chapter 7 scheduling resources and costs - جامعة نزوى · 1 chapter 7 scheduling resources...
TRANSCRIPT
1
Chapter 7 Scheduling
Resources and Costs
2
The Resource ProblemResources and Priorities
Project network times are not a schedule until resources have been assigned.
The implicit assumption is that resources will be available in the required amounts when needed.Adding new projects requires making realistic judgments of resource availability and project durations.
Resource-Constrained SchedulingResource leveling (or smoothing) involves attempting to even out demands on resources by using slack (delaying noncritical activities) to manage resource utilization.
2
3
Types of Project ConstraintsTechnical or Logic Constraints
Constraints related to the networked sequence in which project activities must occur
Resource ConstraintsThe absence, shortage, or unique interrelationship and interaction characteristics of resources that require a particular sequencing of project activities
4
Constraint Examples
3
5
Kinds of Resource Constraints
People
Materials
Equipment
Working Capital
6
Classification of a Scheduling ProblemClassification of Problem
Using a priority matrix will help determine if the project is time or resource constrained
Time Constrained ProjectA project that must be completed by an imposed date
Time is fixed, resources are flexible: additional resources are required to ensure project meets schedule.
Resource Constrained ProjectA project in which the level of resources available cannot be exceeded
Resources are fixed, time is flexible: inadequate resources willdelay the project.
4
7
A Third Constraint: Physical
8
Resource Allocation MethodsLimiting Assumptions
Splitting activities is not allowed—once an activity is start, it is carried to completion.Level of resource used for an activity cannot be changed.Activities with the most slack pose the least risk.Reduction of flexibility does not increase risk.The nature of an activity (easy, complex) doesn’t increase risk.
5
9
Resource Allocation Methods (cont’d)Time-Constrained Projects
Projects that must be completed by an imposed date
Require the use of leveling techniques that focus on balancing or smoothing resource demands by using positive slack (delaying noncritical activities) to manage resource utilization over the duration of the project
Peak resource demands are reduced.
Resources over the life of the project are reduced.
Fluctuation in resource demand is minimized.
10
Botanical Garden
6
11
Botanical Garden (cont’d)
12
Resource Allocation Methods (cont’d)
Resource Demand Leveling Techniques for Time-Constrained Projects
AdvantagesPeak resource demands are reduced.
Resources over the life of the project are reduced.
Fluctuation in resource demand is minimized.
DisadvantagesLoss of flexibility that occurs from reducing slack
Increases in the criticality of all activities
7
13
Resource-Constrained ProjectsProjects that involve resources that are limited in quantity or by their availabilityScheduling of activities requires the use of heuristics (rules-of-thumb) that focus on:
1. Minimum slack2. Smallest (least) duration3. Lowest activity identification number
The parallel method is used to apply heuristics.An iterative process that starts at the first time period of the project and schedules period-by-period any activities scheduled to start using the three priority rules
Resource Allocation Methods (cont’d)
14
Resource-Constrained Schedule through Period 2–3
8
15
Resource-Constrained Schedule through Period 2–3
ES resource load chartES resource load chartES resource load chart
16
Resource-Constrained Schedule through Period 2–3
Resource-constrained schedule through period 2–3ResourceResource--constrained schedule through period 2constrained schedule through period 2––33
9
17
Resource-Constrained Schedule through Period 5–6
Resource-constrained schedule through period 5–6ResourceResource--constrained schedule through period 5constrained schedule through period 5––66
18
Resource-Constrained Schedule through Period 5–6
Final resource-constrained scheduleFinal resourceFinal resource--constrained scheduleconstrained schedule
10
19
Resource-Constrained Schedule through Period 5–6
New, resource-constrained networkNew, resourceNew, resource--constrained networkconstrained network
20
Computer Demonstration ofResource-Constrained Scheduling
EMR ProjectThe development of a handheld electronic medical reference guide to be used by emergency medical technicians and paramedics
ProblemThere are only eight design engineers who can be assigned to the project due to a shortage of design engineers and commitments to other projects.
11
21
EMRProject: NetworkView of Schedule before Resources Leveled
22
EMR Project before Resources Added
12
23
EMR Project—Time Constrained Resource Usage View, January 15–23, 2005
24
Resource Loading Chart for EMR Project, January 15–23, 2005
13
25
EMR Project Network View Schedule after Resources Leveled
26
EMR Project Resources Leveled
14
27
The Impacts of Resource-Constrained Scheduling
Reduces delay but reduces flexibilityIncreases sensitivity of the network Increases scheduling complexityMay make traditional critical path no longer meaningfulCan break sequence of eventsMay cause parallel activities to become sequential and critical activities with slack to become noncritical
28
Splitting/MultitaskingSplitting/Multitasking
A scheduling technique use to get a better project schedule and/or increase resource utilization
Involves interrupting work on an activity to employ the resource on another activity, then returning the resource to finish the interrupted work
Is feasible when startup and shutdown costs are low
Is considered the major reason why projects fail to meet schedule
15
29
Splitting/Multitasking
30
Assigning Project WorkFactors to Consider in Assigning Work:
Don’t always pick the same people for the toughest assignments.Choose people with an eye to fostering their development through participation on the project.Pick people with compatible work habits and personalities but who complement each other.Team-up veterans with new hires to share experience and socialize newcomers into the organization.Select people who may need to learn work together on later stages of the project or other projects.
16
31
Multiproject Resource SchedulesMultiproject Scheduling Problems
Overall project slippageDelay on one project creates delays for other projects.
Inefficient resource applicationThe peaks and valleys of resource demands create scheduling problems and delays for projects.
Resource bottlenecksShortages of critical resources required for multiple projects cause delays and schedule extensions.
32
Multiproject Resource SchedulesManaging Multiproject Scheduling
Create project offices or departments to oversee the scheduling of resources across projects.
Use a project priority queuing system: first come, first served for resources.
Centralize project management: treat all projects as a part of a “megaproject.”
Outsource projects to reduce the number of projects handled internally.
17
33
Creating a Time-Phased Budget
34
Creating a Time-Phased Budget (cont’d)
18
35
Creating a Time-Phased Budget (cont’d)
36
Creating a Time-Phased Budget (cont’d)
19
37
Creating a Time-Phased Budget (cont’d)
38
Monthly Cash Flow Statement
20
39
Resource Usage Table
FIGURE 8.18
40
Key Terms
HeuristicLeveling/smoothingPlanned value (PV)Resource-constrained projectsResource profileSplittingTime-constrained projectsTime-phased baseline