chiller installation method statement.pdf
TRANSCRIPT
-
9/7/2014 Chiller installation method statement
http://www.methodstatementhq.com/chiller-installation-method-statement.html 1/5
H o m e Disclaimer Project HSE Plan Construction Method Statements
Method Statement Template Inspection Checklists Request A Method Statement
Project Execution Plan Customer Support Download Method Statements
Pioneer Air Systems, Inc.pioneerair.com
Air, Water & Gas Processing Non Standard Equip is Our Specialty
Method Statement Free Download
RSS
You are here: Home Method Statements Const ruct ion Method Statements HVAC Method Statements
Method Statements Chiller installat ion method statement
Chiller installation method statement
Tweet
Tweet
Below is a standard operating procedure which can
be used a a method statement for installation of
chillers on its foundation after it is delivered on the
sites. Before starting the activity of chiller installation
following tools/equipment shall be arranged:
Tool Box.
Lifting Equipment (Cranes)
Basic Electrical Tools
Measuring Tape.
Hack Saw Blade
Spirit Level
Electric Drill Machine
Ladders
Threading Machine
Welding/ Brazing Machine (if required)
Torque Wrench
Pipe Cutting Machine
Grinding Machine
Pressure Gauge
Hammer
Water Level Marker
Mobile Scaffolds
Staging Platforms
March 17, 2014 | webmaster
Valme concretepipes
valme.it
Design, production and direct sale
of high quality concrete pipes
SPECIAL RECENT POSTS
Installation of Marble and Granite
Tiles on floor, stairs, walls and
counters
April 4th, 2014
This m ethod statem ent covers the
detailed procedure to be followed for
Supply & Installation of [...]
Method Of Statement For Installation
of wires and cables - Wiring
March 29th, 2014
Below is the list of equipm ent / Tools
required for installation of wires and cables,
which cab be u[...]
Method Statement For Installation &
Testing of SMATV System
March 21st, 2014
Below are the steps or m ethod statem ent
for installation & testing of SMATV System in
a project.[...]
Sanitary Ware Installation Method
Statement
March 20th, 2014
Installation of sanitary ware can be done
step wise as per m entioned procedure or
m ethod statem ent b[...]
Plastering Works Method Statement
March 20th, 2014
Below are the equipm ent involved in
Plaster works that should be arranged
before starting the plaste[...]
Method Statement for Internal Painting
Works
March 20th, 2014
Below is the procedure for doing the
painting works for internal painting. This safe
work m ethod sta[...]
How To Do Installation of Suspended
False Ceilings
March 14th, 2014
Equipm ent Required For Installation of
Suspended Ceilings Leveling Instrum ents
Line dory C[...]
Transformer testing & commissioning
method statement
-
9/7/2014 Chiller installation method statement
http://www.methodstatementhq.com/chiller-installation-method-statement.html 2/5
General Requirements
All the materials received at site shall be as per the approved technical material submittal for
Chillers to be inspected upon receipt & approved by the engineer prior in proceeding with the
installation. Any discrepancies, damages etc., should be reported to the supplier for rectification
or replacement& to be removed from site immediately.
All construction preliminary inspection/testing works shall be carried out in accordance with the
specifications & to be done by qualified Mechanical Engineers and shall be checked and
approved by MEP Subcontractor Construction Manager along with QA/QC Engineer.
Material Transport/ Delivery
Chillers are normally shipped & dispatched from factory as a hermetically assembled package,
factory piped, wired and tested. All openings except for the water box vent & drain holes are
covered or plugged to prevent contamination during shipment & handling.
Special care must be taken to ensure that units are offloaded from containers. Rough handling
can result in damage to the unit.
Use appropriate type of vehicles in transporting the units and that they are protected against
mechanical & weather damage.
As soon as the units arrived at site, raise immediate inspection to the consultant & inspect
thoroughly for damage. Hence, in case of transit damage, supplier/ manufacturer must be
informed immediately.
Ensure that the units have been inspected & accepted by the consultant as per the approved
material submittal prior to offloading & site storage.
Storage on Site Store
Ensure that the storage location of the units has solid foundation, vibration free, dry, &
temperature range shall be -40F to 158F.
It is much recommended not to remove the plastic coverings or packaging materials during the
delivery to avoid any corrosion & deterioration.
Avoid any mechanical shocks and strokes during handling operations.
All packages for the equipment reaching the site shall be identified as per package list.
Sequence of Installation for Chillers
The entire assembly of the Water Cooled Centrifugal Chillers will be rigged from store to place of
installation i.e. roof etc. Refer to Manufacturers Instruction Manual for rigging instructions for the
Chiller.
All site safety rules & regulations shall be complied.
Supervisors will deliver tool box talks, relevant to these activities to all operatives involved in the
installation and shall be recorded.
All operatives will be equipped with minimum personnel protective equipment; hard hat,
coveralls, safety boots, safety glasses.
The persons using cleaning fluid, solvent cement& any other forms of chemicals have to wear
hand gloves.
Ensure only qualified personnel shall install, test & commissioned the equipment.
During installation, display warning sign boards to be provided and barricade the area
whenever necessary. Close monitoring by the site engineers during installation is much highly
recommended.
Only competent, experienced & trained personnel shall perform all the required activities stated
in this method statement.
Ensure that all operatives fully understand the method of these activities.
March 14th, 2014
Below is a standard m ethod statem ent
which can be used as learning purpose and
to prepare further pr[...]
METHOD STATEMENT FOR
INSTALLATION, TESTING AND
COMMISSIONING OF UPS
March 14th, 2014
1.0. PURPOSE: The purpose of this m ethod
statem ent defines the procedure to be
followed for Insta[...]
METHOD STATEMENT FOR R.C.C.
COLUMNS AND SHEAR WALLS
CONSTRUCTION
March 12th, 2014
Below is a general m ethod statem ent for
illustrative purpose, there shall be different
values for di[...]
CATEGORIES
BMS
Cem ent & Clinker Testing
Civil Engineering
Civil Method Statem ents
Concrete Testing
Construction Method Statem ents
Drainage Pipes Installation
Duct Works
Electrical
Electrical Method Statem ents
Fire Suppression System
Health & Safety
HVAC Checklists
HVAC Maintenance
HVAC Method Statem ents
ISO 9001
Method Statem ent Tem plate
Method Statem ents
Piping Method Statem ents
Piping Works
Plum bing Method Statem ents
Pressure Testing
Project HSE Plan
Pum p Installation
Quality Assurance
Quality Managem ent
Risk
Risk Assessm ent
Risk Managem ent
Sam ple Form s & Form ats
Tem plates
Testing & Com m issioning
Water Supply Piping
Welding Risk
What Is Hazard?
What Is Risk?
-
9/7/2014 Chiller installation method statement
http://www.methodstatementhq.com/chiller-installation-method-statement.html 3/5
Preliminary Checks Before Chiller Installation
Before commencement of Installation activity, the supervisor/ engineer must ensure that:
All Installations & Pressure Testing of Pipe/ Duct works have been completed & approved by the
consultant.
Determine whether the units occur damages during the storage & shifting of location.
Permission to start or Civil Clearances prior to installation has been given by the main
contractor.
All relevant Approved Shop drawings for the installation of the equipment shall be available &
approved by the consultant.
Installation activities shall only commence when all associated works by the Civil has been
completed.
Safe access shall be provided by the Main Contractor thru Work Permit in coordination with the
Safety in charge at site.
General Installation Procedures for Chillers
Prior to moving the chillers at site, ensure that the foundation requirements have been done.
Foundation details & requirements for the chillers shall be as per approved shop drawings or as
recommended by the manufacturer as follows:
1. Rigid non-warping mounting pads or a concrete foundation is available prior to shifting chillers
at site.
2. Ensure that the foundation will be able to support the chiller at its full operating weight.
3. For proper unit operation, the chiller must be level within 1.6mm over its length & width when set
into place on the mounting surface.
After ensuring that the foundations for the chillers are satisfactory, shift the chillers by means of
cranes to its exact location.
Ensure that the lifting cables are capable of supporting the entire weight of the chiller. Failure to
properly lift the unit could result to serious injuries & damage of the unit.
System evacuation, dehydration and charging with refrigerant shall be carried out by skilled &
experienced personnel only.
Ensure isolator pads or spring isolators are available in the chiller feet/ legs prior to lowering the
unit to its foundation.
Ensure that all piping connected to the chiller must be properly isolated & supported so that it
does not place any stress on the unit.
It is much recommended to avoid piping from 3 feet minimum to the equipment to allow
proper fit-up upon arrival of the unit at job site.
Pipe the evaporator into the chilled water circuit.
Pipe the condenser into the cooling tower water circuit.
Locate pressure gauge taps in a straight length of pipe. Place tap a minimum of one pipe
diameter downstream of any elbow, orifice, etc.
Install air vents & drain valves on the water boxes. Each water box is provided with 3/4 NPTF
(National Pipe Thread Female) vent & drain connection. Plastic plugs are factory installed in
both openings. Remove & discard the same before installing the water box vents & drain valves.
Install pressure relief valves in the condenser & evaporator water circuits to avoid water box
damage due to hydro-static expansion.
Whenever are applicable, install pressure relief valves at the drain connections on the
evaporator and condenser water boxes.
Install a strainer in the entering side of each piping circuit to avoid possible tube plugging in the
Working At Height
TAGS
& Access Control System Accessories AC Duct ing
Method Statement ac duct installat ion ACMaintenance Acoust ic Lining blank performablank proforma bms system BMS TestingProcedure Building Management SystemBuilding Management System BMS control
measures Electrical Method Statement forhazard hvac HVAC Method Statements
installat ion Installation of GI Conduits &
Accessories method Method
Of Statement Method
Statement met hodst at ement for Inst allat ion Met hodSt at ement Templat e MST MST For BMS
of pipe flushing pressure pumps risk RiskAssessment safe work method samplecheck list sample checksheet Sample
Format Electrical statement swmstemplate test Testing & CommissioningTesting & Commissioning MethodStatement water
DOWNLOAD METHOD STATEMENTS
Download BMS Installation Method Statem ent
Download Chilled Water Pipes Installation &
Testing Method Statem ent
Download Method Statem ent For INSTALLATION
HYDRO TESTING & FLUSHING OF FIRE FIGHTING
PIPING SYSTEM INCLUDING SPRINKLERS
Download Method Statem ent For CENTRAL
BATTERY SYSTEM INSTALLATION
Download Method Statem ent For Fire Alarm
System
Download Method Statem ent For Flushing Of
Chilled Water Piping
Download Method Statem ent For Installation Of
Packaged Units
Download Method Statem ent For Installation Of
Split Units & Risk Assessm ent
Download Method Statem ent For Installation Of
Transform ers
Download Project HSE Plan With All Form s
Hom e
Privacy Policy
Disclaim er
Hom e
-
9/7/2014 Chiller installation method statement
http://www.methodstatementhq.com/chiller-installation-method-statement.html 4/5
chiller with debris.
Install flow sensing device. Use either flow switches or differential pressure switches in conjunction
with the pump interlocks to verify evaporator and condenser water flows.
Install by pass valve system to avoid circulating water through the auxiliary shell when the unit is
shut down.
Pipe the evaporator & condenser as per the approved shop drawings. Ensure that the correct
pipe sizes are to be connected to the evaporator & condenser circuit.
Ensure that the evaporator water piping is clear; check if the chilled water pump is operated
but before initial chiller start-up. If any partial blockages exists removed the same to prevent for
possible tube damage resulting from evaporator freeze-up or erosion.
For condenser & large evaporator connections, arrange the water piping so that the water
supply enters the shell at the lower connection, and exists from the top connection.
Units shall use grooved- pipe connections and flanged connections for 300 psi water boxes, use
welded flanges.
Piping joined using grooved type couplings, like all types of piping systems; require proper
support system to carry out the weight of the pipes & equipment.
Ensure that system refrigerant differential pressure must be maintained above 21 kpa at all times.
Failure to do so could result in operating problems.
Ensure that the discharge piping that allows pressure relief devices to safely vent refrigerant to
the atmosphere if over pressure occurs.
Make sure that the minimum pipe size for the vent must be equals the size of the discharge
connections on the pressure relief device.
When connecting the vent line to the chiller do not apply threading torque to the outside pipe.
If the unit is not factory insulated, install insulation around the evaporator bulb wells and ensure
that the bulb wells and connections for the water box drains and vents are still accessible after
insulation is applied. Ensure that the sensor modules and interconnecting four wire cables must
be raised up above the field installed insulation. Do not insulate over the wiring or sensor
device. Insulation shall be as per approved material submittal.
Install the controller hardware/ equipment which are used to interface with the internal chiller
data & functions provide by the controls. Note that there are four connections on the controller
that support the communication interface.
Install the control panel & ensure low voltage & high voltage areas are in proper route & field
wiring.
Install the display. The display is boxed and shrink-wrapped behind the control panel during the
shipment. Follow the procedure for installation of display as follows
Unwrap control panel & display arm.
Plug the power cable and the Ethernet cable into the bottom of the display.
Adjust the display support arm so the base plate that attaches to the display is horizontal.
Position the display with the LCD screen facing up, on top of the display support arm base plate.
Align the four holes in the display support arm base plate.
Attach the display to the display support arm base plate.
Ensure all Electrical requirements have been wired & connected as follows:
Power supply wiring to the starter
Starter to motor wiring
Starter to control panel wiring
System Control Circuit wiring
Water pump interlock circuits & flow switches & other devices.
Temperature Sensor circuits
Other unit control options present
Any field supplied control devices
Ensure that all wires & cables are of the correct sizes as voltage/ampere requirements of the
units.
After installation of the chillers, raise inspection to the consultant for acceptance prior to
Privacy Policy
Disclaim er
-
9/7/2014 Chiller installation method statement
http://www.methodstatementhq.com/chiller-installation-method-statement.html 5/5
How To Do Installation of Suspended False Ceilings Method Statem ent for Internal Painting Works
proceeding with testing & commissioning.
LIKE US ON FACEBOOK
30 personnes aiment a. Soyez le
premier de vos amis.Jaime Partager
Filed under HVAC Method Statements, Method Statements | Tags: Chiller, Chiller installat ion method statement,
HVAC Method Statements
Portable AirConditioner
alibaba.com
Find Quality Products from Verified
Suppliers. Get a Live Quote Now!
Comments are closed.
Copyright 2014 Method Statement Free Download | zBorder Theme powered by WordPress