cii watercom case study aban power published by cii
TRANSCRIPT
WATERCOM
Objective
Install Air cooled condensers in place of water cooled condensers at ABAN POWER CO. LIMITED, Tanjavur, Tamilnadu
Eliminate fresh water consumption using air Cooled Condensers in place of conventional
cooling towers
Results
HowAchieved( incl. resources)
• Installed Air cooled condensers in place of conventional cooling Towers• Cost of the project : Rs 150 mill ion• Annual Cost saving : Rs 64 mill ion• Payback period : 28 months
Size of Prize188 mil l ion m3 per year(Based on more than 70 % of the CPP’s in India (14,000 MW) operate with wet Cooling towers)
Contact : ( Mr B V Udhayakumar, [email protected], Ph: 0435 - 2451199 )
WaterCom Best Practice Template
• Water savings 2 mil l ion m3/ year• Saving of Rs. 63 mil l ion per year• Reduction in Water Consumption by 2.4 m3/ MWh