Construction Environment, Health & Safety Plan (CEHSP) INSTRUCTIONS This Construction Environmental, Health & Safety Plan is required of each construction project at DOE’s National Renewable Energy Lab site (NREL). Each construction project (contract) requires its own CEHSP; therefore, each CEHSP must be tailored specifically to the project being conducted. This template is provided in electronic format to enable copy-and-paste functions for those subcontractors whose basic data remains unchanged, yet tailor the hazard and controls information to the particular activities/materials/location of the project at- hand. NREL recommends using a graded approach in the development of CEHSP’s. This approach determines the level of rigor for implementing the work planning and control attributes based on the importance/significance of the activity in relation to the associated hazards and consequences. The level of detail within each CEHSP and corresponding AHA(s) should be commensurate with the size, complexity and risk level of the construction project. For larger projects, the prime subcontractor may either flow down this requirement to each of its subcontractors; or serve as a control and coordination point, requiring all subcontractors’ activities to be conducted under the prime subcontractor’s solitary CEHSP. NREL’s Construction Environmental Health and Safety Manual (“CEHS Manual ”) is the governing document that accompanies the CEHSP, and must be utilized when completing this CEHSP to ensure that NREL-specific requirements are being met and incorporated into the project planning process. Your completed CEHSP is to be submitted to the NREL Contracts and Business Services office for review and concurrence by the NREL Project Manager and EHS prior to performing work. This CEHSP is 1 of 5 01/01/12 ver. 2.0

Upload: sabaro4u

Post on 03-Jan-2016

41 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Cehs Plan Template

Construction Environment, Health & Safety Plan (CEHSP)

INSTRUCTIONS

This Construction Environmental, Health & Safety Plan is required of each construction project at DOE’s National Renewable Energy Lab site (NREL).

Each construction project (contract) requires its own CEHSP; therefore, each CEHSP must be tailored specifically to the project being conducted. This template is provided in electronic format to enable copy-and-paste functions for those subcontractors whose basic data remains unchanged, yet tailor the hazard and controls information to the particular activities/materials/location of the project at-hand. NREL recommends using a graded approach in the development of CEHSP’s. This approach determines the level of rigor for implementing the work planning and control attributes based on the importance/significance of the activity in relation to the associated hazards and consequences. The level of detail within each CEHSP and corresponding AHA(s) should be commensurate with the size, complexity and risk level of the construction project.

For larger projects, the prime subcontractor may either flow down this requirement to each of its subcontractors; or serve as a control and coordination point, requiring all subcontractors’ activities to be conducted under the prime subcontractor’s solitary CEHSP.

NREL’s Construction Environmental Health and Safety Manual (“CEHS Manual”) is the governing document that accompanies the CEHSP, and must be utilized when completing this CEHSP to ensure that NREL-specific requirements are being met and incorporated into the project planning process.

Your completed CEHSP is to be submitted to the NREL Contracts and Business Services office for review and concurrence by the NREL Project Manager and EHS prior to performing work. This CEHSP is intended to be a living document; updated as necessary throughout a project as information changes or as the project progresses (e.g. – as additional Activity Hazard Analyses are developed, subcontractors added, etc.).

There are three parts to this CEHSP template. All of the sections in Part 1 are required to be completed for each construction project, regardless of the size or complexity. All of the sections in Part 2 are required to be completed, but checked and filled in as applicable for the particular project’s scope of work. Enter information in all of the fill-in blocks that are applicable. For those that are not applicable, enter “N/A” or other suitable explanation.

An Activity Hazard Analysis (AHA), Part 3, is required for all projects, regardless of the size, scope or complexity of work. This is the heart of the project’s safety information, and acts as a work control document. Every project will have at least one definable construction activity, and therefore at least one AHA. Depending upon the complexity of the project, one or several AHAs may need to be completed. In some cases, AHAs may need to be staged, in coordination with the initiation of the various phases of a project.

1 of 5 01/01/12 ver. 2.0

Page 2: Cehs Plan Template

- PART 1 – PROJECT GOVERNANCE / EMERGENCY INFORMATION -

Section 1 – Project Description and Emergency ContactsFill in the names and telephone numbers of the contact personnel for this particular project. In accordance with 10 CFR 851, the Subcontractor’s designated on-site safety representative must be knowledgeable of the project’s hazards and have the authority to correct unsafe conditions or behavior. Attach the qualifications of your safety representative for this project (see section 9). If you have subcontractors performing work on this project, list their contact information. Update as necessary throughout the project.

Note: Some projects of long duration or complexity may be required to develop an emergency response plan and conduct a drill at least once during the project, or more often as necessary.

Attach a site map showing assembly points and directions to your authorized medical facility (as the last page of your CEHSP to facilitate easy removal for transport). A copy must also be posted at your project field location. Upon award of the work, contact the Project Manager or EHS Point of Contact for electronic copies of building evacuation routes and assembly areas to include in your map(s), as needed.

Refer to Chapter 2 of the CEHS Manual for additional information.

Section 2 – Subcontractor Policy StatementEnter your Company’s health and safety policy statement. At minimum, your policy should include:

Specific statement of intent to comply with the code of federal regulations, Title 29, Part 1910, General Industry Safety and Health Standards and Part 1926, Safety and Health Standards for the Construction Industry, 10 CFR 851, Worker Safety and Health and other applicable codes and standards.

A statement that all requirements of the plan apply to all lower tier subcontractors, and must be flowed down to all subcontractors at all levels.

Statement of employee’s rights and responsibilities regarding a safe and healthful work environment in accordance with the work site OSH poster (i.e. OSHA/DOE poster or equivalent).

Statement of Stop Work Authority for all workers.

Refer to Chapter 2 of the CEHS Manual for additional information regarding program policies.

Section 3 – 10 CFR 851 Acknowledgement

Because NREL is a Department of Energy site, your company must meet the requirements of Title 10, Code of Federal Regulations, “Energy”, Part 851, “Worker Safety and Health Program” (Link to 10 CFR 851). It is your responsibility to ensure you have read and understand the actual regulatory requirements.

Refer to Chapter 2 of the CEHS Manual for additional information regarding program policies.

Section 4 – Safety Briefings and Inspection

The Subcontractor must conduct periodic safety briefings and inspections, based upon the duration and complexity of the project. Describe the frequency and initiation of safety briefings and inspections on your project at NREL.

2 of 5 01/01/12 ver. 2.0

Page 3: Cehs Plan Template

Refer to Chapter 5.0 of the CEHS Manual for additional information regarding minimally-required inspections and briefings.

- PART 2 – PROJECT CHARACTERIZATION -

Section 5 – Project Characterization

Under 10 CFR 851, all Subcontractors must identify existing and potential workplace hazards and assess the risk of associated workers injury and illness. This section will help to serve as first step in characterizing your project and the associated hazards, and will aid in the development of the AHA(s).

List the project’s Definable Work Activities: A definable work activity is a task which is separate and distinct from other tasks, has separate control requirements, and may be identified by different trades or disciplines, or it may be work by the same trade in a different environment.  Add additional lines as necessary to identify all the definable construction activities of your project. Refer to Chapter 4.0 of the CEHS Manual for additional information regarding Definable Work Activities.

Check all of the Hazards/Activities that apply to your project: The checklist in this section includes those activities which are subject to NREL-specific controls beyond what is required by OSHA standards, or have the potential to affect natural resources including storm water, wetlands, streams, air quality, vegetation and wildlife. In the left-hand column, check all activities that will be performed as part of this project. Identify your Competent Person(s) where applicable. Refer to the corresponding Chapters of the CEHS Manual for additional information on each topic area.

This checklist is presented in part for project planning and scheduling purposes, as some activities require NREL-specific permits to be acquired prior to being allowed to perform them. If your project involves an activity that has a check in the right-hand column, then your CEHSP must include a copy of your company program that addresses the controls and requirements for performing that activity at NREL. If your company does not have an established program for a particular activity, then you may attach a project-specific program/plan for performing that activity at NREL or address it in sufficient detail in a thorough AHA (however, this is not an option for OSHA-required programs). Use Section 9 of this template to list and identify attachments of your company programs, policies, procedures and/or plans. Be specific as to the chapter and/or section being reference.

Project-applicable activities that have potential environmental impacts will require NREL EHS coordination and concurrence, as identified in Chapter 18 of the CEHS Manual. The Subcontractor and all lower-tier subcontractors are responsible for implementation and compliance with all federal, state and local laws as well as NREL procedures.

Details of NREL-specific requirements are presented in the NREL “Construction Environment, Health & Safety Manual.” The subcontractor is responsible for knowing and abiding by the requirements of the CEHS Manual.

Section 6 – Project Support Features, Site Control and Logistics

Discuss important site/project control elements that you will employ on your project such as signs, barricades, fencing, briefings, sign-in/out logs, blocked exits, PPE postings, etc. For large or complex projects, attach a diagram showing: construction areas, laydown areas, staging areas, alternative exit routes, material storage areas, pedestrian routes, traffic control, material receiving areas, etc. Attach a copy of your Logistics Plan if one is required by the contract documents, or if you are providing one to

3 of 5 01/01/12 ver. 2.0

Page 4: Cehs Plan Template

better delineate your site control procedures. Use Section 9 of this template to identify which appendix the Logistics Plan appears in your CEHSP.

Section 7 –Required Training/Qualification

Check all boxes applicable to this Project’s work scope.

Where specific training is required (e.g. – OSHA mandated), the subcontractor must maintain, on-site, proof of the particular individuals meeting, and being current in, the training requirements. Identify where you will maintain those records on the NREL Site. Refer to Chapter 2.0 of the CEHS Manual for additional training requirements information.

Section 8 – Hazard Communication

Hazardous chemicals (as defined in 29 CFR 1910.1200) to be brought or used on-site are to be identified and managed appropriately. The subcontractor is responsible for maintaining an up-to-date chemical inventory (only of those chemicals brought on site), and copies of Material Safety Data Sheets (MSDS) must be maintained at the task or project support facilities and made available for review by site workers, the DOE or NREL employees.

Identify the methods you will use to inform the other employer(s) of any precautionary measures that need to be taken to protect NREL and/or other subcontractor employees during normal operating conditions and in foreseeable emergencies.

Identify the methods you will use to inform other affected workers of your labeling system if the labeling system is not readily understandable.

If your existing Hazard Communication Program addresses these requirements, you may attach a copy of it and your project-specific chemical listing instead of filling out the block in this Section (9).

Refer to Chapter 15.0 of the CEHS Manual for additional information regarding NREL’s Hazard Communication requirements.

Section 9 – Plan Attachments

A description of the qualifications (or resume) of all individuals serving as the Designated Safety Representative(s) on this project must be included in the Plan, per 10 CFR 851.

Additionally, if your project involves a hazard/activity that has a check in the right-hand column of Section 5, then your CEHSP must include a copy of your company’s program addressing that topic. Alternatively, your company may submit a project-specific plan/AHA that details your approach to addressing that topic. You are responsible for ensuring that your project-specific controls are in alignment with the NREL site requirements presented in the CEHS Manual, either via your company program or through specific controls identified in the project AHAs.

Use this Section of this template to also list any other plans(s)/procedures you are attaching to this CEHSP. Hardcopies and/or an electronic file or hyperlink to these documents must be reference here.

4 of 5 01/01/12 ver. 2.0

Page 5: Cehs Plan Template

- PART 3 – ACTIVITY HAZARD ANALYSES -

10 CFR 851, Appendix A to Part 851 – Worker Safety and Health Functional Areas, Construction Safety requires that an Activity Hazard Analysis (AHA – sometimes referred to as a Job Safety Analysis, JSA, or Job Hazard Analysis, JHA) be prepared for each separately definable construction activity (e.g., mobilization, excavations, concrete/foundations, structural steel, roofing) prior to the commencement of work. For larger projects, the primary subcontractor may either flow down this requirement to each of its lower-tier subcontractors, or serve as a single control and coordination point for all project AHA’s.

Prior to the start of each phase of work, it will be the responsibility of the subcontractor to develop a thorough AHA that details the hazards and controls for the steps associated with that phase of work, and submit it to NREL EHS for review.

If the project’s complexity and/or schedule necessitate several AHAs to be developed for different phases of the Project, the subcontractor may use the tracking table as a tool to coordinate which AHAs are in effect and which AHAs are yet to be developed.

The CEHSP template is provided in electronic format to enable copy-and-paste functions for those subcontractors whose basic data remains unchanged, yet allow for the work steps, hazard and controls information to be tailored to the particular activities/materials/location of the project at-hand. The AHA template rows can be expanded to include additional tasks, or reduced in number to accommodate changes, and to vary the final product to match the relative complexity of the project.

Refer to Chapter 4.0 of the CEHS Manual for additional information regarding NREL’s Activity Hazard Analyses requirements.

Emergency Assembly Points and Medical Map

A site map showing assembly points and directions to your authorized medical facility is to be provided (as the last page of your CEHSP to facilitate easy removal for transport). A copy must also be posted at your project field location. Upon award of the work, contact the Project Manager or EHS Point of Contact for electronic copies of building evacuation routes and assembly areas to include in your map(s), as needed.

5 of 5 01/01/12 ver. 2.0

Page 6: Cehs Plan Template

NREL CONSTRUCTION PROJECT-SPECIFIC SAFETY PLAN - PART 1

(Project Name)

Construction Environmental, Health & Safety Plan

1 of 8 01/01/12 ver. 2.0

SECTION 1 - PROJECT DESCRIPTION & EMERGENCY CONTACTS

Subcontract / Purchase Order Number

Enter subcontract and/or task order number

Project Start / End Dates Start: Complete:

Project Location Enter the work location(s) at NREL

Scope of Work Enter breakdown and description of work activities

FOR ALL EMERGENCIES CALL:

NREL Emergency Contact number: x1234 - or - (303) 384-6811 from a cell phone.

For all incidents, injuries, property damage, near-misses, work-induced illness or chemical over-exposures, the following personnel MUST be immediately contacted upon scene stabilization, but in all cases within one hour:

Project Personnel Name Phone Number(s) Email

NREL Project Manager Enter the name of NREL Project Manager Enter number: xxx-xxx-xxxx Enter: user@domain

NREL Project EHS Point of Contact

Enter the name of NREL EHS Point of Contact

Enter number: xxx-xxx-xxxx Enter: user@domain

OTHER CONTACT INFORMATION

Subcontractor Project Manager Enter the name of subcontractor Project Manager

Enter number: xxx-xxx-xxxx Enter: user@domain

Subcontractor Site Superintendent

Enter the name of subcontractor's Site Superintendent

Enter number: xxx-xxx-xxxx Enter: user@domain

Subcontractor Health & Safety Representative **

Enter the name of subcontractor health & safety representative

Enter number: xxx-xxx-xxxx Enter: user@domain

Subcontractors - Company Name Name of Designated Safety Representative ** Phone Number

Enter Subcontractor company name Enter name of individual** Enter number: xxx-xxx-xxxx

Enter Subtier company name Enter name of individual** Enter number: xxx-xxx-xxxx

Enter Subtier company name Enter name of individual** Enter number: xxx-xxx-xxxx** Attach a description of qualifications, or resume, for each Safety Representative per Section 9.0.

CEHSP REVIEWS

Reviewed & Approved by: (Subcontracted Company Officer)

Subcontractor CEHSP Reviewed & Concurred by: (NREL)

Subcontractor CEHSP Reviewed & Concurred by: (NREL)

Enter Subcontrator - Company Officer Enter NREL Project Manager or designee Enter NREL Project EHS

Signatures and dates

A map of Emergency Assembly Points and Hospital Route is attached to back of this Project Plan and posted at the work site.

Page 7: Cehs Plan Template

NREL CONSTRUCTION PROJECT-SPECIFIC SAFETY PLAN - PART 1

SECTION 2 - SUBCONTRACTOR POLICY STATEMENT

Enter here the Subcontractor’s policy on occupational safety & health (see instructions):

2 of 8 01/01/12 ver. 2.0

Page 8: Cehs Plan Template

NREL CONSTRUCTION PROJECT-SPECIFIC SAFETY PLAN - PART 1

SECTION 3 - ACKNOWLEDGMENT of 10 CFR 851

As a subcontractor to NREL, while your workers are physically located at NREL you must meet the requirements of Title 10, Code of Federal Regulations, “Energy”, Part 851, “Worker Safety and Health Program” (10 CFR 851). As such, you must be aware of, and comply with, the requirements of this regulation. (Link to 10 CFR 851)

Acknowledgment I, (the author of this CEHSP), certify that that I have read the requirements of 10 CFR 851 and attest that my firm and its sub-tier contractors will comply with the requirements of 10 CFR 851.

Yes No

MEDICAL SURVEILLANCE AND QUALIFICATION

Occupational Medicine Will you have any employees that will work on-site at NREL for 30, eight-hour days in a 12-month period, or are enrolled for any length of time in a medical or exposure monitoring program required by federal, state, or local regulations (including hearing conservation, respiratory protection, lead exposure)? Refer to the CEHS Manual, Section 3.0 for additional information.

Yes No

If yes, you will need to: 1. Comply with the occupational medicine requirements of 10 CFR 851, Appendix A 2. Provide your occupational medicine provider contact information

Clinic / Physician Enter the name and address of your company's medical provider for this project

Enter telephone number: xxx-xxx-xxxx

Enter e-mail address: user@domain

Required Medical Surveillance Task-specific medical testing

DOT/Commercial Vehicle Blood Lead Hearing Conservation Respirator User Fit For Duty Other(s) :List other(s) Substance Abuse Testing

List specific task(s) requiring medical surveillance

SECTION 4 - SAFETY BRIEFINGS AND INSPECTIONS

Safety Briefings: Discuss the conduct of safety briefings on your project at NREL

Safety Inspections:Discuss your conduct of safety inspections during this project at NREL

Refer to the CEHS Manual, Section 5.0 for additional information.

3 of 8 01/01/12 ver. 2.0

Page 9: Cehs Plan Template

NREL CONSTRUCTION PROJECT-SPECIFIC SAFETY PLAN - PART 2

SECTION 5 – PROJECT CHARACTERIZATION

Identify the project’s Definable Work Activities. (e.g., mobilization, excavations, concrete, structural steel erection, dry-walling, electrical install, painting, roofing, landscaping, etc.)

Mobilization (-describe as necessary) Anticipated Start Date

Enter Activity Anticipated Start Date

Enter Activity Anticipated Start Date

Enter Activity Anticipated Start Date

Enter Activity Anticipated Start Date

Enter Activity Anticipated Start Date

Enter Activity Anticipated Start Date

Check all of the hazards/activities below that apply to this Project. Refer to the CEHS Manual for NREL-specified controls.

Yes No Hazard/Activity with specific NREL-based control measures.

NREL Construction ESH

Manual Chapter(s)

NREL-issued Permit

required

Attach copy of Subcontractor

Program or Project Plan

addressing this activity

Asbestos use, alteration, removal or storage 13, 18 (Identify your Competent Person for Asbestos Work here)

Blocking Exits or Exit Pathways 9 Building Surface Penetration 7, 17 Confined spaces 16 Crane Use 10 (Identify your Lift Supervisor here)

Discharges to sanitary/septic system will occur 18

Energized electrical work (>50 v or > 50 mA) 6, 7 Excavation 7, 8 (Identify your Competent Person for Excavations here)

Earth disturbance of greater than one acre 13, 18

Explosives 15 Falls from elevation (work at heights > 6 feet) 11 (Identify your Fall Protection Equipment Competent Person here)

Fire protection system outage or modification 9 Flushing of waterlines, storm/sanitary lines, fire suppression systems or fire hydrants will be performed 18

4 of 8 01/01/12 ver. 2.0

Page 10: Cehs Plan Template

NREL CONSTRUCTION PROJECT-SPECIFIC SAFETY PLAN - PART 2

Hazardous Waste Storage or generation on construction site 18

Yes No Hazard/Activity with specific NREL-based control measures.

NREL Construction ESH

Manual Chapter(s)

NREL-issued Permit

required

Attach copy of Subcontractor

Program addressing this

activity

Hoisting/Rigging 10 (Identify your Hoisting/Rigging Competent Person here)

Hot work 9.0 Lasers. (Class 3B and 4) 13 Lead concerns 13 (Identify your Competent Person for Lead work here)

Lockout/Tagout (Control of Hazardous Energy) 6.0 Night work 13

Outdoor work to be performed between mid-March and mid-September 18

Pesticides and/or herbicides use or storage on site 13, 18

Radioactive materials or Ionizing radiation-generating devices 13 (Identify yourRadiation Safety Officer here)

Scaffolding 11 (Identify your scaffolding Competent Person here)

Structural Steel Erection 11 Traffic Control MUTCD Excavation near Underground Utilities 7, 8 Wetlands, drainage channels, streams, groundwater seeps occur within construction site 18

SECTION 6 - PROJECT SUPPORT FEATURES, SITE CONTROL & LOGISTICS

Check all of the following facilities and equipment that are required for safe completion of work.

Facility/Equipment Description

Project Office Describe office to be used (room/trailer, location, etc.)

Materials Receiving Location Describe (location, size, delivery times, etc.)

Portable Restrooms/wash stations Describe (number, location, etc.)

Supplementary Illumination Describe Supplementary Illumination (Type(s), indoor/outdoor, distribution, etc.)

Emergency Eyewash/Shower Describe (type, location, distribution, etc.)

First Aid Supplies Describe (type,size, location,etc.)

Fire Extinguishers Describe (type,size, location,etc.)

5 of 8 01/01/12 ver. 2.0

Page 11: Cehs Plan Template

NREL CONSTRUCTION PROJECT-SPECIFIC SAFETY PLAN - PART 2

Hazardous Material Storage Describe (materials, amounts, location, etc.)

Spill Containment/Clean-up Describe (materials, location, etc.)

Other: Enter Other Type Describe item, location, number, etc.

Other: Enter Other Type Describe item, location, number, etc.

Site Control / Logistics

Task / Location Specify your task-specific site control/access control measures below.

Enter work task and location Enter specific site/area control procedure

Enter work task and location Enter specific site/area control procedure

Enter work task and location Enter specific site/area control procedure

Check here if you are ALSO attaching a Logistics Plan for your activities. Logistics Plan is attached in Appendix #___

SECTION 7 – REQUIRED TRAINING/QUALIFICATIONS

Training Records Location: Identify where you will maintain training/certification records related to your Project at NREL:

Identify the activities involved on your project which have OSHA-required training:

Yes No

Asbestos activities

Aerial Lift Operation

Crane Operation (minimum NCCCO certification for operator)

Confined Space Entry

Electrical Work requiring NFPA 70E provisions

Electrical Work requiring CPR-trained 2nd worker

Excavation

Fall Protection Equipment

Forklift Operation/Powered Industrial Truck Use

Heavy Equipment Operation List equipment to be used:

Ladder Use

Lock-Out/Tag-Out

Noisy Operations requiring Hearing Conservation training

Scaffolding Erection, Use

Other: (List...)

6 of 8 01/01/12 ver. 2.0

Page 12: Cehs Plan Template

NREL CONSTRUCTION PROJECT-SPECIFIC SAFETY PLAN - PART 2

SECTION 8 - HAZARD COMMUNICATION (HAZCOM)

MSDS Location: Identify where you will maintain your Project Chemical list and MSDSs at NREL

Method of notifying affected NREL employees:If the chemicals you will use on the project may affect NREL employees or other subcontractor employees, describe the method you will use to notify them. Describe your method of instructing others about your labelling system, if it is nonstandard.

Refer to the CEHS Manual, Section 15 for additional information.

SECTION 9 - PLAN ATTACHMENTS

For each activity or hazard checked in Section 5, list and attach your additional corporate, site- or project-specific programs/plans.

Attachment Reference Procedure or Program

1 Project safety representative, Statement of Qualifications for: (insert name)

# List Reference Procedure or program

# List Reference Procedure or program

# List Reference Procedure or program

7 of 8 01/01/12 ver. 2.0

Page 13: Cehs Plan Template

NREL CONSTRUCTION PROJECT-SPECIFIC SAFETY PLAN – PART 3

PART 3 – ACTIVITY HAZARD ANALYSES

Complete an Activity Hazard Analysis for each of your project’s Definable Construction ActivitiesRefer to the CEHS Manual, Section 4.0 for additional information.

Note: A completed, signed AHA must be submitted to NREL EHS for review prior to the start of each phase of work, in order to proceed with that phase.

AHA Tracking Table (use is non-mandatory unless required by EHS contact)

1Enter ActivityAnticipated Start Date

Responsible subcontractor AHA Submittal Date Date AHA accepted by

NREL

2Enter ActivityAnticipated Start Date

Responsible subcontractor AHA Submittal Date Date AHA accepted by

NREL

3Enter ActivityAnticipated Start Date

Responsible subcontractor AHA Submittal Date Date AHA accepted by

NREL

4Enter ActivityAnticipated Start Date

Responsible subcontractor AHA Submittal Date Date AHA accepted by

NREL

5Enter ActivityAnticipated Start Date

Responsible subcontractor AHA Submittal Date Date AHA accepted by

NREL

6Enter ActivityAnticipated Start Date

Responsible subcontractor AHA Submittal Date Date AHA accepted by

NREL

etc (Add others as necessary)

8 of 8 01/01/12 ver. 2.0

Page 14: Cehs Plan Template

ACTIVITY HAZARD ANALYSIS

(Project Name) AHA #: (Number)

Activity Hazard Analysis REVIEWS

Reviewed & Approved by: (Subcontractor Project Manager)

Reviewed & Approved by: Subcontractor Project Superintendent)

Reviewed & Approved by: Subcontractor Safety Officer

Enter name of Subcontractor - Project Manager

Signature and date

Enter name of Subcontractor: Project Superintendent

Signature and date

Enter name of Subcontractor- Safety Officer

Signature and date

All signature blocks completed indicates authorization to perform THIS work.

Drawings Attached: Yes No

Definable Work Activity: Enter Activity Title Revision: Enter revison number or Date

Work Task Potential Hazard(s)Control Measure(s), Required Training, NREL-required Permits or

Plans, and Competent Person(s)

AHA REVIEW/PRE-JOB BRIEF ATTENDANCE ROSTERBy signing below, I agree to the following:

I agree to follow the work steps and implement the controls as written. I agree to stop work when conditions or hazards change or when I encounter unexpected conditions during the execution of work, or when work cannot be performed as written, or instructions

become unclear during execution. I confirm that I am authorized, qualified and fit to perform the work.

Worker (Print /Sign / Date) Worker (Print /Sign / Date)

Worker (Print /Sign / Date) Worker (Print /Sign / Date)

Worker (Print /Sign / Date) Worker (Print /Sign / Date)

Worker (Print /Sign / Date) Worker (Print /Sign / Date)

1 of 1 01/01/12 ver. 2.0

Page 15: Cehs Plan Template

NREL Construction Project-Specific Safety Plan

(Project Name)Emergency Assembly Points and Medical Map

1 of 1 01/01/12 ver. 2.0