city of sunnyvale · culvert and temporary bypass $7,007,000 : $7,300,000 . subtotal $17,924,000 ....
TRANSCRIPT
CITY OF SUNNYVALE
PRIMARY TREATMENT DESIGN
DESIGN INFORMATION MEMORANDUM NO. 12
PRELIMINARY CONSTRUCTION COST ESTIMATE
FINAL
November 2014
Prepared By:______________________ Katy Rogers, P.E.
Reviewed By:______________________ James Wickstrom, P.E.
2 7 0 0 Y G N A C I O V A L L E Y R O A D • S U I T E 3 0 0 • W A L N U T C R E E K , C A L I F O R N I A 9 4 5 9 8 • ( 9 2 5 ) 9 3 2 - 1 7 1 0 • F A X ( 9 2 5 ) 9 3 0 - 0 2 0 8 pw://Carollo/Documents/Client/CA/Sunnyvale/9265A10/DIMs/DIM 12-Construction Cost Estimate.docx
CITY OF SUNNYVALE
PRIMARY TREATMENT DESIGN
DESIGN INFORMATION MEMORANDUM NO. 12
PRELIMINARY CONSTRUCTION COST ESTIMATE
TABLE OF CONTENTS Page No.
1.0 PURPOSE .......................................................................................................... 12-1
2.0 BASIS OF COST ESTIMATE .............................................................................. 12-1
3.0 PRELIMINARY CONSTRUCTION COST ESTIMATE ......................................... 12-2
APPENDIX - Preliminary Construction Cost Estimate Breakdown
LIST OF TABLES Table 12.1 Construction Schedule Basis for Preliminary Cost Estimate ...................... 12-2 Table 12.2 Preliminary Construction Cost Estimate ..................................................... 12-3
November 2014 - FINAL i pw://Carollo/Documents/Client/CA/Sunnyvale/9265A10/DIMs/DIM 12-Construction Cost Estimate.docx
November 2014 - FINAL 12-1 pw://Carollo/Documents/Client/CA/Sunnyvale/9265A10/DIMs/DIM 12-Construction Cost Estimate.docx
Design Information Memorandum No. 12
PRELIMINARY CONSTRUCTION COST ESTIMATE
1.0 PURPOSE
The purpose of this Design Information Memorandum (DIM) is to present the preliminary engineer’s construction cost estimate for the primary treatment design project at the City of Sunnyvale’s Water Pollution Control Plant (WPCP). Please refer to the individual technical memoranda (TMs) included in the preliminary design report for detailed descriptions of the recommended project elements.
2.0 BASIS OF COST ESTIMATE
The preliminary engineer’s construction cost estimate is representative of a 10-percent level design cost estimate. The estimated construction costs presented in this DIM are based on preliminary layouts and preliminary unit sizes as developed in DIM Nos. 1 through 11. Other construction elements that may not be described in the DIMs but are required for the project, such as sitework, yard piping, yard structures, etc., are also included in the cost estimate.
The estimated construction costs were developed from preliminary quantity takeoffs, estimating guides, equipment manufacturers’ quotes, and construction costs of similar facilities at other locations. An estimating contingency of 25 percent is applied to the estimated construction costs to compensate for lack of design details known at this stage, uncertainties in bidding climate, and assumptions used in the estimating methods. A local sales tax of 8.75 percent is included for approximately half the estimated construction costs. A 10 percent factor is applied to the estimate to cover the contractor’s cost to meet the General Conditions of the specifications, including mobilization, demobilization, bonds, insurance, and field overhead. A 13 percent factor is applied to the estimate to cover the general contractor’s home office overhead and profit on the project.
Engineering, legal, and administration costs, as well as construction contingencies for contract change orders, are not included in the estimated construction costs.
While the estimated construction costs represent the average bidding conditions for this project, variations in bidding climate at the time that the facilities are constructed could affect actual construction costs. Furthermore, the size and character of the facilities will be refined during final design based on the most current operational information, evolving design concepts, and plant staff input. For these reasons, it is possible that the actual construction costs may be lower or higher than estimated.
An overall annual cost escalation of 3 percent per year was used to account for cost escalation to the mid-point of construction. For planning purposes, it is anticipated the
November 2014 - FINAL 12-2 pw://Carollo/Documents/Client/CA/Sunnyvale/9265A10/DIMs/DIM 12-Construction Cost Estimate.docx
project will be constructed in three packages. Table 12.1 summarizes the assumed construction start date, construction duration, and mid-point of construction date for each package.
Table 12.1 Construction Schedule Basis for Preliminary Cost Estimate Primary Treatment Design City of Sunnyvale
Package Construction Duration,
months Start of Construction Mid-Point of Construction
1 9 September 2015 June 2016
2 30 August 2016 February 2019
3 9 May 2019 February 2020
3.0 PRELIMINARY CONSTRUCTION COST ESTIMATE
Table 12.2 presents the preliminary construction cost estimate for the primary treatment design project. Detailed construction cost estimate breakdowns for each major element are included in the Appendix.
Table 12.2 Preliminary Construction Cost Estimate Primary Treatment Design City of Sunnyvale
Element No. Description
2014 Construction Cost(1)
Escalated Construction Cost(2)
Package 1 – Site Preparation
1 Demolition(3) $1,578,000 $1,644,000
2 Site Work(4) $9,339,000 $9,731,000
3 Culvert and Temporary Bypass(5) $7,007,000 $7,300,000
Subtotal $17,924,000 $18,675,000 Package 2 – Headworks and PSTs
1 Paving, Grading, Yard Piping, and Yard Structures(6)
$11,580,000 $12,724,000
2 Screening Facility(7) $7,571,000 $8,319,000
3 Grit & Screenings Handling Building(8)
$3,266,000 $3,589,000
4 Influent Pump Station(9) $8,702,000 $9,561,000
5 Grit Basins(10) $6,410,000 $7,043,000
6 Primary Sedimentation Tanks(11) $15,138,000 $16,634,000
7 CEPT Facility(12) $1,090,000 $1,198,000
8 Odor Control Facility(13) $2,536,000 $2,787,000
9 Headworks Electrical Building(14) $2,663,000 $2,926,000
10 Switchgear Building and Electrical & Instrumentation System(15)
$3,889,000 $4,274,000
11 Standby Generator(16) $1,709,000 $1,878,000
12 Exhaust Heat Recovery(17) $1,656,000 $1,819,000
13 Tunnel System(18) $3,899,000 $4,285,000
14 PE Pipeline From Plant to Ponds(19)
$0 $0
Subtotal $70,109,000 $77,037,000 Package 3 – Demolition and Site Restoration
1 Site Demolition(20) $2,393,000 $2,780,000
Subtotal $2,393,000 $2,780,000 Total $90,426,000 $98,492,000
November 2014 - FINAL 12-3 pw://Carollo/Documents/Client/CA/Sunnyvale/9265A10/DIMs/DIM 12-Construction Cost Estimate.docx
Table 12.2 Preliminary Construction Cost Estimate Primary Treatment Design City of Sunnyvale
Element No. Description
2014 Construction Cost(1)
Escalated Construction Cost(2)
Notes: (1) Construction cost in June 2014 dollars. (2) Construction cost to escalated midpoint of construction assuming a 3% annual inflation rate. (3) Includes demolition of the sludge dewatering beds, sludge area drain pump station, and paving,
lighting, and buried utilities in the existing sludge drying bed area. (4) Includes raising the project site area to finished grade (elevation 109.0 ±), surcharging site to
pre-consolidate soils, and removing earthen surcharge material. (5) Includes installation of a new box culvert to replace the storm drainage volume of the existing
drainage ditch located along the southeast edge of the plant. This element also includes temporary bypass pumping to facilitate construction of culvert.
(6) Includes yard piping, yard structures, electrical ductbanks, asphalt paving, site drainage facilities, and fencing.
(7) Includes a new screening facility with four bar screen channels and one bypass channel, one shaftless screw screenings conveyor, and two screenings washer/compactors.
(8) Includes a new two story building housing three grit washers, grit and screenings storage bins and an electrical room.
(9) Includes a new influent pump station with three wet well compartments and six non-clog dry pit submersible pumps located in a dry pit.
(10) Includes three grit basins with six grit slurry transfer pumps. (11) Includes six primary sedimentation tanks, an aerated primary influent channel, a primary
effluent channel, nine primary sludge pumps, four primary scum pumps and two aeration blowers.
(12) Includes a concrete containment area with two 8000 gallon ferric chloride storage tanks, two polymer storage totes, and associated chemical feed systems.
(13) Includes three packaged bioscrubbers on a concrete support pad with associated fans, ducting, control panels, and other appurtenances.
(14) Includes a concrete masonry block building housing 480 volt switchgear, MCCs, influent pump VFDs, switchboards, and PLC and communications cabinets. This element also includes two exterior 12 kV to 480 volt transformers.
(15) Includes a concrete masonry block building housing new 12 kV switchgear, switch gear controls, generator controls, switchgear battery system, and an ACS server room.
(16) Includes a 2000 kW, 12 kV, standby generator housed in a custom-built walk-in enclosure; an aboveground diesel fuel storage tank; and a generator load bank .
(17) Includes the addition of exhaust heat recovery system to the existing engine generators at the PGF facility and new engine generator controls.
(18) Includes a new below grade tunnel system designed for personnel entry with pipe supports, tunnel drainage system, lighting, and ventilation.
(19) Pending condition assessment of existing primary effluent pipeline. Work will not be included in Package 2.
(20) Includes removal of mechanical equipment and piping from the existing primary control building and primary sedimentation tanks, and demolition of the existing auxiliary pump station.
November 2014 - FINAL 12-4 pw://Carollo/Documents/Client/CA/Sunnyvale/9265A10/DIMs/DIM 12-Construction Cost Estimate.docx
Design Information Memorandum No. 12 APPENDIX – PRELIMINARY CONSTRUCTION COST
ESTIMATE BREAKDOWN
November 2014 - FINAL pw://Carollo/Documents/Client/CA/Sunnyvale/9265A10/DIMs/DIM 12-Construction Cost Estimate.docx
Design Information Memorandum No. 12 PACKAGE 1 – SITE PREPARATION
November 2014 - FINAL pw://Carollo/Documents/Client/CA/Sunnyvale/9265A10/DIMs/DIM 12-Construction Cost Estimate.docx
PROJECT : CITY OF SUNNYVALEPRIMARY TREATMENT DESIGNPRELIMINARY COST ESTIMATE - PACKAGE 1 - SITE PREPARATION ESTIMATED MIDPOINT OF CONSTRUCTION : 1/15/2016
JOB # : 9265A.10 COST ESTIMATE PREPARATION DATE : 8/28/2014JOB # : 9265A.10 COST ESTIMATE PREPARATION DATE : 8/28/2014ELEMENT : SUMMARY OF CONSTRUCTION COSTS BY : RN/MP
Rate of Annual Inflation: 3%Estimating Contingency: 25%
Sales Tax: 8.75%General Conditions: 10%
Contractor Overhead and Profit: 13%
ELEMENT # DESCRIPTION TOTAL
1 DEMOLITION $1,644,000
2 SITE WORK $9,731,000
3 CULVERT AND BYPASS $7 300 0003 CULVERT AND BYPASS $7,300,000
Total Estimated Construction Cost = $18,675,000
File: Package 1 - Conceptual Design Cost Estimate.xlsxTab: Summary
Page 1 of 7
PRELIMINARY COST ESTIMATE - PACKAGE 1 - SITE PREPARATION
PROJECT : PRIMARY TREATMENT DESIGN LOCATION FACTOR: 1.000CITY OF SUNNYVALE ESTIMATED MIDPOINT OF CONSTRUCTION : 1/15/2016
JOB # : COST ESTIMATE PREPARATION DATE : 8/26/2014
LOCATION : SUNNYVALE, CA BY : RN/MPELEMENT # : 1 REVIEWED BY: DHELEMENT : DEMOLITION
DIVISION DESCRIPTION QUAN UNIT UNIT COSTLOCATION FACTOR SUBTOTAL TOTAL
2 SITEWORK
Remove AC Paving 3,100 SY $8 1.000 $24,800Remove Dry Sludge and Haul Offsite from Sludge Lagoon 1750 CY $40 1.000 $70,000Remove miscellaneous concrete walls and curbs 1 LS $30,000 1.000 $30,000Remove existing lighting, conduits, and electrical boxes 1 LS $50,000 1.000 $50,000Remove existing Chain Link Fence 900 LF $8 1 000 $7 200Remove existing Chain Link Fence 900 LF $8 1.000 $7,200Tree Removal in Drainage Ditch 1 LS $25,000 1.000 $25,000Demolish Sludge Dewatering Beds and appurtenances 22,000 SF $30 1.000 $660,000Demolish Drain Pump Station 1 LS $30,000 1.000 $30,000Demolish Sludge Pump Station 300 SF $40 1.000 $12,000Demolish Drainage Piping in Sludge Lagoon 1 LS $15,000 1.000 $15,000Demolish Drainage Piping under Sludge Drying Beds 1 LS $15,000 1.000 $15,000Demolish 72" CMP in Ditch 170 LF $196 1.000 $34,000.00
Total, Div. 02000 $973,000
3 CONCRETE
NoneTotal, Div. 03000 $0
4 MASONRY
NoneTotal, Div. 04000 $0
5 METALS
NoneTotal, Div. 05000 $0
6 WOOD AND PLASTICS
NoneTotal, Div. 06000 $0
7 THERMAL AND MOISTURE PROTECTION
None
T t l Di 07000 $0Total, Div. 07000 $0
8 DOORS AND WINDOWS
NoneTotal, Div. 08000 $0
9 FINISHES
NoneTotal, Div. 09000 $0
10 SPECIALITIES
NoneTotal, Div 10000 $0
11 EQUIPMENT
NoneTotal, Div. 11000 $0
12 FURNISHING12 FURNISHING
NoneTotal, Div. 12000 $0
File: Package 1 - Conceptual Design Cost Estimate.xlsxTab: 1 ‐ Demolition
Page 1 of 6
PRELIMINARY COST ESTIMATE - PACKAGE 1 - SITE PREPARATION
PROJECT : PRIMARY TREATMENT DESIGN LOCATION FACTOR: 1.000CITY OF SUNNYVALE ESTIMATED MIDPOINT OF CONSTRUCTION : 1/15/2016
JOB # : COST ESTIMATE PREPARATION DATE : 8/26/2014
LOCATION : SUNNYVALE, CA BY : RN/MPELEMENT # : 1 REVIEWED BY: DHELEMENT : DEMOLITION
DIVISION DESCRIPTION QUAN UNIT UNIT COSTLOCATION FACTOR SUBTOTAL TOTAL
13 SPECIAL CONSTRUCTION
NoneTotal, Div. 13000 $0
14 CONVEYING SYSTEMS
NNoneTotal, Div. 14000 $0
15 MECHANICAL
NoneTotal, Div. 15000 $0
16 ELECTRICAL
NoneTotal, Div. 16000
17 INSTRUMENTATION
NoneTotal, Div. 17000
SUBTOTAL $973,000
Estimating Contingency 25% $243,250SUBTOTAL $1,216,250
Sales Tax on 50% of Subtotal Above 8.75% $53,211SUBTOTAL $1,269,461
General Conditions 10% $126,946SUBTOTAL $1,396,407
General Contractor Overhead and Profit 13% $181,533SUBTOTAL $1,577,940
Escalation to Mid-Point (at 3% Annual Inflation Rate) 4.19% $66,136
ELEMENT CONSTRUCTION COST $1,644,000
File: Package 1 - Conceptual Design Cost Estimate.xlsxTab: 1 ‐ Demolition
Page 2 of 6
PRELIMINARY COST ESTIMATE - PACKAGE 1 - SITE PREPARATION
PROJECT : PRIMARY TREATMENT DESIGN LOCATION FACTOR: 1.000CITY OF SUNNYVALE ESTIMATED MIDPOINT OF CONSTRUCTION : 1/15/2016
JOB # : COST ESTIMATE PREPARATION DATE : 8/26/2014
LOCATION : SUNNYVALE, CA BY : RN/MPELEMENT # : 2 REVIEWED BY: DHELEMENT : SITE WORK
DIVISION DESCRIPTION QUAN UNIT UNIT COSTLOCATION FACTOR SUBTOTAL TOTAL
2 SITEWORK
Site Clearing and Grubbing (incld drainage ditch clear and grub) 1 LS $25,000 1.000 $25,000Finish Grading to drain to existing site waste PS 1 LS $15,000 1.000 $15,000Ditch Dewatering (prior to filling and to remove 72" CMP) 1 LS $10,000 1.000 $10,000Utility Polholing 1 LS $10,000 1.000 $10,000Import and Place Fill over Drainage Ditch to Elevation 109 25 000 CY $24 9 1 000 $623 000Import and Place Fill over Drainage Ditch to Elevation 109 25,000 CY $24.9 1.000 $623,000Import and Place Fill for Package 2 Facilities to Elevation 109 58,000 CY $24.9 1.000 $1,445,360Import and Place Fill for Aeration Basin to Elevation 109 43,000 CY $24.9 1.000 $1,071,560Import and Place Fill to preload site for Package 2 Facilities 42,000 CY $23.8 1.000 $1,001,280Vertical drains to fasten pre-consolidation 1 LS $430,000 1.000 $430,000Export preload 42,000 CY $18 1.000 $756,000Storm water management at construction site 1 LS $25,000 1.000 $25,000Temporary Fence 1 LS $28,600 1.000 $28,600Contractor Access Gate 1 EA $6,000 1.000 $6,000Access Gate 1 EA $8,000 1.000 $8,000Chain Link Fence 1,300 LF $50 1.000 $65,000
Total, Div. 02000 $5,519,800
3 CONCRETE
Sidewalk outside of fence 115 CY $700 1.000 $80,500Segmental Retaining Wall 3,400 SF $40 1.000 $136,000
Total, Div. 03000 $216,500
4 MASONRY
NoneT l Di 04000 $0Total, Div. 04000 $0
5 METALS
NoneTotal, Div. 05000 $0
6 WOOD AND PLASTICS
NoneTotal, Div. 06000 $0
7 THERMAL AND MOISTURE PROTECTION
NoneTotal, Div. 07000 $0
8 DOORS AND WINDOWS
NoneTotal, Div. 08000 $0
9 FINISHES9 FINISHES
NoneTotal, Div. 09000 $0
10 SPECIALITIES
NoneTotal, Div 10000 $0
11 EQUIPMENT
NoneTotal, Div. 11000 $0
File: Package 1 - Conceptual Design Cost Estimate.xlsxTab: 2 ‐ Site Work
Page 3 of 6
PRELIMINARY COST ESTIMATE - PACKAGE 1 - SITE PREPARATION
PROJECT : PRIMARY TREATMENT DESIGN LOCATION FACTOR: 1.000CITY OF SUNNYVALE ESTIMATED MIDPOINT OF CONSTRUCTION : 1/15/2016
JOB # : COST ESTIMATE PREPARATION DATE : 8/26/2014
LOCATION : SUNNYVALE, CA BY : RN/MPELEMENT # : 2 REVIEWED BY: DHELEMENT : SITE WORK
DIVISION DESCRIPTION QUAN UNIT UNIT COSTLOCATION FACTOR SUBTOTAL TOTAL
12 FURNISHING
NoneTotal, Div. 12000 $0
13 SPECIAL CONSTRUCTION
NNoneTotal, Div. 13000 $0
14 CONVEYING SYSTEMS
NoneTotal, Div. 14000 $0
15 MECHANICAL
NoneTotal Div 15000 $0Total, Div. 15000 $0
16 ELECTRICAL
Access gate electrical/security gate/key pad 1 LS $20,000 1.000 $20,000Total, Div. 16000 $20,000
17 INSTRUMENTATION
Access gate instrumentation 1 LS $2,500 1.000 $2,500$2,500
Total, Div. 17000 $0
SUBTOTAL $5,758,800
Estimating Contingency 25% $1,439,700SUBTOTAL $7,198,500
Sales Tax on 50% of Subtotal Above 8.75% $314,934SUBTOTAL $7,513,434
General Conditions 10% $751,343SUBTOTAL $8 264 778SUBTOTAL $8,264,778
General Contractor Overhead and Profit 13% $1,074,421SUBTOTAL $9,339,199
Escalation to Mid-Point (at 3% Annual Inflation Rate) 4% $391,433
ELEMENT CONSTRUCTION COST $9,731,000
File: Package 1 - Conceptual Design Cost Estimate.xlsxTab: 2 ‐ Site Work
Page 4 of 6
PRELIMINARY COST ESTIMATE - PACKAGE 1 - SITE PREPARATION
PROJECT : PRIMARY TREATMENT DESIGN LOCATION FACTOR: 1.000CITY OF SUNNYVALE ESTIMATED MIDPOINT OF CONSTRUCTION : 1/15/2016
JOB # : COST ESTIMATE PREPARATION DATE : 8/26/2014
LOCATION : SUNNYVALE, CA BY : RN/MPELEMENT # : 3 REVIEWED BY: DHELEMENT : CULVERT AND TEMPORARY BYPASS
DIVISION DESCRIPTION QUAN UNIT UNIT COSTLOCATION FACTOR SUBTOTAL TOTAL
2 SITEWORK
Excavation down from elevation 109 17,102 CY $7 1.000 $119,714Sheet Piles 35,860 SF $29 1.000 $1,039,940
Dewatering (during temporary bypass PS and Culvert construction) 1 LS $100,000 1.000 $100,000Temporary Rerouting SD pipes from Culvert Sides 1 LS $40 000 1 000 $40 000Temporary Rerouting SD pipes from Culvert Sides 1 LS $40,000 1.000 $40,000Backfill over Culvert 13,480 CY $8 1.000 $107,840Export Dirt 3,622 CY $18 1.000 $65,196168" x 84" Culvert aggregate base 543 CY $46 1.000 $24,993
Total, Div. 02000 $1,497,683
3 CONCRETE
168" x 84" precast, double barrel concrete culvert (mtrl to site) 815 LF $800 1.000 $652,000Box Culvert Installation 1 LS $270,000 1.000 $270,000Culvert Headwall 40 CY $1,200 1.000 $48,000Culvert Headwall 40 CY $1,200 1.000 $48,000Miscellaneous Concrete 1 LS $10,000 1.000 $10,000Bypass Pump Station Structure 1 LS $200,000 1.000 $200,000
Total, Div. 03000 $1,180,000
4 MASONRY
None
Total, Div. 04000 $0
5 METALS
Miscellaneous Metals 1 LS $5,000 1.000 $5,000
Total, Div. 05000 $5,000
6 WOOD AND PLASTICS
None
Total Div 06000 $0Total, Div. 06000 $0
7 THERMAL AND MOISTURE PROTECTION
None
Total, Div. 07000 $0
8 DOORS AND WINDOWS
NoneTotal, Div. 08000 $0, $0
9 FINISHES
Painting and Protective Coating 1 LS $7,500 1.000 $7,500Total, Div. 09000 $7,500
10 SPECIALITIES
Signs, Identification, Stenciling and Tagging System 1 LS $5,000 1.000 $5,000
Total, Div 10000 $5,000
File: Package 1 - Conceptual Design Cost Estimate.xlsxTab: 3 ‐ Culvert and Bypass
Page 5 of 6
PRELIMINARY COST ESTIMATE - PACKAGE 1 - SITE PREPARATION
PROJECT : PRIMARY TREATMENT DESIGN LOCATION FACTOR: 1.000CITY OF SUNNYVALE ESTIMATED MIDPOINT OF CONSTRUCTION : 1/15/2016
JOB # : COST ESTIMATE PREPARATION DATE : 8/26/2014
LOCATION : SUNNYVALE, CA BY : RN/MPELEMENT # : 3 REVIEWED BY: DHELEMENT : CULVERT AND TEMPORARY BYPASS
DIVISION DESCRIPTION QUAN UNIT UNIT COSTLOCATION FACTOR SUBTOTAL TOTAL
11 EQUIPMENT
Installation of bypass pump station and piping, and removal 1 LS $266,758 1.000 $266,758Standby temp. bypass pumping rental during wet weather season 8 mon. $121,071 1.000 $968,571Fuel for pump 65,000 gal $5 1.000 $325,000
Total, Div. 11000 $1,560,329
12 FURNISHING
NoneTotal, Div. 12000 $0
13 SPECIAL CONSTRUCTION
NoneTotal, Div. 13000 $0
14 CONVEYING SYSTEMS14 CONVEYING SYSTEMS
Connect culvert to 72" CMP and existing ForeBay pump station 1 LS $25,000 1.000 $25,000
Total, Div. 14000 $25,000
15 MECHANICAL
Existing STD pipe connections to new culvert 4 EA $7,500 1.000 $30,000Connect existing 12" SD to culvert 1 EA $10,000 1.000 $10,000
Total, Div. 15000 $40,00016 ELECTRICAL
NoneTotal, Div. 16000
17 INSTRUMENTATION
NoneTotal, Div. 17000
SUBTOTAL $4 320 513SUBTOTAL $4,320,513
Estimating Contingency 25% $1,080,128SUBTOTAL $5,400,641
Sales Tax on 50% of Subtotal Above 8.75% $236,278SUBTOTAL $5,636,919
General Conditions 10% $563,692SUBTOTAL $6,200,611
General Contractor Overhead and Profit 13% $806 079General Contractor Overhead and Profit 13% $806,079SUBTOTAL $7,006,690
Escalation to Mid-Point (at 3% Annual Inflation Rate) 4% $293,671
ELEMENT CONSTRUCTION COST $7,300,000
File: Package 1 - Conceptual Design Cost Estimate.xlsxTab: 3 ‐ Culvert and Bypass
Page 6 of 6
Design Information Memorandum No. 12 PACKAGE 2 – HEADWORKS AND PSTS
November 2014 - FINAL pw://Carollo/Documents/Client/CA/Sunnyvale/9265A10/DIMs/DIM 12-Construction Cost Estimate.docx
PROJECT : CITY OF SUNNYVALE
PRIMARY TREATMENT DESIGN
PRELIMINARY COST ESTIMATE - PACKAGE 2 - HEADWORKS AND PSTS ESTIMATED MIDPOINT OF CONSTRUCTION : 11/3/2017
JOB # : 9265A.10 COST ESTIMATE PREPARATION DATE : 8/28/2014ELEMENT : SUMMARY OF CONSTRUCTION COSTS BY : MK/RN/MP
Midpoint of Construction: 11/3/2017Rate of Annual Inflation: 3%Estimating Contingency: 25%
Sales Tax: 8.75%General Conditions: 10%
Contractor Overhead and Profit: 13%
ELEMENT # DESCRIPTION TOTAL
1 PAVING, GRADING, YARD PIPING, AND YARD STRUCTURES $12,724,000
2 SCREENING FACILITY $8,319,000
3 GRIT & SCREENINGS HANDLING FACILITY $3,589,000
4 INFLUENT PUMP STATION $9,561,000
5 GRIT BASINS $7,043,000
6 PRIMARY SEDIMENTATION TANKS $16,634,000
7 CEPT FACILITY $1,198,000
8 ODOR CONTROL FACILITY $2,787,000
9 HEADWORKS ELECTRICAL BUILDING $2,926,000
10 SWITCHGEAR BUILDING AND ELECTRICAL & INSTRUMENTATION SYSTEM $4,274,000
11 STANDBY GENERATOR $1,878,000
12 EXHAUST HEAT RECOVERY $1,819,000
13 TUNNEL SYSTEM $4,285,000
14 PE PIPELINE FROM PLANT TO PONDS $0
Total Estimated Construction Cost = $77,037,000
File: Package 2 - Conceptual Design Cost Estimate.xlsTab: Summary
Page 1 of 37
PRELIMINARY COST ESTIMATE - PACKAGE 2 - HEADWORKS AND PSTS
PROJECT : PRIMARY TREATMENT DESIGN LOCATION FACTOR: 1.000
CITY OF SUNNYVALE ESTIMATED MIDPOINT OF CONSTRUCTION : 11/3/2017
JOB # : 9265A.10 COST ESTIMATE PREPARATION DATE : 8/28/2014
LOCATION : SUNNYVALE, CA BY : RN
ELEMENT # : 1 REVIEWED BY: DH
ELEMENT : PAVING, GRADING, YARD PIPING, AND YARD STRUCTURES KC
DIVISION DESCRIPTION QUAN UNIT UNIT COST
LOCATION
FACTOR SUBTOTAL TOTAL
2 SITEWORK
Excavations
60" PI 178 CY $17 1.000 $2,971
60" PE 4990 CY $17 1.000 $83,383
42" FA 15 CY $17 1.000 $25536" FA 227 CY $17 1.000 $3,791
30" PI 241 CY $17 1.000 $4,023
24" STD 267 CY $17 1.000 $4,45624" FA 78 CY $17 1.000 $1,30018" STD 519 CY $17 1.000 $8,664
16" FA 6 CY $17 1.000 $102
12" TD 948 CY $17 1.000 $15,844
12" STD 954 CY $17 1.000 $15,943
12" SD 948 CY $17 1.000 $15,844
UW, PW, SA 1800 CY $17 1.000 $30,078
66" SS' 2396 CY $17 1.000 $40,030
66" SS Manholes 62 CY $17 1.000 $1,040
Pipe Embedment
60" PI 80 CY $40 1.000 $3,203
60" PE 1620 CY $40 1.000 $64,782
42" FA 7 CY $40 1.000 $291
36" FA 116 CY $40 1.000 $4,638
30" PI 130 CY $40 1.000 $5,205
24" STD 110 CY $40 1.000 $4,398
24" FA 40 CY $40 1.000 $1,60424" FA 40 CY $40 1.000 $1,604
18" STD 226 CY $40 1.000 $9,059
16" FA 3 CY $40 1.000 $133
12" TD 332 CY $40 1.000 $13,290
12" STD 334 CY $40 1.000 $13,373
12" SD 332 CY $40 1.000 $13,290
66" SS' 694 CY $40 1.000 $27,768
UW, PW, SA 700 CY $40 1.000 $28,000
Backfill
60" PI 53 CY $28 1.000 $1,478
60" PE 365 CY $28 1.000 $10,114
42" FA 4 CY $28 1.000 $113
36" FA 65 CY $28 1.000 $1,796
30" PI 74 CY $28 1.000 $2,052
24" STD 133 CY $28 1.000 $3,695
24" FA 26 CY $28 1.000 $719
18" STD 259 CY $28 1.000 $7,184
16" FA 2 CY $28 1.000 $62
12" TD 593 CY $28 1.000 $16,421
12" STD 596 CY $28 1.000 $16,523
12" SD 593 CY $28 1.000 $16,421
UW, PW, SA 1100 CY $28 1.000 $30,481
66" SS' 1497 CY $28 1.000 $41,488
Hauling Excavated Material
60" PI 124 CY $11 1.000 $1,369
60" PE 2494 CY $11 1.000 $27,434
42" FA 11 CY $11 1.000 $123
36" FA 162 CY $11 1.000 $1,782
30" PI 166 CY $11 1.000 $1,826
24" STD 133 CY $11 1.000 $1,467
24" FA 52 CY $11 1.000 $570
18" STD 259 CY $11 1.000 $2,852
16" FA 4 CY $11 1.000 $43
12" TD 356 CY $11 1.000 $3,911
12" STD 358 CY $11 1.000 $3,936
File: Package 2 - Conceptual Design Cost Estimate.xlsTab: 1
Page 2 of 37
PRELIMINARY COST ESTIMATE - PACKAGE 2 - HEADWORKS AND PSTS
PROJECT : PRIMARY TREATMENT DESIGN LOCATION FACTOR: 1.000
CITY OF SUNNYVALE ESTIMATED MIDPOINT OF CONSTRUCTION : 11/3/2017
JOB # : 9265A.10 COST ESTIMATE PREPARATION DATE : 8/28/2014
LOCATION : SUNNYVALE, CA BY : RN
ELEMENT # : 1 REVIEWED BY: DH
ELEMENT : PAVING, GRADING, YARD PIPING, AND YARD STRUCTURES KC
DIVISION DESCRIPTION QUAN UNIT UNIT COST
LOCATION
FACTOR SUBTOTAL TOTAL
12" SD 356 CY $11 1.000 $3,911
66" SS' 898 CY $11 1.000 $9,882
Site Clearing and Grubbing 1 LS $20,000 1.000 $20,000
AC Paving including Subgrade 164000 SF $3 1.000 $492,000
AB Road 22000 SF $1.50 1.000 $33,000
Finish Grading 1 LS $15,000 1.000 $15,000
Groundwater Dewatering 1 LS $100,000 1.000 $100,000
Utility Potholing 1 LS $30,000 1.000 $30,000
Relocate Existing Utilities for utilidor / piping 1 LS $50,000 1.000 $50,000
Bollards 50 EA $1,600 1.000 $80,000
66" SS Shoring 9,240 SF $29 1.000 $267,960
Miscellaneous shoring 3,200 SF $29 1.000 $92,800
Jacking Pit 1 LS $120,000 1.000 $120,000
Receiving Pit 1 LS $60,000 1.000 $60,000
Ground Improvements for 72" Casing Installations 180 LF $1,000 1.000 $180,000
6' tall Chain Link Fence (Baylands to PE Distribution Box) 600 LF $35 1.000 $21,000
24' wide Access Gate 1 EA $7,500 1.000 $7,500
24' wide Construction Access Gate 1 EA $7,500 1.000 $7,500
Total, Div. 02000 $2,201,167
3 CONCRETE
Influent Junction Box 1 LS $200,000 1.000 $200,000
PE Junction Manhole 1 LS $75,000 1.000 $75,000
PE Junction Box 1 LS $200,000 1.000 $200,000
66" SS Manholes 2 EA $45,000 1.000 $90,000
60" PE Manholes for Tunneling 2 EA $75,000 1.000 $150,00060" PE Manholes for Tunneling 2 EA $75,000 1.000 $150,000
Storm Drain Manholes 12 EA $8,000 1.000 $96,000
Catch Basins 12 EA $3,500 1.000 $42,000
Curb and Gutter 1400 LF $35 1.000 $49,000
Valley Gutter 30 LF $60 1.000 $1,800
Miscellaneous Concrete 1 LS $10,000 1.000 $10,000
Miscellaneous Sidewalks 1 LS $40,000 1.000 $40,000
Total, Div. 03000 $953,800
4 MASONRY
None
Total, Div. 04000 $0
5 METALS
Miscellaneous Metals 1 LS $20,000 1.000 $20,000
Total, Div. 05000 $20,000
6 WOOD AND PLASTICS
None
Total, Div. 06000 $0
7 THERMAL AND MOISTURE PROTECTION
None
Total, Div. 07000 $0
8 DOORS AND WINDOWS
File: Package 2 - Conceptual Design Cost Estimate.xlsTab: 1
Page 3 of 37
PRELIMINARY COST ESTIMATE - PACKAGE 2 - HEADWORKS AND PSTS
PROJECT : PRIMARY TREATMENT DESIGN LOCATION FACTOR: 1.000
CITY OF SUNNYVALE ESTIMATED MIDPOINT OF CONSTRUCTION : 11/3/2017
JOB # : 9265A.10 COST ESTIMATE PREPARATION DATE : 8/28/2014
LOCATION : SUNNYVALE, CA BY : RN
ELEMENT # : 1 REVIEWED BY: DH
ELEMENT : PAVING, GRADING, YARD PIPING, AND YARD STRUCTURES KC
DIVISION DESCRIPTION QUAN UNIT UNIT COST
LOCATION
FACTOR SUBTOTAL TOTAL
None
Total, Div. 08000 $0
9 FINISHES
Painting and Protective Coating 1 LS $10,000 1.000 $10,000
Total, Div. 09000 $10,000
10 SPECIALTIES
Signs, Identification, Stenciling and Tagging System 1 LS $15,000 1.000 $15,000
Total, Div 10000 $15,000
11 EQUIPMENT
None
Total, Div. 11000 $0
12 FURNISHING
None
Total, Div. 12000 $0
13 SPECIAL CONSTRUCTION13 SPECIAL CONSTRUCTION
Temporary Bypass Pumping 1 LS $200,000 1.000 $200,000
Total, Div. 13000 $200,000
14 CONVEYING SYSTEMS
None
Total, Div. 14000 $0
15 MECHANICAL
72" Casing Pipes (60" PE and Future Piping) 360 LF $2,400 1.000 $864,000
66" SS (RCP) 231 LF $528 1.000 $121,968
60" PI (RCP/Steel) 60 LF $480 1.000 $28,800
60" PE (RCP/Steel) 1350 LF $480 1.000 $648,000
42" FA (FRP) 35 LF $280 1.000 $9,800
36" FA (FRP) 175 LF $200 1.000 $35,000
30" PI (DIP) 200 LF $240 1.000 $48,000
24" STD (PVC) 200 LF $192 1.000 $38,400
24" FA (FRP) 100 LF $150 1.000 $15,000
18" STD (PVC) 540 LF $144 1.000 $77,760
16" FA (FRP) 10 LF $100 1.000 $1,000
12" TD (PVC) 800 LF $96 1.000 $76,800
12" STD (PVC) 805 LF $96 1.000 $77,280
12" SD (PVC) 800 LF $96 1.000 $76,800
Potable Water Yard Piping 1400 LF $70 1.000 $98,000
Utility Water Yard Piping 2000 LF $80 1.000 $160,000
Service Air Piping 1 LS $25,000 1.000 $25,000
6" Grit Slurry Piping 200 LF $200 1.000 $40,000
6" Primary Sludge and Scum Piping (Heat Traced) 650 LF $200 1.000 $130,000
Pipe Fittings, Valves, Couplings (5% of sum of piping LF costs) 1 LS $129,000 1.000 $129,000
Miscellaneous Piping 4" and Smaller 1 LS $20,000 1.000 $20,000
Miscellaneous Drain Piping 1 LS $20,000 1.000 $20,000
File: Package 2 - Conceptual Design Cost Estimate.xlsTab: 1
Page 4 of 37
PRELIMINARY COST ESTIMATE - PACKAGE 2 - HEADWORKS AND PSTS
PROJECT : PRIMARY TREATMENT DESIGN LOCATION FACTOR: 1.000
CITY OF SUNNYVALE ESTIMATED MIDPOINT OF CONSTRUCTION : 11/3/2017
JOB # : 9265A.10 COST ESTIMATE PREPARATION DATE : 8/28/2014
LOCATION : SUNNYVALE, CA BY : RN
ELEMENT # : 1 REVIEWED BY: DH
ELEMENT : PAVING, GRADING, YARD PIPING, AND YARD STRUCTURES KC
DIVISION DESCRIPTION QUAN UNIT UNIT COST
LOCATION
FACTOR SUBTOTAL TOTAL
Total, Div. 15000 $2,740,608
16 ELECTRICAL
Conduit/Ductbanks 1 LS $1,000,000 1.000 $1,000,000
Total, Div. 16000 $1,000,000
17 INSTRUMENTATION
None
Total, Div. 17000 $0
SUBTOTAL $7,140,575
Estimating Contingency 25% $1,785,144
SUBTOTAL $8,925,719
Sales Tax on 50% of Subtotal Above 8.75% $390,500
SUBTOTAL $9,316,220
General Conditions 10% $931,622
SUBTOTAL $10,247,842
General Contractor Overhead and Profit 13% $1,332,219General Contractor Overhead and Profit 13% $1,332,219
SUBTOTAL $11,580,061
Escalation to Mid-Point (at 3% Annual Inflation Rate) 9.88% $1,144,175
ELEMENT CONSTRUCTION COST $12,724,000
Note: No cost included for off-site PE pipe installation or rehabilitation
File: Package 2 - Conceptual Design Cost Estimate.xlsTab: 1
Page 5 of 37
PRELIMINARY COST ESTIMATE - PACKAGE 2 - HEADWORKS AND PSTS
PROJECT : PRIMARY TREATMENT DESIGN LOCATION FACTOR: 1.163
CITY OF SUNNYVALE ESTIMATED MIDPOINT OF CONSTRUCTION : 11/3/2017
JOB # : 9265A.10 COST ESTIMATE PREPARATION DATE : 8/28/2014
LOCATION : SUNNYVALE, CA BY : MK
ELEMENT # : 2 REVIEWED BY: KR
ELEMENT : SCREENING FACILITY JW
DIVISION DESCRIPTION QUAN UNIT UNIT COST
LOCATION
FACTOR SUBTOTAL TOTAL
2 SITEWORK
Site Cleaning and Preparation 1 LS $5,000 1.000 $5,000
Cat 235 Trackhoe 1.50CY Bucket, Class C (Hard Digging), 0-20' D 4,264 CY $4.27 1.163 $21,169Native Pipe Bed & Zone/Confined Structure Backfill, Class A 986 CY $28 1.163 $31,682ABC 103 CY $56 1.000 $5,76820 CY Dump Truck, 30 Miles/Round Trip 4,058 CY $13 1.163 $63,412Sheet Piling, 38#/SF To 40' Deep, Pulled & Salvaged (Pits Only) 8,773 SF $29 1.163 $295,887
Total, Div. 02000 $422,918
3 CONCRETE
30" STRUCTURAL FLAT MAT ON GRADE 310 CY $500 1.163 $180,265
30" STRAIGHT WALL >8' HIGH 1108 CY $584 1.163 $752,256
12" ELEVATED SLAB, 21'-26' HIGH 91 CY $545 1.163 $57,727
Class C Fill or Grouting Allowance 1 LS $40,000 1.000 $40,000
Total, Div. 03000 $1,030,248
4 MASONRY
None
Total, Div. 04000 $0
5 METALS
Aluminum Treadplate 345 SF $56 1.163 $22,607
Total, Div. 05000 $22,607
6 WOOD AND PLASTICS
T-Lock Lining 14,663 SF $21 1.000 $314,934
Total, Div. 06000 $314,934
7 THERMAL AND MOISTURE PROTECTION
None
Total, Div. 07000 $0
8 DOORS AND WINDOWS
None
Total, Div. 08000 $0
9 FINISHES
Mechanical Coating Allowance 1 LS $5,000 1.000 $5,000
Total, Div. 09000 $5,000
10 SPECIALTIES
None
Total, Div. 10000 $0
11 EQUIPMENT
File: Package 2 - Conceptual Design Cost Estimate.xlsTab: 2
Page 6 of 37
PRELIMINARY COST ESTIMATE - PACKAGE 2 - HEADWORKS AND PSTS
PROJECT : PRIMARY TREATMENT DESIGN LOCATION FACTOR: 1.163
CITY OF SUNNYVALE ESTIMATED MIDPOINT OF CONSTRUCTION : 11/3/2017
JOB # : 9265A.10 COST ESTIMATE PREPARATION DATE : 8/28/2014
LOCATION : SUNNYVALE, CA BY : MK
ELEMENT # : 2 REVIEWED BY: KR
ELEMENT : SCREENING FACILITY JW
DIVISION DESCRIPTION QUAN UNIT UNIT COST
LOCATION
FACTOR SUBTOTAL TOTAL
Slide Plate 3 EA $6,000 1.000 $18,000
Bar Screen Channel Inlet Gate, 48"x100", Motorized Operator 4 EA $33,389 1.163 $155,324
Bar Screen Channel Outlet Gate, 48"x100", Motorized Operator 4 EA $33,389 1.163 $155,324
Bypass Channel Inlet Gate, 48"x100", Motorized Operator 1 EA $33,389 1.163 $38,831
Bypass Channel Outlet Gate, 48"x100", Motorized Operator 1 EA $33,389 1.163 $38,831
(4) Chain-Drive Multi Rake Bar Screens and (2) Auger Type with
Wash Tub Screenings Washer/Compactor with Sprays 1 EA $1,596,000 1.000 $1,596,000
Total, Div. 11000 $2,002,311
12 FURNISHING
None
Total, Div. 12000 $0
13 SPECIAL CONDITIONS
None
Total, Div. 13000 $0
14 CONVEYING SYSTEMS
Shaftless Screw Screenings Conveyor 1 EA $241,500 1.000 $241,500
Total, Div. 14000 $241,500Total, Div. 14000 $241,500
15 MECHANICAL
Allowance for Foul Air Duct 1 LS $20,000 1.000 $20,000
Total, Div. 15000 $20,000
16 ELECTRICAL
Electrical Allowance (Percentage of Div. 1 - 15) 10% $405,952
Total, Div. 16000 $405,952
17 INSTRUMENTATION
Instrumentation Allowance (Percentage of Div. 1 - 15) 5% $202,976
Total, Div. 17000 $202,976
SUBTOTAL $4,668,445
Estimating Contingency 25% $1,167,111
SUBTOTAL $5,835,557
Sales Tax on 50% of Subtotal Above 8.75% $255,306
SUBTOTAL $6,090,862
General Conditions 10% $609,086
SUBTOTAL $6,699,949
General Contractor Overhead and Profit 13% $870,993
SUBTOTAL $7,570,942
Escalation to Mid-Point (at 3% Annual Inflation Rate) 9.88% $748,051
File: Package 2 - Conceptual Design Cost Estimate.xlsTab: 2
Page 7 of 37
PRELIMINARY COST ESTIMATE - PACKAGE 2 - HEADWORKS AND PSTS
PROJECT : PRIMARY TREATMENT DESIGN LOCATION FACTOR: 1.163
CITY OF SUNNYVALE ESTIMATED MIDPOINT OF CONSTRUCTION : 11/3/2017
JOB # : 9265A.10 COST ESTIMATE PREPARATION DATE : 8/28/2014
LOCATION : SUNNYVALE, CA BY : MK
ELEMENT # : 2 REVIEWED BY: KR
ELEMENT : SCREENING FACILITY JW
DIVISION DESCRIPTION QUAN UNIT UNIT COST
LOCATION
FACTOR SUBTOTAL TOTAL
ELEMENT CONSTRUCTION COST $8,319,000
File: Package 2 - Conceptual Design Cost Estimate.xlsTab: 2
Page 8 of 37
PRELIMINARY COST ESTIMATE - PACKAGE 2 - HEADWORKS AND PSTS
PROJECT : PRIMARY TREATMENT DESIGN LOCATION FACTOR: 1.163
CITY OF SUNNYVALE ESTIMATED MIDPOINT OF CONSTRUCTION : 11/3/2017
JOB # : 9265A.10 COST ESTIMATE PREPARATION DATE : 8/28/2014
LOCATION : SUNNYVALE, CA BY : MK
ELEMENT # : 3 REVIEWED BY: KR
ELEMENT : GRIT & SCREENINGS HANDLING FACILITY JW
DIVISION DESCRIPTION QUAN UNIT UNIT COST
LOCATION
FACTOR SUBTOTAL TOTAL
2 SITEWORK
Site Cleaning and Preparation 1 LS $5,000 1.000 $5,000
Cat 235 Trackhoe 1.50CY Bucket, Class C (Hard Digging), 0-20' D 201 CY $4.27 1.163 $998Native Pipe Bed & Zone/Confined Structure Backfill, Class A 47 CY $28 1.163 $1,510ABC 77 CY $56 1.000 $4,31220 CY Dump Truck, 30 Miles/Round Trip 280 CY $13 1.163 $4,375
Total, Div. 02000 $16,195
3 CONCRETE
8" FLAT NON-FORMED S.O.G. 25 CY $500 1.163 $14,538
18" STRUCTURAL FLAT MAT ON GRADE 92 CY $500 1.163 $53,498
6" FLAT NON-FORMED SLAB ON GRADE 9 CY $500 1.163 $5,234
12" STRAIGHT WALL >8' HIGH 253 CY $962 1.163 $283,091
12" ELEVATED SLAB TO 20' 59 CY $480 1.163 $32,964
24" W X 24" D CONC BEAM 10 CY $774 1.163 $9,002
Class C Fill or Grouting Allowance 1 LS $100,000 1.000 $100,000
Total, Div. 03000 $498,325
4 MASONRY
None
Total, Div. 04000 $0
5 METALS5 METALS
Metal Canopy 481 SF $120 1.163 $67,128
Aluminum Grating, 2" 468 SF $56 1.163 $30,666
Aluminum Stairs, Including Railing and Supports 80 RSR $561 1.163 $52,217
Aluminum OSHA Handrail 71 LF $75 1.163 $6,234
Steel Deck, 3" X 16 Ga. 1591 SF $7 1.163 $12,923
Discharge Chute 3 EA $5,000 1.000 $15,000
Three 10'x10' Roof Hatches and One 4'x4' Roof Hatch (Aluminum) 316 SF $56 1.163 $20,429
Total, Div. 05000 $204,598
6 WOOD AND PLASTICS
None
Total, Div. 06000 $0
7 THERMAL AND MOISTURE PROTECTION
3-1/4" R-20.00 Composite Board Roof Insulation 1,591 SF $4 1.163 $8,308
Neoprene, Fully Adhered With Adhesive, Polychloroprene 1,591 SF $7 1.163 $13,322
Total, Div. 07000 $21,630
8 DOORS AND WINDOWS
7/0 X 7/0 X 1.75" NO LABEL DOUBLE HOLLOW METAL DOOR
W/FRAME & HDWRE 1 EA $1,645 1.163 $1,913
3/0 X 7/0 X 1.75" NO LABEL SINGLE HOLLOW METAL DOOR
W/FRAME & HDWRE 3 EA $853 1.163 $2,974
10'-0" X 12'-0" Roll-Up Overhead Door, Chain Lift, 22 Gauge
Galvanized Steel/Aluminum 2 EA $2,820 1.163 $6,559
Electric Door Operator For Chain Lift Roll-Up Overhead Door, No
Wiring 2 EA $1,740 1.163 $4,047
File: Package 2 - Conceptual Design Cost Estimate.xlsTab: 3
Page 9 of 37
PRELIMINARY COST ESTIMATE - PACKAGE 2 - HEADWORKS AND PSTS
PROJECT : PRIMARY TREATMENT DESIGN LOCATION FACTOR: 1.163
CITY OF SUNNYVALE ESTIMATED MIDPOINT OF CONSTRUCTION : 11/3/2017
JOB # : 9265A.10 COST ESTIMATE PREPARATION DATE : 8/28/2014
LOCATION : SUNNYVALE, CA BY : MK
ELEMENT # : 3 REVIEWED BY: KR
ELEMENT : GRIT & SCREENINGS HANDLING FACILITY JW
DIVISION DESCRIPTION QUAN UNIT UNIT COST
LOCATION
FACTOR SUBTOTAL TOTAL
Total, Div. 08000 $15,494
9 FINISHES
Mechanical Coating Allowance (Percentage of Div. 15) 1% $1,483
Total, Div. 09000 $1,483
10 SPECIALTIES
None
Total, Div. 10000 $0
11 EQUIPMENT
Auger Type Screenings Washer/Compactor with Sprays (Screening
Equipment Quote Included in Area 2) 0 EA - - -
Screenings Rotating Tipping Trough 2 EA $24,000 1.000 $48,000
CONANDA Fine Grit Washer 1 EA $630,000 1.000 $630,000
Ventilation Fans 2 LS $2,000 1.000 $8,000
Odor Control Fans at PST 4 EA $3,000 1.000 $6,000
Total, Div. 11000 $692,000
12 FURNISHING
NoneNone
Total, Div. 12000 $0
13 SPECIAL CONDITIONS
None
Total, Div. 13000 $0
14 CONVEYING SYSTEMS
None
Total, Div. 14000 $0
15 MECHANICAL
8" FLG CLDI PIPE IN BLDG 61 LF $84 1.163 $5,978
8" X 8" CLDI MJ TEE OR WYE 2 EA $1,741 1.163 $4,050
8" 45° 125# CLDI FXF ELL 6 EA $730 1.163 $5,091
10" FLG CLDI PIPE IN BLDG 20 LF $110 1.163 $2,549
Allowance for Foul Air Duct 1 LS $20,000 1.000 $20,000
Additional Piping Allowance 1 LS $75,000 1.000 $75,000
Pipe Support Allowance (Percentage of Div. 15) 5% $112,668 $5,633
HVAC Allowance for Electrical Room 1 EA $30,000 1.000 $30,000
Total, Div. 15000 $148,301
16 ELECTRICAL
Electrical Allowance (Percentage of Div. 1 - 15) 10% $159,803
Total, Div. 16000 $159,803
17 INSTRUMENTATION
File: Package 2 - Conceptual Design Cost Estimate.xlsTab: 3
Page 10 of 37
PRELIMINARY COST ESTIMATE - PACKAGE 2 - HEADWORKS AND PSTS
PROJECT : PRIMARY TREATMENT DESIGN LOCATION FACTOR: 1.163
CITY OF SUNNYVALE ESTIMATED MIDPOINT OF CONSTRUCTION : 11/3/2017
JOB # : 9265A.10 COST ESTIMATE PREPARATION DATE : 8/28/2014
LOCATION : SUNNYVALE, CA BY : MK
ELEMENT # : 3 REVIEWED BY: KR
ELEMENT : GRIT & SCREENINGS HANDLING FACILITY JW
DIVISION DESCRIPTION QUAN UNIT UNIT COST
LOCATION
FACTOR SUBTOTAL TOTAL
PLC Cabinet 1 EA $176,400 $176,400
Instrumentation Allowance (Percentage of Div. 1 - 15) 5% $79,901
Total, Div. 17000 $256,301
SUBTOTAL $2,014,132
Estimating Contingency 25% $503,533
SUBTOTAL $2,517,664
Sales Tax on 50% of Subtotal Above 8.75% $110,148
SUBTOTAL $2,627,812
General Conditions 10% $262,781
SUBTOTAL $2,890,594
General Contractor Overhead and Profit 13% $375,777
SUBTOTAL $3,266,371
Escalation to Mid-Point (at 3% Annual Inflation Rate) 9.88% $322,736
ELEMENT CONSTRUCTION COST $3,589,000
File: Package 2 - Conceptual Design Cost Estimate.xlsTab: 3
Page 11 of 37
PRELIMINARY COST ESTIMATE - PACKAGE 2 - HEADWORKS AND PSTS
PROJECT : PRIMARY TREATMENT DESIGN LOCATION FACTOR: 1.163
CITY OF SUNNYVALE ESTIMATED MIDPOINT OF CONSTRUCTION : 11/3/2017
JOB # : 9265A.10 COST ESTIMATE PREPARATION DATE : 8/28/2014
LOCATION : SUNNYVALE, CA BY : MK
ELEMENT # : 4 REVIEWED BY: KR
ELEMENT : INFLUENT PUMP STATION JW
DIVISION DESCRIPTION QUAN UNIT UNIT COST
LOCATION
FACTOR SUBTOTAL TOTAL
2 SITEWORK
Site Cleaning and Preparation 1 LS $5,000 1.000 $5,000
Cat 235 Trackhoe 1.50CY Bucket, Class C (Hard Digging), 0-20' D 7,518 CY $4.27 1.163 $37,324Native Pipe Bed & Zone/Confined Structure Backfill, Class A 1,432 CY $28 1.163 $46,013ABC 179 CY $56 1.000 $10,02420 CY Dump Truck, 30 Miles/Round Trip 7,518 CY $13 1.163 $117,479Sheet Piling, 38#/SF To 40' Deep, Pulled & Salvaged (Pits Only) 8,760 SF $29 1.163 $295,449
Total, Div. 02000 $511,289
3 CONCRETE
30" STRUCTURAL FLAT MAT ON GRADE 987 CY $500 1.163 $573,941
24" STRAIGHT WALL >8' HIGH 40 CY $650 1.163 $30,234
30" STRAIGHT WALL >8' HIGH 1014 CY $584 1.163 $688,437
12" STRAIGHT WALL >8' HIGH 116 CY $962 1.163 $129,797
12" ELEVATED SLAB, 33'-38' HIGH 120 CY $590 1.163 $82,302
6" FLAT NON-FORMED SLAB ON GRADE 7 CY $500 1.163 $4,071
Pump Pads 7 CY $337 1.163 $2,874
Total, Div. 03000 $1,511,655
4 MASONRY
None
Total, Div. 04000 $0Total, Div. 04000 $0
5 METALS
Checkered Aluminum Plate 1,913 LB $56 1.163 $125,121
Aluminum OSHA Handrail 628 LF $75 1.163 $55,138
Aluminum Stairs, Including Railing and Supports 98 RSR $561 1.163 $63,966
Steel Deck, 3" X 16 Ga. 370 SF $7 1.163 $3,004
Total, Div. 05000 $247,229
6 WOOD AND PLASTICS
T-Lok Lining 5,128 SF $21 1.000 $110,142
Total, Div. 06000 $110,142
7 THERMAL AND MOISTURE PROTECTION
3-1/4" R-20.00 Composite Board Roof Insulation 370 SF $4 1.163 $1,931
Neoprene, Fully Adhered With Adhesive, Polychloroprene 370 SF $7 1.163 $3,097
Total, Div. 07000 $5,028
8 DOORS AND WINDOWS
3/0 X 7/0 X 1.75" NO LABEL SINGLE HOLLOW METAL DOOR
W/FRAME & HDWRE 4 EA $853 1.163 $3,966
Total, Div. 08000 $3,966
9 FINISHES
Mechanical Coating Allowance (Percentage of Div. 15) 1% $8,890
Total, Div. 09000 $8,890
File: Package 2 - Conceptual Design Cost Estimate.xlsTab: 4
Page 12 of 37
PRELIMINARY COST ESTIMATE - PACKAGE 2 - HEADWORKS AND PSTS
PROJECT : PRIMARY TREATMENT DESIGN LOCATION FACTOR: 1.163
CITY OF SUNNYVALE ESTIMATED MIDPOINT OF CONSTRUCTION : 11/3/2017
JOB # : 9265A.10 COST ESTIMATE PREPARATION DATE : 8/28/2014
LOCATION : SUNNYVALE, CA BY : MK
ELEMENT # : 4 REVIEWED BY: KR
ELEMENT : INFLUENT PUMP STATION JW
DIVISION DESCRIPTION QUAN UNIT UNIT COST
LOCATION
FACTOR SUBTOTAL TOTAL
10 SPECIALTIES
None
Total, Div. 10000 $0
11 EQUIPMENT
Dry-Pit Submersible Non-clog Pumps 6 EA $161,850 1.000 $971,100
Wet Well Inlet Gates - SST, Downward Opening, 108x90, Motorized
Operator 3 EA $67,612 1.000 $202,836
Compartment Isolation Gates - SST, Downward Opening, 108x66,
Motorized Operator 2 EA $49,582 1.000 $99,164
Pump Intake Gates, 33x33, Motorized Operator 6 EA $13,254 1.000 $79,525
Sump Pumps 2 EA $6,000 1.000 $12,000
Ventilation Fans 6 LS $2,000 1.000 $8,000
Odor Control Fans at PST 2 EA $3,000 1.000 $6,000
Total, Div. 11000 $1,378,626
12 FURNISHING
None
Total, Div. 12000 $0
13 SPECIAL CONDITIONS13 SPECIAL CONDITIONS
None
Total, Div. 13000 $0
14 CONVEYING SYSTEMS
None
Total, Div. 14000 $0
15 MECHANICAL
30" FLG CLDI PIPE IN BLDG 150 LF $648 1.163 $113,127
20" FXF CAST IRON PLUG VALVE W/HANDWHEEL OP 6 EA $7,071 1.163 $49,342
16"- 125# DI FXF CHECK VALVE 6 EA $33,320 1.163 $232,508
20" FLG CLDI PIPE IN BLDG 78 LF $296 1.163 $26,820
20" 90° 125# CLDI FXF ELL 9 EA $5,423 1.163 $56,766
30" 90° 125# CLDI FXF ELL 5 EA $11,393 1.163 $66,249
30"X24" 125# CLDI FXF CONCENTRIC RDCR 6 EA $12,523 1.163 $87,388
30" Square to Round Transition 6 EA $20,000 1.163 $139,560
20"X18" 125# CLDI FXF CONCENTRIC RDCR 6 EA $7,043 1.163 $49,145
Pump Reducing Intake Elbow 6 EA $6,000 1.163 $41,868
Allowance for Foul Air Duct 1 LS $20,000 1.000 $20,000
Pipe Support Allowance (Percentage of Div. 15) 5% $6,186
Total, Div. 15000 $888,959
16 ELECTRICAL
Electrical Allowance (Percentage of Div. 1 - 15) 10% $466,578
Total, Div. 16000 $466,578
17 INSTRUMENTATION
File: Package 2 - Conceptual Design Cost Estimate.xlsTab: 4
Page 13 of 37
PRELIMINARY COST ESTIMATE - PACKAGE 2 - HEADWORKS AND PSTS
PROJECT : PRIMARY TREATMENT DESIGN LOCATION FACTOR: 1.163
CITY OF SUNNYVALE ESTIMATED MIDPOINT OF CONSTRUCTION : 11/3/2017
JOB # : 9265A.10 COST ESTIMATE PREPARATION DATE : 8/28/2014
LOCATION : SUNNYVALE, CA BY : MK
ELEMENT # : 4 REVIEWED BY: KR
ELEMENT : INFLUENT PUMP STATION JW
DIVISION DESCRIPTION QUAN UNIT UNIT COST
LOCATION
FACTOR SUBTOTAL TOTAL
Instrumentation Allowance (Percentage of Div. 1 - 15) 5% $233,289
Total, Div. 17000 $233,289
SUBTOTAL $5,365,649
Estimating Contingency 25% $1,341,412
SUBTOTAL $6,707,062
Sales Tax on 50% of Subtotal Above 8.75% $293,434
SUBTOTAL $7,000,496
General Conditions 10% $700,050
SUBTOTAL $7,700,545
General Contractor Overhead and Profit 13% $1,001,071
SUBTOTAL $8,701,616
Escalation to Mid-Point (at 3% Annual Inflation Rate) 9.88% $859,768
ELEMENT CONSTRUCTION COST $9,561,000
File: Package 2 - Conceptual Design Cost Estimate.xlsTab: 4
Page 14 of 37
PRELIMINARY COST ESTIMATE - PACKAGE 2 - HEADWORKS AND PSTS
PROJECT : PRIMARY TREATMENT DESIGN LOCATION FACTOR: 1.163
CITY OF SUNNYVALE ESTIMATED MIDPOINT OF CONSTRUCTION : 11/3/2017
JOB # : 9265A.10 COST ESTIMATE PREPARATION DATE : 8/28/2014
LOCATION : SUNNYVALE, CA BY : MK
ELEMENT # : 5 REVIEWED BY: KR
ELEMENT : GRIT BASINS JW
DIVISION DESCRIPTION QUAN UNIT UNIT COST
LOCATION
FACTOR SUBTOTAL TOTAL
2 SITEWORK
Site Cleaning and Preparation 1 LS $5,000 1.000 $5,000
Cat 235 Trackhoe 1.50CY Bucket, Class C (Hard Digging), 0-20' D 2,111 CY $4.27 1.163 $10,480Native Pipe Bed & Zone/Confined Structure Backfill, Class A 972 CY $28 1.163 $31,232ABC 136 CY $56 1.000 $7,61620 CY Dump Truck, 30 Miles/Round Trip 1,529 CY $13 1.163 $23,893Sheet Piling, 38#/SF To 40' Deep, Pulled & Salvaged (Pits Only) 4,620 SF $29 1.163 $155,819
Total, Div. 02000 $234,040
3 CONCRETE
30" STRUCTURAL FLAT MAT ON GRADE 158 CY $500 1.163 $91,877
18" STRUCTURAL FLAT MAT ON GRADE 4 CY $500 1.163 $2,326
12" STRUCTURAL FLAT MAT ON GRADE 57 CY $500 1.163 $33,146
18" STRAIGHT WALL >8' HIGH 212 CY $753 1.163 $185,585
12" STRAIGHT WALL >8' HIGH 359 CY $962 1.163 $401,698
12" ELEVATED SLAB TO 20' 200 CY $480 1.163 $111,741
Class C Fill/Grouting 1 LS $30,000 1.000 $30,000
Total, Div. 03000 $856,373
4 MASONRY
None
Total, Div. 04000 $0
5 METALS
Checkered Aluminum Plate 1,790 LB $56 1.163 $117,076
Aluminum OSHA Handrail 480 LF $75 1.163 $42,143
Aluminum Stairs, Including Railing and Supports 88 RSR $561 1.163 $57,439
Total, Div. 05000 $216,659
6 WOOD AND PLASTICS
T-Lok Lining 12,721 SF $21 1.000 $273,223
Total, Div. 06000 $273,223
7 THERMAL AND MOISTURE PROTECTION
None
Total, Div. 07000 $0
8 DOORS AND WINDOWS
None
Total, Div. 08000 $0
9 FINISHES
Mechanical Coating Allowance (Percentage of Div. 15) 1% $3,662
Total, Div. 09000 $3,662
10 SPECIALTIES
None
File: Package 2 - Conceptual Design Cost Estimate.xlsTab: 5
Page 15 of 37
PRELIMINARY COST ESTIMATE - PACKAGE 2 - HEADWORKS AND PSTS
PROJECT : PRIMARY TREATMENT DESIGN LOCATION FACTOR: 1.163
CITY OF SUNNYVALE ESTIMATED MIDPOINT OF CONSTRUCTION : 11/3/2017
JOB # : 9265A.10 COST ESTIMATE PREPARATION DATE : 8/28/2014
LOCATION : SUNNYVALE, CA BY : MK
ELEMENT # : 5 REVIEWED BY: KR
ELEMENT : GRIT BASINS JW
DIVISION DESCRIPTION QUAN UNIT UNIT COST
LOCATION
FACTOR SUBTOTAL TOTAL
Total, Div. 10000 $0
11 EQUIPMENT
Stop Plates 2 EA $6,000 1.000 $12,000
Eutek HeadCell Grit Vortex System 1 EA $669,600 1.000 $669,600
Grit Pumps 6 EA $61,427 1.000 $368,565
Pump Gallery Sump Pump 1 EA $6,000 1.000 $6,000
42"x108" Influent Channel Gates 3 EA $36,060 1.000 $108,179
48"x72" Bypass Gate 1 EA $24,040 1.000 $24,040
54"x108" Effluent Gates 3 EA $40,567 1.000 $121,702
Automatic Sampler 1 EA $9,600 1.000 $9,600
Odor Control Fans at PST 2 EA $3,000 1.000 $6,000
Total, Div. 11000 $1,325,686
12 FURNISHING
None
Total, Div. 12000 $0
13 SPECIAL CONDITIONS
None
Total, Div. 13000 $0Total, Div. 13000 $0
14 CONVEYING SYSTEMS
None
Total, Div. 14000 $0
15 MECHANICAL
6" FLG CLDI PIPE IN BLDG 185 LF $66 1.163 $14,190
4" FLG CLDI PIPE IN BLDG 275 LF $45 1.163 $14,516
8"X 6" 125# CLDI FXF ECCENTRIC RDCR 6 EA $1,218 1.163 $8,498
6" FXF CAST IRON PLUG VALVE W/HANDWHEEL OP 12 EA $1,024 1.163 $14,293
4" FXF CAST IRON PLUG VALVE W/HANDWHEEL OP 24 EA $740 1.163 $20,654
4"- 200 PSI CI FXF SWING CHECK VALVE 6 EA $1,221 1.163 $8,517
4" Fca Above Ground 6 EA $496 1.163 $3,464
8" Fca Above Ground 9 EA $952 1.163 $9,963
30" FLG CLDI PIPE IN BLDG 126 LF $648 1.163 $95,027
30" 90° 125# CLDI FXF ELL 6 EA $11,393 1.163 $79,499
84" Astm C-76 Class V Rcp In Open Trench 10 LF $376 1.163 $4,377
Allowance for Foul Air Duct 1 LS $20,000 1.000 $20,000
Additional 20% Piping Allowance 20% $58,600
Pipe Support Allowance (Percentage of Div. 15) 5% $14,650
Total, Div. 15000 $366,249
16 ELECTRICAL
Electrical Allowance (Percentage of Div. 1 - 15) 10% $327,589
Total, Div. 16000 $327,589
17 INSTRUMENTATION
Instrumentation Allowance (Percentage of Div. 1 - 15) 5% $163,795
Flowmeter-Magnetic 30" 3 EA $53,085 1.163 $185,215
File: Package 2 - Conceptual Design Cost Estimate.xlsTab: 5
Page 16 of 37
PRELIMINARY COST ESTIMATE - PACKAGE 2 - HEADWORKS AND PSTS
PROJECT : PRIMARY TREATMENT DESIGN LOCATION FACTOR: 1.163
CITY OF SUNNYVALE ESTIMATED MIDPOINT OF CONSTRUCTION : 11/3/2017
JOB # : 9265A.10 COST ESTIMATE PREPARATION DATE : 8/28/2014
LOCATION : SUNNYVALE, CA BY : MK
ELEMENT # : 5 REVIEWED BY: KR
ELEMENT : GRIT BASINS JW
DIVISION DESCRIPTION QUAN UNIT UNIT COST
LOCATION
FACTOR SUBTOTAL TOTAL
Total, Div. 17000 $349,010
SUBTOTAL $3,952,491
Estimating Contingency 25% $988,123
SUBTOTAL $4,940,613
Sales Tax on 50% of Subtotal Above 8.75% $216,152
SUBTOTAL $5,156,765
General Conditions 10% $515,677
SUBTOTAL $5,672,442
General Contractor Overhead and Profit 13% $737,417
SUBTOTAL $6,409,859
Escalation to Mid-Point (at 3% Annual Inflation Rate) 9.88% $633,330
ELEMENT CONSTRUCTION COST $7,043,000
File: Package 2 - Conceptual Design Cost Estimate.xlsTab: 5
Page 17 of 37
PRELIMINARY COST ESTIMATE - PACKAGE 2 - HEADWORKS AND PSTS
PROJECT : PRIMARY TREATMENT DESIGN LOCATION FACTOR: 1.000
CITY OF SUNNYVALE ESTIMATED MIDPOINT OF CONSTRUCTION : 11/3/2017
JOB # : 9265A.10 COST ESTIMATE PREPARATION DATE : 8/28/2014
LOCATION : SUNNYVALE, CA BY : MP
ELEMENT # : 6 REVIEWED BY: CO
ELEMENT : PRIMARY SEDIMENTATION TANKS DH
DIVISION DESCRIPTION QUAN UNIT UNIT COST
LOCATION
FACTOR SUBTOTAL TOTAL
2 SITEWORK
Site Cleaning and Preparation 1 LS $5,000 1.000 $5,000
Excavation 11600 CY $7 1.000 $81,200
Backfilling and Compaction 2,700 CY $10 1.000 $27,000
Aggregate Base under Foundation 1,200 CY $56 1.000 $67,200
Dirt Hauling, 30 miles, round trip 8,900 CY $11 1.000 $97,900
Sheet Piling 4,300 SF $29 1.000 $124,700
Misc. Site Work 1 LS $50,000 1.000 $50,000
Total, Div. 02000 $453,000
3 CONCRETE
Slab on Grade 1500 CY $707 1.000 $1,060,955
Thick Wall (>8" thick) 1100 CY $926 1.000 $1,019,045
Elevated Slab 300 CY $999 1.000 $299,831
Beam 20 CY $999 1.000 $19,989
Column 3 CY $926 1.000 $2,779
Pipe Encasement 24 CY $488 1.000 $11,717
Misc. Concrete (Lean Concrete) 1 LS $40,000 1.000 $40,000
Side Walk and Misc. Pads 40 CY $634 1.000 $25,371
Total, Div. 03000 $2,479,687
4 MASONRY
None
Total, Div. 04000 $0
5 METALS
Handrail 1,600 LF $80 1.000 $128,000
Odor Control Cover 7,300 SF $120 1.000 $876,000
Roof Hatches 100 SF $150 1.000 $15,000
Aluminum Stairs 100 VLF $200 1.000 $20,000
Current Construction for Future Odor Control Cover to Entire PSTs 1 LS $100,000 1.000 $100,000
Misc. Metals 1 LS $50,000 1.000 $50,000
Total, Div. 05000 $1,189,000
6 WOOD AND PLASTICS
T-Lock Lining 11,200 SF $21 1.000 $240,555
Inlet Flocculating Baffles 1 LS $120,000 1.000 $120,000
Mid Tank Baffles 1 LS $180,000 1.000 $180,000
Sludge Hopper Canopy 1 LS $100,000 1.000 $100,000
Effluent Launders 108 LF $80 1.000 $8,640
V-notch weirs 216 LF $120 1.000 $25,920
Misc. Wood and Plastics 1 LS $50,000 1.000 $50,000
Total, Div. 06000 $725,115
7 THERMAL AND MOISTURE PROTECTION
Pump Gallery 1 LS $30,000 1.000 $30,000
Total, Div. 07000 $30,000
8 DOORS AND WINDOWS
Single Door 2 EA $1,900 1.000 $3,800
File: Package 2 - Conceptual Design Cost Estimate.xlsTab: 6
Page 18 of 37
PRELIMINARY COST ESTIMATE - PACKAGE 2 - HEADWORKS AND PSTS
PROJECT : PRIMARY TREATMENT DESIGN LOCATION FACTOR: 1.000
CITY OF SUNNYVALE ESTIMATED MIDPOINT OF CONSTRUCTION : 11/3/2017
JOB # : 9265A.10 COST ESTIMATE PREPARATION DATE : 8/28/2014
LOCATION : SUNNYVALE, CA BY : MP
ELEMENT # : 6 REVIEWED BY: CO
ELEMENT : PRIMARY SEDIMENTATION TANKS DH
DIVISION DESCRIPTION QUAN UNIT UNIT COST
LOCATION
FACTOR SUBTOTAL TOTAL
Double Door 1 EA $3,600 1.000 $3,600
Total, Div. 08000 $7,400
9 FINISHES
Painting and Protective Coating 1 LS $30,000 1.000 $30,000
Air Compression
Painting and Protective Coatings 1 LS $7,000 1.000 $7,000
Total, Div. 09000 $37,000
10 SPECIALTIES
Signs, Identification, Stenciling and Tagging System 1 LS $25,000 1.000 $25,000
Total, Div. 10000 $25,000
11 EQUIPMENT
Chain and Flight Sludge Collector 6 EA $100,000 1.000 $600,000
Ducking/Tilting Trough Skimmer 6 EA $40,000 1.000 $240,000
Scum Pump 4 EA $37,000 1.000 $148,000
Sludge Pump 9 EA $31,000 1.000 $279,000
Sump Pump 1 EA $6,000 1.000 $6,000
Pre-aeration Blowers 2 EA $112,000 1.000 $224,000
Ventilation Fans 4 LS $2,000 1.000 $8,000Ventilation Fans 4 LS $2,000 1.000 $8,000
Odor Control Fans at PST 2 EA $3,000 1.000 $6,000
Dampers 1 LS $4,000 1.000 $4,000
Ductwork and Accessories 1 LS $20,000 1.000 $20,000
Primary Influent Gates - 2' x 3' 18 EA $13,100 1.000 $235,800
Primary Effluent Gates - 3' x 3' 6 EA $14,400 1.000 $86,400
Primary Effluent Channel Gates - 66" x 66" 2 EA $30,000 1.000 $60,000
Stop Plates and Guide - 2' x 5' (Primary Influent Gates) 18 EA $3,000 1.000 $54,000
Stop Plates and Guide - 3' x 5' (Primary Effluent Gates) 6 EA $3,500 1.000 $21,000
Stop Plates and Guide - 5' x 10' (Primary Influent Channel) 2 EA $10,000 1.000 $20,000
Stop Plates and Guide - 4' x 8' (Primary Effluent Channel) 2 EA $7,000 1.000 $14,000
Gate Operators 42 EA $7,500 1.000 $315,000
Misc. Equipment 1 LS $100,000 1.000 $100,000
Air Compression
Rotary Screw Non-lubricated Air Compressors (Duty/Standby) 2 EA $7,500 1.000 $15,000
Includes Packaged Control Panel
Air Receiver 1 EA $1,000 1.000 $1,000
Refrigerant Air Dryer 1 EA $1,000 1.000 $1,000
Desiccant Air Dryer 1 EA $700 1.000 $700
Auto Drain Valves 3 EA $200 1.000 $600
Total, Div. 11000 $2,459,500
12 FURNISHING
None
Total, Div. 12000 $0
13 SPECIAL CONSTRUCTION
None
Total, Div. 13000 $0
14 CONVEYING SYSTEMS
File: Package 2 - Conceptual Design Cost Estimate.xlsTab: 6
Page 19 of 37
PRELIMINARY COST ESTIMATE - PACKAGE 2 - HEADWORKS AND PSTS
PROJECT : PRIMARY TREATMENT DESIGN LOCATION FACTOR: 1.000
CITY OF SUNNYVALE ESTIMATED MIDPOINT OF CONSTRUCTION : 11/3/2017
JOB # : 9265A.10 COST ESTIMATE PREPARATION DATE : 8/28/2014
LOCATION : SUNNYVALE, CA BY : MP
ELEMENT # : 6 REVIEWED BY: CO
ELEMENT : PRIMARY SEDIMENTATION TANKS DH
DIVISION DESCRIPTION QUAN UNIT UNIT COST
LOCATION
FACTOR SUBTOTAL TOTAL
Monorail and Crane 1 LS $50,000 1.000 $50,000
Total, Div. 14000 $50,000
15 MECHANICAL
Primary influent and Effluent Pipes (Connections & 5 ft from Structure) 1 LS $250,000 1.000 $250,000
Sludge Piping and Valving 1 LS $80,000 1.000 $80,000
Scum Piping and Valving 1 LS $50,000 1.000 $50,000
Pre-aeration Air Piping 1 LS $50,000 1.000 $50,000
Sludge & Scum Pre-heating 1 LS $80,000 1.000 $80,000
Air Diffusers 1 LS $38,000 1.000 $38,000
Misc. Piping 1 LS $50,000 1.000 $50,000
Air Compression
Air Piping 1 LS $5,000 1.000 $5,000
Air Valves 1 LS $500 1.000 $500
Pipe Supports 1 LS $2,000 1.000 $2,000
Total, Div. 15000 $605,500
16 ELECTRICAL
Electrical Allowance (Percentage of Div. 1 - 15) 10% $806,120
Total, Div. 16000 $806,120
17 INSTRUMENTATION
PLC Cabinet 1 EA $176,400 1.000 $176,400
Communications Cabinet 1 EA $15,960 1.000 $15,960
Instrumentation and Controls 1 LS $275,000 1.000 $275,000
Total, Div. 17000 $467,360
SUBTOTAL $9,334,682
Estimating Contingency 25% $2,333,671
SUBTOTAL $11,668,353
Sales Tax on 50% of Subtotal Above 8.75% $510,490
SUBTOTAL $12,178,843
General Conditions 10% $1,217,884
SUBTOTAL $13,396,728
General Contractor Overhead and Profit 13% $1,741,575
SUBTOTAL $15,138,302
Escalation to Mid-Point (at 3% Annual Inflation Rate) 9.88% $1,495,749
ELEMENT CONSTRUCTION COST $16,634,000
File: Package 2 - Conceptual Design Cost Estimate.xlsTab: 6
Page 20 of 37
PRELIMINARY COST ESTIMATE - PACKAGE 2 - HEADWORKS AND PSTS
PROJECT : PRIMARY TREATMENT DESIGN LOCATION FACTOR: 1.000
CITY OF SUNNYVALE ESTIMATED MIDPOINT OF CONSTRUCTION : 11/3/2017
JOB # : 9265A.10 COST ESTIMATE PREPARATION DATE : 8/28/2014
LOCATION : SUNNYVALE, CA BY : MP
ELEMENT # : 7 REVIEWED BY: CO
ELEMENT : CEPT FACILITY DH
DIVISION DESCRIPTION QUAN UNIT UNIT COST
LOCATION
FACTOR SUBTOTAL TOTAL
2 SITEWORK
Site Cleaning and Preparation 1 LS $2,000 1.000 $2,000
Excavation 130 CY $7 1.000 $910
Backfilling and Compaction 41 CY $10 1.000 $410
Aggregate Base under Foundation 62 CY $56 1.000 $3,472
Dirt Hauling, 30 miles, round trip 89 CY $11 1.000 $979
Total, Div. 02000 $7,771
3 CONCRETE
Slab on Grade 100 CY $707 1.000 $70,730
Thick Wall (>8" thick) 12 CY $926 1.000 $11,117
Side Walk and Misc. Pads 1 LS $15,000 1.000 $15,000
Misc. Concrete 1 LS $5,000 1.000 $5,000
Total, Div. 03000 . $101,847
4 MASONRY
None
Total, Div. 04000 $0
5 METALS
Stairs, landing and handrails 1 LS $15,000 1.000 $15,000
Metal Canopy 700 SF $120 1.000 $84,000
Total, Div. 05000 $99,000
6 WOOD AND PLASTICS
FRP grating 90 SF $30 1.000 $2,700
Total, Div. 06000 $2,700
7 THERMAL AND MOISTURE PROTECTION
Thermal and Moisture Protection 1 LS $5,000 1.000 $5,000
Total, Div. 07000 $5,000
8 DOORS AND WINDOWS
None
Total, Div. 08000 $0
9 FINISHES
Painting and Protective Coating 1 LS $25,000 1.000 $25,000
Total, Div. 09000 $25,000
10 SPECIALTIES
Signs, Identification, Stenciling and Tagging System 1 LS $5,000 1.000 $5,000
Misc. Specialties (ESEW, etc.) 1 LS $15,000 1.000 $15,000
Total, Div. 10000 $20,000
File: Package 2 - Conceptual Design Cost Estimate.xlsTab: 7
Page 21 of 37
PRELIMINARY COST ESTIMATE - PACKAGE 2 - HEADWORKS AND PSTS
PROJECT : PRIMARY TREATMENT DESIGN LOCATION FACTOR: 1.000
CITY OF SUNNYVALE ESTIMATED MIDPOINT OF CONSTRUCTION : 11/3/2017
JOB # : 9265A.10 COST ESTIMATE PREPARATION DATE : 8/28/2014
LOCATION : SUNNYVALE, CA BY : MP
ELEMENT # : 7 REVIEWED BY: CO
ELEMENT : CEPT FACILITY DH
DIVISION DESCRIPTION QUAN UNIT UNIT COST
LOCATION
FACTOR SUBTOTAL TOTAL
11 EQUIPMENT
Ferric Chloride Storage Tank, 5,000 gal 2 EA $15,000 1.000 $30,000
Polymer Tote, 100 gal 2 EA $1,500 1.000 $3,000
Ferric Chloride Metering Pump Skid 1 EA $12,000 1.000 $12,000
Polymer Blending and Activation Unit 1 EA $16,000 1.000 $16,000
Polymer Metering Pump Skid 1 EA $10,000 1.000 $10,000
Total, Div. 11000 $71,000
12 FURNISHING
None
Total, Div. 12000 $0
13 SPECIAL CONDITIONS
None
Total, Div. 13000 $0
14 CONVEYING SYSTEMS
None
Total, Div. 14000 $0Total, Div. 14000 $0
15 MECHANICAL
All Piping and Valving 1 LS $100,000 1.000 $100,000
Total, Div. 15000 $100,000
16 ELECTRICAL
Electrical 1 LS $40,000 1.000 $40,000
Total, Div. 16000 $40,000
17 INSTRUMENTATION
Instrumentation and Controls 1 LS $200,000 1.000 $200,000
Total, Div. 17000 $200,000
SUBTOTAL $672,318
Estimating Contingency 25% $168,080
SUBTOTAL $840,398
Sales Tax on 50% of Subtotal Above 8.75% $36,767
SUBTOTAL $877,165
General Conditions 10% $87,717
SUBTOTAL $964,882
General Contractor Overhead and Profit 13% $125,435
SUBTOTAL $1,090,316
Escalation to Mid-Point (at 3% Annual Inflation Rate) 9.88% $107,729
File: Package 2 - Conceptual Design Cost Estimate.xlsTab: 7
Page 22 of 37
PRELIMINARY COST ESTIMATE - PACKAGE 2 - HEADWORKS AND PSTS
PROJECT : PRIMARY TREATMENT DESIGN LOCATION FACTOR: 1.000
CITY OF SUNNYVALE ESTIMATED MIDPOINT OF CONSTRUCTION : 11/3/2017
JOB # : 9265A.10 COST ESTIMATE PREPARATION DATE : 8/28/2014
LOCATION : SUNNYVALE, CA BY : MP
ELEMENT # : 7 REVIEWED BY: CO
ELEMENT : CEPT FACILITY DH
DIVISION DESCRIPTION QUAN UNIT UNIT COST
LOCATION
FACTOR SUBTOTAL TOTAL
ELEMENT CONSTRUCTION COST $1,198,000
File: Package 2 - Conceptual Design Cost Estimate.xlsTab: 7
Page 23 of 37
PRELIMINARY COST ESTIMATE - PACKAGE 2 - HEADWORKS AND PSTS
PROJECT : PRIMARY TREATMENT DESIGN LOCATION FACTOR: 1.000
CITY OF SUNNYVALE ESTIMATED MIDPOINT OF CONSTRUCTION : 11/3/2017
JOB # : 9265A.10 COST ESTIMATE PREPARATION DATE : 8/28/2014
LOCATION : SUNNYVALE, CA BY : THK
ELEMENT # : 8 REVIEWED BY: BK
ELEMENT : ODOR CONTROL FACILITY DH
DIVISION DESCRIPTION QUAN UNIT UNIT COST
LOCATION
FACTOR SUBTOTAL TOTAL
2 SITEWORK
Excavation 120 CY $7 1.000 $840
Aggregate Base under Foundation 40 CY $56 1.000 $2,240
Backfilling and Compaction 80 CY $10 1.000 $800
Dirt Hauling, 30 miles, round trip 40 CY $11 1.000 $440
Total, Div. 02000 $4,320
3 CONCRETE
Slab on Grade 70 CY $707 1.000 $49,511
Tank Pads 10 CY $634 1.000 $6,343
Fan Pads 2 CY $634 1.000 $1,269
Total, Div. 03000 $57,122
4 MASONRY
None
Total, Div. 04000 $0
5 METALS
Miscellaneous Metals 1 LS $3,000 1.000 $3,000
Total, Div. 05000 $3,000
6 WOOD AND PLASTICS
None
Total, Div. 06000 $0
7 THERMAL AND MOISTURE PROTECTION
None
Total, Div. 07000 $0
8 DOORS AND WINDOWS
None
Total, Div. 08000 $0
9 FINISHES
Painting 1 LS $7,500 1.000 $7,500
Total, Div. 09000 $7,500
10 SPECIALTIES
None
Total, Div. 10000 $0
11 EQUIPMENT
Packaged Bioscrubber 3 EA $450,000 1.000 $1,350,000
Includes:
Scrubber Tank
Blowers
Control Panel
Water Panel
Piping and Valves Between Panel and Scrubber
Nutrient Feed Pumps and Tank
Initial Nutrients
Material Installation
Total, Div. 11000 $1,350,000
File: Package 2 - Conceptual Design Cost Estimate.xlsTab: 8
Page 24 of 37
PRELIMINARY COST ESTIMATE - PACKAGE 2 - HEADWORKS AND PSTS
PROJECT : PRIMARY TREATMENT DESIGN LOCATION FACTOR: 1.000
CITY OF SUNNYVALE ESTIMATED MIDPOINT OF CONSTRUCTION : 11/3/2017
JOB # : 9265A.10 COST ESTIMATE PREPARATION DATE : 8/28/2014
LOCATION : SUNNYVALE, CA BY : THK
ELEMENT # : 8 REVIEWED BY: BK
ELEMENT : ODOR CONTROL FACILITY DH
DIVISION DESCRIPTION QUAN UNIT UNIT COST
LOCATION
FACTOR SUBTOTAL TOTAL
12 FURNISHING
None
Total, Div. 12000 $0
13 SPECIAL CONDITIONS
None
Total, Div. 13000 $0
14 CONVEYING SYSTEMS
None
Total, Div. 14000 $0
15 MECHANICAL
46" FRP Duct 18 LF $300 1.000 $5,400
32" FRP Duct 16 LF $190 1.000 $3,040
FRP Tees 2 EA $2,000 1.000 $4,000
FRP Elbows 4 EA $1,400 1.000 $5,600
Flexible Duct Connection 6 EA $400 1.000 $2,400
FRP Dampers 3 EA $500 1.000 $1,500
Drain Piping and Fittings 1 LS $10,000 1.000 $10,000
Miscellaneous Piping, Valves, Utility Station 1 LS $5,000 1.000 $5,000
Pipe Supports 1 LS $5,000 1.000 $5,000
Total, Div. 15000 $41,940Total, Div. 15000 $41,940
16 ELECTRICAL
Electrical (Power to manufacturer panels) 1 LS $50,000 1.000 $50,000
Total, Div. 16000 $50,000
17 INSTRUMENTATION
Instrumentation (Remote monitoring to SCADA) 1 LS $50,000 1.000 $50,000
Total, Div. 17000 $50,000
SUBTOTAL $1,563,882
Estimating Contingency 25% $390,971
SUBTOTAL $1,954,853
Sales Tax on 50% of Subtotal Above 8.75% $85,525
SUBTOTAL $2,040,378
General Conditions 10% $204,038
SUBTOTAL $2,244,416
General Contractor Overhead and Profit 13% $291,774
SUBTOTAL $2,536,190
Escalation to Mid-Point (at 3% Annual Inflation Rate) 9.88% $250,590
ELEMENT CONSTRUCTION COST $2,787,000
File: Package 2 - Conceptual Design Cost Estimate.xlsTab: 8
Page 25 of 37
PRELIMINARY COST ESTIMATE - PACKAGE 2 - HEADWORKS AND PSTS
PROJECT : PRIMARY TREATMENT DESIGN LOCATION FACTOR: 1.163
CITY OF SUNNYVALE ESTIMATED MIDPOINT OF CONSTRUCTION : 11/3/2017
JOB # : 9265A.10 COST ESTIMATE PREPARATION DATE : 8/28/2014
LOCATION : SUNNYVALE, CA BY : MK
ELEMENT # : 9 REVIEWED BY: KR
ELEMENT : HEADWORKS ELECTRICAL BUILDING JW
DIVISION DESCRIPTION QUAN UNIT UNIT COST
LOCATION
FACTOR SUBTOTAL TOTAL
2 SITEWORK
Site Cleaning and Preparation 1 LS $2,000 1.000 $2,000
Cat 235 Trackhoe 1.50CY Bucket, Class C (Hard Digging), 0-20' D 160 CY $4.27 1.163 $794Native Pipe Bed & Zone/Confined Structure Backfill, Class A 41 CY $28 1.163 $1,317ABC 44 CY $56 1.000 $2,46420 CY Dump Truck, 30 Miles/Round Trip 195 CY $13 1.163 $3,047
Total, Div. 02000 $9,623
3 CONCRETE
12" STRUCTURAL FLAT MAT ON GRADE 50 CY $500 1.163 $29,075
Total, Div. 03000 $29,075
4 MASONRY
Standard Concrete Block, 8" 283 SF $17 1.163 $5,696
Standard Concrete Block, 12" 2,547 SF $20 1.163 $57,894
Seismic Reinforcement Adder 2,547 SF $1 1.163 $4,194
Full Grout (All cells) 2,830 SF $1 1.163 $4,147
Pilaster Adder 283 SF $82 1.163 $26,994
Total, Div. 04000 $98,925
5 METALS
Structural Steel Shapes & Plates - Sub (ALLOWANCE) 1 EA $10,000 1.000 $10,000
Steel Deck, 3" X 16 Ga. 1,200 SF $7 1.163 $9,747
Aluminum Stairs, Including Railing and Supports 28 RSR $561 1.163 $18,276
Total, Div. 05000 $38,023
6 WOOD AND PLASTICS
None
Total, Div. 06000 $0
7 THERMAL AND MOISTURE PROTECTION
3-1/4" R-20.00 Composite Board Roof Insulation 1,200 SF $4 1.163 $6,266
Neoprene, Fully Adhered With Adhesive, Polychloroprene 1,200 SF $7 1.163 $10,048
Total, Div. 07000 $16,315
8 DOORS AND WINDOWS
7/0 X 7/0 X 1.75" NO LABEL DOUBLE HOLLOW METAL DOOR
W/FRAME & HDWRE 1 EA $1,645 1.163 $1,913
3/0 X 7/0 X 1.75" NO LABEL SINGLE HOLLOW METAL DOOR
W/FRAME & HDWRE 3 EA $853 1.163 $2,974
Total, Div. 08000 $4,888
9 FINISHES
None
Total, Div. 09000 $0
10 SPECIALTIES
File: Package 2 - Conceptual Design Cost Estimate.xlsTab: 9
Page 26 of 37
PRELIMINARY COST ESTIMATE - PACKAGE 2 - HEADWORKS AND PSTS
PROJECT : PRIMARY TREATMENT DESIGN LOCATION FACTOR: 1.163
CITY OF SUNNYVALE ESTIMATED MIDPOINT OF CONSTRUCTION : 11/3/2017
JOB # : 9265A.10 COST ESTIMATE PREPARATION DATE : 8/28/2014
LOCATION : SUNNYVALE, CA BY : MK
ELEMENT # : 9 REVIEWED BY: KR
ELEMENT : HEADWORKS ELECTRICAL BUILDING JW
DIVISION DESCRIPTION QUAN UNIT UNIT COST
LOCATION
FACTOR SUBTOTAL TOTAL
None
Total, Div. 10000 $0
11 EQUIPMENT
None
Total, Div. 11000 $0
12 FURNISHING
None
Total, Div. 12000 $0
13 SPECIAL CONDITIONS
Alarm and Security System 1 EA $30,000 1.000 $30,000
Total, Div. 13000 $30,000
14 CONVEYING SYSTEMS
None
Total, Div. 14000 $0Total, Div. 14000 $0
15 MECHANICAL
HVAC Allowance 1 EA $35,000 1.000 $35,000
Total, Div. 15000 $35,000
16 ELECTRICAL
Allowance for Electrical Equipment 1 LS $1,000,000 $1,000,000
Total, Div. 16000 $1,000,000
17 INSTRUMENTATION
PLC Cabinet 2 EA $176,400 $352,800
Communications Cabinet 1 EA $15,960 $15,960
Instrumentation Allowance (Percentage of Div. 1 - 15) 5% $11,342
Total, Div. 17000 $380,102
SUBTOTAL $1,641,951
Estimating Contingency 25% $410,488
SUBTOTAL $2,052,439
Sales Tax on 50% of Subtotal Above 8.75% $89,794
SUBTOTAL $2,142,233
General Conditions 10% $214,223
SUBTOTAL $2,356,456
General Contractor Overhead and Profit 13% $306,339
SUBTOTAL $2,662,796
Escalation to Mid-Point (at 3% Annual Inflation Rate) 9.88% $263,099
File: Package 2 - Conceptual Design Cost Estimate.xlsTab: 9
Page 27 of 37
PRELIMINARY COST ESTIMATE - PACKAGE 2 - HEADWORKS AND PSTS
PROJECT : PRIMARY TREATMENT DESIGN LOCATION FACTOR: 1.163
CITY OF SUNNYVALE ESTIMATED MIDPOINT OF CONSTRUCTION : 11/3/2017
JOB # : 9265A.10 COST ESTIMATE PREPARATION DATE : 8/28/2014
LOCATION : SUNNYVALE, CA BY : MK
ELEMENT # : 9 REVIEWED BY: KR
ELEMENT : HEADWORKS ELECTRICAL BUILDING JW
DIVISION DESCRIPTION QUAN UNIT UNIT COST
LOCATION
FACTOR SUBTOTAL TOTAL
ELEMENT CONSTRUCTION COST $2,926,000
File: Package 2 - Conceptual Design Cost Estimate.xlsTab: 9
Page 28 of 37
PRELIMINARY COST ESTIMATE - PACKAGE 2 - HEADWORKS AND PSTS
PROJECT : PRIMARY TREATMENT DESIGN LOCATION FACTOR: 1.163
CITY OF SUNNYVALE ESTIMATED MIDPOINT OF CONSTRUCTION : 11/3/2017
JOB # : 9265A.10 COST ESTIMATE PREPARATION DATE : 8/28/2014
LOCATION : SUNNYVALE, CA BY : MK
ELEMENT # : 10 REVIEWED BY: KR
ELEMENT : SWITCHGEAR BUILDING AND ELECTRICAL & INSTRUMENTATION SYSTEM JW
DIVISION DESCRIPTION QUAN UNIT UNIT COST
LOCATION
FACTOR SUBTOTAL TOTAL
2 SITEWORK
Site Cleaning and Preparation 1 LS $2,000 1.000 $2,000
Cat 235 Trackhoe 1.50CY Bucket, Class C (Hard Digging), 0-20' D 241 CY $4.27 1.163 $1,196Native Pipe Bed & Zone/Confined Structure Backfill, Class A 50 CY $28 1.163 $1,607ABC 78 CY $56 1.000 $4,36820 CY Dump Truck, 30 Miles/Round Trip 323 CY $13 1.163 $5,047
Total, Div. 02000 $14,218
3 CONCRETE
12" STRUCTURAL FLAT MAT ON GRADE 78 CY $500 1.163 $45,357
Total, Div. 03000 $45,357
4 MASONRY
Standard Concrete Block, 8" 1,288 SF $17 1.163 $25,924
Standard Concrete Block, 12" 2,966 SF $20 1.163 $67,418
Seismic Reinforcement Adder 2,966 SF $1 1.163 $4,884
Full Grout (All cells) 4,254 SF $1 1.163 $6,234
Pilaster Adder 330 SF $82 1.163 $31,477
Total, Div. 04000 $135,937
5 METALS5 METALS
Structural Steel Shapes & Plates - Sub (ALLOWANCE) 1 EA $10,000 1.000 $10,000
Steel Deck, 3" X 16 Ga. 2,117 SF $7 1.163 $17,196
Aluminum Stairs, Including Railing and Supports 28 RSR $561 1.163 $18,276
Total, Div. 05000 $45,472
6 WOOD AND PLASTICS
None
Total, Div. 06000 $0
7 THERMAL AND MOISTURE PROTECTION
3-1/4" R-20.00 Composite Board Roof Insulation 2,117 SF $4 1.163 $11,055
Neoprene, Fully Adhered With Adhesive, Polychloroprene 2,117 SF $7 1.163 $17,727
Total, Div. 07000 $28,782
8 DOORS AND WINDOWS
7/0 X 7/0 X 1.75" NO LABEL DOUBLE HOLLOW METAL DOOR
W/FRAME & HDWRE 1 EA $1,645 1.163 $1,913
3/0 X 7/0 X 1.75" NO LABEL SINGLE HOLLOW METAL DOOR
W/FRAME & HDWRE 7 EA $853 1.163 $6,940
Total, Div. 08000 $8,853
9 FINISHES
None
Total, Div. 09000 $0
File: Package 2 - Conceptual Design Cost Estimate.xlsTab: 10
Page 29 of 37
PRELIMINARY COST ESTIMATE - PACKAGE 2 - HEADWORKS AND PSTS
PROJECT : PRIMARY TREATMENT DESIGN LOCATION FACTOR: 1.163
CITY OF SUNNYVALE ESTIMATED MIDPOINT OF CONSTRUCTION : 11/3/2017
JOB # : 9265A.10 COST ESTIMATE PREPARATION DATE : 8/28/2014
LOCATION : SUNNYVALE, CA BY : MK
ELEMENT # : 10 REVIEWED BY: KR
ELEMENT : SWITCHGEAR BUILDING AND ELECTRICAL & INSTRUMENTATION SYSTEM JW
DIVISION DESCRIPTION QUAN UNIT UNIT COST
LOCATION
FACTOR SUBTOTAL TOTAL
10 SPECIALTIES
None
Total, Div. 10000 $0
11 EQUIPMENT
None
Total, Div. 11000 $0
12 FURNISHING
None
Total, Div. 12000 $0
13 SPECIAL CONDITIONS
Alarm and Security System 1 EA $30,000 1.000 $30,000
Total, Div. 13000 $30,000
14 CONVEYING SYSTEMS
None
Total, Div. 14000 $0
15 MECHANICAL
HVAC Allowance 1 EA $50,000 1.000 $50,000
Total, Div. 15000 $50,000
16 ELECTRICAL
Allowance for Electrical Equipment 1 LS $1,500,000 $1,500,000
Total, Div. 16000 $1,500,000
17 INSTRUMENTATION
HMI Hardware and Software 1 EA $327,600 $327,600
HMI Development Hardware and Software 1 EA $176,400 $176,400
Server Room UPS 1 EA $20,160 $20,160
Instrumentation Allowance (Percentage of Div. 1 - 15) 5% $15,431
Total, Div. 17000 $539,591
SUBTOTAL $2,398,210
Estimating Contingency 25% $599,553
SUBTOTAL $2,997,763
Sales Tax on 50% of Subtotal Above 8.75% $131,152
SUBTOTAL $3,128,915
General Conditions 10% $312,891
SUBTOTAL $3,441,806
General Contractor Overhead and Profit 13% $447,435
SUBTOTAL $3,889,241
File: Package 2 - Conceptual Design Cost Estimate.xlsTab: 10
Page 30 of 37
PRELIMINARY COST ESTIMATE - PACKAGE 2 - HEADWORKS AND PSTS
PROJECT : PRIMARY TREATMENT DESIGN LOCATION FACTOR: 1.163
CITY OF SUNNYVALE ESTIMATED MIDPOINT OF CONSTRUCTION : 11/3/2017
JOB # : 9265A.10 COST ESTIMATE PREPARATION DATE : 8/28/2014
LOCATION : SUNNYVALE, CA BY : MK
ELEMENT # : 10 REVIEWED BY: KR
ELEMENT : SWITCHGEAR BUILDING AND ELECTRICAL & INSTRUMENTATION SYSTEM JW
DIVISION DESCRIPTION QUAN UNIT UNIT COST
LOCATION
FACTOR SUBTOTAL TOTAL
Escalation to Mid-Point (at 3% Annual Inflation Rate) 9.88% $384,279
ELEMENT CONSTRUCTION COST $4,274,000
File: Package 2 - Conceptual Design Cost Estimate.xlsTab: 10
Page 31 of 37
PRELIMINARY COST ESTIMATE - PACKAGE 2 - HEADWORKS AND PSTS
PROJECT : PRIMARY TREATMENT DESIGN LOCATION FACTOR: 1.163
CITY OF SUNNYVALE ESTIMATED MIDPOINT OF CONSTRUCTION : 11/3/2017
JOB # : 9265A.10 COST ESTIMATE PREPARATION DATE : 8/28/2014
LOCATION : SUNNYVALE, CA BY : MK
ELEMENT # : 11 REVIEWED BY: KR
ELEMENT : STANDBY GENERATOR JW
DIVISION DESCRIPTION QUAN UNIT UNIT COST
LOCATION
FACTOR SUBTOTAL TOTAL
2 SITEWORK
Cat 235 Trackhoe 1.50CY Bucket, Class C (Hard Digging), 0-20' D 176 CY $4.27 1.163 $874Native Pipe Bed & Zone/Confined Structure Backfill, Class A 56 CY $28 1.163 $1,799ABC 48 CY $56 1.000 $2,68820 CY Dump Truck, 30 Miles/Round Trip 202 CY $13 1.163 $3,157
Total, Div. 02000 $8,518
3 CONCRETE
24" STRUCTURAL FLAT MAT ON GRADE 80 CY $500 1.163 $46,520
Total, Div. 03000 $46,520
4 MASONRY
None
Total, Div. 04000 $0
5 METALS
None
Total, Div. 05000 $0
6 WOOD AND PLASTICS6 WOOD AND PLASTICS
None
Total, Div. 06000 $0
7 THERMAL AND MOISTURE PROTECTION
None
Total, Div. 07000 $0
8 DOORS AND WINDOWS
None
Total, Div. 08000 $0
9 FINISHES
None
Total, Div. 09000 $0
10 SPECIALTIES
None
Total, Div. 10000 $0
11 EQUIPMENT
None
Total, Div. 11000 $0
File: Package 2 - Conceptual Design Cost Estimate.xlsTab: 11
Page 32 of 37
PRELIMINARY COST ESTIMATE - PACKAGE 2 - HEADWORKS AND PSTS
PROJECT : PRIMARY TREATMENT DESIGN LOCATION FACTOR: 1.163
CITY OF SUNNYVALE ESTIMATED MIDPOINT OF CONSTRUCTION : 11/3/2017
JOB # : 9265A.10 COST ESTIMATE PREPARATION DATE : 8/28/2014
LOCATION : SUNNYVALE, CA BY : MK
ELEMENT # : 11 REVIEWED BY: KR
ELEMENT : STANDBY GENERATOR JW
DIVISION DESCRIPTION QUAN UNIT UNIT COST
LOCATION
FACTOR SUBTOTAL TOTAL
12 FURNISHING
None
Total, Div. 12000 $0
13 SPECIAL CONDITIONS
None
Total, Div. 13000 $0
14 CONVEYING SYSTEMS
None
Total, Div. 14000 $0
15 MECHANICAL
Piping Allowance 1 EA $20,000 1.000 $20,000
Total, Div. 15000 $20,000
16 ELECTRICAL
Standby Generator 1 EA 708,780$ 1.000 708,780$
Fuel Tanks 1 EA 250,000$ 1.000 250,000$ Fuel Tanks 1 EA 250,000$ 1.000 250,000$
Total, Div. 16000 $958,780
17 INSTRUMENTATION
Miscellaneous Instrumentation - Generator and Fuel Tank 1 EA $20,000 1.000 $20,000
Total, Div. 17000 $20,000
SUBTOTAL $1,053,818
Estimating Contingency 25% $263,454
SUBTOTAL $1,317,272
Sales Tax on 50% of Subtotal Above 8.75% $57,631
SUBTOTAL $1,374,903
General Conditions 10% $137,490
SUBTOTAL $1,512,393
General Contractor Overhead and Profit 13% $196,611
SUBTOTAL $1,709,004
Escalation to Mid-Point (at 3% Annual Inflation Rate) 9.88% $168,859
ELEMENT CONSTRUCTION COST $1,878,000
File: Package 2 - Conceptual Design Cost Estimate.xlsTab: 11
Page 33 of 37
PRELIMINARY COST ESTIMATE - PACKAGE 2 - HEADWORKS AND PSTS
PROJECT : PRIMARY TREATMENT DESIGN LOCATION FACTOR: 1.000
CITY OF SUNNYVALE ESTIMATED MIDPOINT OF CONSTRUCTION : 11/3/2017
JOB # : 9265A.10 COST ESTIMATE PREPARATION DATE : 8/28/2014
LOCATION : SUNNYVALE, CA BY : THK
ELEMENT # : 12 REVIEWED BY: DH
ELEMENT : EXHAUST HEAT RECOVERY
NOTE:
DIVISION DESCRIPTION QUAN UNIT UNIT COST
LOCATION
FACTOR SUBTOTAL TOTAL
2 SITEWORK
Sitework 1 LS $10,000 1.000 $10,000
Total, Div. 02000 $10,000
3 CONCRETE
Concrete Slab/Miscellaneous Concrete 1 LS $10,000 1.000 $10,000
Equipment Pads 1 LS $1,000 1.000 $1,000
Total, Div. 03000 $11,000
4 MASONRY
None
Total, Div. 04000 $0
5 METALS
Miscellaneous metals 1 LS $20,000 1.000 $20,000
Total, Div. 05000 $20,000
6 WOOD AND PLASTICS
NoneNone
Total, Div. 06000 $0
7 THERMAL AND MOISTURE PROTECTION
None
Total, Div. 07000 $0
8 DOORS AND WINDOWS
None
Total, Div. 08000 $0
9 FINISHES
Painting and Protective Coatings (Piping and Equipment) 1 LS $15,000 1.000 $15,000
Total, Div. 09000 $15,000
10 SPECIALTIES
None
Total, Div. 10000 $0
11 EQUIPMENT
Exhaust Heat Recovery 1 LS $350,000 1.000 $350,000
Total, Div. 11000 $350,000
12 FURNISHING
File: Package 2 - Conceptual Design Cost Estimate.xlsTab: 12
Page 34 of 37
PRELIMINARY COST ESTIMATE - PACKAGE 2 - HEADWORKS AND PSTS
PROJECT : PRIMARY TREATMENT DESIGN LOCATION FACTOR: 1.000
CITY OF SUNNYVALE ESTIMATED MIDPOINT OF CONSTRUCTION : 11/3/2017
JOB # : 9265A.10 COST ESTIMATE PREPARATION DATE : 8/28/2014
LOCATION : SUNNYVALE, CA BY : THK
ELEMENT # : 12 REVIEWED BY: DH
ELEMENT : EXHAUST HEAT RECOVERY
NOTE:
DIVISION DESCRIPTION QUAN UNIT UNIT COST
LOCATION
FACTOR SUBTOTAL TOTAL
None
Total, Div. 12000 $0
13 SPECIAL CONDITIONS
None
Total, Div. 13000 $0
14 CONVEYING SYSTEMS
None
Total, Div. 14000 $0
15 MECHANICAL
Exhaust Heat Recovery Piping 1 LS $50,000 1.000 $50,000
Miscellaneous Equipment, Piping, Fittings and Valves 1 LS $145,000 1.000 $145,000
Total, Div. 15000 $195,000
16 ELECTRICAL
Electrical 1 LS $120,000 1.000 $120,000
Total, Div. 16000 $120,000Total, Div. 16000 $120,000
17 INSTRUMENTATION
Controls Improvements 1 EA $300,000 1.000 $300,000
Total, Div. 17000 $300,000
SUBTOTAL $1,021,000
Estimating Contingency 25% $255,250
SUBTOTAL $1,276,250
Sales Tax on 50% of Subtotal Above 8.75% $55,836
SUBTOTAL $1,332,086
General Conditions 10% $133,209
SUBTOTAL $1,465,295
General Contractor Overhead and Profit 13% $190,488
SUBTOTAL $1,655,783
Escalation to Mid-Point (at 3% Annual Inflation Rate) 9.88% $163,601
ELEMENT CONSTRUCTION COST $1,819,000
File: Package 2 - Conceptual Design Cost Estimate.xlsTab: 12
Page 35 of 37
PRELIMINARY COST ESTIMATE - PACKAGE 2 - HEADWORKS AND PSTS
PROJECT : PRIMARY TREATMENT DESIGN LOCATION FACTOR: 1.000
CITY OF SUNNYVALE ESTIMATED MIDPOINT OF CONSTRUCTION : 11/3/2017
JOB # : 9265A.10 COST ESTIMATE PREPARATION DATE : 8/28/2014
LOCATION : SUNNYVALE, CA BY : RN
ELEMENT # : 13 REVIEWED BY: DH
ELEMENT : TUNNEL SYSTEM KC
DIVISION DESCRIPTION QUAN UNIT UNIT COST
LOCATION
FACTOR SUBTOTAL TOTAL
2 SITEWORK
Excavations
8' x 8' Tunnel 6000 CY $7 1.000 $144,000
Backfill
8' x 8' Tunnel 3000 CY $10 1.000 $30,000
Hauling Excavated Material
8' x 8' Tunnel 3000 CY $11 1.000 $33,000
Total, Div. 02000 $207,000
3 CONCRETE
8' x 8' Tunnel 650 LF $2,500 1.000 $1,625,000
Total, Div. 03000 $1,625,000
4 MASONRY
None
Total, Div. 04000 $0
5 METALS
Stairs to Tunnels 3 LS $120,000 1.000 $360,000
Total, Div. 05000 $360,000
6 WOOD AND PLASTICS
None
Total, Div. 06000 $0
7 THERMAL AND MOISTURE PROTECTION
None
Total, Div. 07000 $0
8 DOORS AND WINDOWS
None
Total, Div. 08000 $0
9 FINISHES
None
Total, Div. 09000 $0
10 SPECIALTIES
None
Total, Div. 10000 $0
11 EQUIPMENT
File: Package 2 - Conceptual Design Cost Estimate.xlsTab: 13
Page 36 of 37
PRELIMINARY COST ESTIMATE - PACKAGE 2 - HEADWORKS AND PSTS
PROJECT : PRIMARY TREATMENT DESIGN LOCATION FACTOR: 1.000
CITY OF SUNNYVALE ESTIMATED MIDPOINT OF CONSTRUCTION : 11/3/2017
JOB # : 9265A.10 COST ESTIMATE PREPARATION DATE : 8/28/2014
LOCATION : SUNNYVALE, CA BY : RN
ELEMENT # : 13 REVIEWED BY: DH
ELEMENT : TUNNEL SYSTEM KC
DIVISION DESCRIPTION QUAN UNIT UNIT COST
LOCATION
FACTOR SUBTOTAL TOTAL
None
Total, Div. 11000 $0
12 FURNISHING
None
Total, Div. 12000 $0
13 SPECIAL CONSTRUCTION
None
Total, Div. 13000 $0
14 CONVEYING SYSTEMS
None
Total, Div. 14000 $0
15 MECHANICAL
Pipe Supports in Tunnel 650 LF $150 1.000 $97,500
Tunnel Drainage Pumps and piping 1 LS $25,000 1.000 $25,000
Total, Div. 15000 $122,500
16 ELECTRICAL
Allowance for Lighting 1 LS $30,000 1.000 $30,000
Allowance for Ventilation 1 LS $30,000 1.000 $30,000
Total, Div. 16000 $60,000
17 INSTRUMENTATION
Allowance for Instrumentation 1 LS $30,000 1.000 $30,000
Total, Div. 17000 $30,000
SUBTOTAL $2,404,500
Estimating Contingency 25% $601,125
SUBTOTAL $3,005,625
Sales Tax on 50% of Subtotal Above 8.75% $131,496
SUBTOTAL $3,137,121
General Conditions 10% $313,712
SUBTOTAL $3,450,833
General Contractor Overhead and Profit 13% $448,608
SUBTOTAL $3,899,442
Escalation to Mid-Point (at 3% Annual Inflation Rate) 9.88% $385,287
ELEMENT CONSTRUCTION COST $4,285,000
File: Package 2 - Conceptual Design Cost Estimate.xlsTab: 13
Page 37 of 37
Design Information Memorandum No. 12 PACKAGE 3 – DEMOLITION AND SITE RESTORATION
November 2014 - FINAL pw://Carollo/Documents/Client/CA/Sunnyvale/9265A10/DIMs/DIM 12-Construction Cost Estimate.docx
PROJECT : CITY OF SUNNYVALE
PRIMARY TREATMENT DESIGNPRELIMINARY COST ESTIMATE - PACKAGE 3 - DEMOLITION AND SITE RESTORATION ESTIMATED MIDPOINT OF CONSTRUCTION : 9/21/2019
JOB # : 9265A.10 COST ESTIMATE PREPARATION DATE : 8/28/2014ELEMENT : SUMMARY OF CONSTRUCTION COSTS BY : MK/KR
Rate of Annual Inflation: 3%Estimating Contingency: 25%
Sales Tax: 8.75%General Conditions: 10%
Contractor Overhead and Profit: 13%
ELEMENT # DESCRIPTION TOTAL
1 SITE DEMOLITION $2,780,000
Total Estimated Construction Cost = $2,780,000
File: Package 3 - Conceptual Design Cost Estimate.xlsTab: Summary
Page 1 of 4
PRELIMINARY COST ESTIMATE - PACKAGE 3 - DEMOLITION AND SITE RESTORATION
PROJECT : PRIMARY TREATMENT DESIGN LOCATION FACTOR: 1.163
CITY OF SUNNYVALE ESTIMATED MIDPOINT OF CONSTRUCTION : 9/21/2019
JOB # : 9265A.10 COST ESTIMATE PREPARATION DATE : 8/28/2014
LOCATION : SUNNYVALE, CA BY : MK/KR
ELEMENT # : 1 REVIEWED BY: JW
ELEMENT : SITE DEMOLITION
DIVISION DESCRIPTION QUAN UNIT UNIT COST
LOCATION
FACTOR SUBTOTAL TOTAL
2 SITEWORK
Auxiliary Pump Station
Earthwork Allowance 1 LS $200,000 1.000 $200,000
DEMO LARGE CONCRETE BUILDING 27720 CF $2.00 1.163 $64,477
Offhaul concrete demo 1027 CY $20.00 1.000 $20,533
Remove EquipmentInfluent Sampler 1 EA $2,000 1.000 $2,000
Influent Sluice Gate 1 EA $2,000 1.000 $2,000
Bar Screen 1 EA $10,000 1.000 $10,000Influent Pumps 2 EA $10,000 1.000 $20,000Flow Meter 2 EA $2,000 1.000 $4,000
Dewatering Sump Pump 1 EA $2,000 1.000 $2,000
Grinder Flush Water Valve 1 EA $2,000 1.000 $2,000
Influent Sampler Pump 1 EA $2,000 1.000 $2,000
Remove Piping
30" Influent Pump Discharge 20 LF $79 1.163 $1,840
48" Influent Pipe 23 LF $128 1.163 $3,417
24" Pump Discharge 60 LF $63 1.163 $4,390
Remove Electrical Equipment and Wiring 1 LS $10,000 1.000 $10,000
Primary Control Building
Remove Equipment EA 1.000 $0
Engines 3 $20,000 1.000 $60,000
90 Degree Drives 3 $5,000 1.000 $15,00090 Degree Drives 3 $5,000 1.000 $15,000
Influent Pumps 3 $10,000 1.000 $30,000
Air Blowers and Appurtenances (Silencing Intakes) 3 $10,000 1.000 $30,000
In-channel Grinders 2 $10,000 1.000 $20,000
In-channel Grinder Hydraulic System 1 $10,000 1.000 $10,000
Sludge Pumps 2 $5,000 1.000 $10,000
Screenings Pump 1 $5,000 1.000 $5,000
Heat Recovery System 1 $20,000 1.000 $20,000
Water Softening System 1 $5,000 1.000 $5,000
Boilers and Boiler Stacks 2 $10,000 1.000 $20,000
Repair Roof at Boiler Stack 1 $5,000 1.000 $5,000
Sluice Gates 2 $5,000 1.000 $10,000
Sluice Gate Hydraulic System 1 $5,000 1.000 $5,000
Air Compressors 2 $5,000 1.000 $10,000
Jib Cranes 2 $5,000 1.000 $10,000
Remove Piping LF
Allowance 1 LS $100,000 1.000 $100,000
Remove Electrical Equipment and Wiring 1 LS $30,000 1.000 $30,000
Primary Sedimentation Tanks
Remove Equipment EA 1.000 $0
Raw Sludge Pumps 10 $5,000 1.000 $50,000
Sedimentation Scum Removers 10 $5,000 1.000 $50,000
Sedimentation Cross Collectors 9 $5,000 1.000 $45,000
Sedimentation Longitudinal Collectors 10 $10,000 1.000 $100,000
Sedimentation Tank Drain Valves 10 $1,000 1.000 $10,000
Grit Removal Pumps 10 $5,000 1.000 $50,000
Grit Removal Pump Discharge Control Valves 10 $1,000 1.000 $10,000
Preaeration Air Diffusers in Tanks 10 $2,000 1.000 $20,000
Preaeration Tank Drain Valves 10 $1,000 1.000 $10,000
Preaeration Tank Slide Gates 10 $2,000 1.000 $20,000
Preaeration Tank Air Flowmeters 10 $500 1.000 $5,000
Effluent Launders 20 $1,000 1.000 $20,000
Effluent Slide Gates 20 $1,000 1.000 $20,000
Sedimentation Gallery Exhaust Fan 2 $2,000 1.000 $4,000
File: Package 3 - Conceptual Design Cost Estimate.xlsTab: 1
Page 2 of 4
PRELIMINARY COST ESTIMATE - PACKAGE 3 - DEMOLITION AND SITE RESTORATION
PROJECT : PRIMARY TREATMENT DESIGN LOCATION FACTOR: 1.163
CITY OF SUNNYVALE ESTIMATED MIDPOINT OF CONSTRUCTION : 9/21/2019
JOB # : 9265A.10 COST ESTIMATE PREPARATION DATE : 8/28/2014
LOCATION : SUNNYVALE, CA BY : MK/KR
ELEMENT # : 1 REVIEWED BY: JW
ELEMENT : SITE DEMOLITION
DIVISION DESCRIPTION QUAN UNIT UNIT COST
LOCATION
FACTOR SUBTOTAL TOTAL
Influent Gates 27 $1,000 1.000 $27,000
Scum Removal Air Blower 3 $5,000 1.000 $15,000
Scum Ejector 4 $5,000 1.000 $20,000
Influent Channel Slide Gates 3 $2,000 1.000 $6,000
Effluent Channel Slide Gates 10 $2,000 1.000 $20,000
Remove Piping LF
Allowance 1 LS $100,000 1.000 $100,000
Remove Electrical Equipment and Wiring 1 LS $30,000 1.000 $30,000
Landscaping Allowance 1 LS $100,000 1.000 $100,000
Total, Div. 02000 $1,475,657
3 CONCRETE
None
Total, Div. 03000 $0
4 MASONRY
None
Total, Div. 04000 $0
5 METALS5 METALS
None
Total, Div. 05000 $0
6 WOOD AND PLASTICS
None
Total, Div. 06000 $0
7 THERMAL AND MOISTURE PROTECTION
None
Total, Div. 07000 $0
8 DOORS AND WINDOWS
None
Total, Div. 08000 $0
9 FINISHES
None
Total, Div. 09000 $0
10 SPECIALITIES
None
Total, Div 10000 $0
File: Package 3 - Conceptual Design Cost Estimate.xlsTab: 1
Page 3 of 4
PRELIMINARY COST ESTIMATE - PACKAGE 3 - DEMOLITION AND SITE RESTORATION
PROJECT : PRIMARY TREATMENT DESIGN LOCATION FACTOR: 1.163
CITY OF SUNNYVALE ESTIMATED MIDPOINT OF CONSTRUCTION : 9/21/2019
JOB # : 9265A.10 COST ESTIMATE PREPARATION DATE : 8/28/2014
LOCATION : SUNNYVALE, CA BY : MK/KR
ELEMENT # : 1 REVIEWED BY: JW
ELEMENT : SITE DEMOLITION
DIVISION DESCRIPTION QUAN UNIT UNIT COST
LOCATION
FACTOR SUBTOTAL TOTAL
11 EQUIPMENT
None
Total, Div. 11000 $0
12 FURNISHING
None
Total, Div. 12000 $0
13 SPECIAL CONSTRUCTION
None
Total, Div. 13000 $0
14 CONVEYING SYSTEMS
None
Total, Div. 14000 $0
15 MECHANICAL
None
Total, Div. 15000 $0
16 ELECTRICAL
None
$0
Total, Div. 16000
17 INSTRUMENTATION
None
Total, Div. 17000 $0
SUBTOTAL $1,475,657
Estimating Contingency 25% $368,914
SUBTOTAL $1,844,571
Sales Tax on 50% of Subtotal Above 8.75% $80,700
SUBTOTAL $1,925,271
General Conditions 10% $192,527
SUBTOTAL $2,117,798
General Contractor Overhead and Profit 13% $275,314
SUBTOTAL $2,393,112
Escalation to Mid-Point (at 3% Annual Inflation Rate) 16.16% $386,783
ELEMENT CONSTRUCTION COST $2,780,000
File: Package 3 - Conceptual Design Cost Estimate.xlsTab: 1
Page 4 of 4