Page 1: Chapter 4 continued. Intermittent Inspection –Oversight of several projects makes continuous observation impossible –Do weekly reports instead of dailies

Chapter 4 continued

Page 2: Chapter 4 continued. Intermittent Inspection –Oversight of several projects makes continuous observation impossible –Do weekly reports instead of dailies

• Intermittent Inspection– Oversight of several projects makes

continuous observation impossible– Do weekly reports instead of dailies– Take lots of pictures and notes when on site

Page 3: Chapter 4 continued. Intermittent Inspection –Oversight of several projects makes continuous observation impossible –Do weekly reports instead of dailies

• Report of Field Correction– Provides info for A/E to understand problem , make

determination, issue instructions to field personnel– Only a source of info – Not an authorization for work or a change order– ID problem – why is original construction method not

recommended– Offer solution in detail– Isolated or general condition– RPR does not take any corrective action that will

result in a variation of the plans and specs without A/E approval

Page 4: Chapter 4 continued. Intermittent Inspection –Oversight of several projects makes continuous observation impossible –Do weekly reports instead of dailies

• Field Investigation Report– Need more info to resolve situation– RPR does investigation and reports findings

Page 5: Chapter 4 continued. Intermittent Inspection –Oversight of several projects makes continuous observation impossible –Do weekly reports instead of dailies

• Documentation of Dangerous Safety Hazard Warnings– Document actions taken by RPR staff and

contractor– V important for litigation

Page 6: Chapter 4 continued. Intermittent Inspection –Oversight of several projects makes continuous observation impossible –Do weekly reports instead of dailies

• Steps– 1. get people away from hazard and danger– 2. Notify contractor’s field rep– 3. Issue written notice to contractor to take

immediate action to correct hazard – record in diary

– 4. If refused note time of day, day, call OSHA and make report – record in diary

– 5. write a full report of incident– 6. Call owner to tell them report coming

Page 7: Chapter 4 continued. Intermittent Inspection –Oversight of several projects makes continuous observation impossible –Do weekly reports instead of dailies

Misc. Records

– Manufacturer’s certificates of products– Lab test reports– Truck delivery tickets– Records of pile driving– Record of inspection of structural welding– Sewer infiltration reports – Fab plant inspection reports– Special inspector’s reports– Weld radiographs

Page 8: Chapter 4 continued. Intermittent Inspection –Oversight of several projects makes continuous observation impossible –Do weekly reports instead of dailies

Misc. Records

– Acceptance certificates from public agencies– Discrepancy reports– Deviation requests and action taken– Concrete mix designs– And others– All need to be logged and maintained in the

files

Page 9: Chapter 4 continued. Intermittent Inspection –Oversight of several projects makes continuous observation impossible –Do weekly reports instead of dailies

Labor Standards Review Records

• Federal funds require Davis Bacon Act– Additional responsibilities for RPR– 1. On military projects employee interviews must be

conducted to determine classifications and rates of pay & fringe – record all on daily report to Inspector

– 2. Federal grant projects require certified payrolls from contractor - check for compliance

– 3. On site checks of type and classification of work performed, number of workers in each category

Page 10: Chapter 4 continued. Intermittent Inspection –Oversight of several projects makes continuous observation impossible –Do weekly reports instead of dailies

Labor Standards Review Records

– 4. Federal granting agency will make periodic inspections to check on compliance – be ready

– 5. Check that all equal employment opportunity laws are followed

Page 11: Chapter 4 continued. Intermittent Inspection –Oversight of several projects makes continuous observation impossible –Do weekly reports instead of dailies

• Job Conferences– Need to take minutes of conferences– Time, Date, who attended, end time– Include important statements and overview of

discussed points

Page 12: Chapter 4 continued. Intermittent Inspection –Oversight of several projects makes continuous observation impossible –Do weekly reports instead of dailies

• Construction Photographs– Picture is worth 1000 words– Use to detail progress, damage, technical

detail, type of materials, method of installation, evidence of site conditions, etc

– 4 basic types of photos• PR, progress, safety hazard, claims support

Page 13: Chapter 4 continued. Intermittent Inspection –Oversight of several projects makes continuous observation impossible –Do weekly reports instead of dailies

• Photo ID– Date, time, location on site, id of subject– Photo or negative number– For claims defense

• Time of day & photog name• Direction in which camera was pointed• Where photog was standing

– Log all photos taken• Easy to forget what picture is for if not immediately

recorded – validity in court