CERN, 2007-03-06 O.Pinazza: ALICE TOF DCS 1
ALICE TOF DCS
Answers to DCS Commissioning and Installation related questions
ALICE week at CERNO. Pinazza and the TOF team
CERN, 2007-03-06 O.Pinazza: ALICE TOF DCS 2
Subsystems
HV LV FEE Cooling Gas VME
CERN, 2007-03-06 O.Pinazza: ALICE TOF DCS 3
Sub systems status• HV
– PVSS: ok for both 3.1 and 3.6 (with FW and OPC, custom and standard panels)– FSM: ok on 3.1, not ported yet on 3.6 – HW: 2 SY1527 delivered, ready to be installed in CR4-Z02 and CR4-Z03, needs of 1-ph power
and ethernet connection, besides HV cables (tested, few connectors missing)• LV
– PVSS: fwCAEN is working correctly with 3.6, worse with 3.1, standard panels– FSM: (see FSM for HV)– HW:
• 4 SY1527 and branch controllers delivered, 2 ready to be installed (racks O03-O32, I03-I32, needs of 1ph power, eth, EASY bus patch)
• 12 Maciste: 1 to 2 ready to be installed in racks O04-O31 (1ph power –svc-, 3-ph power, EASY bus, LV bars)
• FEE– PVSS: ok, dpt and dp ready, simple panels, DIM -services and commands- prepared, tested,
strictly FED compliant– FSM: not ready – HW: 2 SM installed with FEE devices, lab setup at Cern and in Italy (see Integration);
needs for optical fibers to PCs in CR3, cooling on SM08• Cooling: PVSS, FSM, HW unknown• GAS: PVSS, FSM, HW unknown• VME: PVSS, FSM, HW unknown
CERN, 2007-03-06 O.Pinazza: ALICE TOF DCS 4
TOF DCS SW issues
• PVSS 3.1 SP2– HV, FEE and FSM projects ok– LV (with new fwCAEN) not yet correct (OPC addresses)
• PVSS 3.6 – HV, LV, FEE projects ok– Unable to convert any of the previous projects– Unable to convert FSM project
HV LV FEE FSM
PVSS 3.1 ok no ok ok
PVSS 3.6 ok ok ok wip
(frozen) ECS interfaceddevelopment
CERN, 2007-03-06 O.Pinazza: ALICE TOF DCS 5
FSMTOF
TOF_SM00TOF_SM08
HV LV
CAEN Ch CAEN Ch DIM devices
CAEN CAEN
OPC OPC
DIM
FERO
CTRL PC
FEE
… … …©P.Antonioli
ECS © F.Cindolo
work in progress
CERN, 2007-03-06 O.Pinazza: ALICE TOF DCS 6
TOF_DCSApplies to: TOF_DCS, TOF_NN_DCS, TOF_INFRA
OFF
STANDBY
STBY_CONFIGURED
GO_STANDBYGO_OFF
MOVING_STBY_CONF
CONFIGURE (RUNMODE)
READY
CALIBRATING
CALIBRATE
ERROR
GO_STBY_CONF
RECOVER
MOVING_READY
GO_READY
All states can fall to the ERROR state
GO_STANDBY
TOF_DCS_NODE
CERN, 2007-03-06 O.Pinazza: ALICE TOF DCS 7
Installation at P2
CERN, 2007-03-06 O.Pinazza: ALICE TOF DCS 8
Installation news
Cables, connections and services in the pit are not fully available 1-ph power
3-ph power LV bars
Ethernet Easy bus
HV connections (CR4) Optical fibers
After last survey at Point 2, we‘re still missing many connectors (rack side). This/next week we’ll hopefully begin to install devices in the racks in UX and CR
Supermodule 08• Starting probably this week, the supermodule will
finally be pushed in its final position• At present, our effort is to set all the connections
and services needed for the SM to be switched on, operated and tested as soon as possible
CERN, 2007-03-06 O.Pinazza: ALICE TOF DCS 9
Final Installation at P2
• Complete SW with PVSS 3.6– A running (but not final) version is going to be installed in
the next days, to test and operate the first SMs – Complete system: not before mid May
• Network, cables and connectors– To be checked early this week
• Devices– Hopefully this week:
• HV PS in CR4• LV PS (SY and Maciste) side O
– PCs: 4/21 linux “farm” pc ready in CR3 (remaining 17 not before May)
CERN, 2007-03-06 O.Pinazza: ALICE TOF DCS 10
Integration
CERN, 2007-03-06 O.Pinazza: ALICE TOF DCS 11
DCS+ECSF. Cindolo
CERN, 2007-03-06 O.Pinazza: ALICE TOF DCS 12
Integration
• DAQ, DA, ECS validated (Dec ’06-Feb ‘07)• Further integration tests to be performed in the TOF
lab at Cern:– February 28: Test of ECS+DCS (CERN, TOF) – March 19-22: Integration test for all DCS components of
TOF in ECS (TOF) with real HW– April 10-13: Combined test with TRG, DAQ, DCS, ECS, DA
on real HW
CERN, 2007-03-06 O.Pinazza: ALICE TOF DCS 13
Conclusions
• SW: Main PVSS subprojects are beings used in the TOF lab; not in their final version, but almost fully functional– Still missing: alarms, interlocks, Oracle archiving, complex
FEE procedures (ex. Calibration, error recovery actions), FSM-FEE tree
• HW: Most of the hardware has been delivered and the first devices are being installed probably this week to test SM08
• Integration tests have started