cet+iia+p id+exercise+2013+ +rev+c

Upload: nicole-lee

Post on 31-Oct-2015

29 views

Category:

Documents


0 download

TRANSCRIPT

  • B. Hallmark

    August 2012

    -1-

    Department of Chemical Engineering and Biotechnology

    University of Cambridge

    CET IIA Exercise 4 Plant control and P&ID drafting

    Submission: Thursday 21

    st February, by 15:00 hrs. Submission via Camtools site ChemEng

    BioT 2011 of P&ID in PDF format, A3 page size and 2-page commentary, A4 page size, in

    PDF format.

    The objectives of this exercise are:

    1. To gain understanding of steady state and unsteady state plant behaviour using

    UniSim dynamics;

    2. To understand the function of various control loops placed on a section of plant using

    UniSim dynamics;

    3. To draft a P&ID for a section of plant using information gained from objectives (1)

    and (2).

    Process description

    The plant section under study can be considered to be a candidate storage and volatiles

    separation system that would precede the distillation columns that were designed in Exercise

    2; the plant flowsheet is shown in Figure 1.

  • B. Hallmark

    August 2012

    -2-

    Figure 1. Plant flowsheet

  • B. Hallmark

    August 2012

    -3-

    Middle oil from a coal tar distillation plant that is contaminated with n-pentane is stored in a

    heated tank, V-100, under a nitrogen blanket. This oil is pumped from the tank by P-100 and

    flows through two pre-heaters, E-101 and E-100. E-101 recovers heat from the exiting

    process stream to pre-heat the oil and E-100 uses high pressure steam to bring the oil to the

    required temperature. A pipe, PIPE-100, having a defined volume joins these two heat

    exchangers. The hot oil is then flashed in V-101, with the resultant vapour stream being rich

    in n-pentane. The liquid stream from V-101 passes through PIPE-101 that has a defined

    volume, through the feed pre-heater E-101 and onto the next section of the plant. The plant is

    sited in a windy part of northern Canada, and operation is studied during early spring where

    the maximum day-time temperature is 25 C and the minimum night-time temperature is

    -20 C; all vessels and pipes are subject to heat loss.

    Task 1 understanding start up, steady state and shutdown control

    Download the file CETIIA-Exercise4.usc from Camtools and load it into UniSim. A

    separate handout has been made available that describes the various features of this

    simulation and how to use the simulation controls; please ensure that you have read and

    understood this document before proceeding any further. Remember that you can stop the

    integrator at any time during the course of a simulation and examine data for streams and unit

    operations in exactly the same way that you would for a steady state simulation. It must be

    remembered that only key control loops have been included in this simulation.

    a. Plant start up.

    Run the simulation for an elapsed time of 400 minutes and then halt it. Write brief

    explanatory notes on the operation of the following control loops:

    i. LIC-100. Observe the level in V-100 (red trace on levels graph) and the position of

    valve VLV-100 (red trace on valve position graph);

    ii. TIC-102. Observe the temperature of V-100 (red trace of temperature graph) and the

    position of valve controlling the steam supply into V-100 (cyan trace on valve

    position graph);

    b. Steady state operation

    Continue running the plant simulation until an elapsed time of 1600 minutes is reached. Halt

    the simulation. Write brief explanatory notes on the behaviour of the control loops listed in

    section (a) and of the n-pentane composition of the vapour exiting the flash drum, V-101

    (blue trace on levels and composition graph). For reference, the pink trace on the flows graph

    corresponds to the ambient air temperature.

  • B. Hallmark

    August 2012

    -4-

    c. Plant shut down

    Save your simulation at 1600 minutes before continuing into the shut down phase. Once

    saved, run the simulation and implement the following shut-down strategy:

    i. With the simulation stopped, put the control loop T-101 into manual mode and

    change the set point of LIC-100 (level in V-100) to around 2 %.

    ii. Run the simulation for an elapsed time of about 150 minutes and then halt it.

    iii. Put all remaining control loops into manual mode and (i) remove the remaining liquid

    from flash drum V-101 by fully opening the control valve VLV-104 and (ii) manually

    close the HP steam control valve, VLV-102.

    iv. Run the simulation until a negative pressure warning is flagged. Stop the simulation.

    v. Examine the levels in vessels V-100 and V-101 and observe any key warnings

    returned by the simulation.

    Make brief explanatory notes on the additional control measures that would need to be

    implemented on the plant to ensure safe shut down, based on your observation of the shut

    down behaviour of the plant. Also detail the mechanical design considerations that you would

    need to include for tank V-100 to ensure that the vessel will be safe for entry during a

    maintenance period.

    Task 2 P&ID drafting

    Now that you have explored the dynamic behaviour of the plant and considered the additional

    control aspects and mechanical design implications for V-100, draw a P&ID of the section of

    the plant outlined in Figure 2. Use Visio to prepare your P&ID with the paper size set to A3.

  • B. Hallmark

    August 2012

    -5-

    Figure 2. Highlight shows section of plant to be drafted as a P&ID

  • B. Hallmark

    August 2012

    -6-

    Remember that your P&ID should clearly indicate every pipe, valve and control system that

    is used to control the process. Standard symbols should be used to indicate unit operations

    and instrumentation should be drawn and tagged according appropriate international

    standards. You may assume that all piping has a nominal diameter of 80 mm. Where control

    signals come from other parts of the plant, use flags in a similar way to process streams. In

    addition to the illustrating the control loops in the simulation, the following aspects should be

    addressed:

    The tank should not overflow whilst being filled.

    P-100 should not cavitate if the tank is accidentally emptied.

    P-100 needs to be started and tested prior to starting up the rest of the plant.

    The tank should not collapse when it is being emptied.

    The tank should not over-pressurise on a hot day.

    Provision needs to be made to take samples from the tank for laboratory analysis.

    The total amount of product fed to the tank from the ship needs to be recorded.

    The total amount of product taken from the tank by the process needs to be

    recorded.

    During shutdowns, people need to be able to enter the tank (with breathing

    apparatus) to inspect the interior.

    Submission

    The explanatory notes prepared for Task 1 should be no longer than two sides of A4 with a

    minimum font size of 11 point; note that this is not a full report, but it must convey your

    observations and explanations concisely. Please submit this document as a PDF file. The

    P&ID prepared for Task 2 should consist of one A3 worksheet. Please also submit this

    document as a PDF file.

    Your PDFs should be submitted to the Camtools site ChemEng BioT 2011 by Thursday

    February 21st at 15:00. Late submissions will generate zero marks unless you have a genuine

    reason, in which case a tutors note from a Tutor or DoS should be sent to Dr Bart Hallmark

    within five calendar days of the deadline.

    Advice

    Accurate P&IDs take time to create. Clear P&IDs also take time. Bad P&IDs can be drawn

    very quickly. You are advised to give yourself sufficient time to be able to not only draw, but

    check and revise your P&ID up to three or four times. Do not leave this exercise to the day

    before the deadline - unless you want to fail.