chapter 4 - road construction 1.ppt - author | the uthm...
TRANSCRIPT
Chapter 4ROAD CONSTRUCTION
1HIGHWAY ENGINEERING BFC31802
� ROAD CONSTRUCTION PROCESS
- Site Investigation, Earthworks, Mass Haul Diagram,
- Preparation of subgrade, sub-base, base
What you will be
learning from this
chapter …
SUB-TOPICS:
HIGHWAY ENGINEERING BFC31802
2
� ASPHALT PAVEMENT CONSTRUCTION (FLEXIBLE)
- Preparation of bituminous coat: prime & tack coat
- Paving a binder & wearing coarse.
� CONCRETE PAVEMENT CONSTRUCTION (RIGID)
- Form, joints, concrete mix, curing, joint awing
� QUALITY ASSURANCE IN PAVEMENT CONSTRUCTION
SITE INVESTIGATIONSITE INVESTIGATIONSITE INVESTIGATIONSITE INVESTIGATION
Site investigation is carried in most cases as a preliminary to new works.
The reasons for site investigation are given below:
• Investigation of defects of existing roads
3
• Investigation of defects of existing roads
• Investigation to the safety of existing works.
• Investigation relating to the suitability and availability of materials for constructional purposes.
HIGHWAY ENGINEERING BFC31802
SITE INVESTIGATIONSITE INVESTIGATIONSITE INVESTIGATIONSITE INVESTIGATION
Investigation of defects of existing roads
This type of investigation is necessary to establish the cause of the failure and to provide information indicative of remedy.
4
Measurements and observations of the structure are taken to indicate whether or not the ground conditions are involved.
This investigation will reveal the level of ground water and the true state of sub-strata.
HIGHWAY ENGINEERING BFC31802
SITE INVESTIGATIONSITE INVESTIGATIONSITE INVESTIGATIONSITE INVESTIGATION
Investigation to the safety of existing works
To investigate existing works and decide whether the latter will adversely be affected by changes in ground conditions.
Existing works may be affected by the following:
• excavations may reduced ground support• tunneling or mining which may cause subsidence
5
• tunneling or mining which may cause subsidence• vibrations ( eg. from piling operation) which may cause fractures• extra load created by new works may overload stratum supportingexisting works
• soil movement due to heat induced by proximity to plantinstallations.
• ground water lowering• disturbed drainage path may cause flooding and instability ofslopes.
HIGHWAY ENGINEERING BFC31802
SITE INVESTIGATIONSITE INVESTIGATIONSITE INVESTIGATIONSITE INVESTIGATION
Investigation relating to the suitability and availability of materials for constructional purposes
There are two quite different problems with the mass movement of earth:
(1) Disposal
6
(1) Disposal- e.g. in the case of spoil from cuts
(2) Acquisition- e.g for large fill projects such as reclaimation
In both cases however, investigation is necessary toestablish the quantity and suitability of the soil for the purpose for which it is to be used.
HIGHWAY ENGINEERING BFC31802
ROAD CONSTRUCTION PROCESS
� ROUTE SURVEY
� SITE INVESTIGATION
7HIGHWAY ENGINEERING BFC31802
� SITE CLEARANCE
� EARTHWORKS
8HIGHWAY ENGINEERING BFC31802
� SUBGRADE COMPACTION AND LEVELLING
� ESTABLISHING THE FORMATION LEVEL
9HIGHWAY ENGINEERING BFC31802
�SUB-BASE CONSTRUCTION
10HIGHWAY ENGINEERING BFC31802
�BASE CONSTRUCTION
11HIGHWAY ENGINEERING BFC31802
� APPLYING OF PRIME COAT
� LAYING OF BINDER COURSE
12HIGHWAY ENGINEERING BFC31802
� APPLYING OF TACK COAT
� LAYING OF WEARING COURSE
ROAD IS COMPLETED.
13HIGHWAY ENGINEERING BFC31802
EARTHWORKS
This process consists of clearing, grubbing and stripping in road construction
area. It also includes the demolition and disposal of soils to a formation level
(top of the sub grade).
Activity Work Description Measurement
Cutting, removal and disposal of
everything above ground level
including object overhanging the
All stumps and roots be removed to a
depth of not less than 0.3 m below the
propose road.
14
Clearing
including object overhanging the
area to be cleared
Levelling of obsolete dikes,
terraces, ditches
propose road.
This requirement also usually holds in
embankment areas where the height of
the feel not less than about 1.5 m.
In embankment section when the
embankment height is to be more than
1.5 m, tree and stump may be left in
place and cut off at ground level or at a
height of 75-150 mm above the existing
ground surface.
Grubbing
Removal and disposal of surface
vegetation, roots, underground
parts of the structure and other
obstruction
Stripping Removal topsoil or stockpiling
HIGHWAY ENGINEERING BFC31802
EARTHWORKS
Excavation- Excavation increases the volume of material.
- It is therefore necessary to use a bulking factor to determine the volume of material that will be created by excavation.
Bulking factor is defined as:
15
Bulking Factor = Volume after Excavation / Volume before Excavation
Similarly a shrinkage factor is defined for the compaction of a soil at it's final destination:
Shrinkage Factor = Volume after Compaction / Volume before Excavation
HIGHWAY ENGINEERING BFC31802
EARTHWORKS
Earthmoving Equipment
Bulldozer - This is used primarily for pushing soil. Vehicles
are generally tracked and require large amounts of
traction. Many bulldozers incorporate hydraulic
attachments at the rear for breaking up soil and rock. The
best known of the vehicles.
Drag Line - This vehicle allows excavation below it's own
Bulldozer
16
Drag Line - This vehicle allows excavation below it's own
level. It is essentially a bucket on the end of a jib and is
used solely for bulk excavation as it is relatively
uncontrolled.
Dump Truck - These are wheeled vehicles and as such are
able to move much faster. This is offset by a lack of
traction and dump trucks are always the first to get stuck.
They are used for transferring material from one part of
the site to another.
Drag Line
Dump Truck
HIGHWAY ENGINEERING BFC31802
EARTHWORKS
Earthmoving Equipment
Shovels - These again are normally wheeled vehicles and
are used to fill up the dump trucks. Typically they take 2-3
loads to fill an average dump truck.
Hydraulic Excavators - These can be either wheeled or
tracked and are used again to excavate below truck level.
Shovel
Excavator
17
tracked and are used again to excavate below truck level.
They have a very small capacity and are extremely
flexible.
Grader - Used to level out deposited fill, ready for
compaction.
Rollers - There are many different types of roller and they
are used for compaction. Different types include vibratory,
sheepsfoot and grid. Vibratory are the most common as
they have effectively double the effect.
Grader
RollerHIGHWAY ENGINEERING BFC31802
MASS HAUL DIAGRAM
o Minimize material waste or borrow.
o A plot of cumulative volume of soil against distance along the road.
o Cut volumes - positive and fill volumes - negative.
18HIGHWAY ENGINEERING BFC31802
MASS HAUL DIAGRAM
A rising curve - increasing volume (cut).
A maximum point - end of a cut.
A falling curve - decreasing volume (fill).
A minimum point - the end of a fill.
19
Areas at the end of the diagram - waste
HIGHWAY ENGINEERING BFC31802
MASS HAUL DIAGRAM
Calculation of Cross Sectional Area
The first stage - cut or fill sectional areas at different points along the road.
For a cut or fill on horizontal ground
Assuming a cut such as the one above, the cross sectional area is given by:
1
20
Area =
= hb + nh2
= h(b + nh)
+ )(
2
12 nhhhb
HIGHWAY ENGINEERING BFC31802
MASS HAUL DIAGRAM
For a cut or fill on sloping ground
Assuming a cut such as the one above, the cross sectional area is found firstly by
calculating WL and WG:
WL = nhb
S
+
2
21
WL =
WG =
Thus Area =
nS +
2
nS
nhb
S
−
+
2
n
bWW
n
bh
GL
4)(
22
12
−+
+
HIGHWAY ENGINEERING BFC31802
MASS HAUL DIAGRAM
Example Calculation
The table below shows ground levels and formation levels for a proposed road construction.
Embankments are to be built with side slopes of 1:2.5 and cuttings with slopes of 1:3.0. The
embankment crest width and cutting base width is 13m. It may be assumed that the ground
is horizontal across the section.
22HIGHWAY ENGINEERING BFC31802
(a) Construct a Mass Haul diagram for the project given the following:
Bulking Factor = 0.8
Shrinkage Factor = 1.0
23HIGHWAY ENGINEERING BFC31802
MASS HAUL DIAGRAM
0
10000
20000
30000
40000
50000
Cu
mu
lati
ve
vo
lum
e (
cu
bic
me
ter)
24
-90000
-80000
-70000
-60000
-50000
-40000
-30000
-20000
-10000
0
0
10
0
20
0
30
0
40
0
50
0
60
0
70
0
80
0
90
0
10
00
11
00
12
00
13
00
14
00
15
00
Chainange (m)
Cu
mu
lati
ve
vo
lum
e (
cu
bic
me
ter)
HIGHWAY ENGINEERING BFC31802
MASS HAUL DIAGRAM
10000
20000
30000
40000
50000
Cu
mu
lati
ve
vo
lum
e (
cu
bic
me
ter)
(b) A river breaks up the project at chainage 1160m. Calculate the volumes of
waste material and borrow for this scenarios:
(i) Material cannot be moved across the river
150 280 500 740 1160 1280
25
-90000
-80000
-70000
-60000
-50000
-40000
-30000
-20000
-10000
0
10000
0
10
0
20
0
30
0
40
0
50
0
60
0
70
0
80
0
90
0
10
00
11
00
12
00
13
00
14
00
15
00
Chainange (m)
Cu
mu
lati
ve
vo
lum
e (
cu
bic
me
ter)
Fill Cut Cut Fill Fill Fill Cut
HIGHWAY ENGINEERING BFC31802
Distance (m) 150 130 220 240 420 120 220
Cut (m3) 15,000 36,000 49,000
Fill (m3) 15,000 36,000 68,000 11,000
Haul (m3) 15,000 36,000 11,000
Borrow (m3) 68,000
River
26
Borrow (m3) 68,000
Waste (m3) 38,000
Borrow = 68,000 m3
Waste = 38,000 m3
HIGHWAY ENGINEERING BFC31802
MASS HAUL DIAGRAM
10000
20000
30000
40000
50000
Cu
mu
lati
ve
vo
lum
e (
cu
bic
me
ter)
(b) A river breaks up the project at chainage 1160m. Calculate the volumes of
waste material and borrow for this scenarios:
(ii) A Bailey bridge is constructed allowing material to be transported across the river
150 280 500 740 1280
27
-90000
-80000
-70000
-60000
-50000
-40000
-30000
-20000
-10000
0
10000
0
10
0
20
0
30
0
40
0
50
0
60
0
70
0
80
0
90
0
10
00
11
00
12
00
13
00
14
00
15
00
Chainange (m)
Cu
mu
lati
ve
vo
lum
e (
cu
bic
me
ter)
Fill Cut Cut Fill Fill Fill Cut
HIGHWAY ENGINEERING BFC31802
Distance (m) 150 130 220 240 540 220
Cut (m3) 15,000 36,000 49,000
Fill (m3) 15,000 36,000 79,000
Haul (m3) 15,000 36,000 49,000
Borrow (m3) 30,000
28
Borrow (m3) 30,000
Waste (m3)
Borrow = 30,000 m3
Waste = 0 m3
HIGHWAY ENGINEERING BFC31802
29HIGHWAY ENGINEERING BFC31802
SUBGRADE PREPARATION
�The subgrade is the in-situ material upon which the pavement structure is placed.
�Increasing the load-bearing capacity of the subgrade - improve pavement load-bearing capacity – increasing pavement strength and performance.
�Greater subgrade structural capacity - thinner (but not excessively thin) and more economical pavement structures.
30
�The finished subgrade should meet elevations, grades and slopes specified in the contract plans.
HIGHWAY ENGINEERING BFC31802
SUBGRADE PREPARATION
Subgrade Performance
A subgrade’s performance generally depends on two interrelated characteristics:
(1) Load bearing capacity
- The subgrade must be able to support loads transmitted from the pavement structure.
31
pavement structure.
- This load bearing capacity is often affected by degree of compaction, moisture content, and soil type.
- A subgrade that can support a high amount of loading without excessive deformation is considered good.
(2) Volume changes
- Most soils undergo some amount of volume change when exposed to excessive moisture.
HIGHWAY ENGINEERING BFC31802
SUBGRADE PREPARATION
Improving Subgrade Performance
Poor subgrade should be avoided if possible, but when it is necessary to build over weak soils there are several methods used to improved subgrade performance:
(1) Removal and replacement (over-excavation)
Poor subgrade soil can simply be removed and replaced with higher quality fill
32
(2) Stabilization with a cementitious or asphaltic binder
The addition of an appropriate binder (such as lime, portland cement or emulsified asphalt) can increase subgrade stiffness and/or reduce swelling tendencies.
(3) Additional base layers
- These layers spread pavement loads over a larger subgrade area
- When designing pavements for poor subgrades the temptation may be to just design a thicker section with more base material because the thicker section will satisfy most design equations.
HIGHWAY ENGINEERING BFC31802
SUBGRADE PREPARATION
Good Practices in Subgrade Preparation
(1) Ensure the compacted subgrade is able to support construction traffic
If the subgrade ruts excessively under construction traffic it may cause premature pavement rutting and will result in variable paving thicknesses.
(2) Remove all debris, large rocks, vegetation and topsoil from the area to be paved
These items either do not compact well or cause non-uniform compaction
33
These items either do not compact well or cause non-uniform compaction and mat thickness.
(3) Treat the subgrade under the area to be paved with an approved herbicide
This will prevent or at least retard future vegetation growth, which could affect subgrade support or lead directly to pavement failure.
HIGHWAY ENGINEERING BFC31802
SUB-BASE AND BASE CONSTRUCTION
Sub-BaseMaterial
i. Natural or prepared aggregate comprising crushed rock
ii. Weathered or fragmented rock
iii. Gravel or crushed gravel
iv. Sand
v. Mixture from any materials above
Requirement
34
Requirement
- small portion of plastic or non-plastic fines
- free from vegetative or other organic matter, clay
- Physical and mechanical characteristic – comply to JKR/SPJ/1988:
Liquid limit < 35 %
Plasticity index in the range of 4 to 10
Aggregate Crushing Value < 35
Gradation – Table 4.2
HIGHWAY ENGINEERING BFC31802
SUB-BASE AND BASE CONSTRUCTION
B.S Sieve
Size
% Passing by Weight
A B C D E F
50.0 mm 100 100 - - - -
Table 4.2: Gradation Limits for Sub-base Material
HIGHWAY ENGINEERING BFC31802
35
50.0 mm
25.0 mm
9.50 mm
4.75 mm
2.00 mm
425 µm
75 µm
100
-
30-65
25-55
15-40
8-20
2-8
100
79-95
40-75
30-60
20-45
15-30
5-20
-
100
50-85
35-65
25-50
15-30
5-20
-
100
60-100
50-85
40-70
25-45
5-20
-
100
-
55-100
40-100
20-50
5-20
-
100
-
70-100
55-100
30-70
8-25
Method of construction
- shaped and compacted
- uniform moisture content – prevent seperation
- compaction not less than 95 % of MDD – BS1377 (Compaction Test 4.5 kg rammer method)
- Pattern of compaction – longitudinal direction
SUB-BASE AND BASE CONSTRUCTION
36
- Pattern of compaction – longitudinal direction
- From outer edge – center
- Superelevation – from lower to higher edge
- Final surface – must : required shape, superelevation, levels and grade within the tolerence
HIGHWAY ENGINEERING BFC31802
SUB-BASE AND BASE CONSTRUCTION
Base Material
i. Crushed aggregate or gravel
ii. Mix of crushed and natural aggregate
Generally - hard, durable, clean and free from clay
Requirement
Physical and mechanical characteristic – comply to JKR/SPJ/1988
37
- Plasticity index < 6
- Flakiness index < 30
- Aggregate Crushing Value < 30
- > 80 % particle retained 4.75 mm sieve – had fractured face
- Soundness test < 12 %
- CBR value > 80 %
- Gradation – Table 4.3
HIGHWAY ENGINEERING BFC31802
Method of construction (refer to sub-base except the thickness preparation)
B.S Sieve Size % Passing by Weight
A B
50.0 mm
37.5 mm
28.5 mm
100
95-100
-
100
85-100
70-100
Table 4.3: Gradation Limits For Crushed Aggregate Roadbase
SUB-BASE AND BASE CONSTRUCTION
28.5 mm
20.0 mm
10.0 mm
5.0 mm
2.36 µm
2.00 µm
600 µm
425 µm
75 µm
-
60-80
40-60
25-40
15-30
-
8-22
-
0-8
70-100
60-90
40-65
30-55
-
20-40
-
10-25
2-10HIGHWAY ENGINEERING
BFC3180238
The method of base construction processes refer to themethod of construction for sub-base except for thethickness specification.
SUB-BASE AND BASE CONSTRUCTION
Sub-base and Base construction
ASPHALT PAVEMENT CONSTRUCTION
Pavements constructed without adequate surface
preparation may not meet smoothness specifications,
Before a pavement is placed, the surface to be
paved must be prepared.
40HIGHWAY ENGINEERING BFC31802
preparation may not meet smoothness specifications,
may not bond to the existing pavement (in the case of
overlays) or may fail because of inadequate subgrade
support.
BITUMINOUS COATSBITUMINOUS COATSBITUMINOUS COATSBITUMINOUS COATS
Prime Coats
� A cutback or emulsion asphalt. According to Asphalt Institute (2001):
(i) Fill the surface voids and protect the subbase from weather.
(ii) Stabilize the fines and preserve the subbase material.
(iii) Promote bonding to the subsequent pavement layers.
ASPHALT PAVEMENT CONSTRUCTION
41
� Carried out – dry, warm weather – final surface essentially dry
� Left undisturbed – 24 hours after application
� Rate of application:
-range 0.9 to 2.3 litre/m2
- temperature
cutback bitumen – 50 C to 70 C during spraying
emulsion – 25 C to 45 C during spraying
HIGHWAY ENGINEERING BFC31802
Tack Coats
� Thin bituminous liquid asphalt, emulsion or cutback
� Between HMA pavement lifts to promote bonding
� Need an adequate bonding – for good result
� Material – emulsion bitumen – rapid setting
BITUMINOUS COATSBITUMINOUS COATSBITUMINOUS COATSBITUMINOUS COATS
ASPHALT PAVEMENT CONSTRUCTION
42
� Material – emulsion bitumen – rapid setting
� Rate and temperature of applications:
- range 0.19 to 0.38 litres/m2
- temperature of the bitumen - 25 C to 45 C
HIGHWAY ENGINEERING BFC31802
SURFACE DRESSING
� Cleaning of the surface
� Binder used – penetration graded bitumen, cutback or emulsion
� Aggregate – from the screed
� It must clean, hard, dry, tough, sound and angular
ASPHALT PAVEMENT CONSTRUCTION
43
� It must clean, hard, dry, tough, sound and angular
HIGHWAY ENGINEERING BFC31802
ASPHALTIC CONCRETE
Aggregate used in the mixture MUST:
� Aggregate Crushing Value < 30
� Soundness Test < 12 %
� Flakiness index < 30
BITUMINOUS COATSBITUMINOUS COATSBITUMINOUS COATSBITUMINOUS COATS
ASPHALT PAVEMENT CONSTRUCTION
44
� Flakiness index < 30
� Water absorption < 2 %
� Polished stone value > 40 (wearing course)
� Gradation and mixture – Comply JKR/SPJ/1988 (Table 4.4, 4.5
� Mixture analysis – Comply JKR/SPJ/1988 (Table 4.6)
HIGHWAY ENGINEERING BFC31802
Laying the Asphaltic Concrete
� Compacted thickness – twice of nominal aggregate size of the mixture.
� Proper laying – avoid the irregularities and segregation of the mix
Compaction Measurement
BITUMINOUS COATSBITUMINOUS COATSBITUMINOUS COATSBITUMINOUS COATS
ASPHALT PAVEMENT CONSTRUCTION
45
Compaction Measurement
� Compaction – reduce the volume of air in HMA
� Expressed as “percent of air voids”
� Determine by the ratio of density of specimen with density of “Theoretical Maximum Density”
� Factor affecting compaction (refer Module)
HIGHWAY ENGINEERING BFC31802
COMPACTION
Compaction is the process by which the volume of air in an Hot Mix Asphalt (HMA) mixture is reduced by using external forces to reorient the constituent aggregate particles into a more closely spaced arrangement.
Compaction is the greatest determining factor in dense graded pavement
BITUMINOUS COATSBITUMINOUS COATSBITUMINOUS COATSBITUMINOUS COATS
ASPHALT PAVEMENT CONSTRUCTION
46
Compaction is the greatest determining factor in dense graded pavement performance.
Inadequate compaction results in a pavement with decreased stiffness, reduced fatigue life, accelerated aging/decreased durability, rutting, raveling, and moisture damage.
HIGHWAY ENGINEERING BFC31802
BITUMINOUS COATSBITUMINOUS COATSBITUMINOUS COATSBITUMINOUS COATS
ASPHALT PAVEMENT CONSTRUCTION
HIGHWAY ENGINEERING BFC31802
47
Compaction Equipment
There are three basic pieces of equipment available for HMA compaction:
(1) Paver screed
(2) Steel wheeled roller
(3) Pneumatic tire roller.
ASPHALT PAVEMENT CONSTRUCTION
48
Paver Screed Steel Wheel Roller Pneumatic Tire RollerHIGHWAY ENGINEERING
BFC31802
RIGID PAVEMENT CONSTRUCTION
• Need to be done carefully and precisely to meet
- structural strength
- structural smoothness
• Follow the sequences
a. Subgrade
b. Subbase (sometimes – 75 to 150 mm)
49
b. Subbase (sometimes – 75 to 150 mm)
c. Placing of form
d. Mixing of Concrete
- batch dry – outside from the site
- in-situ, mixed with water
- for central location – straight away mix with
water and transport to the site
HIGHWAY ENGINEERING BFC31802
• Placing and finishing
- Used ordinary concrete work machines
- Pavement surface – check for the
irregularities
• Joint sawing
• Curing – wet curing ( 1 to 3 days)
50
• Curing – wet curing ( 1 to 3 days)
HIGHWAY ENGINEERING BFC31802
QUALITY ASSURANCE IN PAVEMENT CONSTRUCTION
Quality assurance
Planned and systematic actions
Most efficient, economical, and satisfactory manner possible.
Involves continued evaluation of the activities of planning, design, development of plans and specifications, advertising and awarding of contracts, construction, and maintenance, and the interactions of these
3 KEYS COMPONENT
51
activities
Quality control
To assess production and construction processes- control the level of quality being produced in the end product.
Includes sampling and testing
HIGHWAY ENGINEERING BFC31802
Independent assurance
A management tool that requires a third party, not directly responsible for process control or
acceptance, to provide an independent assessment of the product and/or the reliability of
test results obtained from process control and acceptance testing.
The results of independent assurance tests should not be used as a basis of product
acceptance
Acceptance
52
Sampling, testing, and the assessment of test results to determine whether or not the quality
of produced material or construction is acceptable in terms of the specifications.
.
HIGHWAY ENGINEERING BFC31802
53HIGHWAY ENGINEERING BFC31802