chapter 9 environmental management plan...
TRANSCRIPT
VOL. 5
Final- Rievised Chapter 9
ENVIRONMENTAL MANAGEMENT PLAN (EMP)
AND MONITORING (Revised by EGCB as an addendum according to the requirement of
Senior Environmental Specialist, World Bank)
9.1 SCOPE OF EMP
EMP encompasses the obligation of contractors and operators for good industrial activities, the
EMP will include the following measures:
(a) the measures will be taken during both construction and operation phases of the
project to eliminate or offset adverse environmental impacts, or reduce them to
acceptable levels, which is delineated in bid documents of the 2x 150 MW peaking power
plant project;
(b) a monitoring plan is proposed, and will be finalized in association with contractor to
assess the effectiveness of the management I mitigation m.easures.
(c) the contractor will prepare necessary maps to show the locations for environmental
monitoring points.
(d) currently the EGCB does not have any corporate environmental guidelines and
therefore, the contractors will follow their own corporate guidelines1 rules, WB and
DOE'S environmental guidelines and international guidelines (where applicable:).
Environmental management and monitoring activities for the proposed power plant project will
be accomplished in to two separate phases (a) construction and (b) operation phase. The monthly
environmental monitoring report will be submitted to the World Bank and DOE accordingly.
9.2 Environmental Management Unit (EMU) of EGCB
Currently the EGGB has one Manager Environment [(Environment Management Specialist)
(EMS)] at the corporate office, he is supervising the environmental monitoring activities under
taken by BHEL India, for demolishing and construction of ADB (2x120 MW Peaking Power
Plant, Siddhirganj, Narayangonj) financed power plant, which is now in progress. The
Siddhirganj 210 MW power plant has one water treatment facility along with infrastructure and
some equipment.
The EGCB management will endow this facility under EMU to under take the necessary
environmental monitoring for all three power plants within Siddhriganj Power plant premises.
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
Pub
lic D
iscl
osur
e A
utho
rized
(210MW, 2x120 MW and proposed WB financed 2x150 MW) during the operation phase of
Siddhirganj 2x120 MW Peaking Power Plant project (financed by Asian Development Bank) the
environmental monitoring parameters will be accomplished in house, but at this moment the
environmental monitoring equipments are not in place. The comparative monthly environmental
monitoring cost (if out sourced) and the current cost for necessary equipment1 monitoring
machines are summarized in table 9.7 to take the logical decision within this stipulated time line.
An Effluent Treatment Plant (ETP) will be constructed during the construction of Asian
Development Bank (ADB) financed 2 ~ 1 2 0 M W Peaking Power Plant during 2008. It may be
mentioned that the whole Siddhirganj Power Plant complex has been taken over by EGCB Ltd.
therefore, the ADB financed ETP will be used for the treatment of effluent generated from other
existing and proposed power plants within this premises.
9.3 WORK PLANS AND SCHEDULES
9.31 Construction Phase
The environmental management program is an integrated part of the project planning and
execution. It will evolve dynamically as project implementation proceeds, dealing flexibly with
environmental impacts, both predicted and unpredicted.
The turnkey contractor1 EPC contractor will take over all responsibility for implementation of
environmental monitoring during construction phase which will be clearly elucidated in bid
documents. The Project Director (PD) and Environment Manager (Environment Management
Specialist) EGCB for this specific project will supervise the implementation of the specified
environmental monitoring parameters through EGCB's owner's engineers. The Manager
Environment of the EGCB corporate office with required man power, expertise and find will
ensure proper environmental monitoring and also occupation health and safety as specified in this
chapter under section 9.5. Appropriate measures will be taken to mitigate any adverse impacts
and to enhance beneficial impacts, resulting from the project activities. Manager environment will
report to Director (Technical) and Project Director (PD) about the contractual obligation and
other national and international regulations (where applicable) regarding the environmental issues
need to be fulfilled by the contractor. It may be mentioned that, contractor will also follow their
corporate Health Safety and Environment (HSE) policies, incase of any non-addressed issues in
their HSE policy, only in that case the World Bank EHS policy will be followed, which are
available on the IFC website.
The environmental management during the construction phase will be focused on the following
aspects:
(a) Creationlgeneration and disposal of sewage, solid waste and construction waste
(b) Increased traffic
(c) Creationlgeneration of dust (particulate matter)
(d) Creationlgeneration of noise
(e) Oil spillage from construction equipment and vehicle
For better environmental management the local workforce may be employed during construction
work to avoid un-necessary creation of temporary wastes from construction workers' camp.
Table- 9.1 summarizes the potentially significant environmental impacts during construction
phase, the measures will be taken for elimination of adverse impacts and enhance positive
impacts. The monitoring plan and monitoring schedule has been briefly discussed in this chapter.
Implementation Schedule In accordance to the provision of the Contract document, the Contractor shall prepare an
"Implementation Schedule" for the measures to be carried out as part of the environmental
management and monitoring. Table 9.2 shows a tentative plan for environmental reporting.
9.3.2 Operation Phase
The environmental management during the operational phase the O&M contractor will take care
of the environmental issues and their management and EGCB EMU will supervise: the whole
process. After the expiry of the O&M contractor's tenure, the EGCB will be solely responsible for
all sorts of Environmental Monitoring and other associated issues like occupation health and
safety. The important issues are being addressed in the following way:
(a) Emission from the power plant
(b) Generation of noise
(c) Generation of industrial waste at the plant (Solid and Liquid)
(d) Generation of domestic waste (Sewage and kitchen waste)
The following table (Table 9.1& 9.2) summarizes the potentially significant environmental
impacts during operation phase, the measures need to eliminate or offset adverse impacts and
enhance positive impacts and their reporting. The monitoring plan and monitoring parameters
schedule has been presented in this chapter.
Table 9.1 : Potentially significant environmental impact during construction and operation phase
and their mitigation measures
Activity/lssues Potentially Significant Impacts
Proposed Mitigation and Enhancement
Measures
Responsible Parties during construction
Parties during
Activity/Issues
Construction Phase
Influx of workers
Proposed Mitigation and Enhancement
Measures
Construction of sanitary latrine having facility of septic tank and soak pit system Erecting "no litter" sign, provision of waste binslcans, where appropriate Waste minimization, recycle and reuse Disposal of solid waste in designated municipal dumping place
Clean bill of health a condition for employment HSE training to the workers in every week Regular Medical Check up of the workers
Potentially Significant Impacts
Generation of sewage and solid waste
Possible spread of disease from workers
Responsible Parties during construction
EPC Contractor will take necessary measures for the environmental. monitoring. The EGCB and Owner's Engineer will supervise the process
Responsible Parties during
operation
Transportation of equipment, materials and personnel; storage of materials
Sign$cant Impacts
Increased I
Generation of noise, especially affecting the nearby school and residential areas
air quality fiom increased vehicular movement, affecting people in the surrounding areas
Wind-blown dust from material (e.g., fine aggregate) storage areas
Proposed Mitigation and Enhancement
Measures Scheduling of deliveries during non-school hours and after regular working hours School going children should be protected from traffic hazard during construction phase, with installation of proper traffic sign and warnings Speed reduction to 10 km per hour within the Siddhirganj complex and 05 Krnlhr in front of the school and mosque during school and pray hour At the initial stage of the civil construction, the school children will be protected by temporary noise barrier and gradually permanent noise barrier will be raised to protect the children (in consultation with the civil consultant) Vehicles will be keeping under good condition, with regular checking of vehicle condition to ensure compliance with national standard of emission (fiom vehicles) Watering unpavedfdusty roads Sprinkling and covering stockpiles Covering top of trucks carrying materials to the site and carrying construction debris away fiom the site
Responsible Parties during construction
The EPC Contractor will be responsible for this management which will be indicated in bid documents. EGCB and owner's engineer will supervise the management process
This will be done by EPC contractor during construction phase according to DPP and bid documents of this project
Carrying cost of the construction debris are projected in DPP and Bid documents
Construction activities, including operation of construction equipment
Potentially Significant Impacts
Generation of noise from construction activities (general plant and access road construction), especially will affect the nearby school and residential areas
Deterioration of air quality £?om wind-blown dust and possible use of equipment, such as stone (aggregate crushers)
Proposed Mitigation and Enlzancement
Measures Noise suppressors and mufflers will be used in heavy equipment Heavy construction equipment will be used, avoiding school hours and also at night time Prolonged exposure to noise will be restricted to the (produced by equipment) workers suffer zone between the school and construction site will be created through plantation during construction time (phase by phase) the school children will be protected by temporary noise barrier and gradually wall will be raised to protect the children (in consultation with the civil consultant
No stone crushers will be used, which may produce significant amount of articulate matter ~&struction spoils will be used as filling materials as and when is required, no debris will be left unattained at the construction site. Excavated materials (if any) will be sold/disposed before making any annoyance Continuous watering of bare areas
Responsible Parties during construction
-The EPC Contractor will be responsible for all construction related environmental monitoring and management. This management will be indicated in bid documents. Some of these issues have been addressed earlier in this table. -EGCB and owner's engineer will supervise the management process during construction phase
-The cost of temporary noise barrier will be covered in Bid documents and DPP.
Responsible Parties during
operation
Land filling with soil through truck load during raising of land (the soil will be taken by the contractor having lawful earth cutting license)
Operation Phase
Potentially Significant Impacts
I construction 1 construction debris I
Proposed Mitigation and Enhancement
I
waste
Measures
away from the site and their appropriate disposal in a designated municipal landfill
Generation of I Hauling of
Accidents Regular inspection and maintenance of equipment Environmental health and safety briefing Use of Personal Protective Equipment (PPE)
1 Spills and leaks I Tidiness will be kept leading to soil and water contamination with oil, grease and hydrocarbon
Employment of workllabor force
Generation of dust at the adjacent road Local community may be affected through dust
Proper handling o f lubricating oil and fuel will be ensured Collection of accidental spillage, proper treatment, and disposal will be ensured
The contractor will be requested to employ the local people with possible opportunity.
The moist soil will be taken from the source, this place will be informed by the contractor to the owners The top of the truck will be covered by the normally used covering materials during transportation
Responsible Parties during
The EPC Contractor will be responsible for this activities indicated in bid documents. EGCB and owner's engineer will supervise the process.
Responsible Parties during
Power Generation
Potentially Signzpcant Impacts
Emission fkom the power plant (Possible emission of NOx, temperature, CO)
B Generation of noise
Proposed Mitigation and Enhancement
Measures Using tall stack Using low nitrogen oxide burners Installation of stack emission monitoring equipment for major criteria pollutants Planting of indigenous trees around the project site, especially along the boundary of the school and residential areas located close to the project site Restrictions may also be imposed on installation of industries in the area that emit significant amount of particulate matter.
Provision of silencers for generators and turbines Planting of indigenous trees and shrubs around the project sties Routine maintenance of plant Regular noise monitoring, especially at the school and residential quarters located close by Use of ear-muffs and ear-plugs by plant personnel working in the generator and turbine facilities of the plant
Responsible Parties during construction
This part is under jurisdiction of DOE
Responsible Parties during
operation -The EPC contractor will monitor during warranty period and -O&M contractor will monitor during their operation tenure. -The EGCB will supervise the monitoring process after that period, -EGCB will be responsible for monitoring and management of Environmental parameters -Previously built temporary noise barrier will be replaced by the permanent noise barrier by the EPC contractor, this barrier and that barrier will be maintained by the O&M contractor during their contract period after expiration of that period EGCB will be responsible for all sorts of environmental monitoring and management.
Construction Phase
Responsible Parties during
operation -O&M contractor will monitor during their tenure and after the completion of their tenure, Environmental unit of EGCB will be responsible for monitoring and management of the Gas Turbine cooling and drinking water quality. Environmental unit of EGCB will regularly monitor report to the higher authority and proper mitigation will be ensured according to the same way described earlier
Activi@/Issues
Water Consumption
Waste generation
Table 9.2: The monthly environmental monitoring report
Initial review
Particulars
Before start of work
Potentially Sign if cant Impacts
- Cooling water for the Gas turbine during operation
- Quality of drinking water
Inappropriate disposal of sewage causing environmental pollution Generation of solid and liquid waste including sludge from de- generation (during de mineralization of raw water) process
EPC Contractors with the help of owner's
engineer will prepare an inception report
stating the procedure of environmental
monitoring and management of the project.
The EGCB will review that report.
Frequency1 Stage
Proposed Mitigation and Enhancement
Measures Small amount of water will be used for plant operation, that water will be released only during annual overhauling, the quality of that water will also tested before being release in the natural drain Regular monthly monitoring of drinking water which will be consumed by the residents and officers
The sewage will be disposed through septic tank and soak pit system
Solid waste will be segregated according to the category and will be sent to the designated land fill and recycle. This plant will not use any de-mineralize water
Responsible ~ ~ e n c ~ l
Responsible Parties during construction
Particulars
Environmental Monitoring
Report
Mid-term Review:
review of activities
possible
modification to
procedure andlor
overall plan
Frequency1 Stage
Specific Problems and
Solutions
- Approximate mid-way
of the project
Responsible Agency
Monthly
Owners engineer will review and prepare a
report, which will be reviewed by EGCB
Contractor will prepare that report and will
forward to the PDIManager Environment
(EMS). Ultimately this report will be
forwarded to the DOE, WB and concern
Ministries.
As and when required Project Director1 Project Manager1 Manager
environment may raise (if found), that need
to be resolved by the contractor
Completion Report:
Final Review :
review of program
recommendation
for similar future
program
- At the time of
commission
-The turnkey contractor will prepare monthly
environmental monitoring report and will
forwarded to EMS, EGCB, which will also
be forwarded to the DOE, WB and concern
Ministries.
- Towards the end of the
project
-Owners engineer will review and prepare a
report, which will be reviewed by EGCB
Station will prepare monthly monitoring
report which will be forwarded to the DOE,
Operation Phase
WB and concern Ministries. The EMS,
EGCB will overall supervise and help to
r implement their reporting obligation.
Owner's Engineer with the help of other
chemists working at the Siddhirganj Power 1 Environmental Monitoring
1 Report
Monthly
9.4 ENVIRONMENTAL MONITORING PLAN
The turnkey contractor will prepare a details plan about the environmental parameters and
protocol for taking the environmental monitoring data in consultation with EMS, EGCH along
with owner's engineer.
9.4.1 Monitoring Parameters
The typical environmental monitoring parameters of power plant are briefly described iin this section.
9.4.2 Construction Phase:
Ambient air quality monitoring: Measurement of air quality parameters e.g., NOx, CO, PMlo,
PM2.5 (if required) and temperature will be carried out during the construction period in
accordance with the monitoring plan presented in the table- 9.5. Measurement will be carried out
at locations which are sensitive with respect to air quality, near the school and residence and other
vulnerable locations. The number of locations for monitoring shall be agreed by the EMS, EGCB.
One stationary monitoring station will be installed at a strategically viable location within the
Siddhirganj premises where the greatest impact of the power plants can be expected. This station
will continuously monitor the environmental parameters for all three power plants within this
premises.
Emission: In general at least two diesel cranes, two diesel generators, one forklift, four general
transport and miscellaneous tractor-trailers will be used on site (more specified number will be
provided during preparation of contract documents of EPC contractor). The emission from these
vehicles and equipments to atmosphere would be properly maintained to ensure that their
emissions will be kept within WB and DOE standard.
Drinking water quality monitoring: Drinking water quality will be monitored during the
construction phase if necessary. During construction phase excess water will not bt: produced,
and waste water will not be drained in to the natural stream for this particular project.
Soil quality monitoring: Representative type of agricultural sample will be monitorecl seasonally
around the impact zone; this soil sample will be collected and sent to Soil Resources
Development Institute (SRDI), Dhaka. The parameters of analyzed according to their set
guidelines.
Noise level monitoring:
During construction, diesel generators, heavy construction equipments and vehicles will create
higher noise level affecting human health and the wildlife within the close vicinity of the project
area. The noise level drops along the distance, and barriers so the temporary noise barrier and
indigenous tree plantation will be considering the availability of the plantation area to protect the
school children from the noise. The locations for monitoring of noise level shall be agreed by the
EMS, as stated earlier. Based on regular monitoring the design 1 location etc of the temporary
barrier would be altered if necessary.
Therefore, comprehensive noise monitoring during different stages of construction will be
accomplished regularly and the mitigation measures will be taken. The noise level at the
construction site would be kept within DoE's permissible limit. The cost of these barriers will be
estimated during EPC contract. The cost of this mitigation of noise will be borne by the EPC
contractor.
Waste Management: Records of generated process wastes if any will be recycled and will be
kept separately according to the WB and DoE's guideline. Chain of custody for hazardous waste
and for process non-hazardous waste will be maintained. The schematic flow chart is shown
below. This flow chart will also be used during the operation phase with few changes when ever
necessary.
The present project activities will involve establishment of camps, transport, site development
and construction and operation of power plant. For each activity, various types and quantity of
wastes will be generated. The Engineering Procurement and Construction (EPC) contractor and
owners engineer will prepare a comprehensive list of waste types, sources and plans to manage all
of these wastes in an environmentally friendly manner. The major sources are identified as:
o Camp waste
o Construction & operation waste, and
o Emission
The EPC contractors will implement wastes segregation strategy as a first step of their waste
management program where the hazardous and non-hazardous materials will be separated out
following the waste management flow diagram as shown in Figure 1. The non-hazardous
materials will then be further sorted out into bio-degradable and non-biodegradable groups.
Among the bio-degradable materials, EPC contractor and EGCB will recycle the recyclable
materials and will send the compostables in municipal designated site. In Dhaka few NGOs
(Waste Concern) are preparing bio-fertilizers so those NGOs may be informed for these activities
(Figure 1). Preparation of bio-fertilizer is not any part of this project. But the segregation process
is essential in this project.
Figure. 1 Waste Management flow diagram for the EPC contractor to be followed up to segregation.
Camp Waste Management
The EPC contractor will prepare a list of all identified source and type of wastes that would be generated in their campsite (Table 9.3) and is committed to minimize waste generation as much as possible. Siddhirganj is well communicated area where municipal waste disposal facilities is available therefore, the EPC contractor will facilitate the corporation authority to collect, manage, treat and dispose off the wastes on its own initiative.
Table- 9.3 Types and sources of domestic wastes
The EPC contractor will setup selective waste collection facilities at the site. Special areas for
short-term waste storage will be designated to facilitate the program. The EPC is committed to
comply with the applicable environmental and sanitary norms and have been equipped in due
manner at the proposed facilities, including arrangement for disposal of hazardous wastes (if any)
and the environmental impact of waste generated at the Company's facilities will be minimized.
Type of wastes
Drainage
Emission
Domestic sewage
Domestic refuse
Kitchen waste
Washroom
The EPC contractor will follow regulations and guidelines for wastewater discharges into
surrounding waterways. Liquid wastes that could damage the environment will never be released
or allowed to drain directly into a watercourse. The campsite is provided with septic tank with
closed sewage systems.
Construction and operation Waste Management
Main components
Bathing water, Rainwater
Construction equipments, vehicles, cranes etc.
Biodegradable organic matter
Garbage, packing materials, paper, batteries, paper bags, cartoon, plastic, plastic bottles, cans, wrappers, organic waste, waste, glass bottles etc. Waste vegetable, wastes during processing of vegetables, waste food, soap and detergent, fishes scales, meat's scales and wastes etc produced in kitchen
Bathing and water
The principal industrial wastes arising from construction and operation are domestic waste, some
solid and liquid wastes filter cartridges, various discarded chemical products, empty drums, pipe
Potential constituents of the released wastes Trace amount of oil and grease, soap
Emission of smokes, CO, C02 etc.
Semi-solids, used detergent, coliform bacteria
Plastic, organic waste, batteries, glasses
Protein, bio-degradable organic matters
Soap, detergent, trace amount of oil and grease
dope buckets, household types trash, discarded chemicals, wood pallets, lime, cement and mud
sacks. A list of typical wastes types and sources are shown in table 9.3 & 9.4.
The produced effluent will be treated in the ETP as described in section 9.2 therefore, no further
installation of ETP will be required for WE3 financed 2x 150 MW peaking power plant. 21OMW
and WB financed 2x 150 MW power plants' effluent will channeled up to ADB financed 2x 120
MW power plant.
9.4.3 Hazardous Material Handling and Storage
During construction of the plant, commercially available chemicals (paints, thinners etc) will be
used and stored in the construction area. Hence small amount of unused or spent chemicals (used
paints, motor oils) will be generated. Hazardous wastes likely to be generated during routine
project operations include oily water, spent catalyst, lubricants and cleaning solvents. Operation
and maintenance of the plant also generates some hazardous wastes. These include: waste oil,
spent solvents, batteries, fluorescent light tubes, lubricating oils etc.
The project will also involve the construction and operation of gas pipe line and handling of large
amount of natural gas. Natural gas poses some risk of both fire and explosion. Used lead acid
batteries contain lead, sulfuric acid and several kinds of plastics which are hazardous to human
health. Therefore the ideal place to store used lead acid batteries is inside an acid resistant sealed
container to minimize the risk of an accidental spillage.
The following set of typical storage guidelines will be adopted:
the storage place will be protected from rain and storm water, this place will also be
provided with a good shed.
the storage place will be protected from any sources of heat hazards
the storage place will have a ground cover
the storage place will have an exhaust ventilation system in order to avoid gas
accumulation
the storage place will have a restricted access and be identified as a hazardalus material
storing place
any other lead materials which may eventually arise, such as plumbing, should be
conveniently packaged and stored in accordance with its characteristics
The store premises will be provided with fire protection and fire fighting equipment. These
equipments will be installed, tested and maintained in accordance with the manufacturer's
guidelines. The employer will ensure that a procedure for dealing with emergencies is in place,
implemented, maintained and communicated to persons on the premises who may be affected by
or respond to an emergency.
Ignition sources in hazardous areas will not be allowed. The facility staff will be trained and
equipped with personal protective gear such as rubber gloves, boots, hard hats, apron or splash
suit and a face shield with safety glasses or goggles, as per corporate safety guidelines.
Toxic chemicals will be handled by using protective gear. Volatile toxic chemicals will be
handled in a well ventilated place. Sufficient and suitable lighting will be ensured.
Safe access within and to and from the premises will be ensured. Unauthorized access and
activity on the premises will be prevented. These measures will reduce the chances of accidents
and facilities a safe environment for the workers, the staff and the plant.
Table 9.4 Wastes from construction and operation of power plants
The EPC contractor will reduce the quantity and toxicity during construction and operation of
power plant in the first place thus the impact and cost of environmentally acceptable disposal will
be reduced. EPC and EGCB's proposed approaches are:
Type of waste
Drainage
Gases
Sewage
Canteen
Spent bulk chemicals
Industrial waste
Chemicals Chemical drums (empty)
Waste lubricants
Cement slurries Cement mix water
o Use of best-available technologies to minimize environmental degradation;
Main component
Rainwater
Flue gases, NOx, CO, C02 and temperature
Biodegradable organic matter
Negligible
Cement, bentonite, hydrocarbons, thinners
Batteries
Lube oil, grease
Weighting materials, salts, thinners, viscomers
Potential constituents of the released wastes
Hydrocarbons, chemicals, mud particulates Oxides of nitrogen, Carbon and temperature Semi-solids, detergent, fecal coliform and total coliform bacteria Plastic, organic waste, cans, glasses
Hydrocarbons, organics, solids, alkalis
Acid, heavy metals
Toxic chemicals, acid Toxic chemicals, acid Metals, organic compounds
Heavy metals, high pH salts
o Recycle of recyclable materials
o Proper disposal of hazardous and non-hazardous solid and liquids;
o Minimization of water use in kitchen and worker camp;
o Monitoring and maintaining chain of custody for the disposal wastes and construction
debris;
o Monthly environmental reporting to the concern authorities;
o Involvement of DOE regarding any disposal of wastes, which are not specified in the
environmental guidelines (ECR 1997)
9.4.4 Operational Plzase:
Meteorological measurements: Seasonal meteorological monitoring data will be collected from
the Meteorological office of Agargaon, Dhaka to monitor the wind direction and speed,
temperature, humidity and precipitation as and when is required.
Atmospheric emissions monitoring: One diesel crane, one fork lift, several transport and
miscellaneous equipments will be used on site. The emission from these vehicles to atmosphere
would be negligible. The continuous emission of CO, SO2, NO,, PMlo, oxygen content and
temperature of flue gases will be carried out around the plant sites and up to impact zone.
The DOE may be requested to monitor the illegal emission of gases and dust from the surrounding
areas of the proposed power plant which will facilitate to operate this plant smoothly.
Ambient air quality monitoring: Monthly monitoring of the following air quality indicators
e.g., NOx, SO2, PMlo, PM2,5 (if required) and temperature will be monitored. One monitoring
station will be installed at a strategically viable location within the Siddhirganj Power Plant
premises. This station will be used as continuous monitoring station for ambient air quiality.
Drinking water quality monitoring: Drinking water quality will be monitored during the
operation phase. During operation phase excess water will not be produced, and waste water will
not be drained in to the natural stream for this particular project.
River water monitoring: Although the proposed plant is not expected to be a contrilbutor to the
deterioration of water quality of the Sitalakhya River, a water quality monitoring program during
the dry periods may be conducted for other projects (210MW combined cycle power plant).
Water temperature and dissolved oxygen along with BOD5, COD, Oil, Grease and heavy metals
during March - May and October - December may be tested as and when is required.
Noise level monitoring: Indoor noise levels in the generator and turbine facilities along with the
outdoor noise at the school premises and near the air condenser system will be monitored
regularly. The noise level drops along the distance, and barriers therefore the convenient
temporary noise barrier and indigenous tree plantation will be taken place to protect the school
children from the noise. The previously built barrier during construction will be maintained by
the O&M contractors and EGCB respectively.
On top of the regular monitoring, the comprehensive noise monitoring during operation will be
accomplished regularly and the mitigation measures will be taken. The noise level during
operation on site would be kept within DOE'S permissible limit. The cost of these barriers will be
estimated during EPC contract and will be included in bid documents and DPP which will be
implemented by the EPC contractor.
9.4.5. Monitoring Schedule The following tables provide a summary of the monitoring schedule for the construction and
operational phases of the proposed power plant (Table 9.5).
Table 9.5 Monitoring plan during construction and operation phase of the project.
Construction Phase
required)
Issue
per DOE'S reporting obligation)
Monitoring Frequency Parameters
-This monitoring will be done by the EPC contractor. The bid documents will include this cost. The EGCB will supervise as stated earlier.
Resource Required Responsibility """I
-Presently the Siddhriganj Power Plant has the facility of monitoring temperature, C02 and 02. The other monitoring parameters e.g., NOx, CO, PMl0, will be tested by good quality laboratory in Dhaka.
-EGCB and owner's engineer will supervise the monitoring process at this stage.
Responsibility
BOD5, COD, Oil and Grease and heavy metals (if required)
Agricultural soil may be tested by the SRDI.
Drinking water
Noise level
Physical parameter: - color, turbidity, Chemical parameters: - pH, nitrate, alkalinity,
total hardness, calcium hardness, arsenic, Iron (Fe), C1, Mn, Al, arsenic,
Biological parameters: - total-coliform, faecal-
coliform,
Noise at different locations
Once in every month if required (It is not the part of regular environmental monitoring)
I Process waste
Once in every month (If the workers use drinking water from the contractors supply source)
Solid 1 liquid wastes
As and when is required.
If any adverse reportlinformation is found
Once in every monthly, as and when is required.
-Monitoring at this stage is the obligation of the contractor. -EGCB and owner's engineer will supervise the monitoring process at this stage.
-The contractor will monitor the drinking water parameter. - EGCIB and owner's engineer will supervise the monitoring process at this stage.
The contractor will responsible for cleaning in case: of accidental spillage.
By the supervision of EGCB ithe soil may be tested from SRDI laboratory in Dhaka.
The contractor will be responsilble for the monitoring activities - EGCB and owner's engineer will supervise the monitoring process at this stage.
and when is required. advise a!; when is required
Monitoring data can be taken from the Meteorological Department of Dhaka office
Meteorological measurements
O&M contractor will monitor during their tenure and EGCB's Environmental unit will
Wind direction and speed, temperature, humidity and precipitation.
collect this information after full taken over of the Power Plant project by
Atmospheric emissions
Ambient air quality
1 1ssue
River water
CO, SO27 NO,, PMl0, oxygen content and temperature
Parameters
NOX, So23 PMl0, PM2.5 (if required) and temperature
Water temp., DO, BOD5, COD, Oil and Grease and heavy metals (if required)
Monitoring Frequency
Once in a month
Resource Required and
Once a month
Occasionally as and when is required (It is not the part of regular environmental monitoring)
Responsibility
-O&M contractor will monitor during their tenure and EGCB will supervise. After full taken over of the Power Plant EGCB will monitor these parameters through their own in house arrangement. -During operation of ADB project the EGCB will procure the equipment for measuring NOx, CO, PMlo and PM2.s
-O&M contractor will monitor during their tenure and EGCB will supervise. After full taken over of the Power Plant, EGCB will monitor those parameters through their own in house arrangement. -During operation of ADB project the EGCB will procure the equipment for measuring NOx, CO, PMlo and PM2.5
-O&M contractor will monitor during their tenure and EGCB will supervise. After full taken over of the Power Plant, EGCB will monitor those parameters through their own in house arrangement. -During operation of ADB project the EGCB will procure the equipment for measuring DO, BOD,, COD etc.
Drinking water
Soil quality
Issue
Physical parameter: - color, turbidity, Chemical parameters: - pH, nitrate, alkalinity,
total hardness, calcium hardness, arsenic, Iron (Fe), Cl, Mn, Al, arsenic,
Biological parameters: - total coliform, faecal
coliform,
Monitoring Frequency Parameters
-Soil will be monitored. -Agricultural soil may be tested by the SRDI.
Responsibility
Noise level Noise at different locations
Process waste 1 Solid / liquid wastes
Once in every month (If the workers use drinking water fiom the contractors supply source)
-As and when is required. -If any adverse report/information is found
Once in every monthly, as and when is required.
Wastes will be collected and disposed on daily basis, as and when is required.
-O&M contractor will monitor during their tenure a~nd EGCB will supervise:. After fill taken over of the Power Plant, EGCB will monitor those parameters.
-O&M contractor will monitor during their tenure and EGCB will supervise. After fill taken over of the Power Plant, EGCB will monitor soil parameters may be tested fiom SRDI laboratory in Dhaka.
-O&M contractor will monitor during their tenure and EGCB will supervise. After fill taken over of the Power Plant, EGCB will monitor the noise level through their internal arrangement.
-O&M contractor will monitor during their tenure and EGCB will supervise. After fill taken over of the Power Plant, EGCB 'will monitor the noise le,vel through their internal arrangement.
I I I I I
Note: Actual monitoring time and location will be decided by the proposed Environmental Management Unit during the construction and operation phase along with EPC and owner's engineer.
The table 9.6 gives the estimated cost (Information o f BUET, 2007) o f environmental monitoring during the construction and operation phase. Table 9.7 and 9.8 provide estimated amount of cost for the procurement of new equipments for environmental monitoring and training.
Table 9.6 Showing the estimated cost for monthly environmental monitoring during construction and operation phase if it i s outsourced by the EPC contractor or by EGCB.
S1 No.
Items Number Per Unit Sample Cost Total Cost (Tk)
1 SI 1 Items 1 Number 1 Per Unit Sample Cost 1 Total Cost No.
Operational Plzase
1
2 3 4 -
Construction Phase
The asterisk marks parameters may be tested within the EGCB Siddhirganj Power Station
through buying some equipment. The list and cost of those equipments are summarized in
table 9.7. This option will be briefly included in bid documents so that, EPC contractors and
ultimately EGCB will install the required equipment during operation stage of ADB projects.
Ambient air
Ambient air Drinking water Noise level
The following cost has been calculated projecting the price on January 2008. The equipment can
be purchased according to the requirement of the power station. To make the project cost
effective, establishment of own equipment may be taken under consideration with consultation of
EGCB Management. If the management desires those environmental monitoring equipment will
be procured through the EPC contractor and accordingly the contractor will supply the specific
instrument which will be set by the owners engineer and EGCB management. To operate the in-
house monitoring activities low profile training will be required which are summarized in table
(T k.) -
5 Process waste dumping 10 Total cost for one time sample during construction phase
1
2*
3* 4*
5* 6 1 7
(Tk)
PM2,5 = 10 (if required) PMlo = 10
2 20
0 1 (as and when is
required) NO, and Temp. (01) (10) PMIO (10) 20 0 1 10
Meteorological data collection (Met office real cost of data- 2008)
Atmospheric emissions
Ambient air -- Ambient air
Noise level Drinking water Process waste dumping
5,0001-
Total cost during operation phase Grand total cost
5,0001-
50,0001- 430,0001-
601,600/- 10,31,600/-
66001-
30,0001-
50,0001-
Source: The unit cost shown in the report of BUET, 2007. * The asterisk marks parameters may be tested within the EGCB Siddhirganj Power Station.
66001-
30,0001-
1 0,0001- 15,0001-
1 10,0001-
20,0001- 1 0,0001- 100,0001-
1 0,0001- 200,0001- 15,0001- 15,0001- 5,0001- 50,0001-
9.8. The training for the specific officer is an integral part for successful completion of this
project. Briefly the cost of training has been summarized in the following table (Table 9.8).
Table: 9.7. The table shows the price of the different environmental monitoring equipments.
Qty Unit Price TK SI. No. Description
0 1 Fine Particulate Sampler 0 1
Envirotech, India, APM 550.
ii) 1 GFIA Filter paper, (100 discs). 0 1 7,800.00 1 7 , 8 0 0 . 0 0 ~
02 i)
Extra spares & consumables (Optional) PTFE filter
03
04
05
0 1
Sub Total (A)
BOD Analyzer
BOD Incubator
- 06
I I I I
Sub Total (C)
DRB200 Digital Reactor Block, or Atomic Absorption Spectrophotometer
07
1 Grand Total (A+B+C)
75,000.00
0 1
01
('4'4s) COD Digestion
1 BD Tk. =18,21,500.00 I
75,000.00 7 5,5'7,800.00
0 1
Sub Total (B)
SOX NOx, CO, etc. Analyzer.
Table 9.8 Cost estimate for training during construction and operational phase
88,000.00
0 1
0 1
5700.00
7, 13,700.00
5,50,000.00
Items
Safety and occupational health Environmental management system Total cost during construction and o
5700.00 i
Number (per year)
0 1 0 1
)erational phase
Per Unit Cost (Taka)
200,0001- 200,0001-
Year)
200,0001-
9.4.6 Reporting
Reports of the monitoring data, both during construction and operation phases, will be submitted
to the Department of Environment (DOE) on regular basis as per instruction of clearance clauses
of DOE.
9.4.7 Resources and Implementation
The environmental parameters will be monitored during the construction and operational phases
along with the monitoring schedule have been presented in the previous sections. The contractor
will be responsible for carrying out the monitoring during the construction phase (in accordance
with table no.- 9.5) under the direct guidance of the Manager Environment as mentioned in this
chapter. The contractor will submit monitoring results to EGCB office on a monthly basis, and
accordingly the reports will be consulted with PD and ultimately report will be forwarded to the
DOE and other concern department and World Bank office.
During operation phase, and after full taken over by the EGCB, the environmental monitoring of
this power plant will be carried out by the EMU, EGCB through its own staff and equipment if
available, or can be out sourced to a laboratory. But during turnkey period monitoring work will
be carried out by the contractor.
Potentially significant impact during both the construction and operation phase will be properly
addressed through adaptation of the proposed mitigation and enhancement measures outlined in
the table 9.1. The environmental monitoring chapter and the corporate environmental monitoring
procedures shall be included as an integral part of the contract document of those proposed power
plant project.
Environmental Management Unit headed by Manager Environment, EGCB corporate office will
coordinate the whole process of environmental monitoring with the help of officers working in
water treatment plant at 210 MW CC power plant, Siddhirganj, ultimately the environmental
monitoring of whole Siddhirganj Power Plant complex will be conducted by the EMU unit.
9.5 OCCWATIONAL HEALTH AND SAFETY (OHS)
In work place good industrial practice will be maintained during construction and operation by
the contractor and EMU, EGCB respectively. During construction phase, the contractor will
follow their own corporate Occupation Health and Safety (OHS) procedures, that procedures will
be produced to the EGCB prior to the construction work.
The state of art OHS practice will be followed by the contractor, in case of any lapses in
definition and understanding of the environmental parameters and tests, the Engineering
Procurement Construction (EPC) contractor will be obliged to follow the Bangladesh (DOE) and
World Bank Group's EHS policy which is available on IFC website.
OHS committee will monitor and train the workers. Weekly1 fortnightly training will be
conducted to aware the workers under the contractors obligation. The cost regarding those
activities will be borne by the executors.
9.5.1 General Requirements
Bangladesh Labor Law encompasses the related occupational health and safety obligations.
Labour Law 2006. The labor law itself a huge volume so to avoid this volume of papers only the
labor law has been referenced in this chapter. The labor laws could have been included in review
of law chapter of EIA. This law has focused on occupational hygiene, occupational diseases,
industrial accidents, protection of women and young persons in dangerous occupation. The salient
features of the general requirements for the workers' health and safety stated in the refixed law is
presented in Table 9..9. This law is commonly followed in Bangladesh by employer, incase of
noncompliance there may have some problem during labor dealing.
9.5.2 Workplace Environmental Quality
The proposed power plant project has two main phases - (i) the construction of infrastructure,
installation and commissioning of plant equipment, (ii) operation of the plant etc.
Table 9.9: General requirements for workers' health and safety according to the labor law 2006
(Bangladesh).
Report on fatal accident and treatment Compensation on contract and contract registration I i Appeal
Issues Health and Hygiene
Safety
Compensation for accidents at work
Requirements Cleanliness Ventilation and temperature Dust and fumes Disposal of wastes and effluents Overcrowding Illumination Latrines and urinals Spittoons and dustbins Safety for building and equipment Precautions in case of fue Fencing of machinery Floor, stair and passage way Work on or near machinery in motion Carrying of excessive weights Owner's responsibility for compensation Amount of compensation 1
I Issues I Reauirements I Dust and Fumes Any dust or fumes or other impurities likely to be injurious to the
workers, effective measures shall be taken to prevent its accumulation
Over-crowding and its inhalation by workers No work room in any factory shall be overcrowded
Latrines and urinals
of fire I ~ffect ive measures shall be taken td ensure that all the workers are familiar with the means of escape
At least five hundred cubic feet of space shall be provided for every worker employed in a work room Sufficient latrines and urinals shall be provided Shall be maintained in clean and sanitary condition
Precautions in case
First aid
Shall be adequately lighted and ventilated Shall be provided with means of escape in case of fire
Disposal of wastes and effluents
Occupational and poisoning diseases
Compensation
Fire fighting apparatus should be provide and maintained Provided and maintained fxst aid facility One for every one hundred and fifty workers Shall be kept with a responsible trained person who shall be available during the working hours In every facility where five hundred or more workers are employed, a dispensary shall be provided and maintained Standby Ambulance at project site for any accident Provide with proper disposal system for solid waste and effluents. In case of a factory where no public sewerage system exists, prior approval of the arrangements should be made for the disposal of wastes and effluents 16 occupational diseases notifiable to the Chief Inspector of Factories:
1. lead poisoning 2. lead tetraethyl poisoning 3. phosphorous poisoning 4. mercury poisoning 5. manganese poisoning 6. arsenic poisoning 7. poisoning by nitrous fume 8. carbon di sulfide poisoning 9. benzene poisoning 10. chrome ulceration 11. anthrax 12. silicosis 13. poisoning by halogens 14. primary epitheliomatous cancer of the skin 15. toxic anemia 16. pathological manifestation due to radium or x-rays
If personal injury is caused to workmen by accident arising in the course of employment, employer shall be liable to act according to labor law 2006. 36 occupational diseases for compensation payable Monthly payment as compensation for temporary disablement are
1. Compensation should be paid for the period of disablement or for one year whichever period is shorter
2. Such compensation shall be paid at the rate of full monthly wages for the fxst two months
3. Two thirds of the monthly wages for the next two months and at the rate of the half of the monthly wages for the subsequent months
4. In case of chronic occupational diseases , half of the monthly wages during the period of disablement for a maximum period of two years
I ~ssues I Reauirements 1 shall be paid
5 . International/ national (which ever is beneficial for the oflhcers and workers working under contractor) level insurance coverage shall be arranged for all workers during construction ~ h a s e bv the contractor
9.5.3 Health Hazards
The construction phase includes site preparation, plant construction and access road construction
etc. The health hazards associated with these activities are mainly due to dust and noise pollution.
Excessive noise can cause loss of hearing and psychological changes. Dust pollutioni can cause
eye and respiratory irritation and in some cases allergic reactions. The inhalation of exhaust gases
from construction vehicles and machinery can also cause harmful effect to the health. Stress can
also be caused by working in shifts, high work load, poor living condition of workers etc.
A quantification of the measures of severity in health hazards is not well defined. They are slow
acting and cumulative, their effects may not be visible for years. During plant insta.llation and
commissioning exposure to the chemicals (paints, solvents, thinners etc.), batteries, welding
materials, lubricants etc., may cause hazardous effect to the workers, which ultimately could
cause anemia, liver and kidney damage, cardiovascular diseases and neurological disorder.
9.5.4 Remedial measures
To minimize the hazards arising from the activities at different phases of plant constiruction and
operation, the following measures will be taken:
the employer (contractor during construction phase and in turnkey period) will inform his
employees to submit full scale medical report (if possible) to the authority prior to join in
to the company and medical board of the company will take decision on this report.
works with volatile toxic chemicals will be undertaken in a well ventilated place and as
per the corporate OHS guideline.
laborers handling, toxic chemicals will be provided with protective gear a.nd will be
relieved frequently from their posting.
workers exposed to an excessive noise should be provided with protective gear and be
relieved frequently from their post
workers exposed to dust will be provided appropriate musk and other protective gear.
frequent spraying of water will be undertaken to minimize dust pollution and dispersion.
persons undertaking construction and installation works shall have access to amenities for
their welfare and personal hygiene needs such as sanitary toilets, potable drinking water,
washing facilities, shelter sheds etc.
proper disposal of waste and sullage will be in practice.
health education and information on hygiene will be provided to the workers
regular checks on drinking water quality (if the water supplied by the contractors1
company) will be ensured within work site.
9.5.5 Safety
Strict rules and procedures for the execution of specific tasks, enforcement of the rules, and
discipline amongst workers, maintenance of machineries used by providing all necessary gear or
equipment will be provided for the safety of the workers.
The following guidelines will be followed to maintain the safety of the workers in addition to the
contractors OHS policies:
workers have to be informed about the possible damage or hazards related to their
respective jobs1 occupation
proper warning sign shall be posted at different points during construction and operation
of the power plant
pedestrian movement and the traffic will be safely managed during construction phase
for lowering the associated health and safety risks
sufficient lighting will be ensured, where a person performs construction work or may be
required to pass through, including access ways and emergency exit or passage without
any risk to health and safety
construction site needs to provide safe access to and egress from all places where they
may be required to work or pass through. This includes the provision of emergency
access and egress route that must be free from obstructions. This will be provided along
with the consultation of security of the premises.
adequate perimeter fencing will be installed on the site before construction work
commences and that will be maintained during the construction work and signs will be
placed which is clearly visible from outside the site including emergency telephone
numbers.
electrical installations materials, equipment and apparatus are designed, installed, used,
maintained and tested to eliminate the risk of electrical shock, burns, fire or explosion in
general.
construction site will be kept orderly and tidy. Access ways will be kept clear of materials
and debris. Access ways shall be maintained as non-slippery condition. All materials will
be stored in an orderly manner so that it does not pose any risk to the health or safety of
any person
arrangements of first aid facility will be me made accessible during construction and
operation work.
9.5.6 Work in Confined Spaces
In the operational phase, noise pollution may pose risk to health. Baseline study measured the
noise level near the generators and turbines ranged from 90 dBA to 110 dBA, which may cause
hearing impairment of the workers if exposed 2-4 hourslday.
Supervisors, inspectors and related personnel who work in this area will be provided ear plugs or
ear muffs.
Areas where people may be exposed to excessive noise will be sign posted as "Hearing; Protection
Areas" and their boundaries will be defined with red line. No person will be allowed to enter this
area unless wearing personal hearing protectors.
The confined work spaces will be provided sufficient air to avoid any health risk.
Adequate care will be taken to minimize stress and ergonomic design will be improved in course
of time to minimize health hazards.
First aid facilities will be kept in place and evacuation plans for emergency situations will be
facilitated with adequate drills, instructions and signs. Adequate fire fighting arrangements will
be installed and maintained in workable condition on a regular basis. In case of emergency,
firefighters from district level will be called on.
9.5.7 Training Training is an integral part of a preventive strategy. The training will be provided .to manager
environment, supervisors and technicians and related staff who are responsible for environmental
monitoring activities.
The following issues will be addressed in training of the managers, staff and workers:
Workers will be trained to understand the environmental monitoring issues and
parameters,
Concern officers and staff will be trained how to monitor and operation of the
environmental monitoring equipments
Arrange workplace consultation on noise control
Workers will participate in training and contribute to the noise management strategy
Persons likely to be exposed to risks will be provided with information and instruction in
safety procedures associated with the plant at the work place.
Relevant health and safety information will be provided to persons involved in
installation and commissioning, use and testing of the plant.
Information on emergency procedures relating to the plant will be displayed in a manner
that can be readily observed by persons who may be affected by the operation of the
plant.
Training will be provided to use fire fighting equipment as and when is necessary.
Facility staff will be trained in the safety procedures those are to be implemented during
unloading, transfer and storage of hazardous materials.
9.5.8 Record Keeping and Reporting
Reporting will be regularly communicated to the higher authority as a routine work. Records of
construction, installation, training, equipment maintenance, operation, fault detection and remedy
will be maintained. Records will be maintained for the propose plant in following the corporate
guidelines of the contractors and the owners.
9.5.9 Plant Construction
A person with control of a construction project or control of construction work will retain records
for a reasonable period after the completion of the construction project of the occupational health
and safety induction training and any other training given to persons directly engaged or trained
by them to undertake construction work on the project.
9.5.10 Plant Operation
During operation of the plant, arrangements will be made to keep records on any relevant tests,
maintenance, inspection, commissioning and alteration of the plant, and make those records
available to any employee or relevant health and safety representative.
9.5.11 Noise
Audiometric test records of employees should be kept during the employee's period of
employment and longer as necessary, as they may provide a useful reference for workers'
compensation. The records will be kept in a safe, secure place and held as confidential
documents.
9.5.12 Hazardous Substances
Assessment reports which indicate a need for monitoring and/or health surveillance together with
the results of monitoring and/or health surveillance shall be kept as records in a suitable form for
at least 30 years from the date of the last entry made. Retention for a period of at least 30 years is
necessary because some health effects, such as cancers, may take a long time to become evident.
The information kept will be valuable in epidemiological studies and for developing effective
control strategies.
All other records, including assessment reports not indicating a need for monitoring andlor health
surveillance and records of induction and training, shall be maintained for at least twelve years
one month in a suitable form.
10. Storage Facilities for Chemicals, Fuel, Oil and Grease
10.1 Oil Storage Facilities
In the main EIA report storage facilities has not been clearly addressed has not been adldressed
under this circumstance a briefly described oil and fuel storage facility for constructiorl and
operation is elucidated in this chapter. During construction and operation in site; fuel, lubricants
and other chemicals will be required for heavy equipment, vehicles etc. small portion of which
will be stored on site. The schematic diagram of chemical storage facility may be used by the
EPC contractor and O&M contractor.
Conceptual storage facilities are shown in Figure 2 &3. The bermed or bunded area would be big
enough to hold 1.5 times the volume of the largest tank in the storage facility in the event of spill
or leak. The containment berm will have a mechanism to separate out rainwater and treatment of
oil contaminated water.
Figure 2. Bermed containment facility
The EPC will design a catchments system to minimize spill damage. There is always a risk of fuel
leakage either as the result of an accident, failure to close valves or failure of equipment or
materials. Leaks caused by corrosion in oil storage tanks will be prevented to the maximum
extent possible with coatings and cathodic protection (both interior and exterior). The :EPC
contractor will employ early leak detection monitoring system where personnel will be aware and
trained on oil spill prevention, mitigation and management of the situation such as how to stop
further loss, isolate the source, contain the spread of contamination, clean up spills, and file an
incident report.
Further at each stage of the construction and operation, the EPC and O&M contractor will
maintain an inventory along with Material Safety Data Sheet (MSDS) of hydrocarbon and
chemical sources up-to-date and include fuel tankers, fixed fuel dumps and their locations. The
EPC and O&M will maintain this practice and well developed contingency plan throughout their
construction and operation up to final commissioning and handing over the power plant to the
owner. Contingency plans will be based on the location and volume of potential spills.
Figure.3 Conceptual drawing for the separation of spillage
SUP Oillwater Separator
10.2 Oil Leaks and Drainage Systems
The main fuel is natural gas so there would not be any big types of oil spillage. To maintain a
good industrial practice the EPC and O&M contractor will develop a leak minimization strategy
as an integral part of facility design and maintenance procedures. Oil sumps will be provided for
all drains to prevent contamination of rainwater drainage. Drip pans will be used where needed.
>
The EPC contractor will construct separate storm water drainage systems for rainwater so that oil
and chemical will not contaminate the natural stream. Suitable absorbent material will be
available onsite for immediate prevention.
Oil contaminated water to treatment
facility
> Oil rich water to oil recovery or safe disposal
> Clean water to
discharge
11. House Keeping
The EPC and O&M contractor will maintain housekeeping practice to ensure safe working environment for the workers where waste generation and environmental damage will be minimized. The house keeping will include the following:
o Chemical usage o Erosion minimization o Emission reduction o Segregated waste handling o Periodic chain of custody inspection
12. Emergency Fire Fighting
For emergency situation or fire fighting the Siddhirganj Power Plant (210 MW Combined Cycle)
has its own fire fighting equipment intact under Assistant Director Security (table 9.10:), in
addition to the internal firefighting facility the Siddhirganj premises has the provision of taking
help from the Civil Defense Office of the Narayangonj district. The emergency numbers are
printed in front of the Chief Engineers office at Siddhirganj Power Plant site.
Table 9.10 The list of the firefighting facilities are summarized in the following table
S1 no.
Clzemicals and Sand
Fire Hydrant point ~
Name of the firefighting equipment and facilities
1 I Dry Chemical Powder
3 4 5 6 7 8 9 10
1 11 I Main Building Stair case area of 06 0 5 1 0 1 ~
Capacity Quantity
50 Kg 12
Dry Chemical Powder Dry Chemical Powder Carbondioxide (C02) Carbondioxide (COz) Carbondioxide (C02) Foam type Water Bucket Sand Bucket
1 2 10 MW power plant office I/
2 1 Drv Chemical Powder 8 3 9 5 45
40 Liters 12 0510 112008 5 24 3 2 8 8 22 0510 112008
8 8
1 2 10 MW power plant office
15 11
12 1 Main Building 0-meter area of 10
SI no.
I I I I
Name of the firefighting equipment and facilities
13 1 Main Building Boiler House area
14
15 16 17 18 19 20
L I I I I I
Source: Assistant Director, Security 2 10MW thermal power station, Siddhirganj, Narayangonj.
Capacity
04 of 210 MW Power plant office Main Building 12 & 18 meters area of 2 10 MW Power plant office Water treatment ~ l a n t
In addition to the above mentioned fire extinguisher the complex has its own fire hydrant at different location as per the requirement of the Power plant. After completion of other ongoing and proposed power plant, additional required fire extinguishers will be installed by the EPC contractor in due course.
0510 112008
Hydrogen Plant WorkshopBuilding Oil Refinery Plant PM Warehouse Project area (outside building)
I I
Sub total
The AD security will regularly take part for firefighting drill to make the system effective; the whole drill process will be supervised advised by the Manager Environment of EGCB corporate office.
Quantity
15
06
93 65 21
Date: February 27, 2008
Last date of test
0510 112008
0510 112008 02 07 05 15 23
0510 112008 Fire hose pipe (30 meters each)
0510 112008 0510 112008 05/01/2008 05/01/2008 05/01/2008