chapter 18: capital budgeting with leverage

25
1 CHAPTER 18: CAPITAL BUDGETING WITH LEVERAGE Topics 18.1 – 18.6 Valuation 18.7 Beta and Leverage Core Question: How to determine the NPV of a project if it is financed with debt?

Upload: robyn

Post on 08-Jan-2016

65 views

Category:

Documents


0 download

DESCRIPTION

CHAPTER 18: CAPITAL BUDGETING WITH LEVERAGE. Topics 18.1 – 18.6Valuation 18.7Beta and Leverage Core Question: How to determine the NPV of a project if it is financed with debt?. Background. In chapter 8, there was a four step procedure for evaluating corporate investment decisions: - PowerPoint PPT Presentation

TRANSCRIPT

Page 1: CHAPTER 18: CAPITAL BUDGETING WITH LEVERAGE

1

CHAPTER 18: CAPITAL BUDGETING WITH LEVERAGE

Topics

• 18.1 – 18.6 Valuation

• 18.7 Beta and Leverage

Core Question: How to determine the NPV of a project if it is financed with debt?

Page 2: CHAPTER 18: CAPITAL BUDGETING WITH LEVERAGE

2

Background

• In chapter 8, there was a four step procedure for evaluating corporate investment decisions:

– Forecast cash flows

– assess project risk

– estimate opportunity cost of capital

– compute NPV

• This procedure treats each project like an independent firm that is all-equity financed

• If financing decisions did not matter, this is all that is required. But if they do matter, there are three basic approaches

– Adjusted present value (APV)

– Flow to equity (FTE)

– Weighted average cost of capital (WACC)

Page 3: CHAPTER 18: CAPITAL BUDGETING WITH LEVERAGE

3

18.1 APV Approach

APV = NPVU + NPVF

• NPVU (NPV of unlevered firm)

– project value under all-equity financing

– PV of unlevered cash flows (UCF)

– discount rate: r0

• NPVF (net present value of financing side effects)• PV of tax shields to debt

• costs of issuing new securities

• costs of financial distress

• subsidies to debt financing

Page 4: CHAPTER 18: CAPITAL BUDGETING WITH LEVERAGE

4

APV Example

• A project costs $60,000 and generates expected pre-tax operating cash flows of $10,000 per year in perpetuity. The corporate tax rate is 40% and the cost of capital under all-equity financing is 12%. Should the firm make this investment under all-equity financing? What is there is debt, and the debt-value ratio is 0.06?

Page 5: CHAPTER 18: CAPITAL BUDGETING WITH LEVERAGE

5

18.2 FTE Approach

1. Estimate levered cash flows = cash flow to equityholders of levered firm (LCF)

2. Calculate discount rate rS

3. Compute PV of LCF---Use 1 & 2

4. PV of the project: PV of LCF subtract equity contribution

(equity contribution = initial investment - amount borrowed)

– it is possible for the equity contribution to be negative—this means that the amount borrowed exceeds the initial cost of the investment

– in such cases, the excess can be thought of as a dividend paid out to equity holders

Page 6: CHAPTER 18: CAPITAL BUDGETING WITH LEVERAGE

6

FTE Example

• Consider the same example as for APV above, assuming that the rate of interest on debt is rB = 6%

Page 7: CHAPTER 18: CAPITAL BUDGETING WITH LEVERAGE

7

18.3 WACC

• Discount unlevered cash flows (UCF) at rWACC where

• Compute PV of UCF, subtract initial investment

– The unlevered cash flows (UCF) are the same as used in the APV approach for calculating the present value of future cash flows under all-equity financing

– This method was discussed previously in Chapter 13

BCSWACC r)T(BS

Br

BS

Sr

1

Page 8: CHAPTER 18: CAPITAL BUDGETING WITH LEVERAGE

8

WACC Example

• Continue with the same example from APV and FTE.

Page 9: CHAPTER 18: CAPITAL BUDGETING WITH LEVERAGE

9

Comparison of Approaches

• In the simple example above in a perpetual no-growth setting, all three approaches (APV, FTE, WACC) gave the same answer

• In theory, this should always be the case, but in practice it is usually far simpler to use one method than either of the others

Page 10: CHAPTER 18: CAPITAL BUDGETING WITH LEVERAGE

10

WACC

• Consider the following example. A project costs $80,000 today and generates expected pre-tax operating cash flows of $50,000 per year for four years. The corporate tax rate is 40%, the (levered) cost of equity (rS ) is 20%, the cost of debt is 8%, and the equity-value ratio is 60%

• WACC approach:

rWACC = .60(.20) + .40(.08)(1 − .4) = .1392

NPV = −$80,000 + $50,000(1 − .4) × A.13924

= $7,554.92

Page 11: CHAPTER 18: CAPITAL BUDGETING WITH LEVERAGE

11

What about APV

• Since the debt-value ratio is 40% and the PV of the future cash flows is $87,554.92, the amount to be borrowed is

.4($87,554.92) = $35,021.97• The discount rate under all-equity financing can be

calculated as follows. Since the effects of debt are to be incorporated later, use the weighted average cost of capital but assume that there are no corporate taxes, i.e.

• the value of the project under all-equity financing would be

NPVU = −$80,000 + $50,000(1 − .4) × A.15204 = $5,304.00

• If the debt of $35,021.97 is assumed to be perpetual, then

NPVF = .4($35,021.97) = $14,008.79APV = $5,304.00 + $14,008.79 = $19,312.79

Page 12: CHAPTER 18: CAPITAL BUDGETING WITH LEVERAGE

12

What about APV cont’d

• What if the debt is assumed to be repaid at the end of the project (i.e. after four years)?

• The amount of interest paid per year is

.08($35,021.97) = $2,801.76

• thenNPVF = $2,801.76(.4) × A.08

4 = $3,711.91

APV = $5,304.00 + $3,711.91 = $9,015.91

Page 13: CHAPTER 18: CAPITAL BUDGETING WITH LEVERAGE

13

What About APV? (Cont’d)

• The basic problem here is that the assumptions underlying WACC and APV (so far) are inconsistent

• In particular, WACC assumes that the debt-value ratio is constant over time, whereas (so far) in APV the assumption has been that debt is constant over time– This was consistent in the perpetual case since value is

constant over time in that context• In general, in order to maintain a constant debt-value ratio,

the amount of debt must change throughout the project life– Define a project’s debt capacity d as the amount of debt

needed to maintain the firm’s target debt-value ratio over the life of the project (note that d varies over time)

– Then calculate NPVF assuming that the firm borrows an amount that is equal to its debt capacity d

Page 14: CHAPTER 18: CAPITAL BUDGETING WITH LEVERAGE

14

What About FTE?

• We need to calculate levered cash flows, assuming the same borrowing pattern as for APV, and then discount at rS = 20%:

• This gives

Page 15: CHAPTER 18: CAPITAL BUDGETING WITH LEVERAGE

15

Comparison

• General rule: – Use APV when debt level is constant

– Use WACC and FTE when firm’s debt ratio is constant

APV FTE WACC

Initial Investment All Equity portion All

Cash flows UCF LCF UCF

Discount rates r0 rs rwacc

PV of financing side effects Yes No No

Page 16: CHAPTER 18: CAPITAL BUDGETING WITH LEVERAGE

16

More on APV and Discount rate

• Note that the discount rate of r0 specified for APV above applies to the unlevered cash flows, not the debt tax shield

• The appropriate discount rate for the debt tax shield under APV depends on the debt policy of the firm:– if debt level is constant (e.g. as in perpetuity case), use rB

– if debt level varies with project value (e.g. non-perpetual case), use r0

Page 17: CHAPTER 18: CAPITAL BUDGETING WITH LEVERAGE

17

18.6 More APV examples: Issuing Costs

An investment project costs $3 million and generates pretax operating cash flows of $825,000 per year for 10 years. The corporate tax rate is 40% and r0 is 10%.

(1) What is the all-equity NPV? ($41,561)

Page 18: CHAPTER 18: CAPITAL BUDGETING WITH LEVERAGE

18

Example cont’dFinancing alternative #1: the firm has no cash and will

finance the project with $3 million of new equity, issue costs are 7% of the gross proceeds and are tax deductible. What is APV

Answer: ($-93,923)

Page 19: CHAPTER 18: CAPITAL BUDGETING WITH LEVERAGE

19

Example cont’d

Financing alternative #2: the firm has $1.5 million in cash on hand and can borrow the remaining $1.5 million for 6 years at 8% interest (annual coupon payment). The bond will be issued at par. (Assume no issuing costs of debt.) (Answer: 263,460)

Page 20: CHAPTER 18: CAPITAL BUDGETING WITH LEVERAGE

20

Example cont’d (A more complicated version of last slide)Financing alternative #2: the firm has $1.5 million in cash on hand

and can obtain the remaining $1.5 million through a 6 years, 8% coupon (annual coupon payment) bond issued at par. The issuing costs for the bond is 1% of the amount raised. (Assume that issuing costs for debt are tax-deductible but amortized over the life of the bond.)

APV = NPV + NPV(Floatation costs) + NPV(Loan)

Amount raised: Discount rate:

1. NPV(Floatation costs)floatation costs = Amortized over 6 years, annual tax deduction is Annual tax shield = NPV(Floatation costs) or Net floatation costs

Page 21: CHAPTER 18: CAPITAL BUDGETING WITH LEVERAGE

21

Cont’d

2. NPV (Loan) = Amount borrowed – PV (after-tax interest payments) – PV (principal

repayment) = PV(interest tax shield)

or PV(interest tax shields)

3. APV = 41,561 -10,482 + 224,141 =255,220

Page 22: CHAPTER 18: CAPITAL BUDGETING WITH LEVERAGE

22

Example cont’d

Financing alternative #3: Subsidized financing

The firm has $1.5 million in cash on hand and can borrow the remaining $1.5 million for 6 years from the government at a special interest rate of 5% with no floatation costs (gov’t takes care of it.) Note that if the firm does not use gov’t loan, it has to borrow from the open market at 8%.

Page 23: CHAPTER 18: CAPITAL BUDGETING WITH LEVERAGE

23

18.7 Beta and Leverage

• To use APV, you have to know r0, the cost of unlevered equity.

• If the firm already has debt, you cannot simply use historical stock return data to compute beta, even if the project’s risk is identical to that of the existing firm. The following formula can be derived:

• Risky Corporate Debt:

where is the beta computed using historical returns and is the corresponding beta for an identical (but unlevered) firm

• Risk-free Corporate Debt:

Usually assume

BCUC

S S

B)T(

S

B)T(

11

1

S U

0B UC

S S

BT

)1(

1

Page 24: CHAPTER 18: CAPITAL BUDGETING WITH LEVERAGE

24

Example

• A firm has a debt-equity ratio of 0.5. Based on historical stock return data, the firm’s equity is 1.25. The firm faces a corporate tax rate of 40%. The risk free rate of interest is 5% and the expected market risk premium is 6%. Determine r0 assuming the the firm’s debt has (i) zero systematic risk, and (ii) βB of 0.10.

Page 25: CHAPTER 18: CAPITAL BUDGETING WITH LEVERAGE

25

• Assigned Problems: # 18.1, 4, 7, 8, 9(change the company name to NEC), 12, 14, 16, 17