stipulates that progress payments do not constitute acceptance

• Standard contract typically includes provisions for Owner to reject the work and adjust payment accordingly

53

Construction Contract Administration Practice Guide: 11

Substantial Completion(Project Closeout - Session 13)

• Standard contracts typically define substantial completion when the project, or portion, is determined by A/E to be substantially complete for its intended use

• Substantial completion, or occupancy, does not constitute acceptance of Work not completed according to contract documents

• A/E issues certificate of substantial completion for acceptance by Owner and Contractor

54

Construction Contract Administration Practice Guide: 11

Page 28: CCCA Session 1 - Documents Used During Construction ...eo2.commpartners.com/users/csi/downloads/CCCA_Session_1.pdfconditions and agreements in common use ( AIA Documents A101, A201,

28

Final Completion• Standard contracts typically define final completion

– When Contractor has completed Contract requirements

– A/E has inspected to determine completion

– Owner has made final payment to Contractor

– Contractor has accepted final payment

55

Construction Contract Administration Practice Guide: 11

Retainage• Standard contracts typically establish procedures for

retaining a prescribed percentage of amount due for each progress payment

• Not intended to force Contractor to perform

• Protects Owner by making money available to correct

56

– Errors in estimating cost of the work

– Defective work

– To settle third party claims against Contractor before release of final release

– Latent defects discovered in portions of the work previously paid

Construction Contract Administration Practice Guide: 11

Page 29: CCCA Session 1 - Documents Used During Construction ...eo2.commpartners.com/users/csi/downloads/CCCA_Session_1.pdfconditions and agreements in common use ( AIA Documents A101, A201,

29

Withholding Payment• Standard Contracts typically give A/E right and

responsibility to withhold certification of whole or any part of application for payment to protect the Owner

• Common conditions for A/E to recommend withholding payments to protect interests of Owner– Damaged or non-conforming work requiring repair or correction

– Damaged property, adjacent to project, requiring repair or replacement

– Failure by Contractor to meet scheduled milestone or Contractor’s own approved schedule to extent that liquidated or compensatory damages may be reasonable anticipated

Continued on following slide

57

Construction Contract Administration Practice Guide: 11

Withholding PaymentContinued from previous slide

– Claims made against Owner on account of Contractor’s failure to perform

– Liens filed in connection with nonpayment of subcontractors, suppliers, laborers, and mechanics

– Failure to keep record documents current

– Cost of doing cleaning work, by Owner or others, resulting from Contractor’s failure to perform cleaning work

58

Construction Contract Administration Practice Guide: 11

Page 30: CCCA Session 1 - Documents Used During Construction ...eo2.commpartners.com/users/csi/downloads/CCCA_Session_1.pdfconditions and agreements in common use ( AIA Documents A101, A201,

30

Final Payment• Final change order balances previous payments against

final payment and final contract sum

• Final change order items may include adjustments– To unit price item quantities

– To stipulate allowances

– For liquidated damages or penalty/bonus clauses

– For testing reimbursement when Owner employs testing services and pays for only passing tests

– For reimbursement of utilities

– Adjustments for reimbursement of Owner’s expense for additional A/E services

59

Construction Contract Administration Practice Guide: 11

Project Closeout• Participant roles

• Closeout meeting

• Closeout – Demonstration of systems and equipment and training

– Starting of systems and equipment

– Project record documents

– Operations and maintenance manuals

– Commissioning

– Time of completion

– Substantial completion

– Final completion

• Post construction services

60

Construction Contract Administration Practice Guide: 12

Page 31: CCCA Session 1 - Documents Used During Construction ...eo2.commpartners.com/users/csi/downloads/CCCA_Session_1.pdfconditions and agreements in common use ( AIA Documents A101, A201,

31

The Construction Specifications Institute

PROJECT FEEDBACKSTUDY GUIDE: Submit Matter Area No. 1 - E.

61

Project Feedback• Determination should be made if interpretations and

modifications on a project were– Specific to project

– More general in nature requiring modification of A/E’s standards

• If standard detail or specification requires interpretation or clarification

62

Construction Contract Administration Practice Guide: 8.4

– A/E should review drawing or specification to prevent future need for interpretation or clarification

– Time required to make interpretation or clarification can become costly

Page 32: CCCA Session 1 - Documents Used During Construction ...eo2.commpartners.com/users/csi/downloads/CCCA_Session_1.pdfconditions and agreements in common use ( AIA Documents A101, A201,

32

Project Feedback• Should occur on a continual basis

• Purpose is to provide actual project experience to project team

• Benefits – Enhanced experience in various project types, systems, and process

– Input of valuable information for use on future projects

– Better quality assurance and control methods

– Refinement of innovative designs, materials, and construction techniques

– Identification of correctable situations for benefit of future projects

63

Construction Contract Administration Practice Guide: 8.4

The Construction Specifications Institute

CONTRACT ADMINISTRATION AND PROJECT DELIVERY METHODS

STUDY GUIDE: Submit Matter Area No. 1 – F.

64

1. Single prime contracts2. Multiple prime contracts3. Construction management contracts in

both advisor or agent and constructor roles

4. Design-build contract5. Owner-build contract

Page 33: CCCA Session 1 - Documents Used During Construction ...eo2.commpartners.com/users/csi/downloads/CCCA_Session_1.pdfconditions and agreements in common use ( AIA Documents A101, A201,

33

Contract Types(from PDPG & CH 1)

• Prime contract – Original contract between two original parties for an original purpose

• Subcontract – When either party to prime contract enters into another contract that will be part of the original purpose

Project Delivery Practice Guide: 5.6 65

Single Prime Contracts• A common form of construction contracting

• Owner has separate contracts with A/E and Contractor, but no agreement between A/E and Contractor

• A/E has agreements with consultants

• Contractor has agreements with subcontractors and suppliers, but Contractor remains solely responsible for all of the work required to fulfill the contract

• Neither Owner or A/E have contracts with subcontractors and suppliers

Project Delivery Practice Guide: 5.6.1 66

Page 34: CCCA Session 1 - Documents Used During Construction ...eo2.commpartners.com/users/csi/downloads/CCCA_Session_1.pdfconditions and agreements in common use ( AIA Documents A101, A201,

34

Single Prime Contracts• Contractor and Owner

enters into an agreement formalizing their relationship and their obligations

• Centralization of responsibility can result in simpler project scheduling and coordination

• Lines of responsibility to Owner clearly defined

Project Delivery Practice Guide: 5.6.1 67

Single Prime Contracts

Project Delivery Practice Guide: Figure 5.2 68

Page 35: CCCA Session 1 - Documents Used During Construction ...eo2.commpartners.com/users/csi/downloads/CCCA_Session_1.pdfconditions and agreements in common use ( AIA Documents A101, A201,

35

Single Prime Contracts• Typically used on

– Design-bid-build projects (D-B-B)

– Design-negotiate-build projects (D-N-B)

– Design-build projects (D-B)

Project Delivery Practice Guide: 5.6.1 69

Project Delivery Practice Guide: Figure 7.3 70

Project DeliveryDesign-Bid-Build (D-B-B)

Page 36: CCCA Session 1 - Documents Used During Construction ...eo2.commpartners.com/users/csi/downloads/CCCA_Session_1.pdfconditions and agreements in common use ( AIA Documents A101, A201,

36

Project Delivery Practice Guide: Figure 7.4 71

Project DeliveryDesign-Negotiate-Build (D-B-B)

Single Prime Contracts• A/E typically responsible for following construction contract

administration services– Represents Owner during construction

– Observes work for compliance with contract documents

– Observes project progress associated with review of Contractor’s applications for payment

– Preparation and recommendation of contract modifications

– Attends project meetings

– Inspects project to determine

- Substantial completion- Final completion

72

Construction Contract Administration Practice Guide: 1.4.1

Page 37: CCCA Session 1 - Documents Used During Construction ...eo2.commpartners.com/users/csi/downloads/CCCA_Session_1.pdfconditions and agreements in common use ( AIA Documents A101, A201,

37

Single Prime Contracts• Contractor typically responsible for following construction

project management services

73

Construction Contract Administration Practice Guide: 1.4.1

– Preparing applications for payment

– Administering subcontracts

– Purchasing

– Preparing, monitoring, updating project schedules

– Attending project meetings

– Communicating with A/E and subcontractors

– Preparing proposal requests and responding to A/E

– Issuing contract modification proposals

– Preparing and implementing safety programs

– Requesting clarifications and interpretations of contract documents

– Administering submittal process

Multiple Prime Contracts• Work is divided among several contractors, each enters into

an agreement with the Owner

• A/E may prepare a separate set of documents for each contract

• Unless a contracted entity is assigned responsibility and authority for coordination of multiple contracts, Owner must be responsible

Project Delivery Practice Guide: 5.6.2 74

Page 38: CCCA Session 1 - Documents Used During Construction ...eo2.commpartners.com/users/csi/downloads/CCCA_Session_1.pdfconditions and agreements in common use ( AIA Documents A101, A201,

38

Multiple Prime Contracts

Project Delivery Practice Guide: Figure 5.3 75

Multiple Prime Contracts• Typically used on

– Construction management projects (CMa and CMc)

– Owner-build projects (O-B)

Project Delivery Practice Guide: 5.6.2 76

Page 39: CCCA Session 1 - Documents Used During Construction ...eo2.commpartners.com/users/csi/downloads/CCCA_Session_1.pdfconditions and agreements in common use ( AIA Documents A101, A201,

39

Construction Management Contracts• Owner (CMa) or construction manager (CMc) enters into

separate contracts with multiple prime contracts

• A/E’s construction contract administration similar to design-bid-build project delivery, except administration is for multiple contracts

• Key to success is coordination of prime contractors

• Flow of communications

77

Construction Contract Administration Practice Guide: 1.4.2

– Through A/E for CMa

– Through construction manager for CMc

Project Delivery Practice Guide: Figure 7.5 78

Project DeliveryConstruction Management as

Advisor or Agent (CMa)

Page 40: CCCA Session 1 - Documents Used During Construction ...eo2.commpartners.com/users/csi/downloads/CCCA_Session_1.pdfconditions and agreements in common use ( AIA Documents A101, A201,

40

Construction Management Contracts• Construction manager as advisor or agent (CMa)

• Divides project into multiple contracts for– Procurement

– Contracts

• Provides construction project management services– May provide many services typically provided by A/E

– Represents Owner during construction

– Observes project progress associated with review of Contractor’s applications for payment

– Coordination among contracts

– Reviewing and approving contract modifications

– Attends project meetings

79

Construction Contract Administration Practice Guide: 1.4.2

Project Delivery Practice Guide: Figure 7.6 80

Project DeliveryConstruction Management as

Contractor (CMc)

Page 41: CCCA Session 1 - Documents Used During Construction ...eo2.commpartners.com/users/csi/downloads/CCCA_Session_1.pdfconditions and agreements in common use ( AIA Documents A101, A201,

41

Construction Management Contracts• Construction manager as Contractor (CMc)

– Functions as a Contractor

– Provides construction management services

– Guarantees cost of construction

– Executes subcontracts for most of construction work

• Owner may retain A/E for construction contract administration

• Construction manager provides following to A/E during design stage– Supervises construction

– Construction expertise

– Cost estimating experience

– Scheduling services

81

Construction Contract Administration Practice Guide: 1.4.2

Project Delivery Practice Guide: 7.5 and Figure 7.7 82

Project DeliveryDesign-Build (D-B)

Page 42: CCCA Session 1 - Documents Used During Construction ...eo2.commpartners.com/users/csi/downloads/CCCA_Session_1.pdfconditions and agreements in common use ( AIA Documents A101, A201,

42

Design-Build Contracts• Owner contracts with single D-B entity to design and build

project

• D-B entity may – Retain an independent A/E to provide design services

– Provide design services as part of D-B entity

• Distinction between following services may become blurred because D-B may provide both– A/E’s construction contract administration

– Contractor’s construction project management

• Owner typically retains some construction contract administration responsibilities however, those normally provided by A/E are typically provided by D-B entity

83

Construction Contract Administration Practice Guide: 1.4.3

Design-Build Contracts• D-B agreement must clearly address following

administration and management responsibilities– Construction contract administration

– Construction project management

• Administration and management responsibilities typically provided by one of following– D-B team member

– Owner retains an administrative professional to represent Owner’s interests

84

Construction Contract Administration Practice Guide: 1.4.3

Page 43: CCCA Session 1 - Documents Used During Construction ...eo2.commpartners.com/users/csi/downloads/CCCA_Session_1.pdfconditions and agreements in common use ( AIA Documents A101, A201,

43

Design-Build Contracts• A/E’s services are provided to D-B rather than Owner

– Observes work for conformance with contract documents

– Observes project progress associated with review of Contractor’s applications for payment

– Reviewing contract modifications

– May make recommendations to D-B entity

– A/E must comply with state licensing regulations

85

Construction Contract Administration Practice Guide: 1.4.3

Design-Build Contracts• D-B entity without separate agreement with Contractor

– Assumes responsibility for construction project management services

– Observes project progress associated with review of Contractor’s applications for payment

– Reviewing contract modifications

– May make recommendations to D-B entity

– A/E must comply with state licensing regulations

86

Construction Contract Administration Practice Guide: 1.4.3

Page 44: CCCA Session 1 - Documents Used During Construction ...eo2.commpartners.com/users/csi/downloads/CCCA_Session_1.pdfconditions and agreements in common use ( AIA Documents A101, A201,

44

Project Delivery Practice Guide: 7.6 and Figure 7.8 87

Project DeliveryOwner-Build (O-B)

Owner-Build Contracts• Owner provides many of Contractor’s construction

management services

• Owner may retain an A/E for design services however, amount of construction contract administration services are at Owner’s discretion other than those required by state licensing regulations

• Because Owner is providing Contractor’s construction management services, requirements for submittals, approvals, and similar activities will likely be reduced

88

Construction Contract Administration Practice Guide: 1.4.3

Page 45: CCCA Session 1 - Documents Used During Construction ...eo2.commpartners.com/users/csi/downloads/CCCA_Session_1.pdfconditions and agreements in common use ( AIA Documents A101, A201,

45

The Construction Specifications Institute

Review OutlineSTUDY GUIDE: Subject Matter Area No. 1

DOCUMENTS USED DURING CONSTRUCTION AND PROJECT DELIVERY METHODS

89

A. Definition of Construction Contract Administration

B. Contractual Documents Used in Construction Contract Administration1. Owner-A/E agreements2. Owner-Contractor agreements3. Conditions of the contract4. Division 01 – General

Requirements5. Division 02-49 specifications6. Contract drawings7. Addenda

8. Modifications9. Notice to Proceed

C. Contract Documents Relationships

Continued on following slide

The Construction Specifications Institute

Review OutlineSTUDY GUIDE: Subject Matter Area No. 1

DOCUMENTS USED DURING CONSTRUCTION AND PROJECT DELIVERY METHODS

90

D. Contract Document Requirements for Each Major Construction Contract Administration Activity1. Meetings2. Submittals3. Site visits, observations, and

inspection4. Quality assurance and quality

control5. Interpretations and modifications

6. Executing the work7. Claims and disputes8. Measurements and payment9. Project closeout

E. Project Feedback

F. Contract Administration and Project Delivery Methods1. Single prime contract2. Multiple prime contracts3. Construction management

contracts in both advisor or agent and constructor roles

4. Design-build contract5. Owner-build contract

Continued from previous slide

Page 46: CCCA Session 1 - Documents Used During Construction ...eo2.commpartners.com/users/csi/downloads/CCCA_Session_1.pdfconditions and agreements in common use ( AIA Documents A101, A201,

46

Questions?