churchill subway 13th march 2017 cte panel · churchill subway 13th march 2017 cte panel. costed...
TRANSCRIPT
Costed Options
• Option1 - do minimum to ensure structural integrity, safe access to the public and working drainage, cost estimate £180k.
• Option2 - as option 1, with the addition of new surface finishes, lighting and mirrors, cost estimate £250k.
• Option 3 - as option 2, with the addition of enhanced lighting and parapet reconstruction to DMRB standards - cost estimate £460k.
Atkins Recommendation
• The structural engineering consultant
recommended that the Council pursue option
2 and refurbish the subway at an estimated
cost of £250k.
• In additional a technical note was produced
which clarified why a surface crossing would
not be recommended due to the issues with
congestion, site lines and location.
A36 East pm Peak
Delay Queue
South North
No crossing 3m 14 sec 150m 0 0
30 sec 9min 25 sec 470m 61m 56m
Pedestrian
Wait Time
Queue Stop Line
Churchill Bridge pm Peak
Delay Queue
No crossing 1min 50
30 sec 1min 30 sec 100
Pedestrian
Wait Time
Wellsway pm Peak
Delay Queue
No crossing 2 min 140
30 sec 1 min 43 sec 130
Pedestrian
Wait Time
Delay Queue
South North
No crossing 3m 14 sec 150m 0 0
30 sec 9min 25 sec 470m 61m 56m
60 sec 5min 24 sec 300m 60m 55m
90 sec 4min 12 sec 230m 59m 52m
Queue Stop LinePedestrian
Wait Time
30m
CH2M - Position is absolute minimum
acceptable distance from gyratory on
highway safety grounds . SSD 40-50m
(Design Manual Safe Stopping distance
at 30mph is 65m)
Summary
• Option 2 – Not Safe
• Option 3 – Safe Location, to far from the
pedestrian desire line (30m +30m) and will
result in traffic delays with a 30 second
pedestrian wait
Recommendation
Following the results of the various assessments the
Highway Authority would recommends that the Council
refurbish the subway to ensure structural integrity, safe
access to the public, new surface finishes, lighting and
mirrors, cost estimate £250k.
In addition to this budget should be made available for a
CCTV camera and the communication link (£15K) and the
option for a pumped drainage system (£50k)
Total recommended budget £315k