chapter 12 network scheduling techniques. scheduling techniques gantt or bar charts gantt or bar...
TRANSCRIPT
Chapter 12Chapter 12
Network Network SchedulingSchedulingTechniquesTechniques
Scheduling Scheduling TechniquesTechniques
• Gantt or bar chartsGantt or bar charts
• Milestone chartsMilestone charts
• Line BalancingLine Balancing
• NetworksNetworks– Program Evaluation and Review Technique (PERT)Program Evaluation and Review Technique (PERT)– Arrow Diagram Method (ADM) also called the Arrow Diagram Method (ADM) also called the
Critical Path Method (CPM)Critical Path Method (CPM)– Graphical Evaluation and Review Technique Graphical Evaluation and Review Technique
(GERT)(GERT)– Precedence Diagram Method (PDM)Precedence Diagram Method (PDM)
Scheduling AdvantagesScheduling Advantages
• Needed for planningNeeded for planning
• Evaluate alternatives (what-if’s)Evaluate alternatives (what-if’s)
• Resource schedulingResource scheduling
• ControllingControlling
Bar (Gantt) ChartsBar (Gantt) Charts
TASKS 1 2 3 4 5
4
MONTHS AFTER GO-AHEAD
3
2
1
5
Milestone Milestone ChartChart
ACTIVITY
TESTINGANALYSISREPORTPRESENTATION
TIME
Standard PERT Standard PERT NomenclatureNomenclature
6 3
COMPLETE TESTING COMPLETE FINAL REPORT
3 WEEKS
LEGENDLEGEND
EVENT
ACTIVITY
DependencieDependenciess
7
26 18
31
7
18
31
26
BURST POINT SINK
Simplified PERT Simplified PERT NetworkNetwork
1 9
3
4
2 8765
LEGEND: (TIME = WEEKS)
EVENTACTIVITYCRITICAL PATH ACTIVITY
Dummy Dummy ActivitiesActivities
A
B
C
D
DUMMY
ACTIVITYPRECEDING
ACTIVITYA - B - C B D A,B
NETWORK FOR HOUSE NETWORK FOR HOUSE CONSTRUCTIONCONSTRUCTION
1 2 3 4
67
8
15 17
185
14
13
9
10
11
12
EXC &POUR FOOTINGS
POURFOUND.
ERECTFRAME & ROOF
LAYBRICKWORK
INSTALLDRAINS
POURBASEMENTFLOOR
INSTALL COOLING & HEATING
INSTALL ROUGHELECT. & PLUMB
LAYSTORM DRAINS
FINISHROOF
FINISH GRADING
POUR WALKS &LANDSCAPE
FINISHFLOORS
FINISH ELECTR.WORK
FINISHCARPETING
PAINT
INSTALLKITCHEN EQUIP.
INSTALLFIN. PLUMB
INSTALLDRY WALL
16
INSTALL ROOFDRAINAGE
LAYFLOORING
Slack Slack IdentificationIdentification
C (8,10)
2 (15,17)
EARLIEST START TIME
EARLIEST FINISH TIME
LATEST FINISH TIME
LATEST START TIME
ACTIVITY
TIME
Schedule Schedule CompressionCompression• Elimination of some parts of the project Elimination of some parts of the project
• Addition of more resourcesAddition of more resources
• Substitution of less time-consuming Substitution of less time-consuming components or activitiescomponents or activities
• Parallelization of activitiesParallelization of activities
• Shortening critical path activitiesShortening critical path activities
• Shortening early activitiesShortening early activities
• Shortening longest activitiesShortening longest activities
Schedule Schedule Compression Compression (Continued)(Continued)
• Shortening easiest activitiesShortening easiest activities
• Shortening activities that are least Shortening activities that are least costly to speed upcostly to speed up
• Shortening activities for which you Shortening activities for which you have more resourceshave more resources
• Increasing the number of work hours Increasing the number of work hours per day per day
Resource LevelingResource Leveling• Resource leveling is an attempt to Resource leveling is an attempt to
eliminate the manpower peaks and eliminate the manpower peaks and valleys by smoothing out the period-to-valleys by smoothing out the period-to-period resource requirements. The period resource requirements. The ideal situation is to do this without ideal situation is to do this without changing the end date. However, in changing the end date. However, in reality, the end date moves out and reality, the end date moves out and additional costs are incurred.additional costs are incurred.
Resource AllocationResource Allocation• Resource allocation (or resource Resource allocation (or resource
limited planning) is an attempt to find limited planning) is an attempt to find the shortest possible critical path the shortest possible critical path based upon the available or fixed based upon the available or fixed resources. The problem with this resources. The problem with this approach is that the employees may approach is that the employees may not be qualified technically to perform not be qualified technically to perform work on more than one activity in a work on more than one activity in a network.network.
Types Of Precedence Types Of Precedence ChartsCharts
ACTIVITY 1
ACTIVITY 1
ACTIVITY 2
ACTIVITY 2FINISH-TO-START
START-TO-START
FINISH START
START
START
Types Of Precedence Types Of Precedence ChartsCharts
ACTIVITY 1
ACTIVITY 1
ACTIVITY 2
ACTIVITY 2
FINISH-TO-FINISH
PERCENT COMPLETE
FINISHFINISH
20 %
50 %