chapter 4 measuring sitework, excavation, and piling
TRANSCRIPT
Objectives• Upon completion of this chapter,
you will be able to:– Determine the likely soil conditions at
a site by studying a soils report– Explain the use of swell factor and
compaction factor when calculating volumes of excavation and backfill
Objectives (cont’d.)– Define bank measure and explain
how it applies to sitework takeoffs– Describe and use the “grid method”
of calculating cut and fill volumes– Describe and use the “section
method” of calculating cut and fill volumes
– Explain how piling work is measured in a takeoff
Objectives (cont’d.)– Explain how trenches and basements
are measured in a takeoff– Complete a manual takeoff of
sitework– Complete a computer takeoff of
sitework using Excel spreadsheets and MC2 ICE software
Generally• Measuring sitework and excavation
work – Different from measuring most other
work• Current site condition may not be provided• Dimensions and shape of excavations may
not be disclosed
– Estimators must assess requirements before measuring site work
Soils Report• Provides subsurface condition
information– Usually not a bid document– Includes data for foundation system
design
• Comments on sample soils report– Topsoil, moisture content, soil
compaction, slope ratio, drainage, etc.
Bank Measure, Swell, and Compaction Factors
• Extracted soil – Less dense and will occupy more
space
• Compaction factor– Difference between hole volume and
fill material volume
• Bank measure– Obtained using hole dimensions
Excavation Safety Considerations
• Potential danger to workers– Cave-ins
• OSHA’s Construction Safety and Health Regulations– Requires shoring systems or cutting
back sides to a safe angle• Strongly enforced
Use of Digitizers• Electronic devices
– Enables user to take measurements from drawings • Input directly into computer program
• Digitizer types– Sonic– Tablet
On-Screen Takeoff• Eliminates need for paper-based
printouts– Number of formats– Cost savings– Speed– Convenience
• Plans still have to be drawn to scale
Measuring Notes—Excavation and Backfill
• Include:– Measure in cubic yards or cubic
meters “bank measure”– Classify and measure separately
• Excavations• Materials• Hand excavation• Disposal of surplus soil
Calculation of Cut and Fill Using the “Grid Method”
• Requires a site survey – Showing elevation of existing grade
• Each intersection point on the grid• Plotted at each intersection point• Depth of cut can be obtained at each
point
– Refer to Figures 4.1 and 4.2 • Accuracy depends on grid spacing
Calculation of Cut and Fill Using the Section Method”
• Mostly used with long, relatively narrow areas of cut and fill– Road and railroad construction
• Results quality depends on accuracy of plotting– Refer to Figure 4.3
Trench Excavations• Formula for trench volume:
– Trench Volume = Length of Trench Centerline × Average Width of Trench × Average Depth of Trench
– Refer to Figure 4.4
• Sides of trenches often cut-back due to:– Safety reasons– Soil will not stand vertically
Trench Backfill• Volume of backfill for a trench
– Generally equal to volume of excavation minus volume of what is to be contained
– Surplus occurs when volume of excavation exceeds amount required for backfill• Item for disposal of surplus material is
required
Greater Accuracy• Formula used to calculate volume
of excavation:– Usually sufficient– Some situations require more
accuracy• Example: pit and basement excavations
Measuring Notes—Piling• Often subcontracted to specialized
companies• Typical general contractor items:
– Layout of piles– Cutting off tops of piles– Removing excavated material
Bearing Piles• Generally:
– Measure in linear feet or meters– Include a separate lump-sum item for
equipment– Piles that are measures separately– Measurement may be subdivided– Enumerate splicing and lengthening
of piles
Bearing Piles (cont’d.)• Additional considerations:
– Classification of bearing piles– Timber piles– Steel piles– Precast concrete piles– Poured-in-place concrete piles
Sheet Piling• Generally:
– Described and measured in square feet or square meters
– Separately measure piles– Measurement may be subdivided– Measure withdrawing of piles– Cutting off of sheet piling: measured
in linear feet or meters
Sheet Piling (cont’d.)– Splices: described and measured by
number– Timber sheet piling, concrete sheet
piling, and steel sheet piling: measured according to foregoing principles
– Extraction of piles: measured separately
Additional Examples • Drawings
– Refer to Figures 4.11 and 4.12
• Sitework takeoff– Example 1—The House Project
• Takeoff Shown as Figure 4.6a
– Example 2—The Office/Warehouse Project• Takeoff Shown in Figure 4.14a
– Sitework Takeoff Using ICE Software