CENTRAL MARKS DEPARTMENT-II(LEGAL) Our Ref.:CMD-II(L)/16:16098(Part 2) 13 01 2015 Subject : Grouping guidelines & STI for IS 16098(Part 2):2013 Grouping guidelines & STI for IS 16098 (Part 2):2013 (Structured Wall Plastics Piping Systems For Non Pressure Drainage And Sewerage) approved by DDG(ERO) were circulated to MSD, CED and all ROs/BOs vide mail dated 29 08 2014 for comments. Since then, no comments have been received. The status was reviewed by Competent Authority and it has been decided to treat the Grouping guidelines and STI approved by DDGE as final. A copy of the Grouping guidelines and STI for IS 16098 (Part 2):2013 are enclosed for ready reference. ( P S Yadav ) Sc.E Circulated to : All ROs/BOs

Upload: others

Post on 14-Feb-2021

4 views

Category:

Documents


0 download

TRANSCRIPT

  • CENTRAL MARKS DEPARTMENT-II(LEGAL)

    Our Ref.:CMD-II(L)/16:16098(Part 2) 13 01 2015

    Subject : Grouping guidelines & STI for IS 16098(Part 2):2013

    Grouping guidelines & STI for IS 16098 (Part 2):2013 (Structured Wall Plastics Piping

    Systems For Non Pressure Drainage And Sewerage) approved by DDG(ERO) were

    circulated to MSD, CED and all ROs/BOs vide mail dated 29 08 2014 for comments. Since

    then, no comments have been received. The status was reviewed by Competent Authority and

    it has been decided to treat the Grouping guidelines and STI approved by DDGE as final. A

    copy of the Grouping guidelines and STI for IS 16098 (Part 2):2013 are enclosed for ready

    reference.

    ( P S Yadav )

    Sc.E

    Circulated to : All ROs/BOs

  • DOC: STI/16098-2/ 1

    May 2014

    1 | P a g e

    SCHEME OF TESTING AND INSPECTION

    FOR CERTIFICATION OF STRUCTURED-WALL PLASTIC PIPING SYSTEMS

    FOR NON-PRESSURE DRAINAGE AND SEWERAGE

    Part 2 – Pipes and Fittings with non-smooth external surface, Type B ACCORDING TO IS 16098 (Part 2): 2013

    1. LABORATORY A laboratory shall be maintained, which shall be suitably

    equipped and staffed where different tests given in the specification shall be carried out in

    accordance with the methods given in the specification.

    2. TEST RECORDS All records of tests, inspection and calibration shall be kept in

    suitable forms approved by the Bureau.

    2.1 All testing apparatus/measuring instruments shall be periodically checked and

    calibrated and records of such checks / calibration shall be maintained.

    2.2 Copies of any records and other connected papers that may be required by the Bureau

    shall be made available at any time on request.

    3. QUALITY CONTROL - It is recommended that, as far as possible, Statistical

    Quality Control (SQC) methods may be used for controlling the quality of the product during

    production as envisaged in this Scheme (See IS 397 (Part I):1972, IS 397(Part 2):1985 and IS

    397 (Part 3) : 1980]

    3.1 In addition, efforts should be made to gradually introduce a Quality Management

    System in accordance with IS /ISO 9001 as appropriate to the activities of the organization.

    4. STANDARD MARK The Pipe shall carry the standard mark as given in column1

    of the first schedule of the licence in the form of a transfix label. The mark may also be

    applied by engraving in such a manner that it does not impair the strength of the pipe in any

    way. Marking may also be done by screen printing, inkjet printing, laser printing.

    5. OTHER MARKING In addition the following information shall be clearly marked

    in indelible ink / paint on either end of each straight length of pipe or hot embossed on white

    at intervals of not more than three metres with the following.:

    a) The manufacturer’s name and its recognized trade mark, if any: b) Diameter series & Nominal size c) Stiffness Class d) Material , e) Lot no/ Batch number in code or otherwise which will enable to trace back the

    date of production and the test records;

    f) ISI Logo, IS Code no & License No………………(CM/L ………..) and g) Made in India, if required.

  • DOC: STI/16098-2/ 1

    May 2014

    2 | P a g e

    5.0 LEVELS OF CONTROL - The tests, as indicated in Table 1 attached and at the levels

    of control specified therein, shall be carried out on the whole production of the factory which

    is covered by this scheme and appropriate records and charts maintained in accordance with

    paragraph 2.0 above. All the production which conforms to the Indian Standards and covered

    by the license shall be marked with certification mark of the Bureau.

    5.1 CONTROL UNIT - A Control unit is defined as a continuous extrusion run of one size

    and class of pipe from one extrusion compound up to a maximum of 48 (forty eight) hours

    duration.

    5.2 RAW MATERIAL - Only those additives shall be added which are needed to facilitate

    the manufacture of the pipe and the production of sound and durable pipes of good surface

    finish, mechanical strength. None of these additions shall produce toxic hazard or impair the

    strength of the pipes. Manufacturers own rework material (Complying with IS 16098 (Part 2),

    Cl. 5.2) is permissible. The quantity of rework material used is to be declared by the

    manufacturer. No other rework material shall be used.

    5.3 In case of failure in any of the tests twice the no. of samples should be tested for that

    requirement. If a further failure occurs, the entire lot shall not be marked.

    5.4 In respect of all other clauses of the specification and at all stages of production, the

    factory shall maintain appropriate controls and checks to ensure that their product conforms

    to various requirements of the specification.

    6.0 REJECTIONS - A separate record shall be maintained giving information relating to

    the rejection of the production not conforming to the requirements of the specification and the

    method of its disposal. Such material shall in no circumstances he stored together with that

    conforming to the specification.

    7.0. SAMPLES - The licensee shall supply, free of charge, the samples required in

    accordance with the Bureau of Indian Standards (Certification) Regulations, 1988, as

    subsequently amended, from the, factory or godowns. The Bureau shall pay for the samples

    taken by it from the open market if applicable.

    8.0 REPLACEMENT - Whenever a complaint is received soon after the goods with

    Standard Marks have been purchased and used, and if there is adequate evidence that the

    goods have not been misused, defective goods or their components are to be replaced or

    repaired free of cost by the licensee in case the complaint is proved to be genuine and the

    warranty period (where applicable) has not expired. The final authority to judge the

    conformity of the product to the Indian Standard shall be with the Bureau. The firm shall

    have own complaint investigation system as per IS 15400.

    8.1 In the event of any damages caused by the goods bearing the Standard Mark, or Claim

    being filed by the Consumers against BIS Standard Mark and not “Conforming to” the relevant Indian Standard, entire liability arising out of such non conforming product shall be

    of licensee and BIS shall not in any way be responsible in such cases.

    9.0 STOP MARKING- The marking of the product shall be stopped under intimation to

    the Bureau if, at any time, there is some difficulty in maintaining the

  • DOC: STI/16098-2/ 1

    May 2014

    3 | P a g e

    conformity of their product to the specification, or the testing equipment goes out of order.

    The marking may be resumed as soon as the defects are removed under intimation of Bureau.

    9.1 The marking of the product shall be stopped immediately if directed to do so by

    Bureau for any reason. The marking may then be resumed only after permission by the

    Bureau. The information regarding resumption of markings shall also be sent to the Bureau.

    10.0 PRODUCTION DATA The licensee shall send to BIS as per the enclosed

    Proforma-1 to be authenticated by a Chartered Accountant, a statement of quantity produced,

    marked and exported by him and the trade value thereof at the end of each operative year of

    the license.

    Table 1………

  • DOC: STI/16098-2/ 1

    May 2014

    4 | P a g e

    IS 16098 (Part 2): 2013

    STRUCTURED-WALL PLASTIC PIPING SYSTEMS FOR NON-PRESSURE

    DRAINAGE AND SEWERAGE – SPECIFICATION Table 1: Levels of Control

    (Clause 5 of the Scheme of Testing & Inspection)

    Test Details Levels of Control

    Cl.

    No

    Requirement Test Methods No. of

    Samples

    Frequency Remarks

    Table/

    Clause

    Serial

    No.

    5.1 Material (PE) Table 1 i)

    ii)

    One Each batch in a

    consignment

    If a test certificate is

    received for each

    batch along with each

    consignment of raw

    material further

    testing would not be

    necessary

    iii) One Once in 03 months

    of each grade of

    Raw material

    consignment

    5.1 Material in Solid

    Pipe form (PE)

    Table 2 i)

    ii)

    One Once in a year for

    each variety

    5.1 Material (PP) Table 3 i)

    One Each batch in a

    consignment

    If a test certificate is

    received for each

    batch along with each

    consignment of raw

    material further

    testing would not be

    necessary

    ii) One Once in 03 months

    of each grade of

    Raw material

    consignment

    5.1 Material in Solid

    Pipe form (PP)

    Table 4 i)

    ii)

    One Once in a year for

    each variety

    6.3

    Dimensions of

    Pipes and Fittings

    Cl 6.3,

    7.1

    - One Once in 4 Hrs -

    7.1 ,

    7.1.1

    Visual Appearance

    , finish & Colour

    of Finished Pipes

    Cl 7.1 ,

    7.1.1

    - Each Pipe Each Control unit

    7.2 Resistance to

    Heating (PE)

    Table 6 i) One Each Control unit

    7.2 Resistance to

    Heating (PP)

    Table 7 i) One Each Control unit

    7.3 Effect of Heating

    (Only for PE

    Injection moulded

    components)

    Table 8 i) One Each Control unit

  • DOC: STI/16098-2/ 1

    May 2014

    5 | P a g e

    IS 16098 (Part 2) : 2013

    STRUCTURED-WALL PLASTIC PIPING SYSTEMS FOR NON-PRESSURE

    DRAINAGE AND SEWERAGE – SPECIFICATION Table 1: Levels of Control

    (Clause 5 of the Scheme of Testing & Inspection)

    Test Details Levels of Control

    Cl. Requirement Test Methods No. of

    Samples

    Frequency Remarks

    Table/

    Clause

    Serial

    No.

    7.3 Effect of Heating

    (Only for PP

    Injection moulded

    components)

    Table 9 i) One Each Control unit

    8.1 Ring Stiffness Table

    10

    i) One Each control unit Same for PE and PP

    pipes

    8.1 Impact Strength Table

    10

    ii) One Each control unit Same for PE and PP

    pipes

    8.1 Ring Flexibility Table

    10

    iii) One Each Control unit Same for PE and PP

    pipes

    8.2 Stiffness (Fittings) Table

    11

    i) One Each Control unit Same for PE or PP

    fittings

    8.2 Impact Test

    (Fittings)

    Table

    11

    ii) One Each Control unit Same for PE or PP

    fittings

    8.2 Mechanical

    Strength (Fittings)

    Table

    11

    iii) One Each Control unit Same for PE or PP

    fittings

    8.1 Creep Ratio Table

    10

    iv) One Once in a year for

    each variety

    Same for PE and PP

    pipes

    9 Tightness of

    elastomeric ring

    seal joint

    Table

    12

    i) One Once in a year for

    each variety

    Same for PE and PP

    pipes

    9 Water Tightness Table

    12

    ii) One Once in a year for

    each variety

    Same for PE and PP

    pipes

    9 Resistance to

    combined

    temperature

    cycling and

    external loading

    Table

    12

    iii) One Once in a year for

    each variety

    Same for PE and PP

    pipes

  • DOC: STI/16098-2/ 1

    May 2014

    6 | P a g e