ID SL.NO

Task Name Duration Start Finish

1 1 Design Varification by BUET 30 days Wed 2/5/14 Thu 3/6/142 2 Approval of Design by BSCIC 20 days Thu 2/20/14 Tue 3/11/143 3 Mobilization 21 day... Wed 2/12/14 Tue 3/4/144 Mobilization 0 days? Wed 2/12/14 Wed 2/12/145 Mobilization 0 days? Tue 3/4/14 Tue 3/4/146 Equipment mobilization 21 days Wed 2/12/14 Tue 3/4/147 Materials Mobilization and approval10 days Wed 2/12/14 Fri 2/21/148 Design Mix approval 21 days Wed 2/12/14 Tue 3/4/149 4 Civil Works 478 da... Sat 2/22/14 Wed 7/1/1510 Test piles 28 days Sat 2/22/14 Fri 3/21/1411 Manufacturing of test piles 7 days Sat 2/22/14 Fri 2/28/1412 Driving of test piles 6 days Sat 3/1/14 Thu 3/6/1413 Tesing of test piles 15 days Fri 3/7/14 Fri 3/21/1414 Service pile and civil works 450 da... Sat 3/22/14 Wed 7/1/1515 SLUDGE DEWATERING

DOSING ROOM210 days Sat 3/22/14 Mon 11/3/14

16 OXIDATION DITCH- B 300 days Sat 3/22/14 Sun 2/1/1517 OXIDATION DITCH- A 300 days Mon 4/21/14 Tue 3/3/1518 PRE-AREATION

EQUALISATION TANK210 days Sat 3/22/14 Mon 11/3/14

19 SLUDGE THICKENING &REACTION TANK

120 days Tue 11/4/14 Tue 3/3/15

20 GENERAL BUILDING 300 days Sat 3/22/14 Sun 2/1/1521 DOSING & BLOWER ROOM 120 days Sat 3/22/14 Sat 7/19/1422 TRANSFORMER ROOM 1 & 2300 days Sat 3/22/14 Sun 2/1/1523 DISINFECTING TANK 180 days Tue 11/4/14 Sat 5/2/1524 ENTRANCE GATE 160 days Tue 11/4/14 Sun 4/12/1525 ROADS AND DRAINS 240 days Tue 11/4/14 Wed 7/1/1526 MISCELLANEOUS WORKS 270 days Sat 3/22/14 Fri 1/2/1527 5 EPS1 240 days Wed 3/5/14 Sun 11/16...28 6 EPS2 300 days Wed 3/5/14 Thu 1/15/1529 7 EPS3 330 days Wed 3/5/14 Sat 2/14/1530 8 Electro-Mechanical works 460 da... Wed 3/12/14 Wed 7/1/1531 Manufacturing of Equipments

and accessories150 days Wed 3/12/14 Fri 8/15/14

32 Opening LC 30 days Wed 3/12/14 Thu 4/10/1433 Pre-shipment Inspection 30 days Fri 4/11/14 Sat 5/10/1434 Shipment 90 days Sun 5/11/14 Fri 8/15/1435 Clearance and transport to site 60 days Tue 6/10/14 Fri 8/15/1436 Erection and Installation 360 days Fri 6/20/14 Wed 7/1/1537 9 Common Chrome Recovery Unit 300 days Wed 3/5/14 Thu 1/15/1538 10 Collection and Conveyance System350 days Wed 3/5/14 Fri 3/6/1539 11 Sludge Dumping yard 350 days Wed 3/5/14 Fri 3/6/1540 12 Commissioning and

stabilization(6 Months)180 days Thu 7/2/15 Mon

12/28/1541 13 As built Drawings 60 days Sun 5/3/15 Wed 7/1/1542 14 Visit for checking Manufacturing

Process7 days Mon 4/21/14 Sun 4/27/14

43 15 Operation Training China 7 days Mon 4/28/14 Sun 5/4/1444 16 Operation Traing Bangladesh 7 days Mon 5/5/14 Sun 5/11/14

2/123/4

B M E B M E B M E B M E B M E B M E B M E B M E B M E B M E B M E B M E B M E B M E B M E B M E B M E B M E B M E B M E B M E B M E B M E BFeb '14 Mar '14 Apr '14 May '14 Jun '14 Jul '14 Aug '14 Sep '14 Oct '14 Nov '14 Dec '14 Jan '15 Feb '15 Mar '15 Apr '15 May '15 Jun '15 Jul '15 Aug '15 Sep '15 Oct '15 Nov '15 Dec '15 Jan '16Month 1 Month 2 Month 3 Month 4 Month 5 Month 6 Month 7 Month 8 Month 9 Month 10 Month 11 Month 12 Month 13 Month 14 Month 15 Month 16 Month 17 Month 18 Month 19 Month 20 Month 21 Month 22 Month 23 Month 24

Task

Split

Milestone

Summary

Project Summary

External Tasks

External MileTask

Critical

Inactive Task

Inactive Milestone

Inactive Summary

Manual Task

Duration-only

Manual Summary Rollup

Manual Summary

Start-only

Finish-only

Progress

Split

Work Schedule For Turnkey Construction and Implementation of Common Tannery EffluentPlant including collection and conveyance system, Common Chrome recovery Unit, Solid Waste

Dumping Yard and Central Laboratory of Tannery Estate,Dhaka.