    Rev. 09/25/06 SJSU Bus 140 - David Bentley 1

    Chapter 14 MRP to ERP

    Independent vs. dependentdemand, MRP inputs and

    processing, Closed-loop MRP, MRPII, ERP

  • 7/31/2019 Chapter 14 Mrp to Erpppt4348

    2/16

    Rev. 03/02/05 SJSU Bus 140 - David Bentley 2

    Traditional I/C Problems Reorder point (when to order)

    Assumes known, linear demand (sawtooth)

    Assumes rough knowledge of lead time Uses safety stock (or safety time) as buffer

    Each item planned independently

    EOQ (how much to order) Focuses on mechanics of formula

    Assumes linear (constant) usage

    Always results in inventory

  • 7/31/2019 Chapter 14 Mrp to Erpppt4348

    3/16

    Rev. 09/25/06 SJSU Bus 140 - David Bentley 3

    MRP Material Requirements Planning (MRP)

    Father of MRP: Joseph Orlicky (???? - ????)

    Dependent vs. independent demand concept Other requirements

    Manufacturing Bill of Materials (BOM)

    Accurate, well-managed Master Production

    Schedule (MPS) to drive MRP Computer software to explode BOMs

    Computer hardware speed and data capacity

  • 7/31/2019 Chapter 14 Mrp to Erpppt4348

    4/16

    Rev. 03/02/05 SJSU Bus 140 - David Bentley 4

    Key MRP Inputs Master Production Schedule (MPS)

    Well managed Build Plan

    Bill of Materials (or recipes) Parent/child relationships

    Single level vs. multi-level

    Structured for manufacturing On hand inventory (available to use)

    Material on order (from supplier)

  • 7/31/2019 Chapter 14 Mrp to Erpppt4348

    5/16

    Rev. 03/02/05 SJSU Bus 140 - David Bentley 5

    Key MRP Inputs Planning factors

    Lead time

    Lot sizing algorithm or rule Optional adjustments

    Safety stock

    Safety time

    Yield

    Shrinkage

    etc.

  • 7/31/2019 Chapter 14 Mrp to Erpppt4348

    6/16

    Rev. 03/02/05 SJSU Bus 140 - David Bentley 6

    MRP ProcessingAnswers both questions

    When to order

    How much to order

    Proceeds one level at a time (level-by-level)

    Nets and plans action only when lowestlevel in any BOM is reached

  • 7/31/2019 Chapter 14 Mrp to Erpppt4348

    7/16Rev. 03/02/05 SJSU Bus 140 - David Bentley 7

    Lot Sizing Algorithms Lot for lot

    Seeks to balance supply and demand

    Fixed order quantity May have minimums, maximums, multiples

    Economic Order Quantity (EOQ) Variations are Least Unit Cost, Least Total Cost,

    Part Period Balancing

    Period Order Quantity

    Fixed Period Requirements

    Wagner-Whitin

  • 7/31/2019 Chapter 14 Mrp to Erpppt4348

    8/16Rev. 03/02/05 SJSU Bus 140 - David Bentley 8

    MRP Summary - 1 Big number-cruncher

    Follows rules using built-in logic and tables

    Predicts shortages

    Gross requirements derived from plannedorder releases of parent items

    Processes level-by-level Nets requirements and plans for an item at

    lowest level of use in any BOM

  • 7/31/2019 Chapter 14 Mrp to Erpppt4348

    9/16Rev. 03/02/05 SJSU Bus 140 - David Bentley 9

    MRP Summary - 2 First suggests pull-ins, push-outs,

    cancellations

    Then creates plannedorders (not released)

    Provides action and/or exceptionmessages

    High-speed computers now mean process inminutes rather than hours

    Planner needs to evaluate results before acting

  • 7/31/2019 Chapter 14 Mrp to Erpppt4348

    10/16Rev. 03/02/05 SJSU Bus 140 - David Bentley 10

    Problems with MRP Computer model

    Decisions may be based on inaccurate data

    Inventory-building features have crept in

    Safety stock

    Safety time

    EOQ

    Represents a push system

  • 7/31/2019 Chapter 14 Mrp to Erpppt4348

    11/16Rev. 03/02/05 SJSU Bus 140 - David Bentley 11

    Resource Planning Systems MRP

    Closed loop MRP

    MRP II

    ERP

    SCM Next emphasis > E-commerce

  • 7/31/2019 Chapter 14 Mrp to Erpppt4348

    12/16Rev. 09/25/06 SJSU Bus 140 - David Bentley 12

    Closed Loop MRP and MRP II Oliver Wight (???? 1983)

    Sold concepts to American management

    Closed Loop MRP Feedback any changes in due dates and

    quantities

    Must have accurate due dates

    Manufacturing Resource Planning(MRP II) Integrate Long Range, Intermediate Range,

    Short Range, and Real-time planning

  • 7/31/2019 Chapter 14 Mrp to Erpppt4348

    13/16

    Rev. 03/02/05 SJSU Bus 140 - David Bentley 13

    ERP and SCM Enterprise Resource Planning (ERP)

    Coined by Gartner Group

    Extends integrated planning to CustomerService, Forecasting, Quality, HumanResources, Accounting, Project Management

    Supply Chain Management (SCM) Extends planning to other organizations

    Tightly couples suppliers and customers

  • 7/31/2019 Chapter 14 Mrp to Erpppt4348

    14/16

    Rev. 03/02/05 SJSU Bus 140 - David Bentley 14

    ERP Software Vendors - 2001 Enterprise Resource Planning (ERP)

    SAP Oracle Baan

    PeopleSoft J.D. Edwards

  • 7/31/2019 Chapter 14 Mrp to Erpppt4348

    15/16

    Rev. 04/01/08 SJSU Bus 140 - David Bentley 15

    ERP Software Vendors - 2005 Enterprise Resource Planning (ERP)

    SAPOracle

    PeopleSoft J.D. Edwards

    Baan (financial and legal problems followed by acquisition)

  • 7/31/2019 Chapter 14 Mrp to Erpppt4348

    16/16

    04/01/08 SJSU Bus 140 - David Bentley 16

    ERP Software Vendors - 2008 Enterprise Resource Planning (ERP)

    SAPOracle Infor Global Solutions (SSA ERP - formerly Baan)

    The Sage Group