ch09 finance
TRANSCRIPT
-
8/7/2019 ch09 Finance
1/46
0
Net Present Value and OtherInvestment Criteria
Chapter 9
-
8/7/2019 ch09 Finance
2/46
MBA 819 1
Key Concepts and SkillsBe able to compute payback and discountedpayback and understand their shortcomings
Understand accounting rates of return andtheir shortcomingsBe able to compute the internal rate of returnand understand its strengths and weaknessesBe able to compute the net present value andunderstand why it is the best decisioncriterion
-
8/7/2019 ch09 Finance
3/46
MBA 819 2
Chapter OutlineNet Present Value
The Payback RuleThe Discounted PaybackThe A verage A ccounting Return
The Internal Rate of ReturnThe Profitability IndexThe Practice of Capital Budgeting
-
8/7/2019 ch09 Finance
4/46
MBA 819 3
Good Decision CriteriaWe need to ask ourselves the followingquestions when evaluating decisioncriteria
Does the decision rule adjust for the timevalue of money?
Does the decision rule adjust for risk?Does the decision rule provide informationon whether we are creating value for thefirm?
-
8/7/2019 ch09 Finance
5/46
MBA 819 4
Project Example InformationYou are looking at a new project and youhave estimated the following cash flows:
Year 0: CF = -165,000Year 1: CF = 63,120; NI = 13,620Year 2: CF = 70,800; NI = 3,300Year 3: CF = 91,080; NI = 29,100
A verage Book Value = 82,500Your required return for assets of this risk is12%.
-
8/7/2019 ch09 Finance
6/46
MBA 819 5
Net Present ValueThe difference between the market value of aproject and its cost
Value A dditivity PrincipleHow much value is created from undertakingan investment?
The first step is to estimate the expected future
cash flows.The second step is to estimate the required returnfor projects of this risk level.The third step is to find the present value of thecash flows and subtract the initial investment.
-
8/7/2019 ch09 Finance
7/46
MBA 819 6
NPV Decision RuleIf the NPV is positive, accept the project A positive NPV means that the project isexpected to add value to the firm and willtherefore increase the wealth of the owners.Since our goal is to increase owner wealth,NPV is a direct measure of how well thisproject will meet our goal.However, you may accept a project with annegative NPV for strategic reasons.
-
8/7/2019 ch09 Finance
8/46
MBA 819 7
Computing NPV for the Project Using the formulas:
NPV = 63,120/(1.12) + 70,800/(1.12) 2 +91,080/(1.12) 3 165,000 = 12,627.41
Using the calculator:CF0 = -165,000; CF 1 = 63,120; CF 2 =70,800; CF 3 = 91,080; I/YR = 12; thenyellow NPV = 12,627.41
D o we accept or reject the project?
-
8/7/2019 ch09 Finance
9/46
MBA 819 8
Decision Criteria Test - NPVDoes the NPV rule account for the timevalue of money?
A ssumes reinvestment at the required rate of return
Does the NPV rule account for the risk of the cash flows?
Does the NPV rule provide an indicationabout the increase in value?Should we consider the NPV rule for ourprimary decision criteria?
-
8/7/2019 ch09 Finance
10/46
MBA 819 9
Calculating NPVs with a
Spreadsheet Spreadsheets are an excellent way tocompute NPVs, especially when you have to
compute the cash flows as well.Using the NPV functionThe first component is the required return enteredas a decimalThe second component is the range of cash flowsbeginning with year 1Subtract the initial investment after computing theNPV
-
8/7/2019 ch09 Finance
11/46
MBA 819 10
Payback PeriodHow long does it take to get the initial cost back in a nominal sense?Computation
Estimate the cash flowsSubtract the future cash flows from the initial cost until the initial investment has been recovered
Decision Rule A ccept if the payback period is less than some preset limit
-
8/7/2019 ch09 Finance
12/46
MBA 819 11
Computing Payback For The
Project A ssume we will accept the project if it paysback within two years.
Year 1: 165,000 63,120 = 101,880 still torecoverYear 2: 101,880 70,800 = 31,080 still to recoverYear 3: 31,080 91,080 = -60,000 project pays
back in year 3A nswer is 2 + .34 years or 2.34 years (assumingcash flows are continuous during the year).
D o we accept or reject the project?
-
8/7/2019 ch09 Finance
13/46
MBA 819 12
Decision Criteria Test -
PaybackDoes the payback rule account for the
time value of money?Does the payback rule account for therisk of the cash flows?Does the payback rule provide anindication about the increase in value?Should we consider the payback rule forour primary decision criteria?
-
8/7/2019 ch09 Finance
14/46
MBA 819 13
A dvantages and Disadvantages
of PaybackA dvantages
Easy to understandA djusts foruncertainty of latercash flowsB iased towardsliquidity
DisadvantagesIgnores the time valueof moneyRequires an arbitrarycutoff point Ignores cash flowsbeyond the cutoff dateB
iased against long-term projects, such asresearch anddevelopment, and newprojects
-
8/7/2019 ch09 Finance
15/46
MBA 819 14
Discounted Payback PeriodCompute the present value of each cashflow and then determine how long it takes to payback on a discounted basisCompare to a specified required periodDecision Rule - A ccept the project if it pays back on a discounted basis within the specified time
-
8/7/2019 ch09 Finance
16/46
MBA 819 15
Computing Discounted Payback
for the Project A ssume we will accept the project if it paysback on a discounted basis in 2 years.
Compute the PV for each cash flow anddetermine the payback period usingdiscounted cash flows
Year 1: 165,000 63,120/1.12 1 = 108,643
Year 2: 108,643
70,800/1.122
= 52,202Year 3: 52,202 91,080/1.12 3 = -12,627 project pays back in year 3The answer is 2.57 years.
D o we accept or reject the project?
-
8/7/2019 ch09 Finance
17/46
MBA 819 16
Decision Criteria Test
Discounted PaybackDoes the discounted payback rule account forthe time value of money?Does the discounted payback rule account forthe risk of the cash flows?Does the discounted payback rule provide an
indication about the increase in value?Should we consider the discounted paybackrule for our primary decision criteria?
-
8/7/2019 ch09 Finance
18/46
MBA 819 17
A dvantages and Disadvantages of Discounted Payback
A dvantagesIncludes time valueof moneyEasy to understandDoes not accept negative estimatedNPV investmentsB iased towardsliquidity
DisadvantagesM ay reject positive
NPV investmentsRequires an arbitrarycutoff point Ignores cash flowsbeyond the cutoff point B iased against long-term projects, suchas R&D and newproducts
-
8/7/2019 ch09 Finance
19/46
MBA 819 18
A verage A ccounting ReturnThere are many different definitions foraverage accounting return
The one used in the book is:A verage net income / average book valueNote that the average book value depends on howthe asset is depreciated.
Need to have a target cutoff rateDecision Rule: Acc ept the proje c t if theAAR is greater than a preset rate.
-
8/7/2019 ch09 Finance
20/46
MBA 819 19
Computing AA R For The
Project A ssume we require an average
accounting return of 25%A verage Net Income:(13,620 + 3,300 + 29,100) / 3 = 15,340
AA R = 15,340 / 82,500 = .186 =18.6%
D o we accept or reject the project?
-
8/7/2019 ch09 Finance
21/46
MBA 819 20
Decision Criteria Test - AA RDoes the AA R rule account for the timevalue of money?Does the AA R rule account for the riskof the cash flows?Does the AA R rule provide an indication
about the increase in value?Should we consider the AA R rule for ourprimary decision criteria?
-
8/7/2019 ch09 Finance
22/46
MBA 819 21
A dvantages and
Disadvantages of AA RA dvantages
Easy to calculateNeeded informationwill usually beavailable
DisadvantagesNot a true rate of return; time value of money is ignoredUses an arbitrarybenchmark cutoff rateBased on accounting
net income and bookvalues, not cash flowsand market valuesOvervalues longerprojects
-
8/7/2019 ch09 Finance
23/46
MBA 819 22
Internal Rate of Return (IRR)This is the most important alternative toNPV (also it was the first DCF methodused)It is often used in practice and isintuitively appealing
It is based entirely on the estimatedcash flows and is independent of interest rates found elsewhereA ssumes reinvestment at the IRR
-
8/7/2019 ch09 Finance
24/46
MBA 819 23
IRR Definition and Decision
RuleDefinition: IRR is the return that makesthe NPV = 0Decision Rule: A ccept the project if the I RR is greater than therequired return
-
8/7/2019 ch09 Finance
25/46
MBA 819 24
Computing IRR For The
Project If you did not have a financial calculator,then this calculation becomes a trial anderror processCalculator
Enter the cash flows as you did with NPV
Press yellow IRR/YRIRR = 16.13% > 12% required returnD o we accept or reject the project?
-
8/7/2019 ch09 Finance
26/46
MBA 819 25
NPV Profile For The Project
-20,000
-10,000
0
10,000
20,000
30,000
40,000
50,000
60,000
70,000
0 0.02 0.04 0.06 0.08 0.1 0.12 0.14 0.16 0.18 0.2 0.22
Discount Rate
NPV
IRR = 16.13%
-
8/7/2019 ch09 Finance
27/46
MBA 819 26
Decision Criteria Test - IRRDoes the IRR rule account for the timevalue of money?Does the IRR rule account for the riskof the cash flows?Does the IRR rule provide an indication
about the increase in value?Should we consider the IRR rule for ourprimary decision criteria?
-
8/7/2019 ch09 Finance
28/46
MBA 819 27
A dvantages of IRRKnowing a return is intuitively appealing
It is a simple way to communicate thevalue of a project to someone whodoesn t know all the estimation detailsIf the IRR is high enough, you may not need to estimate a required return,which is often a difficult task
-
8/7/2019 ch09 Finance
29/46
MBA 819 28
Summary of Decisions For The
Project Summary
Net Present ValueA
ccept Payback Period R eject
Discounted Payback Period R eject
A verage A ccounting Return R eject
Internal Rate of Return A ccept
-
8/7/2019 ch09 Finance
30/46
MBA 819 29
Calculating IRRs With A
Spreadsheet You start with the cash flows the same asyou did for the NPVYou use the IRR function
You first enter your range of cash flows, beginningwith the initial cash flowYou can enter a guess, but it is not necessaryThe default format is a whole percent you willnormally want to increase the decimal places toone or two places.
-
8/7/2019 ch09 Finance
31/46
MBA 819 30
NPV Vs. IRRNPV and IRR will generally give us thesame decision
ExceptionsNon-conventional cash flows cash flowsigns change more than onceM utually exclusive projects
Initial investments are substantially different (Size of outflow)Timing of cash flows is substantially different
-
8/7/2019 ch09 Finance
32/46
MBA 819 31
IRR and Non-conventional
Cash FlowsWhen the cash flows change sign more thanonce, there is more than one IRR
When you solve for IRR you are solving forthe root of an equation and when you crossthe x-axis more than once, there will be morethan one return that solves the equation
If you have more than one IRR, which one doyou use to make your decision?Your financial calculator typically will report not found.
-
8/7/2019 ch09 Finance
33/46
MBA 819 32
A n Example Non-conventional
Cash FlowsSuppose an investment will cost $90,000 initially and will generate the
following cash flows:Year 1: 132,000Year 2: 100,000Year 3: -150,000
The required return is 15%.Should we accept or reject the project?
-
8/7/2019 ch09 Finance
34/46
MBA 819 33
NPV Profile
($10 ,000 .00)
($8 ,000 .00)
($6 ,000 .00)
($4 ,000 .00)
($2 ,000 .00)
$0 .00
$2 ,000 .00
$4 ,000 .00
0 0 .05 0 .1 0 .15 0 .2 0 .25 0 . 0 . 5 0 .4 0 .45 0 .5 0 .55
D isc t te
I = 10 .11 % d 42 .66 %
-
8/7/2019 ch09 Finance
35/46
MBA 819 34
Summary of Decision RulesThe NPV is positive at a required returnof 15%, so you should A ccept
If you use the HP 10 B II financialcalculator, you would get an IRR of not found.
You need to recognize that there arenon-conventional cash flows and look at the NPV profileUse the Net Present Value for decision
-
8/7/2019 ch09 Finance
36/46
MBA 819 35
IRR and M utually Exclusive
ProjectsM utually exclusive projects
If you choose one, you can t choose the other
Example: You can choose to purchase a ToyotaCamry or a Ford Taurus, but not both
Intuitively you would use the followingdecision rules:
NPV choose the project with the higher NPVIRR choose the project with the higher IRR
-
8/7/2019 ch09 Finance
37/46
MBA 819 36
Example With M utually ExclusiveProjects
Period Project A
Project B
0 -500 -400
1 325 325
2 325 200
IRR 19.43% 22.17%
NPV 64.05 60.74
The required return
for both projects is10%.
Which projectshould you acceptand why?
-
8/7/2019 ch09 Finance
38/46
MBA 819 37
NPV Profiles
($40 .00)
($20 .00)$0 .00
$20 .00
$40 .00
$60 .00
$80 .00
$100 .00
$120 .00
$140 .00
$160 .00
0 0 .05 0 .1 0 .15 0 .2 0 .25 0 .
D isc t te
AB
I f r A = 19 .43 %
I f r B = 22 .17 %
Cr ss ver i t = 11 .8%
-
8/7/2019 ch09 Finance
39/46
MBA 819 38
Conflicts Between NPV and
IRRNPV directly measures the increase in valueto the firm (Value A dditivity)
Whenever there is a conflict between NPVand another decision rule, you shouldalways use NPVIRR is unreliable in the following situations
Non-conventional cash flowsM utually exclusive projects
-
8/7/2019 ch09 Finance
40/46
MBA 819 39
Profitability IndexM easures the benefit per unit cost, based onthe time value of money ( Bang for theB
uck
)A profitability index of 1.1 implies that forevery $1 of investment, we create anadditional $0.10 in value
This measure can be very useful in situationswhere we have limited capitalThis technique is used in capital rationing.
-
8/7/2019 ch09 Finance
41/46
MBA 819 40
A dvantages and Disadvantages of Profitability Index
A dvantagesClosely related to NPV,generally leading toidentical decisionsEasy to understand andcommunicate
M ay be useful whenavailable investment funds are limited
DisadvantagesM ay lead to incorrect decisions incomparisons of mutually exclusiveinvestments
-
8/7/2019 ch09 Finance
42/46
-
8/7/2019 ch09 Finance
43/46
MBA 819 42
Summary Discounted Cash
Flow CriteriaNet present value
Difference between market value and cost Take the project if the NPV is positiveHas no serious problemsPreferred decision criterion
Internal rate of returnDiscount rate that makes NPV = 0Take the project if the IRR is greater than required returnSame decision as NPV with conventional cash flowsIRR is unreliable with non-conventional cash flows or mutuallyexclusive projects
Profitability IndexBenefit-cost ratioTake investment if PI > 1Cannot be used to rank mutually exclusive projectsM ay be used to rank projects in the presence of capital rationing
-
8/7/2019 ch09 Finance
44/46
MBA 819 43
Summary
Payback CriteriaPayback period
Length of time until initial investment is recoveredTake the project if it pays back in some specifiedperiodDoesn t account for time value of money andthere is an arbitrary cutoff period
Discounted payback period
Length of time until initial investment is recoveredon a discounted basisTake the project if it pays back in some specifiedperiodThere is an arbitrary cutoff period
-
8/7/2019 ch09 Finance
45/46
MBA 819 44
Summary A ccounting
CriterionA verage A ccounting ReturnM easure of accounting profit relative to
book valueSimilar to return on assets measureTake the investment if the AA R exceedssome specified return levelSerious problems and should not beused
But it is used in industry, and it may
determine compensation of the manager.
-
8/7/2019 ch09 Finance
46/46
MBA 819 45
ConclusionCapital Investment Decision Techniques
Net Present ValuePayback PeriodDiscounted PaybackInternal Rate of ReturnProfitability IndexA ccounting Rate of Return
Industry usage