Test Closure
![Page 2: Chapter 7E CSTA CSTP Test Closure](https://reader036.vdocument.in/reader036/viewer/2022082908/577cce181a28ab9e788d4cab/html5/thumbnails/2.jpg)
Introduction
Test Closure Entry Criteria Test Closure Exit Criteria
Test Summary Reports Critical Issue Encountered
![Page 3: Chapter 7E CSTA CSTP Test Closure](https://reader036.vdocument.in/reader036/viewer/2022082908/577cce181a28ab9e788d4cab/html5/thumbnails/3.jpg)
Introduction
• Final phase in STLC.• Ensures that all the testing activities are performed in
adherence to the Test Plan.• Decides whether the project can be moved into the
production phase or not. (means Go/No Go Decision)
![Page 4: Chapter 7E CSTA CSTP Test Closure](https://reader036.vdocument.in/reader036/viewer/2022082908/577cce181a28ab9e788d4cab/html5/thumbnails/4.jpg)
Introduction
Test Closure Entry Criteria Test Closure Exit Criteria
Test Summary Reports Critical Issue Encountered
![Page 5: Chapter 7E CSTA CSTP Test Closure](https://reader036.vdocument.in/reader036/viewer/2022082908/577cce181a28ab9e788d4cab/html5/thumbnails/5.jpg)
Entry Criteria of Test Closure
Scope/Objective should be completed
Defect status should be closed.
All Test cases should be executed.
All the test cases should mapped to the Req
Entry Criteria of Test Closure
![Page 6: Chapter 7E CSTA CSTP Test Closure](https://reader036.vdocument.in/reader036/viewer/2022082908/577cce181a28ab9e788d4cab/html5/thumbnails/6.jpg)
Introduction
Test Closure Entry Criteria Test Closure Exit Criteria
Test Summary Reports Critical Issue Encountered
![Page 7: Chapter 7E CSTA CSTP Test Closure](https://reader036.vdocument.in/reader036/viewer/2022082908/577cce181a28ab9e788d4cab/html5/thumbnails/7.jpg)
Test Summary Report
Critical Issue Encounter
Exit Criteria of Test Closure
Test Closure Exit Criteria
![Page 8: Chapter 7E CSTA CSTP Test Closure](https://reader036.vdocument.in/reader036/viewer/2022082908/577cce181a28ab9e788d4cab/html5/thumbnails/8.jpg)
Introduction
Test Closure Entry Criteria Test Closure Exit Criteria
Test Summary Reports Critical Issue Encountered
![Page 9: Chapter 7E CSTA CSTP Test Closure](https://reader036.vdocument.in/reader036/viewer/2022082908/577cce181a28ab9e788d4cab/html5/thumbnails/9.jpg)
• It contains the following information,• Total No. of Testcases• Total No. of Testcases executed• No. of Testcases failed• No. of failed Testcases has been fixed• No. of Testcases has been rejected and deferred.
Test Summary Reports
![Page 10: Chapter 7E CSTA CSTP Test Closure](https://reader036.vdocument.in/reader036/viewer/2022082908/577cce181a28ab9e788d4cab/html5/thumbnails/10.jpg)
Content of Test Summary Reports1. Test summary Reports
a) Details Of the Build/Runsb) Types of testing Conductedc) Test Environment/Tools Usedd) Items to be Tested and Items Not to be Tested
2. Test Resultsa) Metrics Generated
i. Test Management Metricsii. Test Coverage Metricsiii. Defect Metrics
b) Assessment of Quality3. Test deliverables
a) Known Issuesb) Recommendation
![Page 11: Chapter 7E CSTA CSTP Test Closure](https://reader036.vdocument.in/reader036/viewer/2022082908/577cce181a28ab9e788d4cab/html5/thumbnails/11.jpg)
Contents of Test Summary Reports with Examples
1. Test summary Reportsa) Details Of the Build/Runs. (Scope Of Build)b) Types of testing Conducted. (Functional Or Non
Functional testing)c) Test Environment/Tools Used. ( Server, Platform,
Configuration and Tool used for testing)d) Items to be Tested and Items Not to be Tested.
![Page 12: Chapter 7E CSTA CSTP Test Closure](https://reader036.vdocument.in/reader036/viewer/2022082908/577cce181a28ab9e788d4cab/html5/thumbnails/12.jpg)
2. Test Resultsa) Metrics Generated
i. Test Management Metrics. (Total no of Bug Fixes, Total No of Enhancements, No of Bugs/Enhancements covered in Test Cases, Test case Design Productivity, Test Execution Productivity, Requirement Stability index)
ii. Test Coverage Metrics. (Total test cases-Functional and Regression test cases, Test case in Scope, Total Test case Passed, Total Test Case Failed, Total no of Test case Non-executed, Total Executed Test Cases, Test Coverage (At the End of the Sprints) , Pass percentage (At the End of the Sprints)
iii. Defect Metrics. (Defect Status and Severity, Defect Trend)
![Page 13: Chapter 7E CSTA CSTP Test Closure](https://reader036.vdocument.in/reader036/viewer/2022082908/577cce181a28ab9e788d4cab/html5/thumbnails/13.jpg)
2. b) Assessment of Quality. (Acceptable, Quality Index- System Stability)
3. Test deliverables– Test Cases designed as part of bugs/enhancements– Test Log/Test Summary Results– Requirement Traceability Matrix
a) Known Issuesb) Recommendation
![Page 14: Chapter 7E CSTA CSTP Test Closure](https://reader036.vdocument.in/reader036/viewer/2022082908/577cce181a28ab9e788d4cab/html5/thumbnails/14.jpg)
Introduction
Test Closure Entry Criteria Test Closure Exit Criteria
Test Summary Reports Critical Issue Encountered
![Page 15: Chapter 7E CSTA CSTP Test Closure](https://reader036.vdocument.in/reader036/viewer/2022082908/577cce181a28ab9e788d4cab/html5/thumbnails/15.jpg)
Critical Issue Encountered
The issues that were encountered by the testing team are identified and discussed.
The resolutions for the critical issues are documented.