chittaranjan locomotive works (summer training report)

20
Training Report Submitted By: Deo Nath Jha Adm. No. 2010JE1084 Chittaranjan Locomotive Works

Upload: deo-nath-jha

Post on 16-Apr-2017

5.873 views

Category:

Technology


13 download

TRANSCRIPT

Page 1: Chittaranjan locomotive works (Summer Training Report)

Training Report Submitted By:Deo Nath Jha

Adm. No. 2010JE1084

Chittaranjan Locomotive Works

Page 2: Chittaranjan locomotive works (Summer Training Report)

Basic Information about CLW

Site located in Sept 1947,Construction

started in May 1948.

First loco completed on

January 2,1950.

Steam locomotive produced during 1950-1970.(Total

no.-2351)

Diesel locomotive produced during

1967-1993(Total no. - 842)

First CLW built WCM-5 1500v DC electric loco

LOKMANYA in 1961.

On 16 Nov 1963, first 25kv ac WAG-1

“BIDHAN” was flagged off.

On 30 Jan 1972, WCAM-1 AC/DC ,dual

“vallabh” was produced

First three phase loco was the 6000hp

WAG-9 1998 “NAVYUG”

From 1967, CLW started production of Traction motors.

CLW gets power supply from DVC through 33kv

line. Total demand is nearly about 11.5 MVA

On 29th April,1998 Flagging off of 2500th Electric loco SWARNA

ABHA takes place.

On 26th April, 2002, ISO-14001 certification is awarded to CLW by

IRQS. 

Page 3: Chittaranjan locomotive works (Summer Training Report)

Sections visited during training

Technical Training Center (TTC)

Central Power House (CPH)

Design and Development Centre

(D & D)

Page 4: Chittaranjan locomotive works (Summer Training Report)

Basic Information about Locomotive

Broad gauge (Length=1.76m,denoted by W)

Meter gauge(Length=1m, denoted by Y)

Narrow gauge(Length=2ft 6in,denoted by Z )

Narrow gauge(Length = 2ft,denoted by N)

Types of Tracks

Page 5: Chittaranjan locomotive works (Summer Training Report)

Basic Information about Locomotive

A-acC-dcD-dieselM-mixed (Both goods and passenger)AC-Both ac and dcS-ShuntingU-Multiple unit 3A-3100hp 4B-4200hp

Naming Symbols

For Ex.:- WAP-3A means Broad gauge ac passenger locomotive, 3 denotes that this is chronologically third electric locomotive model running at 3100 hp.

Page 6: Chittaranjan locomotive works (Summer Training Report)

Development of a 3-phase Loco

D - Distance between axles of bogie A - Distance between bogies centre to centre L - Length over buffer

S – GaugeH - Maximum Height with Pantograph locked downB - Overall Width

Page 7: Chittaranjan locomotive works (Summer Training Report)

Development of a 3-phase Loco

Page 8: Chittaranjan locomotive works (Summer Training Report)

Development of a 3-phase Loco

Electrical Features: - Vehicle propulsion concept: 3-phase converter drive. - Main transformer

The main transformer is housed in an aluminium tank. It is mounted under frame between the two bogies.

- Traction Converter The machine room contains one traction converter per bogie with 2-point switching. This comprises a line converter and 3-phase drive converter. The traction motors are supplied with power directly by two relevant bogie selective drive converters with appropriate control electronics.

- Axle drive Three externally ventilated three-phase asynchronous squirrel cage motors of Type 6 FRA 6068 are installed on both bogies. The three traction motors on each bogie are supplied with power by one traction converter.

- Harmonic Filter The harmonic filter consisting of resistor and capacitor reduces the high frequency harmonics.

Page 9: Chittaranjan locomotive works (Summer Training Report)

Development of a 3-phase Loco

Electrical Features: - Auxiliary Circuits

Three modular auxiliary converters (BUR) are used to supply power to the 3-phase auxiliary circuit motors. The auxiliary circuits are designed in a bogie-selective manner.

- Control electronics (MICAS-S2) All functions of the locomotive are controlled by the control electronics. It takes the form of bus stations with processors. The bus stations communicate with each other via fibre optic cables which are resistant to the effects of Electro Magnetic Interference (EMI). The diagnostic equipment comprises a diagnosis computer with monitor and keyboard in the driver’s cab. This provides an effective support for the duties of the locomotive driver and maintenance personnel.

- Multiple Unit Control The locomotive is equipped for multiple unit control with locomotives of the same kind. However, no more than two locomotives can be connected together. Commands are transmitted by the UIC cable.

Comfort Equipment Every driver’s cab is equipped with two fans and a unit for recirculating and heating the air. Recently cab air-condition has been introduced in WAG-9 type locomotive

Page 10: Chittaranjan locomotive works (Summer Training Report)

Development of a 3-phase Loco

ROOF LAYOUT:-

Page 11: Chittaranjan locomotive works (Summer Training Report)

Development of a 3-phase Loco

Due to technical and economical reasons electric traction vehicles are nowadays provided with three phase asynchronous traction motors. The three phase voltage required for operating the traction motors is generated on the vehicle by means of the traction converter connected between the vehicle's main transformer (single phase) and the traction motors.

The traction converter allows the train not only to drive but also to brake electrically. To control the tractive or braking effort, and hence the speed of the vehicle, both the frequency and the amplitude of the three-phase converter output voltage are continuously changed according to the demand from the driver's cab. This shows continuous adjustment of the driving or braking torque of the traction motors, which means that the driving speed changes smoothly. When braking electrically the traction motors act as generators. In the converters the resulting three-phase electrical energy is converted into single-phase energy which is fed back into the line (recuperation brake).

• Output voltage of the Traction converter 2365 V

• Output current 831 A

• Output power 2105 KW

  Earth fault detection is integrated at the output of the Line converter. The main transformer converts the overhead line voltage (25 KV) to the lower operating voltages. There are four secondary traction windings (two on each converter unit, 1269V), one for feeding the auxiliary circuits (1000 V) and one for the harmonic filter (1154 V). A 2-point circuit converter unit is installed on each bogie. The line converter (NSR) converts the constant frequency AC voltage supplied by the transformer into DC voltage (intermediate link).

 

The drive converter (ASR) generates a 3-phase system with variable voltage and frequency. The energy flow is reversed during regenerative braking. To retain control of over voltages in the DC-Link, the DC-Link Is equipped with an over voltage protection unit (MUS). This consists of a resistor and a GTO. In case of a protective shut-down the GTOs of ASR & NSR are blocked and the energy stored In the DC Link is converted into heat in the MUS.

Page 12: Chittaranjan locomotive works (Summer Training Report)

Development of a 3-phase Loco

Breaking System Overview:-

Regenerative brake (controlled by angle transmitter) Pneumatic automatic train brake (controlled by pneumatic automatic

brake handle) Direct loco brake (controlled by direct loco brake handle) Parking brake (controlled by parking brake push button, not for WAP-

7) Anti-spin brake (controlled by SLG, FG90) Emergency brake (controlled by emergency brake valve)

TE/BE Throttle1. Break Handle2. Locking Device

Pneumatic automatic train brakeRegenerative Breaking : Master Controller

Page 13: Chittaranjan locomotive works (Summer Training Report)

Different Sections of CPH

Drawing Section

Main Substation

Pump HouseRefrigeration Section

Construction Section

General Section 12 MVA transformer at Main Sub-Station

Page 14: Chittaranjan locomotive works (Summer Training Report)

Process flow Chart at Pump House

Page 15: Chittaranjan locomotive works (Summer Training Report)

Shop Floor Activities

Page 16: Chittaranjan locomotive works (Summer Training Report)

Different Locomotive Engines produced by CLW

Gauge: 1676 mm

Continuous HP: 6000

Starting Tractive effort: 460KN

Max, Speed: 100 kmph

Breaking: Air, Regenerative& Parking

System Voltage: 25KV AC, 50 Hz.

Weight of loco: 123t.

Type: Freight

WAG-9 - The “Heavy Haul” Freight locomotive of IR

Page 17: Chittaranjan locomotive works (Summer Training Report)

Different Locomotive Engines produced by CLW

Horse Power: 6000 hpSupply System: 25kV, AC, 50 Hz.

Track Gauge: 1676 mm (Broad Gauge)

Total weight: 123.0 + 1%t.Wheel Diameter:

1092 mm (New ),1016 mm (Full Worn)

Continuous Power at wheel rim : 4500 kW (6000 hp)

Starting Tractive effort: 323 KN

Max. Service Speed: 140 kmph

Brake System : Air, Regenerative

WAP-7 -The “Heavy Haul” Passenger locomotive of IR:

Page 18: Chittaranjan locomotive works (Summer Training Report)

Different Locomotive Engines produced by CLW

Track Gauge : 1676 mm

Axle Arrangement : Bo-Bo

Total weight : 78+ 1%t

Axle Load : 19.5 + 2%tWheel Diameter :

1092 mm (new ),1016 mm (Full Worn)

Type of Traction motors : FXA 7059, 3-phase Squirrel Cage Induction Motors

Continuous Power at wheel rim : 4000 kW

Starting Tractive Effort : 258 KN

Control System Voltage : 110 V dc

Brake System : Air, Regenerative & Parking

WAP-5 -5400 hp,25 kV ac, B.G. 160 km/hr. speed,3-phase drive

Page 19: Chittaranjan locomotive works (Summer Training Report)

Different Locomotive Engines produced by CLW

Track Gauge : 1676 mm

Axle arrangement : Co-CoBrake System : Air and Rheostatic

Total weight : 112.8 + 1% t.Wheel Diameter :

1092 mm (New) , 1016 mm (Full worn)

Traction Motor type : DC Series Motor

Continuous Power at Wheel Rim : 5000 HP

Starting Tractive Effort : 30.8 t

Control System Voltage : 110 V

Brake System : Air, Regenerative & Parking

WAP-4 -5000 HP , 25 KV AC ,Passenger Electric Locomotive

Page 20: Chittaranjan locomotive works (Summer Training Report)