Page 2: CHIEF SECRETARY – ESC MEETING 14-12-2008 Update Shelter Response

Developments committments

Hilfswerke Austria committed 100 TS, start in January

Alfullah Bank planning to fund 100 TS, reviewing technical designs, contacting agencies

Al Ameen trust added 100 TS to the committed 130 TS.

Don Basco Church confirmed construction of 35 TSQatar Charity confirmed construction of 100 TS

instead of 50 TSIslamic Relief found funding for additional 128 TSCalculation mistake: Jamaad Ud Dawa 650 double

in sheet + 300 shelter material + NFI’s luted. 1.000 pipeline unsure.

Balance: + 500 – 950 = -/- 450 TS

Page 3: CHIEF SECRETARY – ESC MEETING 14-12-2008 Update Shelter Response

Progress - developments

Eid holiday: difficult to mobilize community, drivers and carpenters. Also the days after Eid

Strikes in Kach and Amadoon, blocked the road for traffic for 3 days, delays distribution.

Teachers are on the ground and instructed for Community Mobilization

Food Package (32 kg) incentives when shelter finished. Food is in the field, distribution / timing to be arranged

ESC permanent field coordinator in Ziarat Aftershock of 5.7 (Richter scale) on Tuesday 10.30 am

possible additional damage, impact on the community. First snow fell in the area. PRCS / IFRC prepares for distribution, material for 1.000

kits arrived in the field, start 15-12 till 31-12. Turkish RC erected 90% of shelters, water supply pending.

Page 4: CHIEF SECRETARY – ESC MEETING 14-12-2008 Update Shelter Response

Community Participation

Community participation important for dealing with psychological aspects of the disaster and building resilience for the future

Not all beneficiaries are erecting the shelters since they are migrating or choosing different solutions

Limited capacity for monitoring / motivating the communities to erect shelter when distributions are ongoing.

Participation of the local government leaders is crucial

Page 5: CHIEF SECRETARY – ESC MEETING 14-12-2008 Update Shelter Response

Progress (sheet corrected as mentioned in meeting)

7-12-2008 14-12-2008 % of committed

Total Committed shelters

9.934 9.522

Distributed shelters

2.808 3.141 26%

Erected shelter 1.055 1.752 18%

Number of shelters erected in last week: 697

Page 6: CHIEF SECRETARY – ESC MEETING 14-12-2008 Update Shelter Response

Erection planning per Agency

Sr.No Agency Done before14th to 20th

dec21st to 27th

dec28th dec to 3rd

jan 4th to 10th jan Total1 APNA 54 0 0 0 0 542 PRCS / IFRC 0 700 1400 1400 500 40003 PRCS / ICRC 241 260 560 610 399 20704 ARC 56 60 70 90 24 3005 CRS 83 75 115 100 27 400

6 UN-HABITAT 234 106 210 260 140 9507 TRCS 110 10 0 0 0 120

8 Islamic Relief 22 55 70 4 0 151

9 Al Ameeen 140 70 20 0 0 230

10 Muslim Aid 55 60 70 15 0 200

11 Muslim Hands 200 0 0 0 0 200

12Jamaat ud

Dawa 500 170* 70* 0 0 50013 Others 57 90 100 100 0 347

Total 1752 1486 2615 2579 1090 9522Cumulative % of total

committed 18% 34% 61% 89% 100%% of essential need covered

(7600) 23% 42% 77% 110%

Page 7: CHIEF SECRETARY – ESC MEETING 14-12-2008 Update Shelter Response

Concerns

If we want to move faster, the government is invited to mobilize additional resources