CF MEP Commissioning. CF Commissioning Plan. Commissioning Plan (CP) developed by Jacobs Facilities (Engineer of Record) Title II project deliverable Reviewed and approved by LCLS CF Eng group leader – Javier Sevilla - PowerPoint PPT Presentation

TRANSCRIPT

Page 1: CF MEP Commissioning

David Saenz

CF Commissioning [email protected]

Oct 30, 2007 1

CF MEP Commissioning

Page 2: CF MEP Commissioning

David Saenz

CF Commissioning [email protected]

Oct 30, 2007 2

CF Commissioning PlanCommissioning Plan (CP) developed by Jacobs Facilities (Engineer of Record)

Title II project deliverableReviewed and approved by LCLS CF Eng group leader – Javier Sevilla

CP includes a comprehensive list of field deliverables and requirements that meet expectations of LCLS

AdministrationDetailed scope of Commissioning workQuality Control PlanTesting and Training Schedule

Field Plumbing and Fire Protection SystemsMechanical SystemsElectrical SystemsElevator and Crane SystemsDemonstration and Testing

CP managed by 3rd party subcontractor, independent of trades and Turner, hired by LCLS

Page 3: CF MEP Commissioning

David Saenz

CF Commissioning [email protected]

Oct 30, 2007 3

Beam Transport Hall – Undulator Hall

Far Experimental Hall –

Electron Beam Dump

Front End Enclosure

Near Experimental Hall/Central Utility Plant/12Kv Substation

X-Ray Transport & Diagnostics Tunnel

Commissioning Areas

Page 4: CF MEP Commissioning

David Saenz

CF Commissioning [email protected]

Oct 30, 2007 4

Beam Transport Hall (BTH)

Page 5: CF MEP Commissioning

David Saenz

CF Commissioning [email protected]

Oct 30, 2007 5

BTH Looking East

Drawings

M4201

A2200

SB 2.3

AHU

Storage tank for runoff water from tunnels

Ductwork

Page 6: CF MEP Commissioning

David Saenz

CF Commissioning [email protected]

Oct 30, 2007 6

NEH

Page 7: CF MEP Commissioning

David Saenz

CF Commissioning [email protected]

Oct 30, 2007 7

NEH Cross SectionHVAC ducting

M4602

Page 8: CF MEP Commissioning

David Saenz

CF Commissioning [email protected]

Oct 30, 2007 8

CUP

Page 9: CF MEP Commissioning

David Saenz

CF Commissioning [email protected]

Oct 30, 2007 9

CUP Plan View Drawing M0203

Electrical Rm

Chillers

Boilers

Mech Room-NEH

Page 10: CF MEP Commissioning

David Saenz

CF Commissioning [email protected]

Oct 30, 2007 10

CENTRAL UTILITY PLANT (CUP)

Title II-IFCTwo Chillers (425 tons/ea), Primary and Secondary CHW loops and Pumps BTH,UH,EBD,FEE, NEH and FEH

One Boiler (150 BHP/ea) Primary and Secondary HW loops and pumps

DDC Temperature Control System to be connected to SLAC network via Web Control

One Air Compressor (268 SCFM@150psi), Air Dryer and Receiver.Will provide service to: BTH, UH, EBD, FEE, NEH,X-RAY, FEH

Wet Sprinkler System-Ordinary Hazard Group 1

One AHU for electrical room

Mechanical room for NEH HVAC system (MAU)

Page 11: CF MEP Commissioning

David Saenz

CF Commissioning [email protected]

Oct 30, 2007 11

Substation 522-Phase I

CUP S522

Page 12: CF MEP Commissioning

David Saenz

CF Commissioning [email protected]

Oct 30, 2007 12

CP ProcurementBased on early estimates, budget was established at $350K

Bids were solicited Aug 07 for CxA (Commissioning Agent)

5 CxA bidders invited4 bidders responded and all 4 were within budget!

Technical evaluation by CF group is completeWeighted point score

Awarded to Engineering Economics Inc (EEI) at $229K

Page 13: CF MEP Commissioning

David Saenz

CF Commissioning [email protected]

Oct 30, 2007 13

CxAEngineering Economics Inc (EEI)

Offices nationwide and able to shift resources if necessary, although not likely

Commissioned over 33 million sfData centers

Medical research labs

Pharmaceutical labs

Federal facilities LCLS Sector 20 Injector Facilities - successful

LCLS Magnetic Measurement Facilities - successful

Page 14: CF MEP Commissioning

David Saenz

CF Commissioning [email protected]

Oct 30, 2007 14

SummaryRoles and responsibilities are clearExpectations are documented and well understoodCxA will be assigned to work with trades, SLAC Facilities maintenance staff and LCLS CF Engineering groupGoal is to deliver a complete and functional project with all MEP systems fully operational, inspected, tested, verified and documented