cesc cable joints

Upload: joydeepd3232

Post on 03-Apr-2018

222 views

Category:

Documents


0 download

TRANSCRIPT

  • 7/28/2019 Cesc Cable Joints

    1/15

    Analysis of HT cable

    and joint failures

    and associateddesign modifications

    Authors:

    K. Rana,

    Manager (Jointing), CESC Ltd.

    B. Dasgupta,

    Mains Engineer,CESC Ltd

    CESC Ltd , in existence since 1897,

    generates and distributes electricity to the

    twin cities of Calcutta and Howrah on either

    side of river Hooghly spanning over an area

    of 567 sq. km, serving a demand of 1657

    MW. It is now a RP-Sanjiv Goenka group

    company.

    Both the cities being highly congested, need

    was felt from the early days for

    underground transmission and distribution

    on preference to cheaper overhead option

    because of greater way leave requirement

    of overhead lines. We presently have 4950

    ckt kms of 6/11KV cable network with a

    consumer base of 1673 HT and 2.49 million

    LT consumers.

    This paper discusses the cable and joint

    fault analysis which is regularly conducted

    in our system consequent to faults. All new

    joint failures and XLPE Cable failures in run

    are analyzed in stages to identify the root

    cause of such failure. The observations

    regarding failure and statistical analysis of

    trends are used to as a tool to development

    of our cable construction and joint design.

    Why cables fail?Power cables are manufactured in factories

    under controlled environment and

    sophisticated online monitoring. The

    completed cables are further tested

    according to standard testing guidelines

    before acceptance for use.

    However, the cables laid at site may notdeliver the required performance due to

    adverse installation conditions and

    unintentional damage during cable laying.

    Jointing is required to be done at site of

    installation where the trench is often

    infested with dust, moisture, vibrations etc.

    these unavoidable factors can be

    detrimental for a high tension cable joint

    which requires a clean environment for

    manufacture. Human factors are also

    present in jointing as the job is done

    manually. Though joints are always done by

    trained and experienced jointers of

    sufficient reliability, human error can creep

    in which is unavoidable.

    Furthermore, a joint is a weakest part of an

    underground cable system owing to the 3

    types of stresses which are predominant in

    joint. These are the thermal stress (caused

    mainly by the externally applied insulationbuild up and joint encapsulation), electrical

    stress (caused mainly due to termination of

    cable screen in high tension cables) and

    mechanical stress (as the conductor jointing

    region is more prone to stress and strain

    during normal cable loading and

    development of transient overcurrent

  • 7/28/2019 Cesc Cable Joints

    2/15

    during fault conditions superimposed on

    daily and annual temperature variations).

    Types of failuresMost of the failures that occur in cable

    system have a cause that is well known. For

    instance, failures due to digging activities of

    other utilities which damages our cable or

    due to ageing of older

    components(eg.Insulation or metallic

    sheath) at their end of life. If we study the

    type of failures keeping in mind the basiccable construction, then we categorize the

    failure along following line:

    a) In conductor : Most found in jointsat the conductor connection points

    b) In insulation : In joint or cable andmostly related to ageing

    c) In sheath (metallic or non-metallic):Mostly in cable and generally it is

    not the ultimate cause but always

    the incipient one.

    Failures in insulation of cables and

    accessories are mostly related to ageing and

    typical basic ageing processes are:

    Thermal breakdown Partial discharge Electrical treeing Water treeing

    Thermal breakdown:

    It is a very common form of breakdown in

    cable insulation. Generally a thermal

    breakdown is recognized by:

    The breakdown channelis radial.

    There is typical burningsmell from the

    breakdown zone.

    Thermal breakdown occurs when rate of

    energy and heat transfer to insulation

    material as a result of electric field exceeds

    the rate of heat dissipation and absorption.

    This type of breakdown is therefore not

    common in XLPE cables but if the properties

    of insulating material are quite inferior then

    there is always possibility of such failure.

    Electrical breakdown:

    Electrical breakdown in polymeric cablescan occur due to treeing. Treeing is a

    phenomenon occurring in polymer

    insulated cables in 2 forms:

    Electrical treeing:

    In high tension cables

    (11KV and above), the

    voltage stress appearing

    across cable insulation is

    considerably high. Every

    precaution is taken in cable

    factories so that the

    polymeric insulation is free

    from voids, impurities,

  • 7/28/2019 Cesc Cable Joints

    3/15

    semicon protrusions etc.

    However, in real life, it is not

    possible to design a 100%

    void and impurity free cable

    insulation. The voids and

    impurities are region oflocalized discharge and

    heating which ultimately

    develops into a carbonized

    path in the insulation.

    Formation of carbonized

    pockets cause the effective

    insulation thickness to

    reduce and develop a

    carbonized conducting

    tracking path which

    ultimately results in

    dielectricbreakdown(Fig : 1).

    Water treeing:

    Polymeric insulations are

    hygroscopic to some extent. The

    seepage of moisture through the

    cable sheath can percolate through

    the insulation(Fig : 2). The watermolecules get charged as the

    conductor acts as cathode and the

    screen as anode. The charged water

    molecules travel through the

    insulation from the earthed screen

    towards the live conductor via

    insulation by a process called

    electrophoresis.

    (Fig : 2)

    (Fig : 1)

    Water causes conducting path

    through the insulation resulting indielectric failure in the long run

    unlike electrical treeing, water

    treeing is a very slow process which

    develops over a long period of time.

    Different seamless water barrier

    tapes and extruded metallic sheaths

    are used in cable to provide water

    tightness to the cable.

    Ageing:

    The term ageing is used for old PILC cables

    in service for more than 50 years. Ageing is

    the natural degradation of the cable

    insulation caused by various reasons. The

    major reason of ageing in PILC cables is the

    cyclic overloading. Overloading heats up the

    paper insulation causing the impregnation

    oil to dry up. Dry paper insulation greatlyhampers the dielectric strength of the same

    which is often sufficient enough to cause

    breakdown.

    The quantity of paper degrades over a

    period of time as it is made up of cellulose.

  • 7/28/2019 Cesc Cable Joints

    4/15

    This phenomenon along with drying of

    impregnating oil can cause failure. The Lead

    sheath of the cable reacts with the

    chemicals present in the soil and gets

    corroded over a period of time. This can

    cause seepage of moisture into the paperinsulationand subsequent breakdown of the

    cable dielectric.

    Our experiences

    Now we will focus on our experiencesregarding cable faults. Our primary high

    tension network comprises of 6 and11KV

    and Sub transmission voltage of 33KV. We

    are recently installing 3 core XLPE insulated

    cables in our primary distribution network

    and single core XLPE cables for 33 KV

    networks.

    We have 3 types of 33KV Grade cables

    existing in our system:

    PILC Cables (3 core H Cables

    and Single core HSL type cables

    XLPE CABLES (Single core

    only)

    Gas Filled PILC Cables

    6/11KV Grade cables:

    PILC belted cables (bothAluminum and Copperconductors)

    XLPE cables (3 corealuminum conductors)

    We are using only XLPE cables in all voltage

    grades now but we still have a large part of

    our existing network comprising of PILC

    cables and few Gas filled cables (33KV). Due

    to the above reason, we often require to

    join our and existing PILC cables to maintain

    network continuity mainly during cable

    breakdowns. It is our observation that these

    transitionjoints is more prone to fault. Thejoint is designed to suit our requirements.

    6/11KV Joint

    failures

    The major areas of fault as observed in our

    system in a 6/11KV straight through joint

    and terminations are discussed below:

    The continuity of the lead sleeve

    with the PILC cable lead sheath:

    In our transition joint design we have a lead

    sleeve prepared at site by beating up a

    rectangular flat lead sheet to size, to

    encapsulate the joint. The earth continuity

    of the joint is ensured by a tinned copper

    braid of suitable size, connected to the

    armour wire of XLPE cable with jubilee clips

    and solder tacked on to lead sleeve of the

    joint. The lead sleeve is plumbed on to the

    sheath of PILC cable and provides actually a

    hermetic sealing on the PILC side of the

    joint which is most vulnerable to moisture

    ingress(Fig : 3).

    (Fig : 3)

  • 7/28/2019 Cesc Cable Joints

    5/15

    The region of contact of the lead sleeve

    with the PILC lead sheath is of crucial

    importance. Insufficient application of

    plumbing metal or inappropriate

    workmanship during plumbing can pose

    high resistance to the earth fault currentdue to any fault in downstream network.

    Repetitiveoccurrence can melt the plumb

    and allow subsoil water to enter the belt

    paper insulation beneath and cause

    dielectric failure (Fig : 4 and 5). Most of our

    failures in transition joint have been

    attributed to the failure of paper insulation

    near the crutch region due to moisture

    ingress.

    The above pie chart shows the percentage of failure

    of transition joints for various reasons in our system.

    (Fig : 4)

    (Fig : 5)

    The above 3 pics show failure of XLPE-PILC

    transition joints from the plumb region.

    Crutch region of the PILC Cable

    PILC Cables existing in our system are

    mostly aged and as a result the strength

    and durability of the paper insulation has

    degraded over the period of long service.

    The oil impregnation of the paper can also

    get partially dried making the paper brittle.

    During breakdown repair jobs, we need to

    join these old PILC Cables with new XLPE

    Cables.

    (Fig : 6)

  • 7/28/2019 Cesc Cable Joints

    6/15

    Handling of the old PILC Cables during

    aligning for jointing is therefore of an

    extremely skillful task to avoid cracking of

    paper insulation at the crutch region which

    is most mechanically stressed. Bad cross in

    PILC cores and damage to paper during corehandling can cause phase-to phase short at

    the crutch region which is in turn most

    electrically stressed also(Fig : 6).

    Conductor jointing region:

    The next most fault prone portion of our

    joint is the ferrule zone. In Al-Al conductor

    jointing in 6/11KV, we employ crimping

    technique using ratchet type crimping tool.Failure from crimping area has been mostly

    due to unacceptable gap between

    successive crimps and incorrect crimping

    sequence resulting in inadequate cold flow

    of the metal inside the ferrule (Fig : 7). On

    dissecting such poorly crimped ferrules, we

    have found voids inside the ferrule and

    consequent radial failure during heating

    under load cycle(Fig : 9).

    (Fig : 7)

    (Fig : 9)

    (Fig : 8)

    However, some of our existing PILC Cables

    have Copper Conductors. We employ solder

    basting technology using weak back Copper

    ferrule for jointing the same with Aluminum

    conductors. It is necessary to ensure that

    the conductor jointing region has low

    resistivity in order to allow smooth flow of

    current across it.

    Insulation build up:

    In our 6KV and 33KV joints, failure at

    conductor joint region was also observed in

    our design in hand applied polymeric

    insulating tape. Analysis of faulty joints

    reveled that failure in all cases have

    occurred from the edge of the ferrule. The

    root cause behind the failure was improper

  • 7/28/2019 Cesc Cable Joints

    7/15

    insulation build up profile. The insulation

    build up on ferrule was done by hand

    applied self-amalgamating insulating tape

    over the conductor jointing region. The

    varying tension of hand applied insulating

    tape can cause insufficient thickness ofbuild up at some places over the ferrule(Fig

    : 10). Dielectric breakdown occurs from the

    region of minimum insulation build up

    which is usually at the edge of ferrule(Fig :

    11).

    Correct procedure of tape buildup: ~

    1.6 times the insulation thickness on

    cable

    Wrongprocedure of tape build up

    (Fig : 11)

    (Fig : 10)

    A typical failure due to inadequate tape

    build up thickness at the edge of the

    ferrule

    Improper core disposition:

    Fault can also develop in transition joints

    where the cores can be in contact with the

    metallic lead sleeve at earth potential dueto improper disposition of the cores as

    shown in the diagram below:

  • 7/28/2019 Cesc Cable Joints

    8/15

    XLPE Insulation and Insulation

    screen cut region

    The extruded XLPE insulation screen isrequired to be removed up to a

    predetermined distance away from the

    insulation cut as specified by the joint

    manufacturer in order to provide the

    necessary safe creepage distance. The

    screen cut region is a region of high electric

    stressand improper termination of screen

    and inadequate stress control can cause

    high partial discharge inside the joint.

    Void filling high permittivity mastics applied

    at the screen cut point

    Accidental nick on exposed portion of XLPE

    insulation or semicon screen can cause

    concentration of high electrical stress at thenick point and resultant dielectric failure

    may occur within a short period of time due

    to electrical treeing. The picture below

    depicts such a breakdown which was

    probably caused for the above reason (Fig :

    12 a and Fig : 12 b).

    (Fig : 12 a)

    (Fig : 12 b)

    A typical fault due to inadequate

    stress control at screen cut region

    Failure at termination:

    The major fault prone areas of a XLPE and

    PILC Termination are:

    The conductor Jointing region Semicon screen cut region

  • 7/28/2019 Cesc Cable Joints

    9/15

    The contact region of the lugwith the dropper or stud

    Earthing region

    (Fig : 13) Failure at semicon screen cut

    region

    The reason of failure due to improper

    conductor jointing is the same as explained

    above in straight through joints. In

    termination joints, it is important to ensuresufficient surface area of contact between

    the palm of the lug and the surface onto

    which it is connected. In our system, it is

    often required to fit the lug made of

    Aluminum with Copper droppers or studs.

    In that case, use of bimetallic washer is

    absolutely essential.

    33KV Joint failures

    In our 33KV system, we have observed fault

    at the following regions of joint:

    Region of armour connection

    In an XLPE XLPE single corestraight through joint, the subsoil

    water can enter the cable sheath

    due to improper joint encapsulation.

    The water can easily travel throughthe Copper Earth braid inside the

    joint used for armour continuity by

    capillary action. The water readily

    oxidizes the Aluminum armour wires

    and the Poly Al sheath. This

    phenomenon is accelerated due to

    the cumulative heating of the screen

    wires resulting from the continuous

    flow of circulating current as both

    ends of the cable screen are solidly

    earthed.

    Due to oxidation of the Al screenwires, the effective electrical cross

    sectional area of the armour gets

    reduced causing continuous over

    heating of the same which in turn

    facilitates further oxidation.

    Moreover, use of spring band of

    different metal at this region to

    make armour and Poly Al

    connectivity has an inherent heatingdue to bimetallic contact of the two.

    This cumulative heating results in

    the thermal breakdown of insulation

    at this region (Fig : 14 a and Fig 14

    b).

  • 7/28/2019 Cesc Cable Joints

    10/15

    (Fig : 14 a)

    (Fig : 14 b)

    It was also seen in some casesthat the spring band has lost its

    constant pressure property

    over a period of time during

    breathing of the cable under

    varying load cycle. This has

    loosened the compression and

    causes heating at the point of

    current transfer between

    aluminum armour wires and the

    copper braid.

    Failure at heat shrink PILC

    terminations

    The impregnation of oil of thepaper insulation often oozes outdue to the effect of gravity and

    breathing of the cable at

    terminations. This causes drying

    of the paper insulation which in

    turn greatly hampers the

    dielectric property of the same.

    This is specifically pronounced inheat shrinkable outdoor type

    terminations in PILC cables.

    Failures in cable

    run

    Apart from joint failures, fault also occurs in

    cable run for the following reasons:

    Direct spiking: -

    In a metropolitan city like ours, the route of

    underground power cables are often shared

    with other utilities like telecommunication,

    municipal sewage or water supply works,

    civil construction works like road widening,

    pillar erection for flyover etc. This can cause

    accidental damage to the power cables laid

    undergrounddue to direct spiking during

    excavation. This problem is specifically

    pronounced in a city distribution network as

    in our case. Direct spiking by pickaxe, JCB or

    other metallic digging instruments is

    therefore a common occurrence which is

    beyond anybodys control.(Fig : 15 a and

    Fig:15 b)show typical direct spike cases.

  • 7/28/2019 Cesc Cable Joints

    11/15

    (Fig : 15 a)

    (Fig : 15 b)

    Typical cases of direct spiking on XLPE

    cables

    After effect of spiking

    Direct spiking can damage the cable but

    often that does not cause feeder tripping

    immediately if the penetration is not that

    serious. However, the damage meted out to

    the cable outer sheath and armour in case

    of PILC Cables can cause corrosion of Lead

    Sheath and provide path for moisture

    seepage into the paper insulation causing

    dielectric breakdown of the cable. XLPE

    cable can also fail in case of damage toscreen or due to damage in armour as XLPE

    insulation is to some extent

    hygroscopic.(Fig : 16)

    (Fig : 16)

    Improper cable laying

    Deviation from standard installation

    procedures can occur in some places due to

    hindrances on cable route like previouslyexisting concrete construction,

    communication cables etc. The inadequate

    depth of laying can increase the chance of

    damage to the cable due to spiking or heavy

    vehicular movement above the cable.

    Ageing of cable

    This is applicable in case of PILC Cables

    which are in service for more than 50 years

    in our system. Apart from the aboveexternal reasons, failure of cable in run can

    also occur due to natural ageing. Ageing can

    be accelerated due to adverse installation

    conditionsand cyclic overloading. The

    dielectric strength of paper insulation can

    degrade due to irregular load pattern,

    frequent overloading with cables installed

    in soil having high thermal resistivity and

    bending the cable beyond the safe radius.

    Corrosion of Lead sheath can also occur due

    to presence of strong chemicals in soil

    which can puncture the Lead sheath and

    allow subsoil water to enter the paper

    insulation.

  • 7/28/2019 Cesc Cable Joints

    12/15

    Manufacturing defects

    The cables manufactured in factory in

    controlled environment are always tested

    prior to acceptance according to Indian

    Standards for Acceptance Testing. However,

    defects can persist in cable like

    discontinuity of screen, damaged insulation

    etc. These defects can generate into fault

    when the cable is placed in cyclic load.

    ____________________________________

    Failure Analysis

    The analysis of failures is done in stages to

    arrive at probable root cause of the failure.

    We do the following routine analysis to all

    our failures.

    Information from fault site: the fault site is

    visited after occurrence of the fault. This

    visit is aimed to obtain relevant information

    which may guide us to identify the cause offault. The type of information includes:

    Installation conditions: The cableinstalled at improper depth,

    inadequate bend etc. can give rise to

    fault. The condition of soil is tested

    to estimate subsoil water level

    which may have entered inside the

    cable or joint during fault.

    Availability of tiles and side blocks:The positioning of protective tiles

    which is usually placed on the laid

    up cable give us an indication of any

    underground excavation job which

    may have been carried out by some

    other agency in near pastand

    ourcable could have been damaged

    in the process. Scattered tiles at the

    fault region indicate that some other

    agency has exposed our cable which

    strengthens the probability of cable

    damage by spiking.

    Local reports of faultsite:Information gathered from local

    residents near the fault zone often

    provide us important clues in fault

    analysis. They apprise us of any

    digging activity along the cable route

    in near past, frequency of

    occurrence of fault at the region etc.

    Load of traffic: In an urbandistribution network like ours, the

    heavy traffic frequency above the

    road often causes joints to vibrate

    under vehicular movement and can

    weaken the sophisticated areas of a

    high voltage joint.

    Equipped with the information gathered

    from fault site, we investigate the following

    records pertaining to the faulty feeder:

    o Load pattern of the cabledaily and annual

    o Tripping history of the cablesection over a period of time

    o Statistics of nature of fault(fault in joint or in cable run

    etc)

    At final stage, we conduct stage by stagedissection of the faulty piece at our

    materials laboratory which is equipped with

    various testing equipmentand tools for this

    type of analysis. The different parts of the

    faulty piece are exposed with utmost care

    so as to preserve the proof of reason of

    failure.

  • 7/28/2019 Cesc Cable Joints

    13/15

    The following pictures show a stage by

    stage post mortem of a PILC cable fault in

    run. The individual cable components are

    separated and observed for clues of failure.

    Stage 1

    Stage 2

    Stage 3

    Stage 4

    Stage 5

    We arrive at probable cause of failure after

    summing up all the relevant information

    and prepare the final report for archiving

    and necessary actions.

    Inference

    Consequent to the above failures, we have

    come to the conclusion that failure of our

    high tension cables and joints are mainly

    occurring for the following reasons:

    Uneven thickness of hand appliedinsulation build up on ferrule

    Ageing of old PILC cables Poor mechanical strength of outer

    jacketing of the cable.

    Inadequate conductor connectiondue to improper crimping.

    Ingress of moisture inside the cableand joints due to elevated subsoil

    water level

    Inadequate path for circulatingcurrent flow in both ends bonded33KV system.

    Migration of impregnatingcompound in 33KV PILC

    terminations.

  • 7/28/2019 Cesc Cable Joints

    14/15

    Remedial

    Measures

    The root causes of failures that were

    detected from our analysis of cable and

    joint failures guided us in making the

    following course corrections in our cable

    and joint design:

    We have phased out the taped typeXLPE joint design and incorporated

    heat shrink technology in all ourhigh tension jointing system.

    Crimping is to some extentdependent on manual skill where

    equal spacing requires to be kept.

    Therefore in order to arrest failures

    at ferrule region due to bad

    crimping, we have introduced

    shearing bolt connector at 33KV

    level.

    We have ceased to use Poly Alsheathed cables in our 33KV system

    and proportionately increased the

    number and cross sectional area of

    the armour wires to compensate

    reduction in area of Poly Al. In our

    modified joint design, the armour

    continuity is being done using

    aluminum connector which has not

    only eliminated the bimetallic effect

    of the spring band but also reduced

    the number of junctions in the path

    of the flow of the circulating current.

    In the process we have done away

    with Copper braid which was

    responsible for ingress of moisture

    inside the joint when the

    encapsulation was not proper. We

    have also selectively gone for single

    end bonding with the other end

    earthed through SVL for long circuits

    lengths where the sheath circulatingcurrent are considerably high. For

    short circuit lengths where the

    sheath induced voltage is within

    limits we have gone for single end

    bonding.

    We have identified the repetitivespike prone cable routes and

    replaced the same as far as

    practicable to minimize the numberof cable breakdowns caused due to

    the presence of innumerable joints

    in between a small cable length and

    thereby reducing chances of failure.

    Our 11KV grade cables hadpreviously PVC as outer sheath

    material which was subsequently

    changed to HDPE owing to its tough

    and rigid property in view to protect

    the cable components from spiking.It is also stressed upon to adhere to

    the installation protocols of HT

    cables regarding depth and

    protection by tiles to minimize

    chance of direct spiking.

  • 7/28/2019 Cesc Cable Joints

    15/15

    Conclusion

    Post mortem of fault is always a probableassumption of the cause of failure as the

    direct evidence for the failure is often

    disappeared in the flashover occurred

    during the fault. This makes confident

    reconstruction of failure difficult as most

    important clues are often lost. In this paper

    we have tried to explain how failure

    analysis of joints and terminations help us

    to establish the most probable cause of

    failure and subsequently give us a directionin which future modifications of cable and

    joint designs should be carried out to

    prevent such failures.

    However, a more futuristic method would

    be an analysis which can detect a failure

    before It actually occurs, thereby ensuring

    that all the evidences of the root cause

    which is responsible for the imminent

    failure are still alive. We in CESC are nowtrying to preempt failures using state of the

    art Condition Monitoring equipments which

    detect abnormal hot spots, partial

    discharges occurring in the joints and

    terminations while they are in service. Any

    abnormalities detected in any joint or

    termination is further analyzed after

    arranging a planned shutdown to ascertain

    the root cause and take necessary

    corrective measures. This technique not

    only helps us to avert possible shutdown or

    blackouts associated with joint or cable

    breakdown but also helps us to pinpoint the

    root cause more accurately.