chorley park trail connecton - working group meeting #3

38
Chorley Park Trail Connection Stakeholder Meeting #3 (Sept. 9, 2015) 1 Chorley Park Trail Connection Stakeholder Meeting #3 (Sept. 9, 2015) 1 Chorley Park Trail Connection Proposed Design Concept and Options Stakeholder Meeting #3 (September 9, 2015)

Upload: toronto-public-consultation-unit

Post on 13-Apr-2017

2.355 views

Category:

Government & Nonprofit


0 download

TRANSCRIPT

Page 1: Chorley Park Trail Connecton - Working Group Meeting #3

Chorley Park Trail Connection Stakeholder Meeting #3 (Sept. 9, 2015) 1Chorley Park Trail Connection Stakeholder Meeting #3 (Sept. 9, 2015) 1

Chorley Park Trail Connection

Proposed Design Concept and Options

Stakeholder Meeting #3 (September 9, 2015)

Page 2: Chorley Park Trail Connecton - Working Group Meeting #3

Chorley Park Trail Connection Stakeholder Meeting #3 (Sept. 9, 2015) 2Chorley Park Trail Connection Stakeholder Meeting #3 (Sept. 9, 2015) 2

Design elements with common ground:

•Provide a reliable trail connection

•Create a design friendly for pedestrians of all ages, families with strollers, and dogs on leash

•Keep the trail as narrow as possible

•Discourage fast cycling and skateboarding

•Retain natural setting

•Minimize visible retaining walls and fencing

•Do not include lighting

•Limit the impacts of parking around Chorley Park

Page 3: Chorley Park Trail Connecton - Working Group Meeting #3

Chorley Park Trail Connection Stakeholder Meeting #3 (Sept. 9, 2015) 3Chorley Park Trail Connection Stakeholder Meeting #3 (Sept. 9, 2015) 3

Design elements required by the City:

•Install a switchback trail that is as universally accessible (barrier free) as possible.

•Create an accessible connection between the top of the trail and the sidewalk.

•Switchback trail surface will be asphalt.

•Include multiple passing/resting areas, with seating where possible.

Page 4: Chorley Park Trail Connecton - Working Group Meeting #3

Chorley Park Trail Connection Stakeholder Meeting #3 (Sept. 9, 2015) 4Chorley Park Trail Connection Stakeholder Meeting #3 (Sept. 9, 2015) 4

North

Sidewalk connects to TTC

C1

C2

Page 5: Chorley Park Trail Connecton - Working Group Meeting #3

Chorley Park Trail Connection Stakeholder Meeting #3 (Sept. 9, 2015) 5Chorley Park Trail Connection Stakeholder Meeting #3 (Sept. 9, 2015) 5

Current - June 2014 proposal comparisonCore elements

Design Element City Proposed Design June 2014 (before Working Group)

City Proposed Design September 2015(after 2 meetings with Working Group)

Trail length 535 metres 375 metres

Trail width 3 metres 2 metres (rest areas an additional 1.5 metres)

Trail surface Asphalt Asphalt

Retaining walls Armour stone 1-3 stones high along approximately 75% of upslope side of trail and approximately 35% of downslope side of trail

All on downslope side of trail, most 2 armour stones high, with small percentage 3 stones high

Fencing 3-rail post and paddle fence along downslope side of trail for entire length

Limited to locations where drop is greater than 1 m (3 stone retaining wall) and where essential for accessibility

Trail slope 6.1% average, 6.8% max 6.1% average, 6.8% max

Connection through Chorley Park

No Yes, along perimeter

passing/resting areas, with seating where possible

No defined passing areas or seating Eight (8) locations are identified and recommended. Most, if not all, should be able to accommodate some seating

Page 6: Chorley Park Trail Connecton - Working Group Meeting #3

Chorley Park Trail Connection Stakeholder Meeting #3 (Sept. 9, 2015) 6Chorley Park Trail Connection Stakeholder Meeting #3 (Sept. 9, 2015) 6

North

Page 7: Chorley Park Trail Connecton - Working Group Meeting #3

Chorley Park Trail Connection Stakeholder Meeting #3 (Sept. 9, 2015) 7Chorley Park Trail Connection Stakeholder Meeting #3 (Sept. 9, 2015) 7

June 2014 proposal

Page 8: Chorley Park Trail Connecton - Working Group Meeting #3

Chorley Park Trail Connection Stakeholder Meeting #3 (Sept. 9, 2015) 8Chorley Park Trail Connection Stakeholder Meeting #3 (Sept. 9, 2015) 8

Most Lengths Where retaining walls greater than 1m are necessary

Where retaining walls less than 1m are necessary

Resting areas ("bump outs")

Page 9: Chorley Park Trail Connecton - Working Group Meeting #3

Chorley Park Trail Connection Stakeholder Meeting #3 (Sept. 9, 2015) 9Chorley Park Trail Connection Stakeholder Meeting #3 (Sept. 9, 2015) 9

Design elements required by the City:Accessible connection

Option C1:

Connect from top

of switchback to

intersection of

Astley and

Douglas

(Northeast corner

of park)

Page 10: Chorley Park Trail Connecton - Working Group Meeting #3

Chorley Park Trail Connection Stakeholder Meeting #3 (Sept. 9, 2015) 10Chorley Park Trail Connection Stakeholder Meeting #3 (Sept. 9, 2015) 10

Design elements required by the City:Accessible connection

Option C2:

Connect from top of switchback along edge of park to heritage

driveway to connect to sidewalk on Douglas Drive

Page 11: Chorley Park Trail Connecton - Working Group Meeting #3

Chorley Park Trail Connection Stakeholder Meeting #3 (Sept. 9, 2015) 11Chorley Park Trail Connection Stakeholder Meeting #3 (Sept. 9, 2015) 11

Design elements yet to be determined:

•Shift Belt Line Trail west (uphill) and introduce bioswale

•Include a natural surface footpath in the forested area

•Include stairs as optional shortcuts connecting to the switchback trail.

•Style of:•Stairs•Seating•Railings

Page 12: Chorley Park Trail Connecton - Working Group Meeting #3

Chorley Park Trail Connection Stakeholder Meeting #3 (Sept. 9, 2015) 12Chorley Park Trail Connection Stakeholder Meeting #3 (Sept. 9, 2015) 12

S1

S2

S3 S4

C1

C2

North

Sidewalk connects to TTC

Potential Additional

Features

Page 13: Chorley Park Trail Connecton - Working Group Meeting #3

Chorley Park Trail Connection Stakeholder Meeting #3 (Sept. 9, 2015) 13Chorley Park Trail Connection Stakeholder Meeting #3 (Sept. 9, 2015) 13

Design Element City Proposed Design June 2014 (before Working Group)

City Proposed Design September 2015(after 2 meetings with Working Group)

Optional natural path Not included Option provided

Optional short cut stairs S1 only Option provided

Optional bioswale for stormwater management

Not included Option provided

Current - June 2014 proposal comparisonPotential additional features

Page 14: Chorley Park Trail Connecton - Working Group Meeting #3

Chorley Park Trail Connection Stakeholder Meeting #3 (Sept. 9, 2015) 14Chorley Park Trail Connection Stakeholder Meeting #3 (Sept. 9, 2015) 14

Potential Additional Features:A) Bioswale

Page 15: Chorley Park Trail Connecton - Working Group Meeting #3

Chorley Park Trail Connection Stakeholder Meeting #3 (Sept. 9, 2015) 15Chorley Park Trail Connection Stakeholder Meeting #3 (Sept. 9, 2015) 15

Potential Additional Features:A) Bioswale

Page 16: Chorley Park Trail Connecton - Working Group Meeting #3

Chorley Park Trail Connection Stakeholder Meeting #3 (Sept. 9, 2015) 16Chorley Park Trail Connection Stakeholder Meeting #3 (Sept. 9, 2015) 16

Proposed Additional Features:B) Natural Surface Path

South of asphalt switchback

Page 17: Chorley Park Trail Connecton - Working Group Meeting #3

Chorley Park Trail Connection Stakeholder Meeting #3 (Sept. 9, 2015) 17Chorley Park Trail Connection Stakeholder Meeting #3 (Sept. 9, 2015) 17

Proposed Additional Features:B) Natural Surface Path

South of asphalt switchback

Page 18: Chorley Park Trail Connecton - Working Group Meeting #3

Chorley Park Trail Connection Stakeholder Meeting #3 (Sept. 9, 2015) 18Chorley Park Trail Connection Stakeholder Meeting #3 (Sept. 9, 2015) 18

S1

S2

S3 S4

North

Stair # # of risers # of landings

S1 24 1

S2 63 2

S3 44 2

S4 15 0

Proposed Additional Features:C) Stairs as Optional Shortcuts

Page 19: Chorley Park Trail Connecton - Working Group Meeting #3

Chorley Park Trail Connection Stakeholder Meeting #3 (Sept. 9, 2015) 19Chorley Park Trail Connection Stakeholder Meeting #3 (Sept. 9, 2015) 19

S1

Proposed Additional Features:C) Stairs as Optional Shortcuts

S2

Page 20: Chorley Park Trail Connecton - Working Group Meeting #3

Chorley Park Trail Connection Stakeholder Meeting #3 (Sept. 9, 2015) 20Chorley Park Trail Connection Stakeholder Meeting #3 (Sept. 9, 2015) 20

S3 & S4

Proposed Additional Features:C) Stairs as Optional Shortcuts

Page 21: Chorley Park Trail Connecton - Working Group Meeting #3

Chorley Park Trail Connection Stakeholder Meeting #3 (Sept. 9, 2015) 21Chorley Park Trail Connection Stakeholder Meeting #3 (Sept. 9, 2015) 21

Stone

A & B Cost to install: ~ $1,100 - $1,800 per step

Proposed Additional Features:D) Stair Material & Style Options

A B

Page 22: Chorley Park Trail Connecton - Working Group Meeting #3

Chorley Park Trail Connection Stakeholder Meeting #3 (Sept. 9, 2015) 22Chorley Park Trail Connection Stakeholder Meeting #3 (Sept. 9, 2015) 22

Concrete

C D

C & D Cost to install: ~ $800 - $1,000 per riser

Proposed Additional Features:D) Stair Material & Style Options

Page 23: Chorley Park Trail Connecton - Working Group Meeting #3

Chorley Park Trail Connection Stakeholder Meeting #3 (Sept. 9, 2015) 23Chorley Park Trail Connection Stakeholder Meeting #3 (Sept. 9, 2015) 23

Wood

E & F Cost Range: ± $1,500 - $1,750 per riser

E F

Proposed Additional Features:D) Stair Material & Style Options

Page 24: Chorley Park Trail Connecton - Working Group Meeting #3

Chorley Park Trail Connection Stakeholder Meeting #3 (Sept. 9, 2015) 24Chorley Park Trail Connection Stakeholder Meeting #3 (Sept. 9, 2015) 24

Steel

G & H Cost to install: ~ $2,200 - $3,800 per riser

G H

Proposed Additional Features:D) Stair Material & Style Options

Page 25: Chorley Park Trail Connecton - Working Group Meeting #3

Chorley Park Trail Connection Stakeholder Meeting #3 (Sept. 9, 2015) 25Chorley Park Trail Connection Stakeholder Meeting #3 (Sept. 9, 2015) 25

S1

S2

S3 S4

C1

C2

North

Sidewalk connects to TTC

Potential Additional

Features

Page 26: Chorley Park Trail Connecton - Working Group Meeting #3

Chorley Park Trail Connection Stakeholder Meeting #3 (Sept. 9, 2015) 26Chorley Park Trail Connection Stakeholder Meeting #3 (Sept. 9, 2015) 26

City of Toronto Standard Park Bench

Cost to install: ~ $1,600 - $2,500 per bench

Stone

A

B

C

Cost to install:

~ $500/m2 face

Cost to install: ~ $275 - $325 per stone

Proposed Additional Features:E) Seating Material & Style Options

Page 27: Chorley Park Trail Connecton - Working Group Meeting #3

Chorley Park Trail Connection Stakeholder Meeting #3 (Sept. 9, 2015) 27Chorley Park Trail Connection Stakeholder Meeting #3 (Sept. 9, 2015) 27

Wood

Cost to install: ~ $80 - $100 per metre length

A

Proposed Additional Features:F) Railing Material & Style Options

Page 28: Chorley Park Trail Connecton - Working Group Meeting #3

Chorley Park Trail Connection Stakeholder Meeting #3 (Sept. 9, 2015) 28Chorley Park Trail Connection Stakeholder Meeting #3 (Sept. 9, 2015) 28

Metal

Cost to install:

~ $200 - $250

per metre length

B C D

Cost to install:

~ $350 - $450

per metre length

Cost to install:

~ $125 – $175

per metre length

Proposed Additional Features:F) Railing Material & Style Options

Page 29: Chorley Park Trail Connecton - Working Group Meeting #3

Chorley Park Trail Connection Stakeholder Meeting #3 (Sept. 9, 2015) 29Chorley Park Trail Connection Stakeholder Meeting #3 (Sept. 9, 2015) 29

Metal/Wood Hybrid

Cost to install: ~ $225 - $350 per metre length

E

Proposed Additional Features:F) Railing Material & Style Options

Page 30: Chorley Park Trail Connecton - Working Group Meeting #3

Chorley Park Trail Connection Stakeholder Meeting #3 (Sept. 9, 2015) 30Chorley Park Trail Connection Stakeholder Meeting #3 (Sept. 9, 2015) 30

How the design has changed in response to input from the Working Group:

•Narrower trail

•Less retaining wall and only on downslope side (less visible)

•Less railing/fencing

•Options for:•Reduced length •Natural surface trail in wooded area•Shortcuts with stairs

Page 31: Chorley Park Trail Connecton - Working Group Meeting #3

Chorley Park Trail Connection Stakeholder Meeting #3 (Sept. 9, 2015) 31Chorley Park Trail Connection Stakeholder Meeting #3 (Sept. 9, 2015) 31

Sir Winston Churchill Park – 2007 (above) and 2014 (below)

Restoration plantings

Page 32: Chorley Park Trail Connecton - Working Group Meeting #3

Chorley Park Trail Connection Stakeholder Meeting #3 (Sept. 9, 2015) 32Chorley Park Trail Connection Stakeholder Meeting #3 (Sept. 9, 2015) 32

Page 33: Chorley Park Trail Connecton - Working Group Meeting #3

Chorley Park Trail Connection Stakeholder Meeting #3 (Sept. 9, 2015) 33Chorley Park Trail Connection Stakeholder Meeting #3 (Sept. 9, 2015) 33

Page 34: Chorley Park Trail Connecton - Working Group Meeting #3

Chorley Park Trail Connection Stakeholder Meeting #3 (Sept. 9, 2015) 34Chorley Park Trail Connection Stakeholder Meeting #3 (Sept. 9, 2015) 34

Restoration – with large caliper trees

Page 35: Chorley Park Trail Connecton - Working Group Meeting #3

Chorley Park Trail Connection Stakeholder Meeting #3 (Sept. 9, 2015) 35Chorley Park Trail Connection Stakeholder Meeting #3 (Sept. 9, 2015) 35

Timeline for Trail Construction

Fall 2015 to early 2016 – detailed design

Spring 2016 – permits and approvals (and associated design

revisions)

Summer 2016 – tender

Fall 2016 – additional site prep (including any additional tree

removals)

Winter 2016/2017 - construction

*Subject to change due to budget, permitting and weather.

Page 36: Chorley Park Trail Connecton - Working Group Meeting #3

Chorley Park Trail Connection Stakeholder Meeting #3 (Sept. 9, 2015) 36Chorley Park Trail Connection Stakeholder Meeting #3 (Sept. 9, 2015) 36

THANK YOU

Page 37: Chorley Park Trail Connecton - Working Group Meeting #3

Chorley Park Trail Connection Stakeholder Meeting #3 (Sept. 9, 2015) 37Chorley Park Trail Connection Stakeholder Meeting #3 (Sept. 9, 2015) 37

FOCP - current proposal overlay

Page 38: Chorley Park Trail Connecton - Working Group Meeting #3

Chorley Park Trail Connection Stakeholder Meeting #3 (Sept. 9, 2015) 38Chorley Park Trail Connection Stakeholder Meeting #3 (Sept. 9, 2015) 38

Nov 2014 - current proposal overlay