change control management

Upload: harold-taylor

Post on 04-Apr-2018

222 views

Category:

Documents


0 download

TRANSCRIPT

  • 7/30/2019 Change Control Management

    1/18

    Change Control

    Management

    Student name : Bandar M. AL-ShubailyPIN : 425035524

    Submitted toProf. Tomas Ucol Ganiron Jr

    1

  • 7/30/2019 Change Control Management

    2/18

    2

    Change Control

    Kellys Concept

    The Wright Brothers greatinsight was that instability

    was necessary formaneuverability. A ponderous

    bird would not fly.

  • 7/30/2019 Change Control Management

    3/18

    3

    Module Overview

    Objectives of change management

    Requirements for good changemanagement

  • 7/30/2019 Change Control Management

    4/18

    4

    Types of Changes

    Scope changes (modify productdocumentation and often project plan):

    Requirements change

    Clarifications Site emergencies

    Work changes (modify project plan): Resource change

    Modified approach Corrective action

  • 7/30/2019 Change Control Management

    5/18

    5

    Definition:Corrective Action

    Steps taken to align future project

    direction with the stakeholderssuccess measures.

  • 7/30/2019 Change Control Management

    6/18

    6

    Evaluating Change Requests

    All change requests are documented: Emergency changes are documented after

    the fact.

    Non-emergencies are documented by therequestor before being considered.

    Change requests should be documentedby the requestor.

  • 7/30/2019 Change Control Management

    7/18

    7

    First Level Approvalof Change Requests

    Usually provided by the project manageror a senior team member:

    Are the expected benefits significant

    enough to merit further investigation? Implications:

    Must have budget for this work!

    Benefits may include cost avoidance

    Organizational politics must be considered

  • 7/30/2019 Change Control Management

    8/18

    8

    Second Level Approval of ChangeRequests

    Usually provided by a Change ControlBoard (CCB):

    Do the expected benefits outweigh the

    costs?

  • 7/30/2019 Change Control Management

    9/18

    9

    Other Considerations

    Life cycle costing purchase cost vs.operating cost:

    Three-lane bridge, two-lane road

    Re-usable code Item costing for quantity-based

    changes: Fixed costs = cost to deliver first unit

    Variable costs = cost per unit

  • 7/30/2019 Change Control Management

    10/18

    10

    Tools and Techniques for ChangeControl

    Change control board (CCB)

    Escalation procedures Work authorization

    Configuration management

  • 7/30/2019 Change Control Management

    11/18

    11

    Change Control Board

    A formally constituted group responsiblefor approving or rejecting changerequests.

    Powers and responsibilities should bewell-defined and agreed upon in advance.

    On larger, more complex projects, theremay be multiple CCBs.

  • 7/30/2019 Change Control Management

    12/18

    12

    Escalation Procedures

    How are differences within the teamhandled?

    Can a CCB decision be appealed? Can

    other decisions be appealed? To whom?

    Under what circumstances?

  • 7/30/2019 Change Control Management

    13/18

    13

    Configuration Management A procedure for applying technical and

    administrative direction and surveillanceto:

    Identify and document the functional andphysical characteristics of an item orsystem.

    Control any changes to such characteristics.

    Record and report the change and itsimplementation status.

    Audit the items and system to verifyconformance to requirements.

  • 7/30/2019 Change Control Management

    14/18

    14

    In Simpler Words

    Is the document current and complete?

    Can you prove it?

  • 7/30/2019 Change Control Management

    15/18

    15

    Summary of

    Key Points

    Change control procedures must bedefined at the start of the project.

    Project budgets must include funds forevaluating change requests.

    Approved changes should generally

    result in updated baselines.

  • 7/30/2019 Change Control Management

    16/18

    7-2 PM responsibility

    The Project Manager needs to measureperformance to find out how progressdiffers from plan in time to initiatecorrective action. The controlling activityoften cause a redefinition of projectobjectives

    16

  • 7/30/2019 Change Control Management

    17/18

    7-2 PM responsibility

    PM produce a Status report including : What did we plan to achieve this period? What did we actually achieve? Why is there a difference? What do we plan to achieve next period? How are we managing existing risks? Are there any new risks? What are the current major issues? What are we doing about them? Are there any change requests to be authorised?

    17

  • 7/30/2019 Change Control Management

    18/18

    www.qec.com.sa:Refrancsection : Prof. Tomas Ucol Ganiron Jr

    Thank you for listing

    for all

    Prepared by Pr Sulaymane Alyahya-

    Pr Abdelghani Toumi 18

    http://www.qec.com.sa/http://www.qec.com.sa/