chiller installation method statement.pdf

5
9/7/2014 Chiller installation method statement http://www.methodstatementhq.com/chiller-installation-method-statement.html 1/5 Home Disclaimer Project HSE Plan Construction Method Statements Method Statement Template Inspection Checklists Request A Method Statement Project Execution Plan Customer Support Download Method Statements Pioneer Air Systems, Inc. pioneerair.com Air, Water & Gas Processing Non Standard Equip is Our Specialty Method Statement Free Download RSS You are here: Home » Method Statements » Construction Method Statements » HVAC Method Statements » Method Statements » Chiller installation method statement Chiller installation method statement Tweet Tweet Below is a standard operating procedure which can be used a a method statement for installation of chillers on its foundation after it is delivered on the sites. Before starting the activity of chiller installation following tools/equipment shall be arranged: Tool Box. Lifting Equipment (Cranes) Basic Electrical Tools Measuring Tape. Hack Saw Blade Spirit Level Electric Drill Machine Ladders Threading Machine Welding/ Brazing Machine (if required) Torque Wrench Pipe Cutting Machine Grinding Machine Pressure Gauge Hammer Water Level Marker Mobile Scaffolds Staging Platforms March 17, 2014 | webmaster Valme concrete pipes valme.it Design, production and direct sale of high quality concrete pipes SPECIAL RECENT POSTS Installation of Marble and Granite Tiles on floor, stairs, walls and counters April 4th, 2014 This m ethod statem ent covers the detailed procedure to be followed for Supply & Installation of [...] Method Of Statement For Installation of wires and cables - Wiring March 29th, 2014 Below is the list of equipm ent / Tools required for installation of wires and cables, which cab be u[...] Method Statement For Installation & Testing of SMATV System March 21st, 2014 Below are the steps or m ethod statem ent for installation & testing of SMATV System in a project.[...] Sanitary Ware Installation Method Statement March 20th, 2014 Installation of sanitary ware can be done step wise as per m entioned procedure or m ethod statem ent b[...] Plastering Works Method Statement March 20th, 2014 Below are the equipm ent involved in Plaster works that should be arranged before starting the plaste[...] Method Statement for Internal Painting Works March 20th, 2014 Below is the procedure for doing the painting works for internal painting. This safe work m ethod sta[...] How To Do Installation of Suspended False Ceilings March 14th, 2014 Equipm ent Required For Installation of Suspended Ceilings Leveling Instrum ents Line dory C[...] Transformer testing & commissioning method statement

Upload: frej10

Post on 07-Nov-2015

1.527 views

Category:

Documents


243 download

TRANSCRIPT

  • 9/7/2014 Chiller installation method statement

    http://www.methodstatementhq.com/chiller-installation-method-statement.html 1/5

    H o m e Disclaimer Project HSE Plan Construction Method Statements

    Method Statement Template Inspection Checklists Request A Method Statement

    Project Execution Plan Customer Support Download Method Statements

    Pioneer Air Systems, Inc.pioneerair.com

    Air, Water & Gas Processing Non Standard Equip is Our Specialty

    Method Statement Free Download

    RSS

    You are here: Home Method Statements Const ruct ion Method Statements HVAC Method Statements

    Method Statements Chiller installat ion method statement

    Chiller installation method statement

    Tweet

    Tweet

    Below is a standard operating procedure which can

    be used a a method statement for installation of

    chillers on its foundation after it is delivered on the

    sites. Before starting the activity of chiller installation

    following tools/equipment shall be arranged:

    Tool Box.

    Lifting Equipment (Cranes)

    Basic Electrical Tools

    Measuring Tape.

    Hack Saw Blade

    Spirit Level

    Electric Drill Machine

    Ladders

    Threading Machine

    Welding/ Brazing Machine (if required)

    Torque Wrench

    Pipe Cutting Machine

    Grinding Machine

    Pressure Gauge

    Hammer

    Water Level Marker

    Mobile Scaffolds

    Staging Platforms

    March 17, 2014 | webmaster

    Valme concretepipes

    valme.it

    Design, production and direct sale

    of high quality concrete pipes

    SPECIAL RECENT POSTS

    Installation of Marble and Granite

    Tiles on floor, stairs, walls and

    counters

    April 4th, 2014

    This m ethod statem ent covers the

    detailed procedure to be followed for

    Supply & Installation of [...]

    Method Of Statement For Installation

    of wires and cables - Wiring

    March 29th, 2014

    Below is the list of equipm ent / Tools

    required for installation of wires and cables,

    which cab be u[...]

    Method Statement For Installation &

    Testing of SMATV System

    March 21st, 2014

    Below are the steps or m ethod statem ent

    for installation & testing of SMATV System in

    a project.[...]

    Sanitary Ware Installation Method

    Statement

    March 20th, 2014

    Installation of sanitary ware can be done

    step wise as per m entioned procedure or

    m ethod statem ent b[...]

    Plastering Works Method Statement

    March 20th, 2014

    Below are the equipm ent involved in

    Plaster works that should be arranged

    before starting the plaste[...]

    Method Statement for Internal Painting

    Works

    March 20th, 2014

    Below is the procedure for doing the

    painting works for internal painting. This safe

    work m ethod sta[...]

    How To Do Installation of Suspended

    False Ceilings

    March 14th, 2014

    Equipm ent Required For Installation of

    Suspended Ceilings Leveling Instrum ents

    Line dory C[...]

    Transformer testing & commissioning

    method statement

  • 9/7/2014 Chiller installation method statement

    http://www.methodstatementhq.com/chiller-installation-method-statement.html 2/5

    General Requirements

    All the materials received at site shall be as per the approved technical material submittal for

    Chillers to be inspected upon receipt & approved by the engineer prior in proceeding with the

    installation. Any discrepancies, damages etc., should be reported to the supplier for rectification

    or replacement& to be removed from site immediately.

    All construction preliminary inspection/testing works shall be carried out in accordance with the

    specifications & to be done by qualified Mechanical Engineers and shall be checked and

    approved by MEP Subcontractor Construction Manager along with QA/QC Engineer.

    Material Transport/ Delivery

    Chillers are normally shipped & dispatched from factory as a hermetically assembled package,

    factory piped, wired and tested. All openings except for the water box vent & drain holes are

    covered or plugged to prevent contamination during shipment & handling.

    Special care must be taken to ensure that units are offloaded from containers. Rough handling

    can result in damage to the unit.

    Use appropriate type of vehicles in transporting the units and that they are protected against

    mechanical & weather damage.

    As soon as the units arrived at site, raise immediate inspection to the consultant & inspect

    thoroughly for damage. Hence, in case of transit damage, supplier/ manufacturer must be

    informed immediately.

    Ensure that the units have been inspected & accepted by the consultant as per the approved

    material submittal prior to offloading & site storage.

    Storage on Site Store

    Ensure that the storage location of the units has solid foundation, vibration free, dry, &

    temperature range shall be -40F to 158F.

    It is much recommended not to remove the plastic coverings or packaging materials during the

    delivery to avoid any corrosion & deterioration.

    Avoid any mechanical shocks and strokes during handling operations.

    All packages for the equipment reaching the site shall be identified as per package list.

    Sequence of Installation for Chillers

    The entire assembly of the Water Cooled Centrifugal Chillers will be rigged from store to place of

    installation i.e. roof etc. Refer to Manufacturers Instruction Manual for rigging instructions for the

    Chiller.

    All site safety rules & regulations shall be complied.

    Supervisors will deliver tool box talks, relevant to these activities to all operatives involved in the

    installation and shall be recorded.

    All operatives will be equipped with minimum personnel protective equipment; hard hat,

    coveralls, safety boots, safety glasses.

    The persons using cleaning fluid, solvent cement& any other forms of chemicals have to wear

    hand gloves.

    Ensure only qualified personnel shall install, test & commissioned the equipment.

    During installation, display warning sign boards to be provided and barricade the area

    whenever necessary. Close monitoring by the site engineers during installation is much highly

    recommended.

    Only competent, experienced & trained personnel shall perform all the required activities stated

    in this method statement.

    Ensure that all operatives fully understand the method of these activities.

    March 14th, 2014

    Below is a standard m ethod statem ent

    which can be used as learning purpose and

    to prepare further pr[...]

    METHOD STATEMENT FOR

    INSTALLATION, TESTING AND

    COMMISSIONING OF UPS

    March 14th, 2014

    1.0. PURPOSE: The purpose of this m ethod

    statem ent defines the procedure to be

    followed for Insta[...]

    METHOD STATEMENT FOR R.C.C.

    COLUMNS AND SHEAR WALLS

    CONSTRUCTION

    March 12th, 2014

    Below is a general m ethod statem ent for

    illustrative purpose, there shall be different

    values for di[...]

    CATEGORIES

    BMS

    Cem ent & Clinker Testing

    Civil Engineering

    Civil Method Statem ents

    Concrete Testing

    Construction Method Statem ents

    Drainage Pipes Installation

    Duct Works

    Electrical

    Electrical Method Statem ents

    Fire Suppression System

    Health & Safety

    HVAC Checklists

    HVAC Maintenance

    HVAC Method Statem ents

    ISO 9001

    Method Statem ent Tem plate

    Method Statem ents

    Piping Method Statem ents

    Piping Works

    Plum bing Method Statem ents

    Pressure Testing

    Project HSE Plan

    Pum p Installation

    Quality Assurance

    Quality Managem ent

    Risk

    Risk Assessm ent

    Risk Managem ent

    Sam ple Form s & Form ats

    Tem plates

    Testing & Com m issioning

    Water Supply Piping

    Welding Risk

    What Is Hazard?

    What Is Risk?

  • 9/7/2014 Chiller installation method statement

    http://www.methodstatementhq.com/chiller-installation-method-statement.html 3/5

    Preliminary Checks Before Chiller Installation

    Before commencement of Installation activity, the supervisor/ engineer must ensure that:

    All Installations & Pressure Testing of Pipe/ Duct works have been completed & approved by the

    consultant.

    Determine whether the units occur damages during the storage & shifting of location.

    Permission to start or Civil Clearances prior to installation has been given by the main

    contractor.

    All relevant Approved Shop drawings for the installation of the equipment shall be available &

    approved by the consultant.

    Installation activities shall only commence when all associated works by the Civil has been

    completed.

    Safe access shall be provided by the Main Contractor thru Work Permit in coordination with the

    Safety in charge at site.

    General Installation Procedures for Chillers

    Prior to moving the chillers at site, ensure that the foundation requirements have been done.

    Foundation details & requirements for the chillers shall be as per approved shop drawings or as

    recommended by the manufacturer as follows:

    1. Rigid non-warping mounting pads or a concrete foundation is available prior to shifting chillers

    at site.

    2. Ensure that the foundation will be able to support the chiller at its full operating weight.

    3. For proper unit operation, the chiller must be level within 1.6mm over its length & width when set

    into place on the mounting surface.

    After ensuring that the foundations for the chillers are satisfactory, shift the chillers by means of

    cranes to its exact location.

    Ensure that the lifting cables are capable of supporting the entire weight of the chiller. Failure to

    properly lift the unit could result to serious injuries & damage of the unit.

    System evacuation, dehydration and charging with refrigerant shall be carried out by skilled &

    experienced personnel only.

    Ensure isolator pads or spring isolators are available in the chiller feet/ legs prior to lowering the

    unit to its foundation.

    Ensure that all piping connected to the chiller must be properly isolated & supported so that it

    does not place any stress on the unit.

    It is much recommended to avoid piping from 3 feet minimum to the equipment to allow

    proper fit-up upon arrival of the unit at job site.

    Pipe the evaporator into the chilled water circuit.

    Pipe the condenser into the cooling tower water circuit.

    Locate pressure gauge taps in a straight length of pipe. Place tap a minimum of one pipe

    diameter downstream of any elbow, orifice, etc.

    Install air vents & drain valves on the water boxes. Each water box is provided with 3/4 NPTF

    (National Pipe Thread Female) vent & drain connection. Plastic plugs are factory installed in

    both openings. Remove & discard the same before installing the water box vents & drain valves.

    Install pressure relief valves in the condenser & evaporator water circuits to avoid water box

    damage due to hydro-static expansion.

    Whenever are applicable, install pressure relief valves at the drain connections on the

    evaporator and condenser water boxes.

    Install a strainer in the entering side of each piping circuit to avoid possible tube plugging in the

    Working At Height

    TAGS

    & Access Control System Accessories AC Duct ing

    Method Statement ac duct installat ion ACMaintenance Acoust ic Lining blank performablank proforma bms system BMS TestingProcedure Building Management SystemBuilding Management System BMS control

    measures Electrical Method Statement forhazard hvac HVAC Method Statements

    installat ion Installation of GI Conduits &

    Accessories method Method

    Of Statement Method

    Statement met hodst at ement for Inst allat ion Met hodSt at ement Templat e MST MST For BMS

    of pipe flushing pressure pumps risk RiskAssessment safe work method samplecheck list sample checksheet Sample

    Format Electrical statement swmstemplate test Testing & CommissioningTesting & Commissioning MethodStatement water

    DOWNLOAD METHOD STATEMENTS

    Download BMS Installation Method Statem ent

    Download Chilled Water Pipes Installation &

    Testing Method Statem ent

    Download Method Statem ent For INSTALLATION

    HYDRO TESTING & FLUSHING OF FIRE FIGHTING

    PIPING SYSTEM INCLUDING SPRINKLERS

    Download Method Statem ent For CENTRAL

    BATTERY SYSTEM INSTALLATION

    Download Method Statem ent For Fire Alarm

    System

    Download Method Statem ent For Flushing Of

    Chilled Water Piping

    Download Method Statem ent For Installation Of

    Packaged Units

    Download Method Statem ent For Installation Of

    Split Units & Risk Assessm ent

    Download Method Statem ent For Installation Of

    Transform ers

    Download Project HSE Plan With All Form s

    Hom e

    Privacy Policy

    Disclaim er

    Hom e

  • 9/7/2014 Chiller installation method statement

    http://www.methodstatementhq.com/chiller-installation-method-statement.html 4/5

    chiller with debris.

    Install flow sensing device. Use either flow switches or differential pressure switches in conjunction

    with the pump interlocks to verify evaporator and condenser water flows.

    Install by pass valve system to avoid circulating water through the auxiliary shell when the unit is

    shut down.

    Pipe the evaporator & condenser as per the approved shop drawings. Ensure that the correct

    pipe sizes are to be connected to the evaporator & condenser circuit.

    Ensure that the evaporator water piping is clear; check if the chilled water pump is operated

    but before initial chiller start-up. If any partial blockages exists removed the same to prevent for

    possible tube damage resulting from evaporator freeze-up or erosion.

    For condenser & large evaporator connections, arrange the water piping so that the water

    supply enters the shell at the lower connection, and exists from the top connection.

    Units shall use grooved- pipe connections and flanged connections for 300 psi water boxes, use

    welded flanges.

    Piping joined using grooved type couplings, like all types of piping systems; require proper

    support system to carry out the weight of the pipes & equipment.

    Ensure that system refrigerant differential pressure must be maintained above 21 kpa at all times.

    Failure to do so could result in operating problems.

    Ensure that the discharge piping that allows pressure relief devices to safely vent refrigerant to

    the atmosphere if over pressure occurs.

    Make sure that the minimum pipe size for the vent must be equals the size of the discharge

    connections on the pressure relief device.

    When connecting the vent line to the chiller do not apply threading torque to the outside pipe.

    If the unit is not factory insulated, install insulation around the evaporator bulb wells and ensure

    that the bulb wells and connections for the water box drains and vents are still accessible after

    insulation is applied. Ensure that the sensor modules and interconnecting four wire cables must

    be raised up above the field installed insulation. Do not insulate over the wiring or sensor

    device. Insulation shall be as per approved material submittal.

    Install the controller hardware/ equipment which are used to interface with the internal chiller

    data & functions provide by the controls. Note that there are four connections on the controller

    that support the communication interface.

    Install the control panel & ensure low voltage & high voltage areas are in proper route & field

    wiring.

    Install the display. The display is boxed and shrink-wrapped behind the control panel during the

    shipment. Follow the procedure for installation of display as follows

    Unwrap control panel & display arm.

    Plug the power cable and the Ethernet cable into the bottom of the display.

    Adjust the display support arm so the base plate that attaches to the display is horizontal.

    Position the display with the LCD screen facing up, on top of the display support arm base plate.

    Align the four holes in the display support arm base plate.

    Attach the display to the display support arm base plate.

    Ensure all Electrical requirements have been wired & connected as follows:

    Power supply wiring to the starter

    Starter to motor wiring

    Starter to control panel wiring

    System Control Circuit wiring

    Water pump interlock circuits & flow switches & other devices.

    Temperature Sensor circuits

    Other unit control options present

    Any field supplied control devices

    Ensure that all wires & cables are of the correct sizes as voltage/ampere requirements of the

    units.

    After installation of the chillers, raise inspection to the consultant for acceptance prior to

    Privacy Policy

    Disclaim er

  • 9/7/2014 Chiller installation method statement

    http://www.methodstatementhq.com/chiller-installation-method-statement.html 5/5

    How To Do Installation of Suspended False Ceilings Method Statem ent for Internal Painting Works

    proceeding with testing & commissioning.

    LIKE US ON FACEBOOK

    30 personnes aiment a. Soyez le

    premier de vos amis.Jaime Partager

    Filed under HVAC Method Statements, Method Statements | Tags: Chiller, Chiller installat ion method statement,

    HVAC Method Statements

    Portable AirConditioner

    alibaba.com

    Find Quality Products from Verified

    Suppliers. Get a Live Quote Now!

    Comments are closed.

    Copyright 2014 Method Statement Free Download | zBorder Theme powered by WordPress