Chapter 6
The Work Breakdown Structure and Project
Estimation
Copyright 2012 John Wiley & Sons, Inc.6-1
![Page 2: Chapter 6 The Work Breakdown Structure and Project Estimation Copyright 2012 John Wiley & Sons, Inc. 6-1](https://reader036.vdocument.in/reader036/viewer/2022062322/56649e855503460f94b8706a/html5/thumbnails/2.jpg)
Announcements
• RTP Bus Trip - Friday, 10/3
• Midterm Review – Monday, 10/6
• Midterm – Wednesday, 10/8
• Introduction to PM Software – Friday, 10/10
6-2
![Page 3: Chapter 6 The Work Breakdown Structure and Project Estimation Copyright 2012 John Wiley & Sons, Inc. 6-1](https://reader036.vdocument.in/reader036/viewer/2022062322/56649e855503460f94b8706a/html5/thumbnails/3.jpg)
Project Planning Framework
3-3Copyright 2012 John Wiley & Sons, Inc.
![Page 4: Chapter 6 The Work Breakdown Structure and Project Estimation Copyright 2012 John Wiley & Sons, Inc. 6-1](https://reader036.vdocument.in/reader036/viewer/2022062322/56649e855503460f94b8706a/html5/thumbnails/4.jpg)
PMBOK – Knowledge Areas
![Page 5: Chapter 6 The Work Breakdown Structure and Project Estimation Copyright 2012 John Wiley & Sons, Inc. 6-1](https://reader036.vdocument.in/reader036/viewer/2022062322/56649e855503460f94b8706a/html5/thumbnails/5.jpg)
PMBOK ® – Project Time Management
Define Activities Identifying what activities must be completed to produce the project
scope deliverablesSequence Activities
Determining whether activities can be completed sequentially or in parallel and any dependencies that may exist among them
Estimate Activity Resources Identifying the type of resources (people, technology, facilities, etc.)
and the quantity of resources needed to carry out project activitiesEstimate Activity Durations
Estimating the time to complete each activityDevelop Schedule
Based on the availability of resources, the activities, their sequence, and time estimates, a schedule for the entire budget can be developed
Control Schedule Ensuring that proper processes and procedures are in place in order
to control changes to the project schedule
6-5
![Page 6: Chapter 6 The Work Breakdown Structure and Project Estimation Copyright 2012 John Wiley & Sons, Inc. 6-1](https://reader036.vdocument.in/reader036/viewer/2022062322/56649e855503460f94b8706a/html5/thumbnails/6.jpg)
Importance of Project Schedules
Managers often cite delivering projects on time as one of their biggest challenges
Schedule issues are the main reason for conflicts on projects, especially during the second half of projects
6
![Page 7: Chapter 6 The Work Breakdown Structure and Project Estimation Copyright 2012 John Wiley & Sons, Inc. 6-1](https://reader036.vdocument.in/reader036/viewer/2022062322/56649e855503460f94b8706a/html5/thumbnails/7.jpg)
Work Breakdown Structure (WBS)
The WBS represents a logical decomposition of the work to be performed and focuses on how the product, service, or result is naturally subdivided. It is an outline of what work is to be performed
– PMBOK Guide® (17).
Work Packages
6-7
![Page 8: Chapter 6 The Work Breakdown Structure and Project Estimation Copyright 2012 John Wiley & Sons, Inc. 6-1](https://reader036.vdocument.in/reader036/viewer/2022062322/56649e855503460f94b8706a/html5/thumbnails/8.jpg)
Deliverables versus Milestones
Deliverables
Milestones
6-8
![Page 9: Chapter 6 The Work Breakdown Structure and Project Estimation Copyright 2012 John Wiley & Sons, Inc. 6-1](https://reader036.vdocument.in/reader036/viewer/2022062322/56649e855503460f94b8706a/html5/thumbnails/9.jpg)
Developing the WBS
A work package is developed for each of the phases and deliverables defined in the Deliverable Structure Chart (DSC)
6-9
![Page 10: Chapter 6 The Work Breakdown Structure and Project Estimation Copyright 2012 John Wiley & Sons, Inc. 6-1](https://reader036.vdocument.in/reader036/viewer/2022062322/56649e855503460f94b8706a/html5/thumbnails/10.jpg)
Deliverable: Test Results Report
Logical Activities:1. Review the test plan with the client so that key
stakeholders are clear as to what will be tested, how the tests will be conducted, and when the tests will be carried out.
2. Carry out the tests as outlined in the plan.3. Once the test results are collected, we need to
analyze them.4. The results should be summarized in the form of
a report and presentation to the client.5. If all goes well, the client will sign-off or approve
the test results and then we can move on to the implementation phase of the project. If not, then we need to address and fix any problems.
6-10What are the deliverables? Milestones?
![Page 11: Chapter 6 The Work Breakdown Structure and Project Estimation Copyright 2012 John Wiley & Sons, Inc. 6-1](https://reader036.vdocument.in/reader036/viewer/2022062322/56649e855503460f94b8706a/html5/thumbnails/11.jpg)
Example Work Breakdown Schedule
6-11
![Page 12: Chapter 6 The Work Breakdown Structure and Project Estimation Copyright 2012 John Wiley & Sons, Inc. 6-1](https://reader036.vdocument.in/reader036/viewer/2022062322/56649e855503460f94b8706a/html5/thumbnails/12.jpg)
The WBS Should Follow the Work Package Concept
6-12
![Page 13: Chapter 6 The Work Breakdown Structure and Project Estimation Copyright 2012 John Wiley & Sons, Inc. 6-1](https://reader036.vdocument.in/reader036/viewer/2022062322/56649e855503460f94b8706a/html5/thumbnails/13.jpg)
The WBS…
Should be “deliverable-oriented”Should support the project’s MOVHave enough detail to support planning and controlShould involve those who will be doing the workShould include learning cycles and past lessons
learned
6-13
What do we do now that we have the activities defined?
![Page 14: Chapter 6 The Work Breakdown Structure and Project Estimation Copyright 2012 John Wiley & Sons, Inc. 6-1](https://reader036.vdocument.in/reader036/viewer/2022062322/56649e855503460f94b8706a/html5/thumbnails/14.jpg)
6.2 Test Results Report6.2.1 Review test plan with client 1
day6.2.2 Carry out test plan 5
days6.2.3 Analyze results 2
days6.2.4 Prepare test results report and presentation 3
days6.2.5 Present test results to client 1
day6.2.6 Address any software issues or problems 5
days
Estimates are made for each activity in the WBS
6-14
How did we come up with these estimates? Using a technique,or combination of techniques, with the exception of guestimating!
![Page 15: Chapter 6 The Work Breakdown Structure and Project Estimation Copyright 2012 John Wiley & Sons, Inc. 6-1](https://reader036.vdocument.in/reader036/viewer/2022062322/56649e855503460f94b8706a/html5/thumbnails/15.jpg)
Estimation Techniques - TraditionalProject Management Approaches
GuesstimatingDelphi TechniqueTime BoxingTop-DownBottom-UpAnalogous Estimates (Past experiences)
6-15
![Page 16: Chapter 6 The Work Breakdown Structure and Project Estimation Copyright 2012 John Wiley & Sons, Inc. 6-1](https://reader036.vdocument.in/reader036/viewer/2022062322/56649e855503460f94b8706a/html5/thumbnails/16.jpg)
Guestimating
6-16
![Page 17: Chapter 6 The Work Breakdown Structure and Project Estimation Copyright 2012 John Wiley & Sons, Inc. 6-1](https://reader036.vdocument.in/reader036/viewer/2022062322/56649e855503460f94b8706a/html5/thumbnails/17.jpg)
Delphi Technique and Time Boxing
Delphi Technique• Involves multiple, anonymous experts• Each expert makes an estimate• Estimates compared
If close, can be averaged If not, do another iteration until consensus is
reached
6-17
Time Boxing:• A “box” of time is allocated for
a specific activity, task, or deliverable
• Can focus a team if used effectively
• Can demoralize a team if not used effectively
![Page 18: Chapter 6 The Work Breakdown Structure and Project Estimation Copyright 2012 John Wiley & Sons, Inc. 6-1](https://reader036.vdocument.in/reader036/viewer/2022062322/56649e855503460f94b8706a/html5/thumbnails/18.jpg)
Top-Down
Top & middle managers determine overall project schedule &/or cost
Lower level managers are expected to breakdown schedule/budget estimates into specific activities (WBS)
6-18
![Page 19: Chapter 6 The Work Breakdown Structure and Project Estimation Copyright 2012 John Wiley & Sons, Inc. 6-1](https://reader036.vdocument.in/reader036/viewer/2022062322/56649e855503460f94b8706a/html5/thumbnails/19.jpg)
Bottom-Up and Analogous Estimates
6-19
• Schedules & budgets are constructed from WBS
• Starts with people who will be doing the work
• Schedules & budgets are the aggregate of detailed activities & costs
![Page 20: Chapter 6 The Work Breakdown Structure and Project Estimation Copyright 2012 John Wiley & Sons, Inc. 6-1](https://reader036.vdocument.in/reader036/viewer/2022062322/56649e855503460f94b8706a/html5/thumbnails/20.jpg)
Remember: Difference b/w Duration & Effort
Activity Duration Estimating• Duration vs. Effort
People doing the work should help create estimates, and an expert should review them
20
![Page 21: Chapter 6 The Work Breakdown Structure and Project Estimation Copyright 2012 John Wiley & Sons, Inc. 6-1](https://reader036.vdocument.in/reader036/viewer/2022062322/56649e855503460f94b8706a/html5/thumbnails/21.jpg)
Software Engineering Approaches
6-21
![Page 22: Chapter 6 The Work Breakdown Structure and Project Estimation Copyright 2012 John Wiley & Sons, Inc. 6-1](https://reader036.vdocument.in/reader036/viewer/2022062322/56649e855503460f94b8706a/html5/thumbnails/22.jpg)
What is one way to estimate software development?
Use project characteristics (parameters) in a mathematical model to estimate
6-22
![Page 23: Chapter 6 The Work Breakdown Structure and Project Estimation Copyright 2012 John Wiley & Sons, Inc. 6-1](https://reader036.vdocument.in/reader036/viewer/2022062322/56649e855503460f94b8706a/html5/thumbnails/23.jpg)
Lines of Code
6-23
Example: $50/ LOC based on:• Programming language• Level of expertise• Size & complexity
![Page 24: Chapter 6 The Work Breakdown Structure and Project Estimation Copyright 2012 John Wiley & Sons, Inc. 6-1](https://reader036.vdocument.in/reader036/viewer/2022062322/56649e855503460f94b8706a/html5/thumbnails/24.jpg)
Function Point Analysis
5 Primary Elements Inputs Outputs Inquiries Logical Files Interfaces
6-24
![Page 25: Chapter 6 The Work Breakdown Structure and Project Estimation Copyright 2012 John Wiley & Sons, Inc. 6-1](https://reader036.vdocument.in/reader036/viewer/2022062322/56649e855503460f94b8706a/html5/thumbnails/25.jpg)
Complexity
Low Average High Total
Internal Logical Files
(ILF)_3 x 7 = 21 _2 x 10 = 20 _1 x 15 = 15 56
External Interface
Files (EIF)__ x 5 = __ _2 x 7 = 14 __ x 10 = __ 14
External Input (EI)
_3 x 3 = 9 _5 x 4 = 20 _4 x 6 = 24 53
External Output (EO)
_4 x 4 = 16 _2 x 5 = 10 _1 x 7 = 7 33
External Inquiry (EQ)
_2 x 3 = 6 _5 x 4 = 20 _3 x 6 = 18 44
Total Unadjusted Function Points (UAF) 200
6-25
![Page 26: Chapter 6 The Work Breakdown Structure and Project Estimation Copyright 2012 John Wiley & Sons, Inc. 6-1](https://reader036.vdocument.in/reader036/viewer/2022062322/56649e855503460f94b8706a/html5/thumbnails/26.jpg)
General System Characteristic Degree of Influence
Data Communications 3
Distributed Data Processing 2
Performance 4
Heavily Used Configuration 3
Transaction Rate 3
On-line Data Entry 4
End User Efficiency 4
Online Update 3
Complex Processing 3
Reusability 2
Installation Ease 3
Operational Ease 3
Multiple Sites 1
Facilitate Change 2
Total Degrees of Influence 40
Value Adjustment Factor VAF = (TDI * 0.01) + .65 VAF = (40 * .01) + .65 = 1.05
Total Adjusted Function Points = FP = UAF * VAF FP = 200 * 1.05 = 210
6-26
![Page 27: Chapter 6 The Work Breakdown Structure and Project Estimation Copyright 2012 John Wiley & Sons, Inc. 6-1](https://reader036.vdocument.in/reader036/viewer/2022062322/56649e855503460f94b8706a/html5/thumbnails/27.jpg)
Language Average Source LOC per Function Pont
Average Source LOC for a 210 FP Application
Access 38 7,980
Basic 107 22,470
C 128 26,880
C++ 53 11,130
COBOL 107 22,470
Delphi 29 6,090
Java 53 11,130
Machine Language
640 134,440
Visual Basic 5 29 6,090
Source: http://www.spr.com/library/0langtbl.htm
6-27
![Page 28: Chapter 6 The Work Breakdown Structure and Project Estimation Copyright 2012 John Wiley & Sons, Inc. 6-1](https://reader036.vdocument.in/reader036/viewer/2022062322/56649e855503460f94b8706a/html5/thumbnails/28.jpg)
The seeds of major software disasters are usually sown in the first three months of commencing the software project. Hasty scheduling, irrational commitments, unprofessional estimating techniques, and carelessness of the project managementfunction are the factors that tend to introduce terminal problems. Once a project blindly lurches forward toward an impossible delivery date, the rest of the disaster will occur almost inevitably.
T. Capers Jones, 1988 Page 120
6-28
![Page 29: Chapter 6 The Work Breakdown Structure and Project Estimation Copyright 2012 John Wiley & Sons, Inc. 6-1](https://reader036.vdocument.in/reader036/viewer/2022062322/56649e855503460f94b8706a/html5/thumbnails/29.jpg)
What happens when project run long?
6-29
So, your estimates were inaccurate….should you add more manpower to the project
![Page 30: Chapter 6 The Work Breakdown Structure and Project Estimation Copyright 2012 John Wiley & Sons, Inc. 6-1](https://reader036.vdocument.in/reader036/viewer/2022062322/56649e855503460f94b8706a/html5/thumbnails/30.jpg)
The Man Month
6-30
Mon
ths
People
Mon
ths
PeopleTime versus number of workersperfectly partitionable task – i.e.,No communication among theme.g., reaping wheat.
When a task that cannot be partitionedbecause of sequential constraints, theapplication of more effort has noeffect on the schedule.
![Page 31: Chapter 6 The Work Breakdown Structure and Project Estimation Copyright 2012 John Wiley & Sons, Inc. 6-1](https://reader036.vdocument.in/reader036/viewer/2022062322/56649e855503460f94b8706a/html5/thumbnails/31.jpg)
Adding People
6-31
![Page 32: Chapter 6 The Work Breakdown Structure and Project Estimation Copyright 2012 John Wiley & Sons, Inc. 6-1](https://reader036.vdocument.in/reader036/viewer/2022062322/56649e855503460f94b8706a/html5/thumbnails/32.jpg)
What can cause inaccurate estimates?
6-32
![Page 33: Chapter 6 The Work Breakdown Structure and Project Estimation Copyright 2012 John Wiley & Sons, Inc. 6-1](https://reader036.vdocument.in/reader036/viewer/2022062322/56649e855503460f94b8706a/html5/thumbnails/33.jpg)
In Reality…Estimating is quite challenging
Stable Activities straightforward estimating
Dependent Activities amount needed for testing is dependent on a successful
test or unsuccessful test. 3-point estimates or analogous work well.
Uncertain Activities No previous precedence (complex projects) Start with 3-point estimate to set boundaries then use
analogous to set actual estimate
33