    CII Benchmarking & Metrics

    (Project Questionnaire Version 9.0)

    Glossary of Terms

    Glossary of Terms Page 1

    Acceptance Testing. Facility capacity testing at the time a project is expected to reach design capacity. Thetiming in which this takes place varies by type of facility. Acceptance testing may occur shortly after start-up

    of a process unit, 6 to 12 months on building or mechanical trains, or 2 to 3 years for a paper mill.

    Addition (Add-on). - A new addition that ties in to an existing facility, often intended to expand capacity.

    Synonym: Expansion.

    Alliance Partner. A participant in a long-term association with a non-affiliated organization, used to furtherthe common interests of the members. The continued association is based upon mutual trust and the

    satisfactory performance of each participant, and the alliance as a whole, rather than a pure contractual

    obligation.

    Automation/Integration (AI) Technology. The Automation and Integration Technology practice addresses

    the degree of automation/level of use and integration of automated systems for predefined tasks/workfunctions common to most projects.

    Bar Coding. The use of automatic identification technology by labeling, identifying, and controlling items,

    materials, and equipment through the use of bar codes. A bar code can be defined as a self contained messagewith information encoded in the widths of bars and spaces in a printed pattern.

    Change. A change is any event that results in a modification of the project work, schedule or cost. Owners

    and designers frequently initiate changes during design development to reflect changes in project scope or

    preferences for equipment and materials other than those originally specified. Contractors often initiate

    changes when interferences are encountered, when designs are found to be not constructable, or other design

    errors are found.

    Change Management. Change Management is the process of incorporating a balanced change culture of

    recognition, planning and evaluation of project changes in an organization to effectively manage project

    changes.

    Constructability. Constructability is the effective and timely integration of construction knowledge into the

    conceptual planning, design, construction and field operations of a project to achieve the overall project

    objectives in the best possible time and accuracy, at the most cost-effective levels.

    Contingency. All costs in contingency accounts including but not limited to normal contingency, allowances,reserves, indirect costs for schedule contingency, escalation, etc.

    Cost of Land. The cost of land includes the purchase price of the land obtained for project use. It does not

    include the cost of preparing the land for use, such as soil remediation, demolition of existing structures, sitepreparation, etc.

    Cost of Quality Management. The sum of those costs associated with quality deviation prevention and

    appraisal activities. Examples include: Quality System/Program Development Personnel Qualification Testing Formal Design Check/Review On/Off-Site Inspection

    Direct Cost of Field Rework. The sum of those costs associated with actual performance of tasks involved inrework. Examples include:

  • 8/2/2019 CII Bench Marking & Metrics

    2/53

    CII Benchmarking & Metrics

    (Project Questionnaire Version 9.0)

    Glossary of Terms

    Glossary of Terms Page 2

    Labor Materials Equipment Supervisory personnel Associated overhead cost

    Electronic Data Interchange (EDI). EDI is a technology that permits the direct computer-to-computer

    exchange of data in a standard format. Data is transmitted in a standard industry format, checked for error,

    and imported directly into the receiving computer system without re-keying.

    Expansion. - A new addition that ties in to an existing facility, often intended to expand capacity. Synonym:Addition.

    Grass Roots (Green Field). A new facility from the foundations and up. A project requiring demolition of an

    existing facility before new construction begins is also classified as grass roots.

    Integrated Database. An integrated database is a concept of organizing, storing, and managing all electronic

    data relating to a project in such a fashion that data is entered and stored once and then accessed and utilizedby multiple users and applications. The users may include those involved with facility planning, design,

    procurement, construction, plant operations, and suppliers.

    Materials Management. Materials management is an integrated process for planning and controlling allnecessary efforts to make certain that the quality and quantity of materials and equipment are appropriately

    specified in a timely manner, are obtained at a reasonable cost, and are available when needed. The materials

    management systems combine and integrate the takeoff, vendor evaluation, purchasing, expediting,

    warehousing, distribution, and disposing of materials functions.

    Mechanical Completion. The point in time when a plant is capable of being operated although some trim,insulation, and painting may still be needed. This occurs after completion of precommissioning. In some

    industries, mechanical completion may have the same general meaning as beneficial occupancy.

    Modernization. A facility for which a substantial amount of the equipment, structure, or other components isreplaced or modified, and which may expand capacity and/or improve the process or facility. Synonyms:Renovation, Upgrade.

    Modularization. Modularization refers to the use of offsite construction. For the purposes of thebenchmarking data, modularization includes all work that represents substantial offsite construction and

    assembly of components and areas of the finished project. Examples that would fall within this categorization

    include:

    Skid assemblies of equipment and instrumentation that naturally ship to the site in one piece, andrequire minimal on-site reassembly.

    Super-skids of assemblies of components that typically represent substantial portions of the plant,intended to be installed in a building.

    Prefabricated modules comprising both industrial plant components and architecturally finishedenclosures.

  • 8/2/2019 CII Bench Marking & Metrics

    3/53

    CII Benchmarking & Metrics

    (Project Questionnaire Version 9.0)

    Glossary of Terms

    Glossary of Terms Page 3

    Modularization does not include offsite fabrication of components. Examples of work that would be excluded

    from the definition of modularization include:

    Fabrication of the component pieces of a structural framework Fabrication of piping spool-pieces

    Planning for Startup. Startup is the transitional phase between plant construction completion and commercial

    operations, including all of the activities that bridge these two phases. Planning for Startup consists of a

    sequence of activities that begins during requirements definition and extends through initial operations.

    Pre-Project Planning. Pre-Project Planning involves the process of developing sufficient strategic

    information that owners can address risk and decide to commit resources to maximize the chance for a

    successful project. Pre-project planning includes putting together the project team, selecting technology,

    selecting project site, developing project scope, and developing project alternatives. Pre-project planning is

    often perceived as synonymous with front-end loading, front-end planning, feasibility analysis, andconceptual planning.

    Project Budget at Authorization to Proceed. This is the estimated cost for your companys portion of theproject at authorization to proceed. If your contract had cost changes before authorization to proceed, then

    these changes should be included in the project budget. Do not include estimated costs for change orders

    received during project execution. .

    Project Development Changes. Changes required to execute the original scope of work or obtain original

    process basis. Examples include:

    Unforeseen site conditions that require a change in design / construction methods Changes required due to errors and omissions Acceleration Change in owner preferences Additional equipment or processes required to obtain original planned throughput Operability or maintainability changes

    Project Change Management. Practices related to the management and control of both scope changes and

    project changes.

    P&IDs (Piping and Instrumentation Diagrams). Schematic diagrams which show the layout andrelationship of piping and instrumentation.

    Quality Management. Quality Management incorporates all activities conducted to improve the efficiency,contract compliance and cost effectiveness of design, engineering, procurement, QA/QC, construction, and

    start-up elements of construction projects.

    Renovation. A facility for which a substantial amount of the equipment, structure, or other components is

    replaced or modified, and which may expand capacity and/or improve the process or facility. Synonyms:Modernization, Upgrade.

    Scope Changes. Changes in the base scope of work or process basis. Examples include:

    Feedstock change Changed site location

  • 8/2/2019 CII Bench Marking & Metrics

    4/53

    CII Benchmarking & Metrics

    (Project Questionnaire Version 9.0)

    Glossary of Terms

    Glossary of Terms Page 4

    Changed throughput Addition of unrelated scope

    Team Building. Team Building is a project-focused process that builds and develops shared goals,interdependence, trust and commitment, and accountability among team members and that seeks to improve

    team members problem-solving skills.

    Total Actual Project Cost. This is the total actual cost of all work performed by your company, including

    costs attributable to work added or deducted by change orders.

    Turnaround/Shutdown/Outage . The period during which a boiler, generating unit, transmission line, orother facility is shutdown and unable to perform its normal operations. The shutdown of a facility including

    for maintenance, inspection, testing, regulatory changes, or, in some cases, for refuelling is known as a

    planned shutdown. Turnaround is interchangeable with shutdown or outage depending on industry groups.

    Upgrade. A facility for which a substantial amount of the equipment, structure, or other components isreplaced or modified, and which may expand capacity and/or improve the process or facility. Synonyms:

    Modernization, Renovation.

    Zero Accidents. Zero accident techniques include the site specific safety programs and implementation,

    auditing and incentive efforts to create a project environment and a level of training that embraces the mind

    set that all accidents are preventable and that zero accidents is an obtainable goal.

    3D CAD modeling. Computer aided drafting system that provides three-dimensional views for checkingphysical interferences in addition to providing two and three dimensional drafting capabilities.

  • 8/2/2019 CII Bench Marking & Metrics

    5/53

    CII Benchmarking & Metrics

    (Project Questionnaire Version 9.0)

    Glossary of Terms

    Glossary of Terms Page 5

    Project Phase Table

    Project Phase Start/Stop Typical Activities & Products Typical Cost Elements

    Pre-Project Planning

    Typical Participants:

    Owner Personnel Planning Consultants

    Constructability Consultant

    Alliance / Partner

    Start: Defined Business Need

    that requires facilities

    Stop: Total Project Budget

    Authorized

    Options Analysis

    Life-cycle Cost Analysis

    Project Execution Plan

    Appropriation Submittal Pkg P&IDs and Site Layout

    Project Scoping

    Procurement Plan Arch. Rendering

    Owner Planning Team PersonnelExpenses

    Consultant Fees & Expenses

    Environmental Permitting Costs Project Manager / Construction

    Manager Fees

    Licensor Costs

    Detail Design

    Typical Participants:

    Owner Personnel

    Design Contractor

    Constructability Expert Alliance / Partner

    Start: Design Basis

    Stop: Release of all approved

    drawings and specs for

    construction (or last package

    for fast-track)

    Drawing & spec preparation Bill of material preparation

    Procurement Status Sequence of operations

    Technical Review

    Definitive Cost Estimate

    Owner Project ManagementPersonnel

    Designer Fees Project Manager / Construction

    Manager Fees

    Demolition / Abatement

    (see note below)

    Typical Participants:

    Owner Personnel

    General Contractor Demolition Contractor

    Remediation / AbatementContractor

    Start: Mobilization for

    demolition

    Stop: Completion of demolition

    Remove existing facility or

    portion of facility to allow

    construction or renovation toproceed

    Perform cleanup or abatement /

    remediation

    Owner Project Management

    Personnel

    Project Manager / ConstructionManager Fees

    General Contractor and/or Demolition

    Specialist Charges Abatement / Remediation Contractor

    Charges

    Note: The demolition / abatement phase should be reported when the demolition / abatement work is a separate schedule activity (potentially

    paralleling the design and procurement phases) in preparation for new construction. Do not report the demolition / abatement phase if the

    work is integral with modernization or addition activities.

  • 8/2/2019 CII Bench Marking & Metrics

    6/53

    CII Benchmarking & Metrics

    (Project Questionnaire Version 9.0)

    Glossary of Terms

    Glossary of Terms Page 6

    Project Phase Table (Cont.)

    Project Phase Start/Stop Typical Activities & Products Typical Cost Elements

    Procurement

    Typical Participants:

    Owner personnel Design Contractor Alliance / Partner

    Start: Procurement Plan for

    Engineered Equipment

    Stop: All engineered

    equipment has been

    delivered to site

    Vendor Qualification

    Vendor Inquiries Bid Analysis Purchasing Expediting Engineered Equipment

    Transportation Vendor QA/QC

    Owner project management personnel

    Project Manager / ConstructionManager fees

    Procurement & Expediting personnel Engineered Equipment Transportation

    Shop QA / QC

    Construction

    Typical Participants:

    Owner personnel

    Design Contractor(Inspection)

    Construction Contractor and

    its subcontractors

    Start: Beginning of continuous

    substantial construction

    activityStop: Mechanical Completion

    Set up trailers

    Site preparation

    Procurement of bulks Issue Subcontracts

    Construction plan forMethods/Sequencing

    Build Facility & Install

    Engineered Equipment

    Complete Punchlist Demobilize construction

    equipment

    Warehousing

    Owner project management personnel

    Project Manager / Construction

    Manager fees

    Building permits

    Inspection QA/QC Construction labor, equipment &

    supplies

    Bulk materials Construction equipment Contractor management personnel Warranties

    Start-up / Commissioning

    Note: Does not usually apply toinfrastructure or building type

    projects

    Typical Participants:

    Owner personnel Design Contractor

    Construction Contractor

    Training Consultant Equipment Vendors

    Start:Mechanical Completion

    Stop: Custody transfer touser/operator (steady state

    operation)

    Testing Systems

    Training Operators Documenting Results Introduce Feedstocks and

    obtain first Product

    Hand-off to user/operator

    Operating System Functional Facility

    Warranty Work

    Owner project management personnel

    Project Manager / ConstructionManager fees

    Consultant fees & expenses

    Operator training expenses

    Wasted feedstocks

    Vendor fees

  • 8/2/2019 CII Bench Marking & Metrics

    7/53

    CII Benchmarking & Metrics

    (Project Questionnaire Version 9.0)

    Glossary of Terms

    Glossary of Terms Page 7

    PDRI (Project Definition Rating Index) Buildings

    SECTION I: BASIS OF PROJECT DECISION

    A. BUSINESS STRATEGY

    A1. Building Use

    Identify and list building uses or functions. These may include uses such as:

    Retail

    Institutional

    Instructional

    Medical

    Storage

    Food service

    Recreational

    Research

    Multimedia

    Office

    Light manufacturing

    A description of other options which could also meet the facility need should be defined. (As an example, was

    renovating existing space rather than building new space considered?) A listing of current facilities that will

    be vacated due to the new project should be produced.

    A2. Business Justification

    Identify driving forces for the project and specify what is most important from the viewpoint of the owner

    including both needs and expectations. Address items such as:

    Need date

    Target consumers Building utilization justification

    Possible competitors

    Level of amenities

    Location

    Sales or rental levels Market capacity

    Use flexibility

    Number of lessons/occupant types

    Support new business initiatives Facility replacement/consolidation

    A3. Business Plan

    A project strategy should be developed that supports the business justification in relation to the following

    items:

  • 8/2/2019 CII Bench Marking & Metrics

    8/53

    CII Benchmarking & Metrics

    (Project Questionnaire Version 9.0)

    Glossary of Terms

    Glossary of Terms Page 8

    Funding availability

    Cost and financing

    Schedule milestones (including known deadlines)

    Types and sources of project funds

    Related/resulting projects

    A4. Economic Analysis

    An economic model should be developed to determine the viability of the venture. The model should

    acknowledge uncertainty and outline the boundaries of the analysis. It should acknowledge items such as:

    Design life

    Building ownership

    Tax implications of investment including length of ownership

    Long-term operating and maintenance costs

    Resale/lease potential or in the case of institutional buildings,

    long-term use plans Analysis of capital and operating cost versus sales or occupancy and profitability

    A5. Facility Requirements

    Facility size requirements are many times determined by applicable code and are often driven by occupancy.

    Note that this analysis is at the macro level. Some considerations are listed below:

    Number of occupants

    Volume

    Net and gross square footage by area uses

    Support infrastructure

    Classroom size Linear feet of display space

    Number of laboratory stations

    Occupant accommodation requirements (i.e., number of hospital beds, number of desks,

    number of workstations, on-site child care, on-site medical care, cot space, etc.)

    A6. Future Expansion/Alteration Considerations

    The possibility of expansion and/or alteration of the site and building should be considered for facility design.

    These considerations consist of a list of items that will facilitate the expansion or evolution of building use

    including adaptability/flexibility.

    Evaluation criteria may include:

    Provisions for site space in case of possible future expansion up or out

    Technologically advanced facility requirements

    Are departments or functional areas intended to grow in place during the future phase? If there will not be a future expansion of the building, how will departments or areas

    expand?

  • 8/2/2019 CII Bench Marking & Metrics

    9/53

    CII Benchmarking & Metrics

    (Project Questionnaire Version 9.0)

    Glossary of Terms

    Glossary of Terms Page 9

    Are any functional areas more likely than others to move out of the building in the future to

    allow others to expand or move in?

    Who will occupy the building in five, 10, 15, 20 years?

    Flexibility or adaptability for future uses.

    Future phasing plan

    A7. Site Selection Considerations

    Evaluation of sites should address issues relative to different locations (i.e., global, country, or local). This

    evaluation may take into consideration existing buildings or properties, as well as new locations. The

    selection criteria include items such as:

    General geographic location

    o Access to the targeted market area

    o Local availability and cost of skilled labor (e.g., construction, operation)

    o Available utilities

    o Existing facilities

    o Economic incentive zoneso Tax

    Land availability and developed costs

    Legal constraints

    Unusual financing requirements in region/locality

    Domestic culture vs. international culture

    Community relations

    Labor relations

    Government relations

    Political issues/constraints

    Education/training

    Safety and health considerations

    Environmental issues Symbolic and aesthetic

    Historic preservation

    Weather/climate

    Permitting Schedule

    A8. Project Objectives Statement

    This statement defines the project objectives and priorities for meeting the business strategy. It should be

    clear, concise, measurable, and specific to the project. It is desirable to obtain total agreement from the entire

    project team regarding these objectives and priorities to ensure alignment. Specifically, the priorities among

    cost, schedule, and value-added quality features should be clear. The objectives also should comply with any

    master plans if applicable.

    B. OWNER PHILOSOPHIES

    B1. Reliability Philosophy

  • 8/2/2019 CII Bench Marking & Metrics

    10/53

    CII Benchmarking & Metrics

    (Project Questionnaire Version 9.0)

    Glossary of Terms

    Glossary of Terms Page 10

    A brief description of the project intent in terms of reliability should be defined. A list of the general design

    principles to be considered to achieve optimum/ideal operating performance from the facility/building

    should be addressed. Considerations may include:

    Critical systems redundancy

    Architectural/structural/civil durability Mechanical/electrical/plumbing reliability

    B2. Maintenance Philosophy

    A list of the general design principles to be considered to meet building maintenance requirements should be

    identified. This evaluation should include life cycle cost analysis of major facilities. Considerations may

    include:

    Daily occupancy loads

    Maximum building occupancy requirements

    Equipment monitoring requirements

    Energy conservation programs Selection of materials and finishes

    Requirements for building finishes

    B3. Operating Philosophy

    A list of the general design issues that need to be considered to support routine operations should be

    developed. Issues may include:

    Operating schedule/hours

    Provisions for building rental or occupancy assignments (i.e., by room, floor, suite)

    including flexibility of partitioning

    Future renovation schedule User finish out philosophy

    Flexibility to change layout

    B4. Design Philosophy

    A listing of design philosophy issues should be developed. These issues should be directed at concerns such

    as the following:

    Design life

    Aesthetic requirements

    Compatibility with master plan

    Theme Image

    Environmentally sustainable design (internal/external)

    Quality of life

    C. PROJECT REQUIREMENTS

  • 8/2/2019 CII Bench Marking & Metrics

    11/53

    CII Benchmarking & Metrics

    (Project Questionnaire Version 9.0)

    Glossary of Terms

    Glossary of Terms Page 11

    C1. Value-Analysis Process

    A structured value analysis approach should be in place to consider design and material alternatives in terms

    of their cost effectiveness. Items that impact the economic viability of the project should be considered. Items

    to evaluate include issues such as:

    Discretionary scope issues

    Expensive materials of construction

    Life-cycle analysis of construction methods and structure

    C2. Project Design Criteria

    Project design criteria are the requirements and guidelines which govern the design of the project. Any design

    review board or design review process should be clearly articulated. Evaluation criteria may include:

    Level of design detail required

    Climatic data

    Codes and standardso National

    o Local

    o Owner specific

    o International

    Utilization of design standards

    o Owners

    o Contractorso Designers

    o Mixed

    Level of design detail required

    Donor or benefactor requirements

    Sole source requirements for equipment or systems Insurance underwriter requirements

    Cultural preferences

    C3. Evaluation of Existing Facilities

    If existing facilities are available, then a condition assessment must be performed to determine if they will

    meet facility requirements. Evaluation criteria may include:

    Capacity

    Power

    Utilities (i.e., potable water, gas, oil)

    Fire water Waste treatment/disposal

    Sanitary sewer

    Telecommunications

    Security

    Storm water containment system/filtration

    Access

  • 8/2/2019 CII Bench Marking & Metrics

    12/53

    CII Benchmarking & Metrics

    (Project Questionnaire Version 9.0)

    Glossary of Terms

    Glossary of Terms Page 12

    o Rail

    o ADA or local standards

    o Roads

    Parking areas

    Type and size of buildings/structures

    Amenitieso Food service

    o Ambulatory access

    o Medical facilities

    o Recreation facilities including public outdoor spaces

    o Change rooms

    Condition assessment of existing facilities and infrastructure

    Other

    C4. Scope of Work Overview

    This work statement overview is a complete narrative description of the project that is discipline-oriented and

    supports development of the project schedule and project cost estimate. It sets the limits of work by eachinvolved party and generally articulates their financial, task, and contractual responsibilities. It clearly states

    both assumptions and exclusions used to define the scope of work.

    C5. Project Schedule

    Ideally, the project schedule should be developed by the project team (owner, A/E, and construction

    contractor). It should include milestones, unusual schedule considerations and appropriate master schedule

    contingency time (float), procurement of long-lead or critical pacing equipment, and required submissions and

    approvals.

    C6. Project Cost Estimate

    The project cost estimate should address all costs necessary for completion of the project. This cost estimate

    may include the following:

    Construction contract estimate

    Professional fees Land cost

    Furnishings

    Administrative costs

    Contingencies

    Cost escalation for elements outside the project cost estimate

    Startup costs including installation

    Miscellaneous expenses including but not limited to:o Specialty consultants

    o Inspection and testing services

    o Bidding costs

    o Site clearance

    o Bringing utilities to the site

    o Environmental impact mitigation measures

  • 8/2/2019 CII Bench Marking & Metrics

    13/53

    CII Benchmarking & Metrics

    (Project Questionnaire Version 9.0)

    Glossary of Terms

    Glossary of Terms Page 13

    o Local authority permit fees

    o Occupant moving and staging costs

    o Utility costs during construction (if paid by owner)

    o Interest on borrowed funds (cost of money)

    o Site surveys, soils tests

    o Availability of construction laydown and storage at site or in remote or rented facilities

    SECTION II: BASIS OF DESIGN

    D. SITE INFORMATION

    D1. Site Layout

    The facility should be sited on the selected property. Layout criteria may include items such as:

    Access (e.g., road, rail, marine, air)

    Construction access

    Historical/cultural Trees and vegetation

    Site massing and context constraints or guidelines (i.e., how a building will look in three

    dimensions at the site)

    Access transportation parking, delivery/service, and pedestrian circulation considerations

    Open space, street amenities, urban context concerns Climate, wind, and sun orientation for natural lighting views, heat loss/gain, energy

    conservation, and aesthetic concerns

    D2. Site Surveys

    The site should be surveyed for the exact property boundaries, including limits of construction. A topography

    map with the overall plot and site plan is also needed. Evaluation criteria may include:

    Legal property descriptions with property lines

    Easements

    Rights-of-way

    Drainage patterns Deeds

    Definition of final site elevation

    Benchmark control systems

    Setbacks

    Access and curb cuts

    Proximity to drainage ways and flood plains

    Known below grade structures and utilities (both active and inactive) Trees and vegetation

    Existing facility locations and conditions

    Solar/shadows

    D3. Civil/Geotechnical Information

  • 8/2/2019 CII Bench Marking & Metrics

    14/53

    CII Benchmarking & Metrics

    (Project Questionnaire Version 9.0)

    Glossary of Terms

    Glossary of Terms Page 14

    The civil/geotechnical site evaluation provides a basis for foundation, structural, and hydrological design.

    Evaluations of the proposed site should include items such as:

    Depth to bedrock

    General site description (e.g., terrain, soils type, existing structures, spoil removal, areas of

    hazardous waste, etc.) Expansive or collapse potential of soils

    Fault line locations

    Spoil area for excess soil (i.e., location of on-site area or off-site instructions)

    Seismic requirements

    Water table elevation

    Flood plain analysis

    Soil percolation rate and conductivity

    Ground water flow rates and directions

    Need for soil treatment or replacement

    Description of foundation design options

    Allowable bearing capacities

    Pier/pile capacities Paving design options

    Overall site analysis

    D4. Governing Regulatory Requirements

    The local, state, and federal government permits necessary to construct and operate the facility should be

    identified. A work plan should be in place to prepare, submit, and track permit, regulatory, re-zoning, and

    code compliance for the project. It should include items such as:

    Construction

    Unique requirements

    Environmental Structural calculations

    Building height limits

    Setback requirements

    Fire

    Building Occupancy

    Special

    Signage

    Historical issues

    Accessibility

    Demolition

    Solar Platting

    Air/water

    Transportation

    The codes that will have a significant impact on the scope of the project should also be investigated and

    explained in detail. Particular attention should be paid to local requirements. Regulatory and code

  • 8/2/2019 CII Bench Marking & Metrics

    15/53

    CII Benchmarking & Metrics

    (Project Questionnaire Version 9.0)

    Glossary of Terms

    Glossary of Terms Page 15

    requirements may affect the defined physical characteristics and project cost estimate. The project schedule

    may be affected by regulatory approval processes. For some technically complex buildings, regulations may

    change frequently.

    D5. Environmental Assessment

    An environmental assessment should be performed for the site to evaluate issues that can impact the costestimate or delay the project. These issues may include:

    Archeological

    Location in an EPA air quality non-compliance zone

    Location in a wet lands area

    Environmental permits now in force

    Existing contamination

    Location of nearest residential area

    Ground water monitoring in place

    Downstream uses of ground water

    Existing environmental problems with the site

    Past/present use of site Noise/vibration requirements

    Air/water discharge requirements and options evaluated

    Discharge limits of sanitary and storm sewers identified

    Detention requirements

    Endangered species

    Erosion/sediment control

    D6. Utility Sources with Supply Conditions

    The availability/non-availability of site utilities needed to operate the facility with supply conditions of

    quantity, temperature, pressure, and quality should be evaluated. This may include items such as:

    Potable water

    Drinking water

    Cooling water

    Fire water

    Sewers Instrument air

    Facility air

    Heating water

    Gases

    Steam

    Electricity (voltage levels)

    Communications (e.g., data, cable television, telephones) Special requirement (e.g., deionized water or oxygen)

    D7. Site Life Safety Considerations

  • 8/2/2019 CII Bench Marking & Metrics

    16/53

    CII Benchmarking & Metrics

    (Project Questionnaire Version 9.0)

    Glossary of Terms

    Glossary of Terms Page 16

    Fire and life safety related items should be taken into account for the selected site. These items should

    include fire protection practices at the site, available firewater supply (amounts and conditions), and special

    safety requirements unique to the site. Evaluation criteria may include:

    Wind direction indicator devices (e.g., wind socks)

    Fire monitors and hydrants Flow testing

    Access and evacuation plan

    Available emergency medical facilities

    Security considerations (site illumination, access control)

    D8. Special Water and Waste Treatment Requirements

    On-site or pretreatment of water and waste should be evaluated. Items for consideration may include:

    Wastewater treatment

    Process waste

    Sanitary waste Waste disposal

    Storm water containment and treatment

    E. BUILDING PROGRAMMING

    E1. Program Statement

    The program statement identifies the levels of performance for the facility in terms of space planning and

    functional relationships. It should address the human, physical, and external aspects to be considered in the

    design. Each performance criteria should include these issues:

    A performance statement outlining what goals are to be attained (e.g., providing sufficientlighting levels to accomplish the specified task safely and efficiently)

    A measure that must be achieved (e.g., 200 foot-candles at surface of surgical table)

    A test which is an accepted approach to establish that the criterion has been met (e.g., using

    a standard light meter to do the job)

    E2. Building Summary Space List

    The summary space list includes all space requirements for the entire project. This list should address specific

    types and areas. Possible space listings include:

    Building population

    Administrative offices Lounges

    Food Service Cafeteria

    Conference rooms

    Vending alcoves

    Janitorial closets

    Elevators

  • 8/2/2019 CII Bench Marking & Metrics

    17/53

    CII Benchmarking & Metrics

    (Project Questionnaire Version 9.0)

    Glossary of Terms

    Glossary of Terms Page 17

    Stairs

    Loading docks

    Dwelling units

    Special technology considerations

    Classrooms

    Laboratories Corridors

    Storage facilities

    Mechanical rooms

    Electrical rooms

    Parking space

    Entry lobby

    Restrooms

    Data/computer areas

    A room data sheet should correspond to each entry on the summary space list. Room data sheets are discussed

    in element E11. The room data sheet contains information that is necessary for the summary space list. This

    list is used to determine assignable (usable) and non-assignable (gross) areas.

    E3. Overall Adjacency Diagrams

    The overall adjacency diagrams depict the layout of each department or division of the entire building. They

    show the relationship of specific rooms, offices, and sections. The adjacency diagrams must adequately

    convey the overall relationships between functional areas within the facility. Note that these diagrams are

    sometimes known as bubble diagrams or balloon diagrams. They are also commonly expressed in anadjacency matrix.

    E4. Stacking Diagrams

    A stacking diagram portrays each department or functional unit vertically in a multi-story building. Stackingdiagrams are drawn to scale, and they can help establish key design elements for the building. These diagrams

    are easily created with space lists and adjacency (or bubble) diagrams. Critical vertical relationships may

    relate to circulatory (stairs, elevators), structural elements, and mechanical or utility shafts. Stacking diagrams

    can establish building elements such as floor size. This type of diagram often combines functional adjacencies

    and space requirements and also shows how the project is sited.

    E5. Growth and Phased Development

    Provisions for future phases or anticipated use change must be considered during project programming. A

    successful initial phase necessitates a plan for the long term phases. The following phasing issues may be

    addressed.

    Guidelines to allow for additions (i.e., over-design of structural systems, joist layout,

    column spacing)

    Technology needs as facility grows and expands or changes (e.g., mechanical systems,

    water demands)

    Compare the additional costs involved with making the building expandable versus theprobability of the future expansion occurring as envisioned.

  • 8/2/2019 CII Bench Marking & Metrics

    18/53

    CII Benchmarking & Metrics

    (Project Questionnaire Version 9.0)

    Glossary of Terms

    Glossary of Terms Page 18

    Provisions for infrastructure that allow for future expansion

    E6. Circulation and Open Space Requirements

    An important component of space programming is common-area open spaces, both interior and exterior.These areas include the items listed and considerations such as:

    Exterior

    o Service dock areas and access

    o Circulation to parking areas

    o Passenger drop-off areas

    o Pedestrian walkways

    o Courtyards, plazas, or parks

    o Landscape buffer areas

    o Unbuildable areas (e.g., wetlands or slopes)

    o Sidewalks or other pedestrian routes

    o Bicycle facilitieso Lobbies and entries

    o Security considerations (e.g., card access or transmitters)

    o Snow removal plan

    o Postal and newspaper delivery

    o Waste removal

    o Fire and life-safety circulation considerations

    Interior

    o Interior aisle ways and corridors

    o Vertical circulation (i.e., personnel and material transport including elevators and

    escalators)

    o Directional and location signage

    E7. Functional Relationship Diagrams/Room by Room

    Room by room functional relationship diagrams show the structure of adjacencies of a group of rooms. With

    these adjacency diagrams (also known as bubble diagrams), the architect can convert them into a floor plan

    with all the relationships. Each space detail sheet should have a minimum of one functional relationshipdiagram. Rooms are often represented by circles, bubbles, squares, or rectangles. Larger rooms are

    represented with bigger symbols. They are also commonly expressed in an adjacency matrix.

    E8. Loading/Unloading/Storage Facilities Requirements

    list of requirements identifying materials to be unloaded and stored and products to be loaded along with

    their specifications. This list should include items such as:

    Storage facilities to be provided and/or utilized

    Refrigeration requirements and capabilities

    Mail/small package delivery

    Recycling requirements

  • 8/2/2019 CII Bench Marking & Metrics

    19/53

    CII Benchmarking & Metrics

    (Project Questionnaire Version 9.0)

    Glossary of Terms

    Glossary of Terms Page 19

    E9. Transportation Requirements

    Specifications for implementation of facility transportation (e.g., roadways, conveyers, elevators) as well as

    methods for receiving and shipping of materials (e.g., air, rail, truck, marine) should be identified. Provisions

    should be included for items such as:

    Facility access requirements based on transportation

    Drive-in doors

    Extended ramps for low clearance trailers

    Rail car access doors

    Service elevators

    Loading docks

    Temporary parking

    E10. Building Finishes

    Levels of interior and exterior finishes should be defined for the project. For example, the finishes may

    include categories such as:

    Interior Schedule:

    Type A

    o Floor: vinyl composition tile

    o Walls: painted

    Type B

    o Floor: direct glue carpet

    o Walls: vinyl wall covering

    Type C

    o Floor: carpet over pad

    o Walls: wood paneling

    Exterior Schedule: Type 1

    o Walls: brick

    o Trim: brick

    Type 2

    o Walls: overlapping masonryo Trim: cedar

    Finishes and local design standards are further defined in category F.

    E11. Room Data Sheets

    Room data sheets contain the specific requirements for each room considering its functional needs. A roomdata sheet should correspond to each room on the building summary space list. The format of the room data

    sheet should be consistent. Possible issues to include on room data sheets are:

    Critical dimensions

    Technical requirements (e.g., fireproof, explosion resistance, X-ray)

    Furnishing requirements

  • 8/2/2019 CII Bench Marking & Metrics

    20/53

    CII Benchmarking & Metrics

    (Project Questionnaire Version 9.0)

    Glossary of Terms

    Glossary of Terms Page 20

    Equipment requirements

    Audio/visual (A/V) data and communication provisions

    Lighting requirements

    Utility requirements

    Security needs including access/hours of operation

    Finish type Environmental issues

    Acoustics/vibration requirements

    Life-safety

    E12. Furnishings, Equipment, and Built-Ins

    All moveable furnishings, equipment, and built-ins should be listed on the room data sheets. Moveable and

    fixed in place equipment should be distinguished. Building modifications, such as wide access doors or high

    ceilings, necessary for any equipment also need to be listed. Long delivery time items should be identified

    and ordered early. It is critical to identify the utility impact of equipment (e.g., electrical, cooling, special

    water or drains, venting, radio frequency shielding). Examples may include:

    Furniture

    Kitchen equipment

    Medical equipment

    Material handling

    Partitions

    New items and relocated existing items must be distinguished in the program. The items can be classified in

    the following categories.

    New Items:

    Contractor furnished and contractor installed Owner furnished and contractor installed

    Owner furnished and owner installed

    Existing Items:

    Relocated as is and contractor installed

    Refurbished and installed by contractor

    Relocated as is and owner installed

    Refurbished and installed by owner

    E13. Window Treatment

    Any special fenestration window treatments for energy and/or light control should be noted in order to have

    proper use of natural light. Some examples include:

    Blocking of natural light

    Glare reducing windows

    Exterior louvers

  • 8/2/2019 CII Bench Marking & Metrics

    21/53

    CII Benchmarking & Metrics

    (Project Questionnaire Version 9.0)

    Glossary of Terms

    Glossary of Terms Page 21

    Interior blinds

    F. BUILDING/PROJECT DESIGN PARAMETERS

    F1. Civil/Site Design

    Civil/site design issues should be addressed to provide a basis for facility design. Issues to address may

    include:

    Service and storage requirements

    Elevation and profile views

    High point elevations for grade, paving, and foundations

    Location of equipment

    Minimum overhead clearances

    Storm drainage system

    Location and route of underground utilities

    Site utilities

    Earth work Subsurface work

    Paving/curbs

    Landscape/xeriscape

    Fencing/site security

    F2. Architectural Design

    Architectural design issue should be addressed to provide a basis for facility design. These issues may include

    the following:

    Determination of metric (hard/soft) versus Imperial (English) units (Note: The term hard

    metric means that materials and equipment are identified on the drawings and have to be delivered in metric-sized unit dimensions such as 200mm by 400mm. Soft metric means that materials and equipment can bedelivered using sizes that approximate the metric dimensions given on the drawings, such as three-inch length

    instead of eight cm. It is important to set these dimensions and not mix and match.)

    Requirements for building location/orientation horizontal and vertical Access requirements

    Nature/character of building design (e.g., aesthetics)

    Construction materials

    Acoustical considerations

    American with Disabilities Act requirements or other local access requirements

    Architectural Review Boards

    Planning and zoning review boards Circulation considerations

    Seismic design considerations

    Color/material standards

    Hardware standards

    Furniture, furnishings, and accessories criteria

    Design grid

  • 8/2/2019 CII Bench Marking & Metrics

    22/53

    CII Benchmarking & Metrics

    (Project Questionnaire Version 9.0)

    Glossary of Terms

    Glossary of Terms Page 22

    Floor to floor height

    F3. Structural Design

    Structural design considerations should be addressed to provide a basis for the facility design. These

    considerations may include the following:

    Structural system (e.g., construction materials, constraints)

    Seismic requirements

    Foundation system

    Corrosion control requirements/required protective coatings

    Client specifications (e.g., basis for design loads, vibration, deflection)

    Future expansion/flexibility considerations

    Design loading parameter (e.g., live/dead loads, design loads, collateral load capacity,

    equipment/material loads, wind/snow loads, uplift)

    Functional spatial constraints

    F4. Mechanical Design

    Mechanical design parameters should be developed to provide a basis for facility design. Items to consider

    include:

    Special ventilation or exhaust requirements

    Equipment/space special requirements with respect to environmental conditions (e.g., air

    quality, special temperatures)

    Energy conservation and life cycle costs

    Acoustical requirements

    Zoning and controls

    Air circulation requirements

    Outdoor design conditions (e.g., minimum and maximum yearly temperatures) Indoor design conditions (e.g., temperature, humidity, pressure, air quality)

    Building emissions control

    Utility support requirements

    System redundancy requirements

    Plumbing requirements Special piping requirements

    Seismic requirements

    F5. Electrical Design

    Electrical design parameters provide the basis for facility design. Consider items such as:

    Power sources with available voltage and amperage

    Special lighting considerations (e.g., lighting levels, color rendition)

    Voice, data, and video communications requirements

    Uninterruptable power source (UPS) and/or emergency power requirements

    Energy consumption/conservation and life cycle cost

    Ability to use daylight in lighting

  • 8/2/2019 CII Bench Marking & Metrics

    23/53

    CII Benchmarking & Metrics

    (Project Questionnaire Version 9.0)

    Glossary of Terms

    Glossary of Terms Page 23

    Seismic requirements

    Lightning/grounding requirements

    F6. Building Life Safety Requirements

    Building life safety requirements are a necessity for building operations. They should be identified at thisstage of the project. Possible safety requirements are listed below:

    Fire resistant requirements

    Explosion resistant requirements

    Area of refuge requirements in case of catastrophe

    Safety and alarm requirements

    Fire detection and/or suppression requirements

    Eye wash stations

    Safety showers

    Deluge requirements and foam

    Fume hoods

    Handling of hazardous materials Isolation facilities

    Sterile environments

    Emergency equipment access

    Personnel shelters

    Egress

    Public address requirements

    Data or communications protection in case of disaster or emergency

    Fall hazard protection

    Gas hazard detection

    F7. Constructability Analysis

    CII defines constructability as, the optimum use of construction knowledge and experience in planning,design, procurement, and field operations to achieve overall project objectives. Maximum benefits occur

    when people with construction knowledge and experience become involved at the very beginning of a

    project. Is there a structured approach for constructability analysis in place? Have provisions been made to

    provide this on an ongoing basis? This would include examining design options and details of constructionthat minimize construction costs while maintaining standards of safety, quality, and schedule. Elements of

    constructability during pre-project planning include:

    Constructability program in existence

    Construction knowledge/experience used in project planning

    Early construction involvement in contracting strategy development

    Developing a construction-sensitive project schedule Considering major construction methods in basic design approaches

    Developing site layouts for efficient construction

    Early identification of project team participants for constructability analysis

    Usage of advanced information technologies

    F8. Technological Sophistication

  • 8/2/2019 CII Bench Marking & Metrics

    24/53

    CII Benchmarking & Metrics

    (Project Questionnaire Version 9.0)

    Glossary of Terms

    Glossary of Terms Page 24

    The requirements for intelligent or special building systems should be evaluated. Examples of these systems

    may include:

    Video conferencing

    Internet connections Advanced audio/visual (A/V) connections

    Personnel sensing

    Computer docking stations

    Smart heating or air-conditioning Intercommunication systems

    Security systems

    Communication systems

    Conveyance systems

    G. EQUIPMENT

    G1. Equipment List

    Project-specific equipment should be defined and listed. (Note: Building systems equipment is addressed in

    element F4Mechanical Design and F5Electrical Design). In situations where owners are furnishing

    equipment, the equipment should be properly defined and purchased. The list should define items such as:

    Process

    Medical

    Food service/vending

    Trash disposal

    Distributed control systems

    Material handling

    Existing sources and characteristics of equipmento Relative sizes

    o Weights

    o Location

    o Capacities

    o Materials of constructiono Insulation and painting requirements

    o Equipment related access

    o Vendor, model, and serial number once identified

    o Equipment delivery time, if known

    G2. Equipment Location Drawings

    Equipment location/arrangement drawings identify the specific location of each item of equipment in a

    project. These drawings should identify items such as:

    Plan and elevation views of equipment and platforms

    Location of equipment rooms

    Physical support requirement (e.g., installation bolt patterns)

  • 8/2/2019 CII Bench Marking & Metrics

    25/53

    CII Benchmarking & Metrics

    (Project Questionnaire Version 9.0)

    Glossary of Terms

    Glossary of Terms Page 25

    Coordinates or location of all major equipment

    G3. Equipment Utility Requirements

    This evaluation should consist of a tabulated list of utility requirements for all major equipment items such as:

    Power and/or all utility requirements

    Flow diagrams

    Design temperature and pressure

    Diversity of use

    Gas

    Water

    SECTION III: EXECUTION APPROACH

    H. PROCUREMENT STRATEGY

    H1. Identify Long-lead/Critical Equipment and Materials

    Identify engineered equipment and material items with lead times that will impact the design for receipt of

    supplier information or impact the construction schedule with long delivery times.

    H2. Procurement Procedures and Plans

    Procurement procedures and plans include specific guidelines, special requirements, or methodologies for

    accomplishing the purchasing, expediting, and delivery of equipment and materials required for the project.

    Evaluation criteria may include:

    Who will perform procurement?

    Listing of approved vendors, if applicable Client or contractor purchase orders

    Reimbursement terms and conditions

    Guidelines for supplier alliances, single source, or competitive bids

    Guidelines for engineering/construction contracts

    Who assumes responsibility for owner-purchased items?o Financial

    o Shop inspection

    o Expediting

    Tax strategy

    o Depreciation capture

    o Local sales and use tax treatment

    o Investment tax credits Definition of source inspection requirements and responsibilities

    Definition of traffic/insurance responsibilities

    Definition of procurement status reporting requirements

    Additional/special owner accounting requirements

    Definition of spare parts requirements

    Local regulations (e.g., tax restrictions, tax advantages)

  • 8/2/2019 CII Bench Marking & Metrics

    26/53

    CII Benchmarking & Metrics

    (Project Questionnaire Version 9.0)

    Glossary of Terms

    Glossary of Terms Page 26

    Incentive/penalty strategy for contracts

    Storage

    J. DELIVERABLES

    J1. CADD/Model Requirements

    Computer Aided Drafting and Design (CADD) requirements should be defined. Evaluation criteria may

    include:

    o Software system required by client (e.g., AutoCAD, Intergraph)

    o Will the project be required to be designed using 2D or 3D CADD? Will rendering be

    required?

    o If 3D CADD is to be used, will a walk-through simulation be required?

    o Owner/contractor standard symbols and details

    o How will data be received and returned to/from the owner?

    o Disk

    o Electronic transfero Tape

    o Reproducibles

    o Full-size mock-ups

    Physical model requirements depend upon the type needed for analysis, such as study models or design

    checks.

    J2. Documentation/Deliverables

    Documentation and deliverables required during project execution should be identified. If electronic media

    are to be used, format and application packages should be outlined. The following items may be included in a

    list of deliverables:

    o Drawings and specifications

    o Project correspondence

    o Permits

    o Maintenance and operating information/startup procedureso Facility keys, keying schedules, and access codes

    o Project data books (quantity, format, contents, and completion date)

    o Equipment folders (quantity, format, contents, and completion date)

    o Design calculations (quantity, format, contents, and completion date)

    o Spare parts and maintenance stock (special forms)

    o Procuring documents/contract documents

    o Record (as-built) documentso Quality assurance documents

    o Project signage

    o Guarantees/warranties

    o Inspection documents

    o Certificates of inspection

    o Shop drawings and samples

  • 8/2/2019 CII Bench Marking & Metrics

    27/53

    CII Benchmarking & Metrics

    (Project Questionnaire Version 9.0)

    Glossary of Terms

    Glossary of Terms Page 27

    o Bonds

    o Distribution matrix

    K. PROJECT CONTROL

    K1. Project Quality Assurance and Control

    Quality assurance and quality control procedures need to be established. Responsibility for approvals needs to

    be developed. Electronic media requirements should be outlined. These issues may include:

    o Responsibility during design and construction

    o Testing of materials and workmanship

    o ISO 9000 requirements

    o Submittals and shop drawing approach

    o Inspection reporting requirements

    o Progress photos

    o Reviewing changes and modifications

    o Communication documents (e.g., RFIs, RFQs)o Commissioning tests

    o Lessons-learned feedback

    K2. Project Cost Control

    Procedures for controlling project cost need to be outlined and responsibility assigned. Electronic media

    requirements should be identified. These may include cost control requirements such as:

    o Financial (client/regulatory)

    o Phasing or area sub-accounting

    o Capital vs. non-capital expenditures

    o Report requirementso Payment schedules and procedures

    o Cash flow projections/draw down analysis

    o Cost code scheme/strategy

    o Costs for each project phase

    o Periodic control check estimateso Change order management procedure, including scope control

    K3. Project Schedule Control

    The project schedule is created to show progress and ensure that the project is completed on time. The

    schedule is necessary for design and construction of the building. A schedule format should be decided on at

    the beginning of the project. Typical items included in a project schedule are listed below.

    o Milestones

    o Unusual schedule considerations

    o Required submissions and/or approvals

    o Required documentation and responsible party

    o Baseline vs. progress to date

  • 8/2/2019 CII Bench Marking & Metrics

    28/53

    CII Benchmarking & Metrics

    (Project Questionnaire Version 9.0)

    Glossary of Terms

    Glossary of Terms Page 28

    o Long-lead or critical pacing equipment delivery

    o Critical path activities

    o Contingency or float timeo Permitting or regulatory approvals

    o Activation and commissioning

    o Liquidated damages/incentives

    The owner must also identify how special project issues will be scheduled. These items may include:

    o Selection, procurement, and installation of equipment

    o Design of interior spaces (including furniture and accessory selection)

    o Stages of the project that must be handled differently than the rest of the project

    o Tie-ins, service interruptions, and road closures

    K4. Risk Management

    Major project risks need to be identified, quantified, and management actions taken to mitigate problems

    developed. Pertinent elements may include:

    o Design risks

    o Expertise

    o Experience

    o Work load

    o Teamwork orientation

    o Communication

    o Integration and coordination

    o Construction risks

    o Availability of craft labor and construction materials

    o Weather

    o Differing/unforeseen/difficult site conditionso Long-lead item delays

    o Strikes

    o Inflation

    o Scope growth

    o Management riskso Availability of designers

    o Critical quality issues

    o Bidders

    o Human error

    o Cost and schedule estimates

    o Timely decisions

    o Team chemistryo Insurance considerations

    K5. Safety Procedures

    Safety procedures and responsibilities must be identified for design consideration and construction. Safety

    issues to be addressed may include:

  • 8/2/2019 CII Bench Marking & Metrics

    29/53

    CII Benchmarking & Metrics

    (Project Questionnaire Version 9.0)

    Glossary of Terms

    Glossary of Terms Page 29

    o Hazardous material handling

    o Interaction with the public

    o Working at elevations/fall hazards

    o Evacuation plans and procedures

    o Drug testingo First aid stations

    o Accident reporting and investigation

    o Pre-task planning

    o Safety orientation and planning

    o Safety incentives

    o Other special or unusual safety issues

    L. PROJECT EXECUTION PLAN

    L1. Project Organization

    The project team should be identified including roles, responsibilities, and authority. Items to considerinclude:

    o Core team members

    o Project manager assigned

    o Project sponsor assigned

    o Working relationships between participants

    o Communication channels

    o Organizational chart

    o Approval responsibilities/responsibility matrix

    L2. Owner Approval Requirements

    All documents that require owner approval should be clearly defined. These may include:

    o Milestones for drawing approval by phase

    o Comment

    o Approval

    o Bid issues (public or private)o Construction

    o Durations of approval cycle compatible with schedule

    o Individual(s) responsible for reconciling comments before return

    o Types of drawings/specifications

    o Purchase documents/general conditions and contract documents

    o Data sheets

    o Inquirieso Bid tabulations

    o Purchase orders

    o Supplier information

    L3. Project Delivery Method

  • 8/2/2019 CII Bench Marking & Metrics

    30/53

    CII Benchmarking & Metrics

    (Project Questionnaire Version 9.0)

    Glossary of Terms

    Glossary of Terms Page 30

    The methods of project design and construction delivery, including fee structure should be identified. Issues

    to consider include:

    o Owner self-performed

    o Designer and constructor qualification selection process

    o Selected methods (e.g., design/build, CM at risk, competitive sealed proposal, bridging,design-bid-build)

    o Contracting strategies (e.g., lump sum, cost-plus)

    o Design/build scope package considerations

    L4. Design/Construction Plan and Approach

    This is a documented plan identifying the specific approach to be used in designing and constructing the

    project. It should include items such as:

    o Responsibility matrix

    o Subcontracting strategy

    o Work week plan/schedule

    o Organizational structureo Work Breakdown Structure (WBS)

    o Construction sequencing of events

    o Site logistics plan

    o Safety requirements/program

    o Identification of critical activities that have potential impact on facilities (i.e., existing

    facilities, crane usage, utility shut downs and tie-ins, testing)

    o Quality assurance/quality control (QA/QC) plan

    o Design and approvals sequencing of events

    o Equipment procurement and staging

    o Contractor meeting/reporting schedule

    o Partnering or strategic alliances

    o Alternative dispute resolutiono Furnishings, equipment, and built-ins responsibility

    L5. Substantial Completion Requirements

    Substantial Completion (SC) is defined as the point in time when the building is ready to be occupied. Thefollowing may need to be addressed:

    o Have specific requirements for SC responsibilities been developed?

    o Have warranty, permitting, insurance, and tax implications been considered?

    o Commissioning

    o Equipment/systems startup and testing

    o Occupancy phasingo Final code inspection

    o Calibration

    o Verification

    o Documentation

    o Training

    o Acceptance

  • 8/2/2019 CII Bench Marking & Metrics

    31/53

    CII Benchmarking & Metrics

    (Project Questionnaire Version 9.0)

    Glossary of Terms

    Glossary of Terms Page 31

    o Landscape requirements

    o Punchlist completion plan and schedule

    o Substantial completion certificate

  • 8/2/2019 CII Bench Marking & Metrics

    32/53

    CII Benchmarking & Metrics

    (Project Questionnaire Version 9.0)

    Glossary of Terms

    Glossary of Terms Page 32

    PDRI (Project Definition Rating Index) Industrial

    SECTION I - BASIS OF PROJECT DECISION

    A. MANUFACTURING OBJECTIVES CRITERIA

    A1. Reliability Philosophy

    A list of the general design principles to be considered to achieve dependable operating performance from the

    unit. Evaluation criteria should include:

    Justification of spare equipment

    Control, alarm, and safety systems redundancy

    Extent of providing surge and intermediate storage capacity to permit independent shutdown

    of portions of the plant

    Mechanical / structural integrity of components (metallurgy, seals, types of couplings, bearing

    selection, etc.)

    A2. Maintenance Philosophy

    A list of the general design principles to be considered to meet unit up-time requirements. Evaluation criteria

    should include:

    Scheduled unit / equipment shutdown frequencies and durations

    Equipment access / monorails / cranes

    Maximum weight or size requirements for available repair equipment

    Equipment monitoring requirements (vibrations monitoring, etc.)

    A3. Operating Philosophy

    A list of the general design principles that need to be considered to support the routine scheduled production

    from the unit in order to achieve the projected overall on-stream time or service factor.

    Evaluation criteria should include:

    Level of operator coverage and automatic control to be provided

    Operating time sequence (ranging from continuous operation to five day, day shift only)

    Necessary level of segregation and clean out between batches or runs Desired unit turndown capability

    Design requirements for routine startup and shutdown

    B. BUSINESS OBJECTIVES

    B1. Products

    A list of product(s) to be manufactured and their specifications. It should address items such as:

    Chemical composition

  • 8/2/2019 CII Bench Marking & Metrics

    33/53

    CII Benchmarking & Metrics

    (Project Questionnaire Version 9.0)

    Glossary of Terms

    Glossary of Terms Page 33

    Allowable impurities

    Physical form

    By-products

    Raw materials

    Wastes

    B2. Market Strategy

    Has a market strategy been developed and clearly communicated? It must identify the driving forces (other

    than safety) for the project and specify what is most important from the viewpoint of the business group. It

    should address items such as:

    Cost

    Schedule

    Quality

    B3. Project Strategy

    Has a project strategy been defined that supports the market strategy in relation to the following items:

    Cost

    Schedule

    Quality

    B4. Affordability / Feasibility

    Have items that may improve the affordability of the project been considered? These should include

    incremental cost criteria such as:

    Consideration of feedstock availability and transport to the job site Performing an analysis of capital and operating cost versus sales and profitability

    Results of these studies should be communicated to the project team.

    B5. Capacities

    The design output of a given specification product from the unit. Capacities are usually defined as:

    On-stream factors

    Yield

    Design rate

    B6. Future Expansion Considerations

    A list of items to be considered in the unit design that will facilitate future expansion. Evaluation criteria

    should include:

    Providing space for a possible new reactor train

  • 8/2/2019 CII Bench Marking & Metrics

    34/53

    CII Benchmarking & Metrics

    (Project Questionnaire Version 9.0)

    Glossary of Terms

    Glossary of Terms Page 34

    Providing tie-ins to permit a duplicate or mirror image unit that can be added without

    necessitating a shutdown

    Guidelines for over design of structural systems to allow for additions

    B7. Expected Project Life Cycle

    This is the time period that the unit is expected to be able to satisfy the products and capacities required. Have

    requirements for ultimate disposal and dismantling been considered? These requirements should include:

    Cost of ultimate dismantling and disposal

    Dismantling equipment requirements

    Presence of contaminants

    Disposal of hazardous materials

    Possible future uses

    B8. Social Issues

    Evaluation of various social issues such as:

    Domestic culture vs. international culture

    Community relations

    Labor relations

    Government relations

    Education / training

    Safety and health considerations

    C. BASIC DATA RESEARCH & DEVELOPMENT

    C1. Technology

    The chemistry used to convert the raw materials supplied to the unit into the finished product. Proven

    technology involves least risk, while experimental technology has a potential for change. Technology can be

    evaluated as:

    Existing / proven Duplicate

    New

    Experimental

    C2. Processes

    A particular, specific sequence of steps to change the raw materials into the finished product. Provenprocesses involve the least risk, while experimental processes have a potential for change. Processes can be

    evaluated as:

    Existing / proven

    Duplicate

    New

  • 8/2/2019 CII Bench Marking & Metrics

    35/53

    CII Benchmarking & Metrics

    (Project Questionnaire Version 9.0)

    Glossary of Terms

    Glossary of Terms Page 35

    Experimental

    D. PROJECT SCOPE

    D1. Project Objectives Statement (Y/N)

    This is a mission statement that defines the project objectives and priorities for meeting the businessobjectives. It is important to obtain total agreement from the entire project team regarding these objectives

    and priorities to ensure alignment.

    D2. Project Design Criteria

    The requirements and guidelines which govern the design of the project. Evaluation criteria should

    include:

    Level of design detail required

    Climatic data

    Codes & standards

    National

    Local Utilization of engineering standards

    Owner's

    Contractor's

    Mixed

    D3. Site Characteristics Available vs. Required (Y/N)

    An assessment of the available vs. the required site characteristics. Evaluation criteria should include:

    Capacity

    Utilities

    Power Fire water

    Pipe racks

    Flare systems

    Waste treatment / disposal

    Cooling water Storm water containment system

    Type of buildings / structures

    Amenities

    Food service

    Recreation facilities

    Change rooms

    Ambulatory access Medical facilities

    Product shipping facilities

    Material receiving facilities

    Material storage facilities

    Product storage facilities

    Security

  • 8/2/2019 CII Bench Marking & Metrics

    36/53

    CII Benchmarking & Metrics

    (Project Questionnaire Version 9.0)

    Glossary of Terms

    Glossary of Terms Page 36

    D4. Dismantling and Demolition Requirements

    Has a scope of work been defined for the dismantling of existing equipment and/or piping which may be

    necessary for completing new construction? Evaluation criteria should include:

    Timing

    Permits

    Approval

    Safety requirements

    Hazardous operations

    Plant / operations requirements

    Narrative (scope of work) for each system

    Are the systems that will be dismantled...

    Named & marked on process flow diagrams

    Named & marked on P&ID's

    Denoted on line lists and equipment lists

    Denoted on piping plans or photo-drawings

    D5. Lead / Discipline Scope of Work

    This is a complete narrative description of the project, generally discipline oriented. This should be developed

    through the use of the Work Breakdown Structure (WBS) (Halpin et al. 1987).

    D6. Project Schedule (Y/N)

    Has the project milestone schedule been developed, analyzed, and agreed upon by the major project

    participants? This should involve obtaining early constructability input from:

    Operations

    Engineering

    Construction

    E. VALUE ENGINEERING

    E1. Process Simplification (Y/N)

    Identify activities (through studies, reviews, etc.) for reducing the number of steps or the amount of

    equipment needed in the process in order to optimize performance.

    E2. Design & Material Alternatives Considered / Rejected (Y/N)

    Is there a structured approach in place to consider design and material alternatives? Has it been implemented?

    E3. Design For Constructability Analysis

  • 8/2/2019 CII Bench Marking & Metrics

    37/53

    CII Benchmarking & Metrics

    (Project Questionnaire Version 9.0)

    Glossary of Terms

    Glossary of Terms Page 37

    Is there a structured approach for constructability analysis in place? Have provisions been made to provide

    this on an ongoing basis? This would include examining design options that minimize construction costs

    while maintaining standards of safety, quality, and schedule. CII defines constructability as, "the optimum use

    of construction knowledge and experience in planning, design, procurement, and field operations to achieve

    overall project objectives. Maximum benefits occur when people with construction knowledge and experience

    become involved at the very beginning of a project" (CII 1986).

    SECTION II - FRONT END DEFINITION

    F. SITE INFORMATION

    F1. Site Location (Y/N)

    Has the geographical location of the proposed project been defined? This involves an assessment of the

    relative strengths and weaknesses of alternate site locations. A site that meets owner requirements and

    maximizes benefits for the owner company should be selected. Evaluation of sites may address issues relative

    to different types of sites (i.e. global country, local, "inside the fence," or "inside the building"). This decision

    should consider the long-term needs of the owner company (CII 1995). The selection criteria should includeitems such as:

    General geographic location

    o Access to the targeted market area

    o Near sources of raw materials

    o Local availability and cost of skilled labor (e.g.

    construction, operation, etc.)

    o Available utilities

    o Existing facilities

    Land availability and costs

    Access (e.g. road, rail, marine, air, etc.)

    Construction access and feasibility Political constraints

    Legal constraints

    Regulatory constraints

    Financing requirements

    Social issues Weather

    Climate

    F2. Surveys & Soil Tests

    Survey and soil test evaluations of the proposed site should include items such as:

    Topography map

    Overall plant plot plan

    General site description (e.g. terrain, existing structures, spoil removal, areas of hazardous

    waste, etc.)

    Definition of final site elevation

    Benchmark control system

  • 8/2/2019 CII Bench Marking & Metrics

    38/53

    CII Benchmarking & Metrics

    (Project Questionnaire Version 9.0)

    Glossary of Terms

    Glossary of Terms Page 38

    Spoil area (i.e. location of on-site area or off-site instructions)

    Seismic requirements

    Water table

    Soil percolation rate & conductivity

    Existing contamination

    Ground water flow rates and directions Downstream uses of ground water

    Need for soil treatment or replacement

    Description of foundation types

    Allowable bearing capacities

    Pier / pile capacities

    F3. Environmental Assessment

    Evaluation of the site by characteristics such as:

    Location in an EPA air quality non-compliance zone

    Location in a wet lands area Environmental permits now in force

    Location of nearest residential area

    Ground water monitoring in place

    Containment requirements

    Existing environmental problems with the site

    Past / present use of site

    F4. Permit Requirements

    Is there a permitting plan in place? The local, state, and federal government permits necessary to construct

    and operate the unit should be identified. These should include items such as:

    Construction

    Fire

    Local

    Building

    Environmental Occupancy

    Transportation

    Special

    F5. Utility Sources With Supply Conditions

    Has a list been made identifying availability / nonavailability of site utilities needed to operate the unit withsupply conditions of temperature, pressure, and quality? This should include items such as:

    Potable water

    Instrument air

    Drinking water

    Plant air

  • 8/2/2019 CII Bench Marking & Metrics

    39/53

    CII Benchmarking & Metrics

    (Project Questionnaire Version 9.0)

    Glossary of Terms

    Glossary of Terms Page 39

    Cooling water

    Gases

    Fire water

    Steam

    Sewers

    Condensate Electricity (voltage levels)

    F6. Fire Protection & Safety Considerations

    A list of fire and safety related items to be taken into account in the design of the facility. These items should

    include fire protection practices at the site, available firewater supply (amounts and conditions), special safety

    requirements unique to the site, etc. Evaluation criteria should include:

    Eye wash stations

    Deluge requirements

    Safety showers

    Wind direction indicator Fire monitors & hydrants devices (i.e. wind socks)

    Foam

    Alarm systems

    Evacuation plan

    Medical facilities

    Security fencing

    G. PROCESS / MECHANICAL

    G1. Process Flow Sheets

    Drawings that provide the process description of the unit. Evaluation criteria should include:

    Major equipment items

    Flow of materials to and from the major equipment items

    Primary control loops for the major equipment items

    Sufficient information to allow sizing of all process lines

    G2. Heat & Material Balances

    Heat balances are tables of heat input and output for major equipment items (including all heat exchangers)

    within the unit. Material balances are tables of material input and output for all equipment items within the

    unit. The documentation of these balances should include:

    Special heat balance tables for reaction systems

    Information on the conditions (e.g. temperature and pressure)

    Volumetric amount (GPM, ACFM, etc.)

    G3. Piping and Instrumentation Diagrams (P&ID's)

  • 8/2/2019 CII Bench Marking & Metrics

    40/53

    CII Benchmarking & Metrics

    (Project Questionnaire Version 9.0)

    Glossary of Terms

    Glossary of Terms Page 40

    These are often referred to by different companies as:

    EFD's - Engineering Flow Diagrams

    MFD's - Mechanical Flow Diagrams

    PMCD's - Process & Mechanical Control Diagrams

    In general, P&ID's are considered to be a critical element within the scope definition package of an industrial

    project. Since incomplete information on P&ID's is frequently identified as a source of project escalation, it is

    important to understand their level of completeness. It often requires several iterations, or passes, to obtain all

    of the necessary information from each discipline specialist. During each iteration, additional information is

    added to the P&ID's. Thus, it is unlikely for P&ID's to be completely defined in a project's scope definition

    package.

    VALVES

    o Process needed valves

    o Valves needed for maintenance

    o Bypasses, blocks, and bleedso Drains, vents, freeze protection, etc.

    o Type of valve designated

    o Non-line sized valves indicated

    o Control valves sized

    o Miscellaneous designated valves added

    o Valve tags added (not always done)

    o Valve design details added (as necessary)

    PIPING SPECIALTY ITEMS

    o Identification of items

    o Numbering of items (usually by piping)o Specialty item design details (as necessary)

    UTILITIES

    o Main connections and continuationso Remaining connections and continuations

    o Overall distribution and control

    o Utilities design details

    INSTRUMENTATION

    o Elements, loops, and functionso Primary elements

    o Local panel or control house location

    o Control panel or CRT location

    o Computer inputs and outputs

    o Process steam traps (may be specialty items)

    o Hard wired interlocks

  • 8/2/2019 CII Bench Marking & Metrics

    41/53

    CII Benchmarking & Metrics

    (Project Questionnaire Version 9.0)

    Glossary of Terms

    Glossary of Terms Page 41

    o Motor controls (need schematics)

    o Type of primary elements

    o Instrument numbers

    o Uniform logic control details

    o Indicator lights

    o Instrumentation design details (as necessary)

    SAFETY SYSTEMS

    o Process Safety Management Hazard Analysis review

    o Key process relief valves

    o Remaining relief valves

    o Failure mode of control valves

    o Car sealed valves (as necessary)

    o Relief valve sizes (instrumentation / process check)

    o Relief system line sizes

    o System design details (as necessary)

    SPECIAL NOTATIONS

    o Identification of sloped lines

    o Barometric legs (seals)

    o Critical elevations and dimensions

    o Vendor or designer supplied notes

    o Critical locations (valves, etc.)

    o Notes on venting or draining

    o Vessel trim notes

    o Startup and shutdown notes

    o Design detail notes (as necessary)

    G4. Process Safety Management (PSM)

    This refers to OSHA Regulation 1910.119 compliance requirements. Has the owner clearly communicated

    the requirements, methodology, and responsibility for the various activities?

    G5. Utility Flow Diagrams

    Utility flow diagrams are similar to P&ID's in that they show all utility lines from generation or supply (i.e.

    pipeline). They are generally laid out in a manner to represent the geographical layout of the plant. Utility

    flow diagrams are evaluated using the same criteria as P&ID's.

    G6. Specifications

    General specifications for the design, performance, manufacturing, material, and code requirements

    should include items such as:

    o Classes of equipment (e.g. pumps, exchangers, vessels, etc.)

  • 8/2/2019 CII Bench Marking & Metrics

    42/53

    CII Benchmarking & Metrics

    (Project Questionnaire Version 9.0)

    Glossary of Terms

    Glossary of Terms Page 42

    o Process pipe heating

    o Process

    o Freeze

    o Jacketed

    o Process pipe cooling

    o Jacketedo Traced

    o Piping

    o Protective coating

    o Insulation

    o Valves

    o Bolts / gaskets

    G7. Piping System Requirements

    Pipe stress criteria should be provided to establish guidelines for analysis of piping systems and equipment

    such as:

    o Allowable forces and moments on equipment

    o Graphical representation of piping line sizes that require analysis based on:

    o Temperature

    o Pressure

    o Cyclic conditions

    o Flex

    o Stress

    o Pulsation

    o Seismic

    G8. Plot Plan

    The plot plan will show the location of new work in relation to adjoining units. It should include items such

    as:

    o Plant grid system with coordinateso Unit limits

    o Gates & fences

    o Off-site facilities

    o Tank farms

    o Roads & access ways

    o Roads

    o Rail facilitieso Green space

    o Buildings

    o Major pipe racks

    o Laydown areas

    o Construction / fabrication areas

  • 8/2/2019 CII Bench Marking & Metrics

    43/53

    CII Benchmarking & Metrics

    (Project Questionnaire Version 9.0)

    Glossary of Terms

    Glossary of Terms Page 43

    G9. Mechanical Equipment List

    The mechanical equipment list should identify all mechanical equipment by tag number, in summary format,

    to support the project. The list should define items such as:

    o Existing sourceso Modified

    o Dismantled

    o Relocated

    o Rerated

    o New sources

    o Purchased new

    o Purchased used

    o Relative sizes

    o Weights

    o Location

    o Capacities

    o Materialso Power requirements

    o Flow diagrams

    o Design temperature and pressure

    o Insulation & painting requirements

    o Equipment related ladders and platforms

    G10.Line List

    The line list designates all pipe lines in the project (including utilities). It should include items such as:

    o Unique number for each line

    o Sizeo Termination

    o Origin

    o Reference drawing

    o Normal and upset operating

    o Temperatureo Pressure

    o Design temperature & pressure

    o Test requirements

    o Pipe specifications

    o Insulation requirements

    o Paint requirements

    G11.Tie-in List

    A list of all piping tie-ins to existing lines. It should include items such as:

    o Location

    o Insulation removal requirements

  • 8/2/2019 CII Bench Marking & Metrics

    44/53

    CII Benchmarking & Metrics

    (Project Questionnaire Version 9.0)

    Glossary of Terms

    Glossary of Terms Page 44

    o Decontamination requirements

    o Reference drawings

    o Pipe specifications

    o Timing / schedule

    o Type of tie-in / size

    o Hot tapo Cold cut

    o Flange

    o Screwed

    o Weld

    o Cut & weld

    G12.Piping Specialty Items List

    This list is used to specify in-line piping items not covered by piping material specifications. It should identify

    all special items by tag number, in summary format. It should include items such as:

    o Tag numberso Full purchase description

    o Quantities

    o Materials of construction

    o Piping plans referenced

    o P&ID's referenced

    o Piping details

    o Line / equipment numbers

    G13.Instrument Index

    This is a complete listing of all instruments by tag number. Evaluation criteria should include:

    o Tag number

    o Instrument type

    o Service

    o P&ID number

    o Manufacturero Model number

    o Line number

    o Relieving devices (e.g. relief valves, rupture disks, etc.)

    H. EQUIPMENT SCOPE

    H1. Equipment Status

    Has the equipment been defined, inquired, bid tabbed, or purchased? This includes all engineer