PETER JACOBSSON MARTINSON TRÄBROAR AB www.martinsons.se CHALLENGES OF THE SUPERSTRUCTURE ”ÄLVSBACKA BRIDGE” ICTB 2013

Upload: others

Post on 04-Apr-2020

1 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: CHALLENGES OF THE SUPERSTRUCTURE ”ÄLVSBACKA BRIDGE” · challenges of the superstructure ... can the bridge deck be pulled out instead of lifted out? - erecting the pylons & long

PETER JACOBSSON

MARTINSON TRÄBROAR AB

www.martinsons.se

CHALLENGES OF THE SUPERSTRUCTURE ”ÄLVSBACKA BRIDGE”

ICTB 2013

Page 2: CHALLENGES OF THE SUPERSTRUCTURE ”ÄLVSBACKA BRIDGE” · challenges of the superstructure ... can the bridge deck be pulled out instead of lifted out? - erecting the pylons & long

ICTB 2013

OUTLINE - What has been built

- Background to the chosen solution - Assembly method

- Conclusions

Page 3: CHALLENGES OF THE SUPERSTRUCTURE ”ÄLVSBACKA BRIDGE” · challenges of the superstructure ... can the bridge deck be pulled out instead of lifted out? - erecting the pylons & long

ICTB 2013

WHAT HAS BEEN BUILT ? CABLE STAYED BRIDGE IN TIMBER - Distance between pylons, span length: 130 m, total length 182 m. - Free width of decking: 4 m - Height of pylons: 24 m - Amount of timber: Approximately 200 ton, 400 m3 - Amount of steel: Approximately 70 ton, 9 m3 - PERFORMED ACCORDIN

- PERFORMED ACCORDING TO THE SWEDISH BRIDGE CODE “BRO 2004”

- DESIGN WORK COWI & MARTINSONS

Page 4: CHALLENGES OF THE SUPERSTRUCTURE ”ÄLVSBACKA BRIDGE” · challenges of the superstructure ... can the bridge deck be pulled out instead of lifted out? - erecting the pylons & long

ICTB 2013

BUILT IN SKELLEFTEÅ CITY 2011, CROSSING THE ”SKELLEFTEÅ RIVER ” CLIENT- MUNICIPALITY OF SKELLEFTEÅ

Page 5: CHALLENGES OF THE SUPERSTRUCTURE ”ÄLVSBACKA BRIDGE” · challenges of the superstructure ... can the bridge deck be pulled out instead of lifted out? - erecting the pylons & long

ICTB 2013

BACKGROUND TO THE BUILT SOLUTION INITIALLY SUGGESTED DESIGN FROM THE MUNICIPALITY IN COOPERATION WITH A LOCAL ARCHITECT

DISADVANTAGE: - THE COST MUCH HIGHER

THAN THE MUNICIPALITIES BUDGET

ADVANTAGES: - DOES NOT INTRUDE ON THE LANDAREA - CONSIDERD AS ESTETHICAL AND A GREAT LANDMARK

Page 6: CHALLENGES OF THE SUPERSTRUCTURE ”ÄLVSBACKA BRIDGE” · challenges of the superstructure ... can the bridge deck be pulled out instead of lifted out? - erecting the pylons & long

ICTB 2013

- A NEW EVALUATION PROCESS WITH LESS REQUIREMENTS ON APPEARANCE TOOK PLACE

- IF THE SUPPORT IN THE RIVER COULD BE EXCLUDED A LOT OF THE COST WOULD DISAPPEAR.

- SUGGESTED SOLUTION FROM MARTINSONS AND COWI

- THE MUNICIPALITY CHOOSE TO CONTRACT MARTINSONS TO BUILD THIS SOLUTION

Page 7: CHALLENGES OF THE SUPERSTRUCTURE ”ÄLVSBACKA BRIDGE” · challenges of the superstructure ... can the bridge deck be pulled out instead of lifted out? - erecting the pylons & long

ICTB 2013

- MAIN CHALLENGES

- ASSEMBLY METHOD

- DYNAMIC BEHAVIOUR - LARGE STATIC FORCES THAT HAD TO BE TAKEN CARE OF

- PERFORMANCE TO ACHEIVIE A LONG LIFETIME AND PROTECTION

AGAINST MOISTURE INFLUENCE.

Page 8: CHALLENGES OF THE SUPERSTRUCTURE ”ÄLVSBACKA BRIDGE” · challenges of the superstructure ... can the bridge deck be pulled out instead of lifted out? - erecting the pylons & long

ICTB 2013

IDEA OF ASSEMBLING METHOD CAN THE BRIDGE DECK BE PULLED OUT INSTEAD OF LIFTED OUT? - ERECTING THE PYLONS & LONG BARS WITH TRANSVERSE BEAM - STRETCHING UP THE BAR SYSTEM - PULLING OUT THE BRIDGE DECK PIECES.

- A LOT OF TIME WAS SPENT DURING DESIGN WORK TO MAKE THE METHOD FEASIBLE AND EFFECTIVE

Page 9: CHALLENGES OF THE SUPERSTRUCTURE ”ÄLVSBACKA BRIDGE” · challenges of the superstructure ... can the bridge deck be pulled out instead of lifted out? - erecting the pylons & long

ICTB 2013

ASSEMBLING METHOD – TWO TEMPORARY CABLES

Page 10: CHALLENGES OF THE SUPERSTRUCTURE ”ÄLVSBACKA BRIDGE” · challenges of the superstructure ... can the bridge deck be pulled out instead of lifted out? - erecting the pylons & long

ICTB 2013

ASSEMBLING METHOD – PULLING OUT BARS AND TRANSVERSE MID BEAM

Page 11: CHALLENGES OF THE SUPERSTRUCTURE ”ÄLVSBACKA BRIDGE” · challenges of the superstructure ... can the bridge deck be pulled out instead of lifted out? - erecting the pylons & long

ICTB 2013

ASSEMBLING METHOD – PYLONS TO NORTH BRIDGE SITE ON THEIR WAY..

Page 12: CHALLENGES OF THE SUPERSTRUCTURE ”ÄLVSBACKA BRIDGE” · challenges of the superstructure ... can the bridge deck be pulled out instead of lifted out? - erecting the pylons & long

ICTB 2013

ASSEMBLING METHOD – PYLONS READY TO BE ERECTED

Page 13: CHALLENGES OF THE SUPERSTRUCTURE ”ÄLVSBACKA BRIDGE” · challenges of the superstructure ... can the bridge deck be pulled out instead of lifted out? - erecting the pylons & long

ICTB 2013

ASSEMBLING METHOD – PYLONS ON THEIR WAY UP

Page 14: CHALLENGES OF THE SUPERSTRUCTURE ”ÄLVSBACKA BRIDGE” · challenges of the superstructure ... can the bridge deck be pulled out instead of lifted out? - erecting the pylons & long

ICTB 2013

ASSEMBLING METHOD – PYLONS IN PLACE

Page 15: CHALLENGES OF THE SUPERSTRUCTURE ”ÄLVSBACKA BRIDGE” · challenges of the superstructure ... can the bridge deck be pulled out instead of lifted out? - erecting the pylons & long

ICTB 2013

ASSEMBLING METHOD – PULLING OUT BARS AND TRANSVERSE BEAMS

Page 16: CHALLENGES OF THE SUPERSTRUCTURE ”ÄLVSBACKA BRIDGE” · challenges of the superstructure ... can the bridge deck be pulled out instead of lifted out? - erecting the pylons & long

ICTB 2013

ASSEMBLING METHOD – FIRST BRIDGE DECK PIECE ON SITE

Page 17: CHALLENGES OF THE SUPERSTRUCTURE ”ÄLVSBACKA BRIDGE” · challenges of the superstructure ... can the bridge deck be pulled out instead of lifted out? - erecting the pylons & long

ICTB 2013

ASSEMBLING METHOD – PASSING MIDSPAN

Page 18: CHALLENGES OF THE SUPERSTRUCTURE ”ÄLVSBACKA BRIDGE” · challenges of the superstructure ... can the bridge deck be pulled out instead of lifted out? - erecting the pylons & long

ICTB 2013

ASSEMBLING METHOD – IN POSITION FOR THE FOURTH BRIDGE DECK

Page 19: CHALLENGES OF THE SUPERSTRUCTURE ”ÄLVSBACKA BRIDGE” · challenges of the superstructure ... can the bridge deck be pulled out instead of lifted out? - erecting the pylons & long

ICTB 2013

ASSEMBLING METHOD – BRIDGE DECK IN POSITION

REMAINING WORK FOR 2-3 WEEKS - ADJUSTMENTS - PERMANENT LOOKING - REMOVING TEMPORARY MATERIAL - INSTALLATIONS - REAMINING CLADDING

COMPLETING THE CONCRETE FOUNDATION

Page 20: CHALLENGES OF THE SUPERSTRUCTURE ”ÄLVSBACKA BRIDGE” · challenges of the superstructure ... can the bridge deck be pulled out instead of lifted out? - erecting the pylons & long

ICTB 2013

CONCLUSIONS

- The assembly method - worked out well and is definitely something we will use again if the

opportunity comes up. - can be refined to achieve an even more effective method. - handled 270 ton material with only a small barge in he river. Can it be don

without the barge? – That’s a future challenge we would like to evaluate.

- THE ”Älvsbacka” bridge is frequentley used every day and is appreciated of the citizens

- Very positive response from users – dynamic response OK! - The client, Municipality of Skellefteå, is very satisfied

Page 21: CHALLENGES OF THE SUPERSTRUCTURE ”ÄLVSBACKA BRIDGE” · challenges of the superstructure ... can the bridge deck be pulled out instead of lifted out? - erecting the pylons & long

ICTB 2013

THANK YOU FOR YOUR ATTENTION!