cern/tc/2oo 61/9 18.7.1961 european · pdf filewill be made to make the bubble chamber and...
TRANSCRIPT
1882/p
I - 2138
CERN/Tc/2oo 61/9 18.7.1961
EUROPEAN ORGANIZATION FOR NUCLEAR RESEARC~
TECHNICAL SPECIFICATIONS OF THE SAFETY VENT LINE FOR TBE 2 m
HYDROGEN BUBBLE CHAMBf :d.
The European Organization for Nuclear Research (CERN)
has constructed a 28 thousand million electronvolt Proton
Synchrotron at Meyrin near Geneva.
For nuclear physics experiments with this machine
a visual detector of the tracks of ionizing particles, balled
a hydrogen bubble chamber, is being built.
The bubble chamber will con~ain about 1000 litres of 9.
liquid hydrogen at a temperature of about -·250 C and a pressure
of 5-7 ata. The extremely low temperature of liquid hydrogen
requires that it be insulated with a high vacuum. Every effort
will be made to make the bubble chamber and surrounding tank as
vacuum tight as possible, however even a small leak would destroy
the vacuum insulation. In this ,,ase the liquid hydrogen would
vaporize very rapidly and upon warming to room temperature would
expand nearly a thousand fold. This quantity of gas, about
1000 normal cubic meters, would P.resent an extreme explosion
hazard if it were allowed to vent to the atmosphere. · . For
safety of personnel and equipment a safety exhaust system con
sisting of rupture discs and relief valves, a safety vent line
and a 500 cubic meter sphere is required to handle and store the
gaseous hydrogen in the event of such an emergency.
The following specifications are concerned only with
the safety vent line.
1882/p
- 2 -
I N D E X
1.. EXTENT OF OFFER, FACILITIES y GUARANTEES, DELIVERY AND
ERECTION DATES
1.1 Extent of Offer
1,2 Facilities
1.3 Guarantee
1.4 Delivery and erection dates
2, GENERAL INFORMATION
2.1 Operation
2.1.1 Normal Conditions
2.1.2 Emergency Conditions
2.1.3 Return to normal conditions
2,2 Construction rules
2.3 Design prescriptions
2.3.1 Material and nominal bore
2.3.2 Temperatures
2.3,3 Pressures
2.3.4 Vacuum requirements
2.4 General Arrangements
3. DE'I'AILED SPECIFICATIONS
3.1 General
3,1,1 Tubes
3 .1. 2 Flanges
3,1,3 Gaskets
3.1,4 Expansion joints
3 .1. 5 Valves
1882/p
- 3 -
3. 2 Straight line inside the bub-ble chamber building
3.3 Straight section through the ventilation duct
3.4 Expansion joint between valve adaptor and bubble chamber building
3. 5 Expansion joint between bubble ch_ambelr? and wallmounted line
3.6 Stop valve
3.7 Section inside the sphere
3.8 Adapting pieces for the valve
4. ERECTION
4.1 Civil engineering work
4.2 Supports
4.3 Erection and lining up
_5. MATERIALS AND EXECUTION OF WORK
5.1 Vent line
5.1~1 Material and work
5,1,2 Welding
5,1.3 Cleaning
5.2 Supports
6. INSPECTION DURING FABRICATION
1. TESTS AND CERTIFICATJ!~S
7.1 General
7.2 Steel plates
7.3 Welding
7.4 Tests at CERN si "':e
1882/p
.. 4 "'
8, GENERAL FORM OJi' 'IHI: TE~LLER
8.1 TechnicQl inforTiation
8,2 Commercial information
B.3 Calendar fo~ benders
1882/p
- 5 ..
1. EXTENT OF OFFER, FACILITIES, GUAPJi.N'l1EES, DEJ~IVER.Y AND ERECTION DATES
1. 1 J!::::isten t gf _ of:f eT
CERN will have preference for a tcmder of the com
plete safety vent line including accessories, erection and
tests as specified under par. 3, 4 and 7.
However, as the installation includes items normally
manufactured by specialised firms, CERN will also consider
tenders for one or more parts of the installation.
The offer shall include transport to CERN site at
Meyrin near Geneva. Transport from Geneva railway statim
to the CERN site can be either by normal road truck or the
railway truck can be drawn on trailers for unloading at
CERN. The cost fer the latter way of transportation is
about Fr.Sw. 150.- per truck depending on the size.
CERN vvill provide on site fre(:J of charge g
a) Electrical energy 380 volts, 3 phase, 50 cycles
from fixed points;
b) Welding gases;
c) Compressed air (6 kg/cm2 , moist);
d) Nitrogen gas for testing;
e) Equipment for the pneumatic pressure test and
for the vacuum test;
f) Scaffolding, ladders and light lifting gear for
erection work;
g) A site hut for the contractor's men,
Tenderer should indicate how many electrical
connections, kw., Nm3 of gas etc. will be necessary.
1882/p
-· 6 '°'
All other equipment, mateTials, tools cmd instruments 1
necessary for erection and testing must be provided by tho
contractor.
A limited area will be available on the site for the
storage of material at the contractors risk, Due to spac,2
limitation the size and shape of the area to be used must be
discussed between the contractor Bnd CEHN.
1.3 Guarantee
The successful tenderer(s) shall be responsible for the
quality and proper performance of the whole installation
as well as of the component parts supplied by himself or
by his subcontractors J.:.PJ a perL<:?.LS!.! _one ye_q.L.£. starting the
day after succes.sful complE~tion of tests on CERN site and
the taking over b;y CEHH, It must be stated clearly by the
tenderer that he is willing to give th~s guarantee,
l , 4 ~L...§11q~?r(C~£.:hJ2~n De~ Gs_
CER.N should f)e informed at least 10 days in advance
of any delivery of material to CERN site, The complete
safety vent line with all accessories is required to be
erected, tested and ~eady for ope~ation, at the latest
by March 31, 1962. A shorter delivery time would however
be much appreciated,
2. GENERAL INFORl/I.A.rrroN
2.1 0120~.12
2. 1, l .~ro1:n1~L..££.D§i tj~£..rn1
The safety vent lire will as a rule be under a
vacuum of about io-3 torr obtains~ by means of a suita~le vacuum pump, However CERN hes the pcrnsi bili ty to fill
it with purified H2 gas at slight overpressure (1,05 ata)
1882/p
- 7 -
instead of always keeping the vent line at a high
vacuum, Ambient temperatures can fluctuate in
extreme cases between-30°c and +40°C.
2,1,2 Emergency conditions
The frequency of this condition is of cours im-
possible to predict, However, in all probability it
will take place very rarely, if at all;
In the case of emergency a mixture of evaporated
hydrogen and liquid hydrogen will stream through the
vent line entering the tube with a temperature which 0
can be as low as -250 C, During the passage the li-
quid will evaporate and at the same time the safety
vent line will be cooled down violently.
The final pressure will be about 3 ata if the
safety sphere was previously filled with hydrogen and
less if it was evacuated. If for some reason the
safety sphere were filled with air there would be the
possibility that an explosion will take place when the
evaporated hydrogen streams intb the sphere. The
maximum pressure from an explosion is calculated to be 2
about 15kg/cm gauge,
2.1.3 Return to normal conditions
When tho equilibrium stage has been reached after
an emergency, the safety vent line will be emptied and
finally brought back to normal operation conditions.
2,2 Construction rules
CERN requires the construction to be approved by
"Schweizerische Verein von Dampfkesselbesitzorn (SVDB)"*,
*Address~ Plattonstrasso 77, Ziirich, Switzerland,
1882/p
- 8 -
which means that the tenderer can uso the regulations
governing pressure vessels issued this authority, or
the rules of his own country, whichever are the more
stringent, Special attention must be paid to tho wel-
ding factor and to the impact stress, especially at low
temperatures.
The tenderers attention is also called to the vacuum
specification. This is perhaps stricter than found in
normal industrial practice and only the highest quality
workmanship and material, especially the welding, will
meet this specification,
2. 3 Design prescripti9ns
2.~.l Material and nominal bore
CERN wants a 350 mm nominal llore safety vent
line made of a stai~less steel quali Lcppropria te
for the temperature, pressure and vacuum conditions
pr~scribed below. HoweveT the tenderer should boar
in mind tho very rare occasions of the ultimate low
temperature which in addition will only act during
a short time.
,- ')c Maximum tempcratuer ~·JG-
2 i:::r'oC Ultimats low temperature - )0 ;
Pressures 2
Ultimate highest working pressure = 15 kg/cm gauge
Hydraulic tE:rnt pressure = kg/cm 2 gauge·
1882/p
- 9 -
2.3.4 Vacuum reguirements
The design and construction shall be such .that
the safety line can be evacuated to an absolute
pressure of at least 10-3 torr with a vacuum pump
stand having an effective pumping speed of 2000 l/sec,
The total leak rate should not be greater than
1 x 10- 2 .torr-liter per second.
2.4 peneral arrangement
The arrangement is shown on the attached drawing,s
155-68-0C, 155-69-0A and 155-72-0B.
As will be seen from these drawings the .vent line
consists of:
a) About 50 m of flanged tube along the inside
NW wall of the bubble chamber building;
b) a section (with vacuum valve) passing the ven
tilation duct in a 450 mm tube and throug]1 .the
building wall;
q) a s~cition, allowtng thermal expansion, between
(b) and the valve (e);
d) a section allowing thermal expansion between
the bubble chamber and (a), As the bubble chamber
is movable along the entire length of the building,
it is foreseen by CERN to make adapting pieces for the
connection of (a) and (d),
The nearest section of (a) will then be removed,
e) A 350 mm bore - stop valve;
f) a section with flanges about 4 m in length, inside the sphere;
g) adapting pieces for the connection at the valve to the line and to the sphere nozzle of 500mm bore.
1882/p
- 10 -
h) Hardware, brackets, nuts and bolts, blind
flanges for the testing of the complete assembly
and other miscellaneous items necess~ry to make up
the complete project.
The component parts (a) to (h) are further
specified in the following section.
3. DETAILED SPECIFICATIONS
3.1 Gene rel ~·-·--
3 .1.1 Tubes
The tubes forming the vent line ~ust be manu
fnctured with only one longitudinal welding seam.
Circumf~rential seams must be limited to the minimum.
possible and 2 longitudinal seams should never meet,
3.1.2 Flo.nges
The tenderer should use DIN or ASA norms for
the flanges in respect of thickness, bolts etc,
Owing to the vacuum requirements the flange
joints must be extremely tightg CERN~ with past ex-
perience of pressure and vacuum vessels, proposes
the use of 11 0 11 -rings to seal the joints. The align-
ment of tho individual pipes must be such that all the
flanges are drawn up metal-to-metal completely· around
the circumfo:rence; this is necessary if the 11 0 11 -ring
is to be confined entirely in the event of a pressure
surge,
In principle CERN has adopted as standard the
11 0 11 -ring groove dimensions given by the compilation
of Angst and Pfister A.G. of Zilrich, Switzerland. If
the tenderer elects to use machined grooves in the
1882/p
·- ii -
flanges, then it is suggested that the grooves be
locCtted in the flanges facing the sphere, The coun
terflanges must then have a polished are·a opposite to
the grooves.
Alternatively the tenderer may elect to polish
both flanges and f:urnish the n0 11 -ring confined between
two concentric retaining rings in a manner similar to
that indicated by Heraeus GmbH of Hanau, Germany, in
their cato.logue on vacuum equipment; 3Td Ed., Section A,
page VIII - 2,
The tenderor's attention is drawn to th8 fact
that for reliable sealing, the surfaces of the flanges
in contact with the 11 0"-rings must be .finished to better
than 64 microinches roughness. No redial grooves or
scratches of any kind can be t'olera ted,.
The tenderer can of course also proposo his own
solution for the sealing of the flange joj.nts. He should
then be prepared to provide samples and tests to de
monstrate that the method prOpo~ed by him is at leist
as good and as sriitable for the present application as
the 11 0 11 -r_ing seals,
Nuts and bolts for tho flan~e connec.tions shall
be made of stainless steel,
3.1.3 Gaskets
· Standard rubber 0-rings shall be supplied b~
the successful' tenderer. However CEP.2~· reserves tho
right to supply 0-rihgs of another (low temperature)
material which then should be used for the erection,
1882/p
- 12 -
3 .1. 4 Ex12ansion section<L
The sections (c) and (d) mentioned in para
graph 2,4 must nllow thermal expan,sions, CErn~· propose
1.Jellows expansion joint~~ which must be equipped with tie
bars to take the pressure forces. The tenderer is in-
vited to propose another solution taking into account
that forcea in excess of 5 tons should not act on the
bubble chamber or on the building.
3 .1. 5 Valves ~---=·;<;
They should be non-lubricated, pressu~e and
vcccuum tight and of a well tried, reliable type suitable
for the pressure, temperature and vacuum conditions
requested,
3. 2 Strair,;ht line inside. the bubble ch2,mbe:r: buildiJ:l.€i
The section (a) consists of 7 pieces flanged together,
each piece having a length of 6500 mm,
3,3 Straight section through the ventilat_ion duct
Section (b) will consist of one straight tube with
flangos, Inside the building there must be a stud
carrying a flangod-on 100 mm bore valve having particulars
as specified in 3.1.5; furthor a stud of 20 mm bore for
pressure indication and a thormomoter well must be
provicled,
Outside the building the tube will be attached to
the concrste vnll: the contractor must design the proper
cons true tion so the:-c t this ono o.nd only 11 in termodie, te fixed
point" is capnble of tccking the lood of 5 tons mentioned
previously.
1882/p
- 13 -·
3,4, Expansion joint between valve adaptor and bubble
chamber building
This section (c) ~ill cohtain a sharp bend at about
30° relative to the direction defined by the outer wall of
the bubble chamber building along which the safety line runs,
and a straight part carrying one or two bellows with tie bars
for almost all the length. As far as possible this section
should have flanges only at the ends. The tenderer should
propose a proper design and the contractor in consultation
'with CERN must make the final construction.
3, 5. Expansion ,joint between bubble chamber and wall
mounted line
This part (d) contains one horizontal and one verti.cal
90° bond (which should be kept as short as possible), one
straight tube with bellows J.nd tie bars and one short·aQ,ap
ting piece in the horizontal part between the, two bends.
The other particulars are as mentioned in 3.4,
3. 6 Stop ve.l ve
One 350 mm full bore stop valve (e) should be delivered
having the following cnQracteristics:
Vacuum conditions: 'The.valve housing, stem seal and seat
must be tight for 10-3 Torr on one side . ' 2
and. 1 kg/cm gauge on tho other side.
Leak rate should be l~ss than 1 x 10-3 Torr
liter por second.
Pressure conditions: The valve body and stem seal must moot
the working and test pressures noted in
paragraph 2, 3. 3 with. the seat open Ein'd
closed. The valve ioat should withstand
13 atmbspheres (gauge) pressure from ~~ther
1882/p
- 14 -
direction, and it should bo bubble tight
with ~ pressure difference of 6 atmo
spheres (gauge) across it,
CERN is fully EHvare that a valve
meeting the full pressure and vacuum
specifications may not 1rn corr:mercially
Dvailable, CERN :Ls prepL1T(0d to work
with tho successful tenderer in the
adaptation of existing commercial equip
ment.
Flanges should have polished surfaces for tho 0-rings,
One straight tube (f) of about 5 m length complete
with flangos,
Two adapting pieces short as possible must be
supplied for the fitting of the valve
to the 500 mm nozzle of the sphere,
to the vent line and
For seal of the
flanges see remarks of paragraph 3,1,2. Detnils will be
discussod further between CERN o.nd tho contractor, Noto
that the valve may have ASA flanges and the balance of the
work.DIN flanges.
4, ERECTION
4,1 Civil engineering work
CERN will supply and instc.11 b:rackets fitted to the
I-beams of the bubble chambe:r walls and to the I-beams of
the crane bridge, If consido:red necessary by the contrac-
tor a pillar with bracket could be erected close to the big
valve.
1882/p
- 15 -
Outside the building there will be no other possibili
ties for supports other than those mentioned,
The tube of 450 mm bore insicle which the vent lino must
pass th7 ventilation duct will also be supplir:;d D.nd instoILed
by CERN.
The contractor must in due tima supply the necessary
information and drawings indicating his wishes. If further
beams and brackets are wantod along the wall, tho contractor
must supply the ma terLtl yvhile CERN will make the ins talla-
ti on. This also applies to tho intermediate fixed point.
No work affecting buildings, foundations or other in-
stallations will be allowed~ Therefore any modification
affecting such p~rts ~ due to delay of the contract or
insufficient information will be made by CERN at the
contractor's expenses.
4.2 Supl?orts
Tho successful tenderer shall supply all supports,
Bolts and nuts necessary for the erection of the safety
vent line.
The supports which should be bolted to the above-mention
ed br2ckets must be der>igned to allow 2. froe thermal con
traction along tho axi~ of tho tubo and should at the samo
time guide it properly.
Supports inside tho bubble chamber building must in
2ddition be designed to ensure an easy dismounting of each
of the 6.5 m long tubes (supports shown on t~e attached
drawings are intended as an indication only).
4,3 Erection and li~
The contractor shall erect, carefully line up and
assemble the complete safety vent line in 2 way that secures
the vacuum tightness and prevents any undue stressing.
1882/p
- 16 -
5. MATERIALS AND EXECUTION o:E1 WORK
5.1 Vent line
5.1.1 Materiel and work ~~--~~-~-~--~
It must be new and of approved qu2lity for the
pressure nnd temperature conditions mentioned in para-
gro.ph 2.3. · Further it must meet all requirements for
operation with hydrogen gas, All work shall be exo-
cuted sccording to thl'> highest stcmd,::i.rds of workmanship,
Tho plates shall be handled during all stages of
fabrication and erection in a way that secures the
greatest possible final cleanliness,
5 .1. 2 Vfolding
The welding factor must comply with tho rules
used and shall be indicated in the tender together with
the calculation of the wall thickness. Tho electrodes
and the procedures must be approved by the surveyor.
Only welders having certificate for stainless steel
welding must be used 9 at the contractorls factory ns
well as on the CERN site. CERN requires the success-
ful tenderer to deliver two welding samples of the same
thickness as will be used for the vent line,
The welds shall hnve a quality complying with
tho most recent standards fer completely pressure and
v,?cuw-0:1 tight vrelding sear1s.
The greatest possible cleanliness should be ob
served and all scale removed after each welding,
After completion of ull welding ea.ch seam muEit be
completely X-rny or rnagnaflux tested and ::my defec;t
repaired by the contractor without expense to CERN•
1882/p
17
The inner surface must be extremely clel'.n in
order to avoid contamination of the highly purified
H2 gas which might be stored in the sphere. When
the final pressure and vacuum tests are finished the
surface must be washed with c~rbon tetrachloride,
trichloroethylene or similar liquids. Any residue
of oil, water, dust e,nd. chemicals mi;cs t be renoved,
5.2 Supports
The choice. of material is left to tho tenderer who
however should consider the dhnger of cooling down any
supporting structure of the building.
Bolts, nuts washers and similar iteus, if made of
steel, shall be cadmium plated while other steel parts
shall have a coating of red lead.
6. INSPECTION DURING FABRICATION
CERN reserves the right to inspect the mnnufacturo of
all items at the factory of the contractor·or his subcom~rac~
tors and at CERN site at any stage of producti:rn 2~nd ::ct any
normal working time,
7, TESTS AND CERTIFICATES
7.1 General
All testing demanded must be su:pervif.rnd by the surveyor
mutually agreed upon by CERN and the successful tenierer.
CERN should be informed by the contractor not lnt0T thRn
seven do.ys in advance of o.ny planned t(rnt ou-Csido CERN site
whereupon CERN will inform him whether or not it will p~r-
ticipo..te, Any test on CERN site will be v;i tnessed by CERN,
1882/p
18
Faulty material or faulty manufacture detected by any test
shall be, as.CERN decides, replaced or repaired without
cost to CERN.
All expenses for tssts and certificates are at the cost
of the contractor who must accordingly make provisions for
thee in his offer, For every test mentioned below under
7,2, 7,3 and 7,4 certificates in duplicate have to bo sup
plied,
7,2 Steel plates
Material certificates must be submitted covering the
process of steel fabrication and giving chemical composition,
yield point, tensile strength, elongation (in o/o), and
impact strength, at the temperature limits mentioned in
paragraph 2.3.
7.3 ~slding
As previously mentionSd a complete X-ray or magnaflux
testing of all wolding seams shall bo made. Films must be
examined by the surveyor and shall finally become the pro
perty of CERN.
7J4. Tests at CERN site
After erection the contractor shall test the installation
as follows:
a) A hydraulic pressure test of the completed line
with all apertures firmly closed shall be made at the 2
CERN site, with a test pressure of 24 kg/cm • The
expansion bellows, links etc. must of course be de
signed to withstand these pressures,
b) By filling slowly the vent line with air up to
15 kg/cm 2 gauge with simultaneous soap solution testing,
The final pressure shall be maintained for at least
2 hours and still no leaks shall be detected by soap
solution tests.
1882/p
- 19 -
c) By evacuating the line to 10-3 Torr, closing and
studying the pressure rise during 48 hours. The leak -2 rate shall be lower th2n 10 Torr liter per second.
If (c) proves unsuccessful:
d) By filling the line with helium to 15 kg/cm2 gauge
and using a helium leak detector for finding the leak(s)
(leak detector will be supplied by CERN).
8. GENERAL FORM OF THE TENDER
In order to facilitate the adjudication the tender
shall be divided into the following sections:
a) technical information
b) commerDial information
c) calendar for tenders.
B.l Technidal information
The tenderer must describe the design, the materials
and methods of manufacture, the wolding, erecting, testing
and finish of the complete installation as specified in
s·ections 2,3,4,5 and 7. In particular he should pay atten-
tion to all points where CERN has asked him to make pro-
posals.
All calculations, weight, dimensions and certain. tech
nical data (e.g. resulting strains) must be mentioned.
Preliminary drawings of the supports and the expansion
joints as well as prospectus describing valves shall ~e
attached to the tend~r, together with a list of the pro
posed subcontractors.
After settlement of the contract detailed plans of
tubes, supports and fixations and other component parts
have to be supplied at jointly agreed dates. Should the
contractor not deliver the drawings in time all modifications
1882/p
or changes due to this delay shall be made at his expense
or by himself,
The tenderer must propose a delivery programme stating
dates of material delivery to CERN, time of erection and
a programme for tho tests on site.
8.2
8,3
This section must unit nna total prices of
the follo
3.6, 3,7, 3,8, The costs for certificates, tests and third com-
pany inspections made at the factory of the contractor
or his subcontractors must be indicated.
The sumnation of these costs must give the total
fixed
B. Total coc3 ts of , transport, insurance,
erection and final test at CERN site should be stated
sep1:;,ra te1y,
C. The summation A+ B should give the total fixed
price of the safety vent line ready for operation,
D. Any price or price difference due to alterations
should be stated separately.
E. The altornativos include:
a) other material than staihless stool (for
instnnce aluminium, co1Jper or other cold re-
0i· "+0r1t ma+e-~i·~1°)· i...J U vC, ... . J "-·--~ ,; ..i.. ..... ~ 0 '
b) other suggestions by the tenders~
'l'lw closing date for receipt of tenders t CERN is
tho 29thof Se ember 1961, at noon, No extension after
this d::ct to c~m be od,