chapter 7 – bennett's dam projects – power to the lower ......the portage mountain (now...
TRANSCRIPT
Page 67CHAPTER 7 – Bennett’s Dam Projects
CHAPTER 7 – Bennett's Dam Projects – Power to the Lower Mainland
DURING THE 1960s British Columbia undertook what remains the greatest building project in its history,
dwarfing previous undertakings such as the Kitimat Smelter and the Trans Mountain Pipeline. The Portage
Mountain (now W.A.C. Bennett) dam on the Peace River and the Mica Creek dam on the Columbia River were
each in their own right what are now called “world class” projects, but building them at the same time made them
among the most ambitious construction projects in history. When it was officially opened in 1968 the Portage
Mountain Dam was the largest dam in the western world: only the Soviet Union’s Bratsk hydro station dam in
Siberia was larger. Mica Creek, when its dam was completed in 1973, was the site of the largest earth-filled dam
anywhere in the world.
The dam projects were a product of Premier W.A.C. Bennett’s determination to develop British Columbia’s natural
resources as quickly as possible. As noted in Chapter 3, Bennett believed that it was his government’s job to build
the infrastructure which would make it possible for private corporations to develop the province’s natural resources.
But while he began building highways almost from the moment he came to power, it was not until the 1960s that
he was presented with an opportunity to undertake the massive, and massively expensive, hydro-electric projects
of which he dreamed.
BENNETT’S TWO RIVERS POLICY One obvious place to build the kind of dams Bennett wanted was in the Kootenays, on the Canadian side of the
Columbia River. The U.S. had already built a series of dams on its side of the international border as part of a system
of flood control and hydro-electric power development. To complete its own Columbia River development plans,
the U.S. needed Canada to build a series of dams on its side of the international border, thus helping to control
floods on the U.S. side of the border and provide hydro-electric power for export to U.S. towns and industry.
Desultory discussions between the U.S. and Canadian governments on this question had been underway since 1944
and the United States had even offered to make a contribution towards Canada’s construction costs, although on
terms the Canadian government at first refused to consider. Canada felt itself to be in a strong negotiating position,
since in the federal government’s opinion, the U.S. needed Columbia River development far more urgently than
Canada. The federal government was particularly reluctant to agree to the export of any power from the Columbia,
arguing that Canada might later need the power for its own use. This was not, however, the opinion of the British
Columbia government: it publicly and repeatedly stated that the Columbia should be developed as quickly as
possible in order to promote BC’s industrial growth.
As a mere Premier, Bennett could not compel the federal government to adopt his view, especially since it was
a highly unpopular view. Although most Canadians did not oppose building dams on the Columbia, a very large
Page 68 CHAPTER 7 – Bennett’s Dam Projects
number of them, including the LiUNA Local 168 members who would be employed in building the dams, opposed
Miner drilling off for a blast on surface on the left bank escarpment.Photo courtesy British Columbia Hydro and Power Authority
Page 69CHAPTER 7 – Bennett’s Dam Projects
building them on the
U.S. government’s terms.
But Bennett was able to
ignore public opinion and
outmanoeuvre the federal
government thanks to what
was known as his “Two Rivers
Policy,” a strategy of building
dams on the Columbia while
simultaneously building a
dam on the Peace River in
northeastern BC. In 1957,
Bennett had signed an
agreement with Axel Wenner-
Gren, a Swedish industrialist
with rather a shady reputation
(it included having been good
friends with Reichsmarschall
Hermann Goering), for a grandiose proposal to build a monorail which would open up northeastern BC to
development, creating a string of new mines, pulp mills, and towns as well as a major hydro-electric project on the
Peace River. The proposal for the monorail with its associated mines and mills quickly foundered, but it had alerted
Bennett to the Peace River’s tremendous hydro-electric potential. In addition, the Peace was not an international
river, meaning the federal government had no jurisdiction and could not interfere with the Premier’s plans for it.
Many of the province’s business leaders were strongly opposed to building an expensive hydro-electric project
on a site as remote as the Peace River. This opposition was led by the province’s principal electric utility, the
privately owned BC Electric Company, which held a virtual monopoly on the production and sale of electricity
in the province. It regarded the proposal as uneconomic and unnecessary, not to mention more expensive than
damming the Columbia River. It publicly announced that it would refuse to buy power from the Peace at any price.
But the Premier was a master of political tactics and he seldom allowed opposition to his plans to go unpunished.
He commissioned a study which reported that damming the Peace would be less expensive than damming the
Columbia—but only if the dam
were built by a government-owned,
i.e. crown, corporation. The study
argued that the lower interest rates
available to crown corporations
would greatly reduce the dam’s
financing costs, thus making it
cheaper to build than a Columbia
River dam.
In 1961 Bennett struck. Study in
hand and temporarily forgetting
about his near-religious
commitment to “free enterprise,”
he nationalized the BC Electric
Company. With one blow, he both
removed the centre of private
Bennett Dam powerhouse access tunnel.Photo courtesy British Columbia Hydro and Power Authority
Phot
o co
urte
sy B
ritish
Col
umbi
a H
ydro
and
Pow
er A
utho
rity
Page 70 CHAPTER 7 – Bennett’s Dam Projects
sector opposition to his Peace River Dam and
created a ready-made crown corporation, BC
Hydro, with all the expertise required to build
his dam for him. By removing all obstacles
to the construction of the Peace River dam,
Bennett had also fatally undermined the
federal government’s case against exporting
power from dams built on the Columbia: much
of this power would now clearly be surplus to
the province’s needs for decades to come. The
result was the implementation in 1963 of the
Columbia River Treaty, under which Canada
agreed to build three dams on the Columbia in
return for an allocation for its own use of half
the electricity generated by these dams and
a formula providing financial compensation
for a portion of its construction costs.
THE PORTAGE MOUNTAIN DAMPlanning and surveying for the Portage
Mountain Dam had already begun three
years before the BC Electric Company was
nationalized, enabling construction to start
almost immediately. The dam was 600 feet
high (183 metres), 1.25 miles (2,000 metres)
long, half a mile (800 metres) wide at its base,
and 30 feet (9 metres) wide at the top. One Drilling and coring at the Bennett Dam.Photo courtesy British Columbia Hydro and Power Authority
Phot
o co
urte
sy B
ritish
Col
umbi
a H
ydro
and
Pow
er A
utho
rity
Page 71CHAPTER 7 – Bennett’s Dam Projects
hundred million tons of gravel, sand, and rock were used to fill its core and the dam alone took four years to build.
Its reservoir flooded some 635 square miles (1,650 square kilometres), was 225 miles (360 kilometres) long, and had
a shoreline of 1,100 miles (1,770 kilometres), making the reservoir BC’s largest lake. The main civil works began in
November when LiUNA members from Local 168 started drilling an exploratory diversion tunnel. Seven years later
the first power from the Portage Mountain Dam was delivered to the Lower Mainland. The dam’s official cost to the
people of British Columbia was $487 million (some $3.1 billion in today’s dollars) and at its peak it had employed
some 4,850 workers, as many as 700 of them being Labourers. Its total payroll stood at $46.2 million ($295 million
today), less than 10 per cent of the dam’s total cost.
When it was officially opened in 1968, the Portage Mountain project was still far from complete. Five hundred feet
(152 metres) below the dam’s left abutment, LiUNA tunnellers had finished work on the world’s largest powerhouse,
890 feet (270 metres) long, 67 feet (20.5 metres) wide, and 153 feet (46.5 metres) high. But only three of the
project’s ten generators were online. It was expected to take another five years and cost another $240 million ($1.5
billion today) to install the remaining seven 310,000 horsepower turbines, each capable of generating over 250,000
kilowatts. Yet even as the finishing touches were being put to the Portage Mountain Dam, work was beginning on
a second, smaller dam 14 miles (23 kilometres) downstream and only 4 miles (6 kilometres) from Hudson’s Hope.
This 164 foot (50 metre) high Site One Dam (now the Peace Canyon Dam) is a concrete rather an earthen dam and
generates 700,000 kilowatts from four generating units: it was completed in 1980.
THE MICA CREEK DAMThe Mica Creek Dam was one of three dams which Canada had committed itself to building under the Columbia
River Treaty. Work on all three began in 1964, when construction on the Portage Mountain Dam was already in
full swing. By 1968, two of them, the Duncan and Arrow Lakes Dams, were complete. But the Mica Creek was so
enormous that it took another five years—nine years in all—just to finish the dam. It took a further four years
to build the powerhouse and install the turbines and generators. When it was officially opened in 1977, thirteen
years after construction started, only four of its six generators were operational. Once all six were installed, Mica
Miners have drilled and blasted the cavern that will become the powerhouse later named after Gordon M. Shrum.Photo courtesy British Columbia Hydro and Power Authority
Page 72 CHAPTER 7 – Bennett’s Dam Projects
Creek would generate 2.8 million
kilowatts, 300,000 more than
Portage Mountain. (The final two
500 MW generators were installed
in 2014 and in 2015.)
The Mica Creek Dam was 800 feet
(243 metres) high and required
42 million cubic yards of fill
(32 million cubic metres). Its
reservoir covered 100,000 acres
(404 square kilometres) and
drained a catchment area of some
8,300 square miles (21,500 square
kilometres). The powerhouse was
778 feet (237 metres) long,
80 feet (24.4 metres) wide, and
145 feet (44 metres) high. At
its peak it employed some five
thousand workers, as many as
seven hundred and fifty of them
LiUNA members from Local 168.
The dam alone cost $330 million
($2 billion today) and it was expected that a further $460 million ($2.85 billion today) would be spent to complete
the project. The combined cost of the Columbia River and Portage Mountain dams was some $1.5 billion (perhaps
$9.3 billion today) spread over some twenty years.
THE FIRST AHC AGREEMENTPremier Bennett was gambling his political career on the success of his Two Rivers policy. He considered it essential
that nothing stand in the way of completing the
dams on or ahead of schedule and on or under
budget. But if the dams were to be completed
on schedule, he could not afford any labour
disputes on the projects. Although they had
no stake in the Premier’s success—indeed they
bitterly opposed, among other things, his labour
policies—LiUNA and the other building trades
unions were prepared, for the right price, to
guarantee him labour peace. After six weeks of
negotiations with Peace Power Constructors, the
project’s government-owned prime contractor,
on February 12, 1962 the Allied Hydro Council,
which represented the unions, signed an at the
time unheard of ten year no-strike, no-lockout
collective agreement. The agreement would
cover all government dam work in the province
and any disputes which did arise were to be
settled by binding arbitration. In exchange, the
Mica Dam construction of single family accommodation.Photo courtesy British Columbia Hydro and Power Authority
Phot
o co
urte
sy B
ritish
Col
umbi
a H
ydro
and
Pow
er A
utho
rity
Page 73CHAPTER 7 – Bennett’s Dam Projects
government agreed automatically to accept any wage increases and improvements to benefits and conditions the
building trades obtained through collective bargaining with its private sector contractors. This was a major success
for the building trades’ negotiators, since the province-wide labour shortage dam construction was about to create
would greatly strengthen the unions’ position in future negotiations with their other contractors.
This was not at first apparent to the government. The chair of BC Hydro told the press that the agreement was
helping firms cut costs and observed that “If this scheme [the dam] is not successful, we won’t be able to blame
the unions. It will be the fault of our engineers.” Less than three years later, after the rest of the industry signed
an agreement providing for free room and board, paid coffee breaks, and a 20 per cent wage increase, the chair
changed his tune. All thought of blaming the project’s engineers forgotten, he began bleating to the press about
how the unions were deliberately sabotaging the province’s development.
BUILDING ON TWO RIVERSDrilling on a pilot diversion tunnel for the Portage Mountain Dam had begun in November, 1961 and less than
two years later, on September 16, 1963, a beaming W.A.C. Bennett personally triggered the explosion which broke
the plug holding the river back from the project’s now completed diversion tunnels. A week later, once the rubble
from the explosion was cleared away, work on the dam itself moved into high gear. Premier Bennett had good
reason to beam when he opened the diversion tunnels: they had been completed on time and under budget.
And throughout the project’s construction, he would make it a point to ensure that management understood that
meeting deadlines and budgets was his, and therefore their, chief priority.
Phot
o co
urte
sy B
ritish
Col
umbi
a H
ydro
and
Pow
er A
utho
rity
Page 74 CHAPTER 7 – Bennett’s Dam Projects
Fully aware of the importance of satisfying the Premier’s expectations, management did everything humanly
possible to make the dam a political as well as an engineering success. Men and machinery operated twenty-four
hours a day and finding ways to speed-up the work and cut corners on “non-essential” items such as safety was a
constant preoccupation. In 1965 management even offered to buy back their newly-negotiated paid coffee breaks
from the workers who operated the conveyor belt that supplied the dam with fill. Meanwhile, money for “frills” was
so scarce that one superintendent complained that there was a shortage of personnel vehicles and that much of
the equipment he did have was second-hand. He told a reporter for the Victoria Colonist that he’d “never seen so
much used equipment in my life outside a dealer’s yard.” An engineer told the reporter that if “Premier Bennett
walked through that door tomorrow and chucked us a satchel with $400 million in it, we couldn’t move any faster.
We couldn’t save one day.”
THE CONDITIONS – PORTAGE MOUNTAINThe Peace River country is notorious for its blistering, blackfly infested summers and harsh winters. The winters
were so cold that the drills run by LiUNA’s tunnellers had to be kept running twenty-four hours a day to prevent
them from freezing up. In the spring and fall the rains were often so heavy that construction virtually ground to
a halt as roads became impassable and the giant Euclid earth-movers hauling fill to the dam’s core bogged down.
On at least one occasion, the site was completely cut off from the outside world after a wash-out closed the only
road out. R.L. McDonald, an experienced hard-rock miner and later President of LiUNA Local 1611’s Retiree Council,
described a trip to the Peace River in 1963 in less than flattering terms: “It was the middle of winter and we were
trying to collar a shaft. Cold as hell and completely disorganized, so I buggered off pretty quick from that job.”
Although not housed in tents as they had been at Kemano, the camp in which Portage Mountain’s workers spent
most of their time off-shift did little to make working there more attractive. In November, 1962 the Victoria Colonist
reporter visiting the site described the superintendent’s living quarters as “comfortable but spartan.” He noted that
meals were “ample but it is a long time between T-bones” and recreation for several hundred workers consisted of
one room containing nothing but a ping-pong table. A few months later, an Italian-born tunneller described camp
life to Norman Cribbens, a reporter for the Victoria Times. “I buy cigarettes, beer, papers, magazines, and film for my
camera. I play poker, I go to movies, and dance hall—not much else. Save plenty for when I get laid off and go to
Vancouver.” The movie theatre and dance hall were both twelve miles away in Hudson’s Hope, a village so small it
Mica Dam tunnel outlet structure showing lining form in place.Photo courtesy British Columbia Hydro and Power Authority
Page 75CHAPTER 7 – Bennett’s Dam Projects
had no high school. According to Cribbens, the movie theatre was “primitive,” the dance hall just a large shack. Even
the local bank was housed in a trailer, ready to leave town as soon as the project closed down.
“The rooms weren’t very big. Two cots, a shelf, a little reading lamp, a table in between you. And you
might have had three feet of floor space between the bunks, that was it. And a little closet for your
clothes. They were just a trailer set up, you know. They were adequate, at the time, if you had a good
roommate. Yeah, I thought it was quite fine. We were used to that type of set up, anyway. … Lotsa poker
games. That was the only activity, really. And on payday, they’d go into Hudson’s Hope. Had a bootlegger
there, you know. Stuff like that, guys sit around. There was a bar, bootlegger, bank. It was on the rail,
wheels, I think, ready to leave for the next town.”
– R.L. McDonald
THE CONDITIONS – MICA CREEK
The living conditions at the Mica Creek site, sixty-eight miles north of Revelstoke in the Kootenays, were
a considerable improvement on Portage Mountain. BC Hydro decided to build not only a camp for single workers
but also a married quarters for the project’s twenty-five hundred workers and their fifteen hundred dependents.
The married quarters were in fact a fair-sized village, nearly the size of Revelstoke itself, which even became
incorporated under the province’s Municipal Act. The village had its own water, power, sewer, road, telephone and
drainage systems. There was also a small business district with a grocery store, a dry goods store, a barber, a beauty
parlour, a drug store, a gas station, a post office, and a fire hall. For recreation there was a bowling alley, soccer
fields, tennis courts, and even an auditorium for concerts, plays, and musicals.
THE OVERTIME BANGiven the conditions under which they lived and worked, it is hardly surprising that the only way the Portage
Mountain Dam could attract and retain workers was with higher than average pay. Since the hourly wage rate was
established under province-wide agreements, overtime was the only way to achieve this. In 1963, working seven
days a week, a tunneller earned about $1,000 a month. The 1965 contract increased this to $1,200 a month, or
nearly three times the average monthly earnings of construction labourers working in Vancouver. On January 1,
1967, stung by the effect he thought high overtime costs were having on his dam projects’ budgets (though as
previously noted, wages represented only 10 per cent of Portage Mountain’s costs), Bennett retaliated by outlawing
all overtime throughout the entire province. He justified this particularly ill-considered example of his seat-of-his-
pants style of governing
by declaring that the
labour movement made
him do it: it had ignored
his call for wage restraint
in a time of recession and
unemployment. Bennett’s
little exercise in restricting
the hours of work was
short-lived. Of the twenty-
nine hundred workers who
had left Portage Mountain
for the Christmas holidays,
almost half did not return
until the overtime ban
was lifted.Mica Dam spillway.Photo courtesy British Columbia Hydro and Power Authority
Page 76 CHAPTER 7 – Bennett’s Dam Projects
NO STRIKES, JUST WOBBLESWhen the AHC accepted Premier Bennett’s ten year no strike clause, he did not realize that the two parties had a
very different understanding of what was meant by the phrase “no strike”. To the Premier it meant no job action
whatsoever, to the unions it merely meant no “interest” strikes, that is an official strike against an employer or
group of employers to obtain a satisfactory collective agreement. But in the 1960s, when workers in BC felt that an
employer was violating the terms of an existing collective agreement, they did not demand that the union take the
matter up with an arbitrator or the Labour Relations Board. They walked off the job.
There is a myth still current that until at least the 1980s, British Columbia’s workers were more strike prone than
those of any other province. In reality, factoring in the province’s higher union density, the number of official strikes
in BC was around the Canadian average. What distinguished BC’s union workforce from the rest of the country in
the 1950, 60s, and 70s was its willingness to conduct short illegal or wildcat strikes, “wobbling the job” as many
still called it. It was a practice particularly common in the forest and construction industries. For example, between
1949 and 1959 there were thirty-three official, i.e. legal, strikes in the construction industry and forty-five wobbles.
Wobbles were never industry-wide: they usually broke out at one particular work site and seldom spread even to
neighbouring job sites. They were almost always triggered by a collective grievance specific to the job site and
seldom lasted more than a few days.
The first wildcat at Portage Mountain took place on July 30, 1962, less than six months after the Premier had
obtained his labour peace clause. It followed a tunnellers’ meeting on July 26 chaired by Bill Milner, later Local
168’s Business Manager, at which it was moved and carried unanimously “That if the food doesn’t improve, that the
members will not work, by 1st of the week.” Eighteen hours after it started, Peace Power Constructors agreed to
investigate the catering company responsible and the tunnellers returned to work.
There were to be more. As Russ St Eloi, a Vancouver Labour Council delegate from the UA (Plumbers’ Union) told
a meeting in 1965:
“It’s not rosy on the Peace and Columbia like they thought it would be. There is growing dissatisfaction
amongst workers over living and other job conditions, contracts are being let to firms which can’t properly
handle the jobs and taxpayers’ money is being used to compile a labour blacklist.”
Mica Dam diversion tunnel.Photo courtesy British Columbia Hydro and Power Authority
Page 77CHAPTER 7 – Bennett’s Dam Projects
Even the Vancouver Sun’s Pat Carney, later a Progressive Conservative MP and then Senator, agreed that there was
trouble on the dam sites. In her October 13, 1965 column, she said that there was evidence to support the building
trades’ charges that management was responsible for deteriorating working conditions, bad labour relations, and
the use of “cheap technicalities” in the handling of grievances.
In 1968, nine hundred workers walked off the Mica Dam for three days “because of the unsafe conditions on the
job, and because of the safety director.” Columbia Hydro Constructors’ general manager threatened to fire the
strikers, who responded by planning to occupy the project and stage a sit-down strike. The strike was only settled
because a WCB inspector visited the site and took action to remedy at least some of the strikers’ safety concerns.
He issued a stop work order on one of the project’s roads because several workers had been injured by slides from
the hillside above. He also ordered that Columbia Hydro Constructors immediately begin complying with dust
control regulations in the tunnelling portions of the project.
THE CRAFTThe sheer scale and ambition of the Peace and Columbia River dam projects continue to impress historians
and many stories about working on them have been collected over the years. Local 1611’s R.L. McDonald was
interviewed in 2007 by Meg Stanley for Voices from the Two Rivers: BC Hydro Pioneers, a book on the projects
prepared by Commonwealth Historic Resource Management. In it, he provides a slightly longer description of his
1963 visit to the site (the original transcription by Eileen Mak has here been edited):
“I was drilling on the bottom … that’s where they’d been going for ten months and they were down
56 feet, which they should have done in a week. So, you know, the equipment wasn’t right. We were
freezing up. And nobody really cared, it seemed. Everybody wanted to know what we were doing …
Finally, we said, ‘Well, just leave us alone and we’ll show you what we’re doing.’ And we stayed there, but
there were too many chiefs and not enough Indians. I guess I can put it that way. I think everybody was
looking on the point system for themselves, climbing up that ladder. So I stayed thirty days. That’s what
your contract was. And then I came out.”
For the uninitiated, it can be nearly impossible to understand what they mean when construction workers
talk about how they do their jobs. But R.L. has a knack for explaining things. Except for “Rock Bolting”, the
Loading explosives on left abutment at Mica Dam.Photo courtesy British Columbia Hydro and Power Authority
Page 78 CHAPTER 7 – Bennett’s Dam Projects
explanations below are from
his description of the work at
Portage Mountain.
Bench Drilling “[I]n a shaft, in
a small shaft like that, we used
to take what you call a six-foot
bench. So, you would start out
with a starter steel, and the first
hole would be roughly at forty-
five degrees, and you would fan
back with your drill to allow two
feet on the bottom of the hole,
for breaking. So you would go
back, possibly, five holes and
you would blast half the shaft.
And that would give you a little
bit of sump. The other side
would be higher, so that the
water would drain into it. And
when we were drilling, we never
had any ’cause there was no
water. But, if there would have
been water, you have a little
pump set up in your bucket to
hoist the water to the surface.
Then, the next time, we’d go
on the other side, and drill the
bench again. … This is how
you kept your work area clear of water. Because, if you didn’t, you’d have muck going into the hole, and
it would be hard to drill and pull your steel out, hard to load, cut your wires, and cause misfires, and stuff
like this. So it was a proven system over the years, and always been there. … Benching they call it.”
Blasting “There was four men on the crew and that was, usually, standard in a three-compartment shaft.
And the procedure used to be three experienced, and, if you were breaking in a person, you’d have one
greenhorn, on the bottom. … [Y]ou had to drill, let’s say, five or six holes apiece. And when we were all
done drilling, you blow the bench, put a blowpipe in to clear the holes, throw all your gear in the bucket,
hoist the bucket up to the surface. And you’d have floodlights hanging down, when you’re working. You
cut off your electrical power. And then we’d bring down our powder and load. That’s a safety precaution,
so they wouldn’t have any caps going off prematurely.”
Mucking “Down there we had just one man on the bottom and one on the clam. The clam operator
loaded the bucket. … And when it goes up, a man has to be by it, put his shoulder into it to steady the
bucket, so it will not catch the timber and clean them up off the side. … That’s the biggest worry in the
shaft, is something falling on you. One time, I finished drilling and took off my gloves to start loading
and my glove was full of blood. I thought, ‘What’s going on here?’ We got up on surface and the first
aid looked and I had a little piece of wafer, and it just went down through my oilers, my underwear and
that, and stuck on my shoulder. … He just pulled it out and that was it. But that’s the biggest worry of
underground, or down a shaft, is somebody dropping something on you. And you’re very, very cautious.”
Mica Dam 1973.Photo courtesy British Columbia Hydro and Power Authority
Page 79CHAPTER 7 – Bennett’s Dam Projects
Rock Bolting “Work at the Mica went
quickly because the rock was ‘clean’.
The only slow part was the rock
bolting which is inserting a steel rod
into a hole drilled into the roof or
walls to support the roof or sides of
a mine or tunnel.
“We would have to torque [each]
bolt. I think it was either twenty-six
thousand pound torque or twenty-
six ton, I’m not certain. But, you had
a ratchet, and when you reached
your twenty-six thousand, it would
click. You knew the bolt is set. But,
if … the bolt started pulling and it
wouldn’t click, you had to pull out
and go over again. That’s the only
slow work I had there.”
White Hand “We wore long-johns,
underwear, coveralls, and oilers
overtop. With our hard hats and our
gloves. And we had insulated gloves. That’s the biggest problem when you’re working these pneumatic
drills, air. The drilling and that, it kills all your nerves and you get ‘white hands’. A lot of times, when you’d
be loading, you would have to take and shove your hands underneath your armpits to get the feeling in
your fingers, to twist your wire or so.” [Note: “White Hand” or Raynaud’s Syndrome is a potentially crippling
industrial injury caused by working with vibrating tools and machinery. See Chapter 4.]
From Burnt-Out to Experienced “The Peace River, the Mica, and the Revelstoke Projects were the greatest
thing for a miner in his forties. Instead of being a burnt-out miner he now became an experienced
construction worker. The difference between bulling a jackleg all shift and working on the jumbos was the
biggest bonus we had ever received in years.”
SITE ONE (PEACE CANYON DAM)Chuck Chatten, a General Foreman on dam projects and later Local 1611’s Kootenay Business Agent describes an
incident on the Site One concrete dam from 1978:
The contractor used 100 ton and 120 ton Whirley cranes to raise forms during the day and place concrete
at night. They had two experienced six-man crews placing concrete on the upstream side of the intake
structure, working about 90 to 120 feet above the ground. There was a push on to get the intake finished
and we were working ten to sixteen hours a day.
We were topping off a pour with two Whirley cranes swinging in four yard buckets to finish the pour
as quickly as we could. About 3:30 or 4:00 in the morning, we’re just finishing it off and the upstream
wall started to make a strange sound. I don’t want to say it sounded like a zipper, but the coil rods were
popping—pop, pop, pop. There were about 20 coil rods across the upstream wall holding the form to the
previous pour and as they popped the concrete pushed out the upstream wall.
Phot
o co
urte
sy B
ritish
Col
umbi
a H
ydro
and
Pow
er A
utho
rity
Page 80 CHAPTER 7 – Bennett’s Dam Projects
Lazar Milisic, we called him Louie Milisic, was
the concrete foreman, a first class concrete
man, and he saved some lives that night. He
was usually a quiet man but he realized what
was happening and hollered at us to get
away from that form, to get right out of there.
As soon as we saw the look on his face, him
yelling “Hurry up!” at the top of his voice,
a number of us did just that.
But Jack Martins couldn’t hear him. Jack was
a very short fellow, from Portugal, lived in
Chetwynd, about 5’4”, stocky and a really hard
working guy, always on concrete. He was
on the upstream wall running what we call
the glad-hand which opened and closed the gate on the concrete bucket. It controlled the pour so you
don’t dump out four yards when you only need one. Anyway, Jack was still looking up at the bucket-gate,
concentrating on opening and closing the glad-hand to keep the concrete flowing, when the coil rods
popped open half way up and he got thrown clear off the form and he disappeared over the upstream
side of the dam.
Of course we shut the pour down right away. We were in a kind of panic. We’d just lost a man and we
figured he had to be dead but we had to try to find him. So we swung the bucket down onto the deck
below, we got rid of the glom hook that holds the bucket, and we jumped into a safety skip with a
stretcher, myself, Louie Milisic, and our signal man, Rick Barber. We signalled the crane to pick us up and
a guy by the name of Dennis Heth, who was the Operating Engineer running the crane—awesome crane
operator—swung us over the upstream side of the dam.
The upstream side was pitch black. There was no lighting whatsoever on that side, so the lights from the
crane’s boom were the only light that we had and they weren’t all that shiny. Where we were pouring
was about 110 feet or so above the rocks below. The upstream side earthworks were finished and so
the upstream dewatering pumps were shut down and three or four feet of water had collected in some
places. We could make out rocks the size of small cars sticking out of the water near the vertical wall of
the intake.
So Dennis started lowering us in the basket to pick up the body—at least, that’s what we thought—and
as we’re going down lower and lower, Rick and Louie and I were calling out “Jack? Can you hear us?
Jack?” No answer. He had a nickname Peanuts because he was a small guy, you know how it is? So we
called “Peanuts?” And then we heard this sound, kind of a strange sound, a sort of moaning. We had no
flashlights, just the boom lights, so we signalled “Down easy, down easy, down easy” and there’s Jack, in
one of those puddles. He was holding his arms up in the air, his eyes are like a deer’s in headlights, and he
says “Mr. Chuck, I am a-born again.” Well by the Jesus, we were down there in seconds to pick him up. We
got him in the safety skip, him saying “I am okay, I’m a-good”, and we got him back onto the trestle.
Dennis and the three of us in the skip are thrilled that this man is alive and claiming to be okay, but we
don’t know if he’s in shock or what. When we got back to the trestle, the ambulance was there to pick him
up and get him to the first aid shack. Our first aid attendant, a very large fellow named Tom Crown, he
examined Jack and told us that other than a swollen calf, there was nothing wrong with the guy. So Jack
went home that night and Lazar pulled out a bottle of very good cognac and we all got shit-faced. That’s
Phot
o co
urte
sy B
ritish
Col
umbi
a H
ydro
and
Pow
er A
utho
rity
Page 81CHAPTER 7 – Bennett’s Dam Projects
the story of Jack Martins falling roughly a 105 feet into around 5 or 6 feet of water with rocks sticking up
all over. It was one of those experiences where you just can’t believe it, but you were there, you saw it
happen.
THE PROJECTS’ LEGACYThere is no question that the dams constructed under Premier Bennett’s Two Rivers policy were a remarkable
engineering and political feat. But whether they achieved the results the Premier intended is another matter.
Building the dams required a masterful juggling act, not just political but also financial. Yet while Bennett reaped
the full political benefits of his success, it is less clear to what extent British Columbians as a whole benefited.
The Premier himself stated that the purpose of all his dam and highway projects was to build the foundations for
bringing prosperity to even the remotest corners of the province. In this, he signally failed to succeed. Mica Creek
is no longer an incorporated village and the benefits from the Columbia River dams appear to have bypassed the
Kootenays, whose economic base has actually declined since the 1960s. Although not economically depressed
at the time of writing, the Peace River region has also seen little benefit from the dams the Premier built there.
Apart from the oil and gas industry, a spill-over from Alberta, there has been little in the way of new industrial
development in the area. Although the region’s main city in BC, Fort St John, has now doubled its population to
just over twenty thousand, this hardly compares with the growth on the Alberta side of the border where Grande
Prairie, with sixty-eight thousand people, has become the Peace River region’s real capital city. It is to Grande Prairie,
not Fort St John, that the citizens of Dawson Creek and Mackenzie drive when they wish to go shopping. In the
end, it was the Lower Mainland, last on the list of places he claimed he intended to benefit, which gained and grew
the most as a result of Premier Bennett’s projects.
Although the Portage Mountain Dam was subsequently renamed in the Premier’s honour, there is no monument,
not even a plaque, at the site honouring the sixteen workers who were killed building it. Many more workers were
maimed and seriously injured because of the Premier’s haste to see his projects completed. The precise number of
the dead and injured sacrificed to build his failed vision will never now be known, but they have an equal right to
be considered alongside the era’s dams and highways as part of W.A.C. Bennett’s legacy.
[See Chapter 13: Bennett’s Two Rivers Strategy - The Price of Success for more on the dams’ cost in workers’ lives].
Portage Mountain Dam, now the Bennett Dam.