city of sunnyvale · culvert and temporary bypass $7,007,000 : $7,300,000 . subtotal $17,924,000 ....

67
CITY OF SUNNYVALE PRIMARY TREATMENT DESIGN DESIGN INFORMATION MEMORANDUM NO. 12 PRELIMINARY CONSTRUCTION COST ESTIMATE FINAL November 2014 Prepared By:______________________ Katy Rogers, P.E. Reviewed By:______________________ James Wickstrom, P.E. 2700 YGNACIO VALLEY ROAD • SUITE 300 • WALNUT CREEK, CALIFORNIA 94598 (925) 932 - 1710 • FAX (925) 930 -020 8 pw://Carollo/Documents/Client/CA/Sunnyvale/9265A10/DIMs/DIM 12-Construction Cost Estimate.docx

Upload: doandan

Post on 28-Apr-2019

226 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: City of Sunnyvale · Culvert and Temporary Bypass $7,007,000 : $7,300,000 . Subtotal $17,924,000 . ... Includes installation of a new box culvert to replace the storm drainage volume

CITY OF SUNNYVALE

PRIMARY TREATMENT DESIGN

DESIGN INFORMATION MEMORANDUM NO. 12

PRELIMINARY CONSTRUCTION COST ESTIMATE

FINAL

November 2014

Prepared By:______________________ Katy Rogers, P.E.

Reviewed By:______________________ James Wickstrom, P.E.

2 7 0 0 Y G N A C I O V A L L E Y R O A D • S U I T E 3 0 0 • W A L N U T C R E E K , C A L I F O R N I A 9 4 5 9 8 • ( 9 2 5 ) 9 3 2 - 1 7 1 0 • F A X ( 9 2 5 ) 9 3 0 - 0 2 0 8 pw://Carollo/Documents/Client/CA/Sunnyvale/9265A10/DIMs/DIM 12-Construction Cost Estimate.docx

Page 2: City of Sunnyvale · Culvert and Temporary Bypass $7,007,000 : $7,300,000 . Subtotal $17,924,000 . ... Includes installation of a new box culvert to replace the storm drainage volume
Page 3: City of Sunnyvale · Culvert and Temporary Bypass $7,007,000 : $7,300,000 . Subtotal $17,924,000 . ... Includes installation of a new box culvert to replace the storm drainage volume

CITY OF SUNNYVALE

PRIMARY TREATMENT DESIGN

DESIGN INFORMATION MEMORANDUM NO. 12

PRELIMINARY CONSTRUCTION COST ESTIMATE

TABLE OF CONTENTS Page No.

1.0 PURPOSE .......................................................................................................... 12-1

2.0 BASIS OF COST ESTIMATE .............................................................................. 12-1

3.0 PRELIMINARY CONSTRUCTION COST ESTIMATE ......................................... 12-2

APPENDIX - Preliminary Construction Cost Estimate Breakdown

LIST OF TABLES Table 12.1 Construction Schedule Basis for Preliminary Cost Estimate ...................... 12-2 Table 12.2 Preliminary Construction Cost Estimate ..................................................... 12-3

November 2014 - FINAL i pw://Carollo/Documents/Client/CA/Sunnyvale/9265A10/DIMs/DIM 12-Construction Cost Estimate.docx

Page 4: City of Sunnyvale · Culvert and Temporary Bypass $7,007,000 : $7,300,000 . Subtotal $17,924,000 . ... Includes installation of a new box culvert to replace the storm drainage volume
Page 5: City of Sunnyvale · Culvert and Temporary Bypass $7,007,000 : $7,300,000 . Subtotal $17,924,000 . ... Includes installation of a new box culvert to replace the storm drainage volume

November 2014 - FINAL 12-1 pw://Carollo/Documents/Client/CA/Sunnyvale/9265A10/DIMs/DIM 12-Construction Cost Estimate.docx

Design Information Memorandum No. 12

PRELIMINARY CONSTRUCTION COST ESTIMATE

1.0 PURPOSE

The purpose of this Design Information Memorandum (DIM) is to present the preliminary engineer’s construction cost estimate for the primary treatment design project at the City of Sunnyvale’s Water Pollution Control Plant (WPCP). Please refer to the individual technical memoranda (TMs) included in the preliminary design report for detailed descriptions of the recommended project elements.

2.0 BASIS OF COST ESTIMATE

The preliminary engineer’s construction cost estimate is representative of a 10-percent level design cost estimate. The estimated construction costs presented in this DIM are based on preliminary layouts and preliminary unit sizes as developed in DIM Nos. 1 through 11. Other construction elements that may not be described in the DIMs but are required for the project, such as sitework, yard piping, yard structures, etc., are also included in the cost estimate.

The estimated construction costs were developed from preliminary quantity takeoffs, estimating guides, equipment manufacturers’ quotes, and construction costs of similar facilities at other locations. An estimating contingency of 25 percent is applied to the estimated construction costs to compensate for lack of design details known at this stage, uncertainties in bidding climate, and assumptions used in the estimating methods. A local sales tax of 8.75 percent is included for approximately half the estimated construction costs. A 10 percent factor is applied to the estimate to cover the contractor’s cost to meet the General Conditions of the specifications, including mobilization, demobilization, bonds, insurance, and field overhead. A 13 percent factor is applied to the estimate to cover the general contractor’s home office overhead and profit on the project.

Engineering, legal, and administration costs, as well as construction contingencies for contract change orders, are not included in the estimated construction costs.

While the estimated construction costs represent the average bidding conditions for this project, variations in bidding climate at the time that the facilities are constructed could affect actual construction costs. Furthermore, the size and character of the facilities will be refined during final design based on the most current operational information, evolving design concepts, and plant staff input. For these reasons, it is possible that the actual construction costs may be lower or higher than estimated.

An overall annual cost escalation of 3 percent per year was used to account for cost escalation to the mid-point of construction. For planning purposes, it is anticipated the

Page 6: City of Sunnyvale · Culvert and Temporary Bypass $7,007,000 : $7,300,000 . Subtotal $17,924,000 . ... Includes installation of a new box culvert to replace the storm drainage volume

November 2014 - FINAL 12-2 pw://Carollo/Documents/Client/CA/Sunnyvale/9265A10/DIMs/DIM 12-Construction Cost Estimate.docx

project will be constructed in three packages. Table 12.1 summarizes the assumed construction start date, construction duration, and mid-point of construction date for each package.

Table 12.1 Construction Schedule Basis for Preliminary Cost Estimate Primary Treatment Design City of Sunnyvale

Package Construction Duration,

months Start of Construction Mid-Point of Construction

1 9 September 2015 June 2016

2 30 August 2016 February 2019

3 9 May 2019 February 2020

3.0 PRELIMINARY CONSTRUCTION COST ESTIMATE

Table 12.2 presents the preliminary construction cost estimate for the primary treatment design project. Detailed construction cost estimate breakdowns for each major element are included in the Appendix.

Page 7: City of Sunnyvale · Culvert and Temporary Bypass $7,007,000 : $7,300,000 . Subtotal $17,924,000 . ... Includes installation of a new box culvert to replace the storm drainage volume

Table 12.2 Preliminary Construction Cost Estimate Primary Treatment Design City of Sunnyvale

Element No. Description

2014 Construction Cost(1)

Escalated Construction Cost(2)

Package 1 – Site Preparation

1 Demolition(3) $1,578,000 $1,644,000

2 Site Work(4) $9,339,000 $9,731,000

3 Culvert and Temporary Bypass(5) $7,007,000 $7,300,000

Subtotal $17,924,000 $18,675,000 Package 2 – Headworks and PSTs

1 Paving, Grading, Yard Piping, and Yard Structures(6)

$11,580,000 $12,724,000

2 Screening Facility(7) $7,571,000 $8,319,000

3 Grit & Screenings Handling Building(8)

$3,266,000 $3,589,000

4 Influent Pump Station(9) $8,702,000 $9,561,000

5 Grit Basins(10) $6,410,000 $7,043,000

6 Primary Sedimentation Tanks(11) $15,138,000 $16,634,000

7 CEPT Facility(12) $1,090,000 $1,198,000

8 Odor Control Facility(13) $2,536,000 $2,787,000

9 Headworks Electrical Building(14) $2,663,000 $2,926,000

10 Switchgear Building and Electrical & Instrumentation System(15)

$3,889,000 $4,274,000

11 Standby Generator(16) $1,709,000 $1,878,000

12 Exhaust Heat Recovery(17) $1,656,000 $1,819,000

13 Tunnel System(18) $3,899,000 $4,285,000

14 PE Pipeline From Plant to Ponds(19)

$0 $0

Subtotal $70,109,000 $77,037,000 Package 3 – Demolition and Site Restoration

1 Site Demolition(20) $2,393,000 $2,780,000

Subtotal $2,393,000 $2,780,000 Total $90,426,000 $98,492,000

November 2014 - FINAL 12-3 pw://Carollo/Documents/Client/CA/Sunnyvale/9265A10/DIMs/DIM 12-Construction Cost Estimate.docx

Page 8: City of Sunnyvale · Culvert and Temporary Bypass $7,007,000 : $7,300,000 . Subtotal $17,924,000 . ... Includes installation of a new box culvert to replace the storm drainage volume

Table 12.2 Preliminary Construction Cost Estimate Primary Treatment Design City of Sunnyvale

Element No. Description

2014 Construction Cost(1)

Escalated Construction Cost(2)

Notes: (1) Construction cost in June 2014 dollars. (2) Construction cost to escalated midpoint of construction assuming a 3% annual inflation rate. (3) Includes demolition of the sludge dewatering beds, sludge area drain pump station, and paving,

lighting, and buried utilities in the existing sludge drying bed area. (4) Includes raising the project site area to finished grade (elevation 109.0 ±), surcharging site to

pre-consolidate soils, and removing earthen surcharge material. (5) Includes installation of a new box culvert to replace the storm drainage volume of the existing

drainage ditch located along the southeast edge of the plant. This element also includes temporary bypass pumping to facilitate construction of culvert.

(6) Includes yard piping, yard structures, electrical ductbanks, asphalt paving, site drainage facilities, and fencing.

(7) Includes a new screening facility with four bar screen channels and one bypass channel, one shaftless screw screenings conveyor, and two screenings washer/compactors.

(8) Includes a new two story building housing three grit washers, grit and screenings storage bins and an electrical room.

(9) Includes a new influent pump station with three wet well compartments and six non-clog dry pit submersible pumps located in a dry pit.

(10) Includes three grit basins with six grit slurry transfer pumps. (11) Includes six primary sedimentation tanks, an aerated primary influent channel, a primary

effluent channel, nine primary sludge pumps, four primary scum pumps and two aeration blowers.

(12) Includes a concrete containment area with two 8000 gallon ferric chloride storage tanks, two polymer storage totes, and associated chemical feed systems.

(13) Includes three packaged bioscrubbers on a concrete support pad with associated fans, ducting, control panels, and other appurtenances.

(14) Includes a concrete masonry block building housing 480 volt switchgear, MCCs, influent pump VFDs, switchboards, and PLC and communications cabinets. This element also includes two exterior 12 kV to 480 volt transformers.

(15) Includes a concrete masonry block building housing new 12 kV switchgear, switch gear controls, generator controls, switchgear battery system, and an ACS server room.

(16) Includes a 2000 kW, 12 kV, standby generator housed in a custom-built walk-in enclosure; an aboveground diesel fuel storage tank; and a generator load bank .

(17) Includes the addition of exhaust heat recovery system to the existing engine generators at the PGF facility and new engine generator controls.

(18) Includes a new below grade tunnel system designed for personnel entry with pipe supports, tunnel drainage system, lighting, and ventilation.

(19) Pending condition assessment of existing primary effluent pipeline. Work will not be included in Package 2.

(20) Includes removal of mechanical equipment and piping from the existing primary control building and primary sedimentation tanks, and demolition of the existing auxiliary pump station.

November 2014 - FINAL 12-4 pw://Carollo/Documents/Client/CA/Sunnyvale/9265A10/DIMs/DIM 12-Construction Cost Estimate.docx

Page 9: City of Sunnyvale · Culvert and Temporary Bypass $7,007,000 : $7,300,000 . Subtotal $17,924,000 . ... Includes installation of a new box culvert to replace the storm drainage volume

Design Information Memorandum No. 12 APPENDIX – PRELIMINARY CONSTRUCTION COST

ESTIMATE BREAKDOWN

November 2014 - FINAL pw://Carollo/Documents/Client/CA/Sunnyvale/9265A10/DIMs/DIM 12-Construction Cost Estimate.docx

Page 10: City of Sunnyvale · Culvert and Temporary Bypass $7,007,000 : $7,300,000 . Subtotal $17,924,000 . ... Includes installation of a new box culvert to replace the storm drainage volume
Page 11: City of Sunnyvale · Culvert and Temporary Bypass $7,007,000 : $7,300,000 . Subtotal $17,924,000 . ... Includes installation of a new box culvert to replace the storm drainage volume

Design Information Memorandum No. 12 PACKAGE 1 – SITE PREPARATION

November 2014 - FINAL pw://Carollo/Documents/Client/CA/Sunnyvale/9265A10/DIMs/DIM 12-Construction Cost Estimate.docx

Page 12: City of Sunnyvale · Culvert and Temporary Bypass $7,007,000 : $7,300,000 . Subtotal $17,924,000 . ... Includes installation of a new box culvert to replace the storm drainage volume
Page 13: City of Sunnyvale · Culvert and Temporary Bypass $7,007,000 : $7,300,000 . Subtotal $17,924,000 . ... Includes installation of a new box culvert to replace the storm drainage volume

PROJECT : CITY OF SUNNYVALEPRIMARY TREATMENT DESIGNPRELIMINARY COST ESTIMATE - PACKAGE 1 - SITE PREPARATION ESTIMATED MIDPOINT OF CONSTRUCTION : 1/15/2016

JOB # : 9265A.10 COST ESTIMATE PREPARATION DATE : 8/28/2014JOB # : 9265A.10 COST ESTIMATE PREPARATION DATE : 8/28/2014ELEMENT : SUMMARY OF CONSTRUCTION COSTS BY : RN/MP

Rate of Annual Inflation: 3%Estimating Contingency: 25%

Sales Tax: 8.75%General Conditions: 10%

Contractor Overhead and Profit: 13%

ELEMENT # DESCRIPTION TOTAL

1 DEMOLITION $1,644,000

2 SITE WORK $9,731,000

3 CULVERT AND BYPASS $7 300 0003 CULVERT AND BYPASS $7,300,000

Total Estimated Construction Cost = $18,675,000

File: Package 1 - Conceptual Design Cost Estimate.xlsxTab: Summary

Page 1 of 7

Page 14: City of Sunnyvale · Culvert and Temporary Bypass $7,007,000 : $7,300,000 . Subtotal $17,924,000 . ... Includes installation of a new box culvert to replace the storm drainage volume
Page 15: City of Sunnyvale · Culvert and Temporary Bypass $7,007,000 : $7,300,000 . Subtotal $17,924,000 . ... Includes installation of a new box culvert to replace the storm drainage volume

PRELIMINARY COST ESTIMATE - PACKAGE 1 - SITE PREPARATION

PROJECT : PRIMARY TREATMENT DESIGN LOCATION FACTOR: 1.000CITY OF SUNNYVALE ESTIMATED MIDPOINT OF CONSTRUCTION : 1/15/2016

JOB # : COST ESTIMATE PREPARATION DATE : 8/26/2014

LOCATION : SUNNYVALE, CA BY : RN/MPELEMENT # : 1 REVIEWED BY: DHELEMENT : DEMOLITION

DIVISION DESCRIPTION QUAN UNIT UNIT COSTLOCATION FACTOR SUBTOTAL TOTAL

2 SITEWORK

Remove AC Paving 3,100 SY $8 1.000 $24,800Remove Dry Sludge and Haul Offsite from Sludge Lagoon 1750 CY $40 1.000 $70,000Remove miscellaneous concrete walls and curbs 1 LS $30,000 1.000 $30,000Remove existing lighting, conduits, and electrical boxes 1 LS $50,000 1.000 $50,000Remove existing Chain Link Fence 900 LF $8 1 000 $7 200Remove existing Chain Link Fence 900 LF $8 1.000 $7,200Tree Removal in Drainage Ditch 1 LS $25,000 1.000 $25,000Demolish Sludge Dewatering Beds and appurtenances 22,000 SF $30 1.000 $660,000Demolish Drain Pump Station 1 LS $30,000 1.000 $30,000Demolish Sludge Pump Station 300 SF $40 1.000 $12,000Demolish Drainage Piping in Sludge Lagoon 1 LS $15,000 1.000 $15,000Demolish Drainage Piping under Sludge Drying Beds 1 LS $15,000 1.000 $15,000Demolish 72" CMP in Ditch 170 LF $196 1.000 $34,000.00

Total, Div. 02000 $973,000

3 CONCRETE

NoneTotal, Div. 03000 $0

4 MASONRY

NoneTotal, Div. 04000 $0

5 METALS

NoneTotal, Div. 05000 $0

6 WOOD AND PLASTICS

NoneTotal, Div. 06000 $0

7 THERMAL AND MOISTURE PROTECTION

None

T t l Di 07000 $0Total, Div. 07000 $0

8 DOORS AND WINDOWS

NoneTotal, Div. 08000 $0

9 FINISHES

NoneTotal, Div. 09000 $0

10 SPECIALITIES

NoneTotal, Div 10000 $0

11 EQUIPMENT

NoneTotal, Div. 11000 $0

12 FURNISHING12 FURNISHING

NoneTotal, Div. 12000 $0

File: Package 1 - Conceptual Design Cost Estimate.xlsxTab: 1 ‐ Demolition

Page 1 of 6

Page 16: City of Sunnyvale · Culvert and Temporary Bypass $7,007,000 : $7,300,000 . Subtotal $17,924,000 . ... Includes installation of a new box culvert to replace the storm drainage volume

PRELIMINARY COST ESTIMATE - PACKAGE 1 - SITE PREPARATION

PROJECT : PRIMARY TREATMENT DESIGN LOCATION FACTOR: 1.000CITY OF SUNNYVALE ESTIMATED MIDPOINT OF CONSTRUCTION : 1/15/2016

JOB # : COST ESTIMATE PREPARATION DATE : 8/26/2014

LOCATION : SUNNYVALE, CA BY : RN/MPELEMENT # : 1 REVIEWED BY: DHELEMENT : DEMOLITION

DIVISION DESCRIPTION QUAN UNIT UNIT COSTLOCATION FACTOR SUBTOTAL TOTAL

13 SPECIAL CONSTRUCTION

NoneTotal, Div. 13000 $0

14 CONVEYING SYSTEMS

NNoneTotal, Div. 14000 $0

15 MECHANICAL

NoneTotal, Div. 15000 $0

16 ELECTRICAL

NoneTotal, Div. 16000

17 INSTRUMENTATION

NoneTotal, Div. 17000

SUBTOTAL $973,000

Estimating Contingency 25% $243,250SUBTOTAL $1,216,250

Sales Tax on 50% of Subtotal Above 8.75% $53,211SUBTOTAL $1,269,461

General Conditions 10% $126,946SUBTOTAL $1,396,407

General Contractor Overhead and Profit 13% $181,533SUBTOTAL $1,577,940

Escalation to Mid-Point (at 3% Annual Inflation Rate) 4.19% $66,136

ELEMENT CONSTRUCTION COST $1,644,000

File: Package 1 - Conceptual Design Cost Estimate.xlsxTab: 1 ‐ Demolition

Page 2 of 6

Page 17: City of Sunnyvale · Culvert and Temporary Bypass $7,007,000 : $7,300,000 . Subtotal $17,924,000 . ... Includes installation of a new box culvert to replace the storm drainage volume

PRELIMINARY COST ESTIMATE - PACKAGE 1 - SITE PREPARATION

PROJECT : PRIMARY TREATMENT DESIGN LOCATION FACTOR: 1.000CITY OF SUNNYVALE ESTIMATED MIDPOINT OF CONSTRUCTION : 1/15/2016

JOB # : COST ESTIMATE PREPARATION DATE : 8/26/2014

LOCATION : SUNNYVALE, CA BY : RN/MPELEMENT # : 2 REVIEWED BY: DHELEMENT : SITE WORK

DIVISION DESCRIPTION QUAN UNIT UNIT COSTLOCATION FACTOR SUBTOTAL TOTAL

2 SITEWORK

Site Clearing and Grubbing (incld drainage ditch clear and grub) 1 LS $25,000 1.000 $25,000Finish Grading to drain to existing site waste PS 1 LS $15,000 1.000 $15,000Ditch Dewatering (prior to filling and to remove 72" CMP) 1 LS $10,000 1.000 $10,000Utility Polholing 1 LS $10,000 1.000 $10,000Import and Place Fill over Drainage Ditch to Elevation 109 25 000 CY $24 9 1 000 $623 000Import and Place Fill over Drainage Ditch to Elevation 109 25,000 CY $24.9 1.000 $623,000Import and Place Fill for Package 2 Facilities to Elevation 109 58,000 CY $24.9 1.000 $1,445,360Import and Place Fill for Aeration Basin to Elevation 109 43,000 CY $24.9 1.000 $1,071,560Import and Place Fill to preload site for Package 2 Facilities 42,000 CY $23.8 1.000 $1,001,280Vertical drains to fasten pre-consolidation 1 LS $430,000 1.000 $430,000Export preload 42,000 CY $18 1.000 $756,000Storm water management at construction site 1 LS $25,000 1.000 $25,000Temporary Fence 1 LS $28,600 1.000 $28,600Contractor Access Gate 1 EA $6,000 1.000 $6,000Access Gate 1 EA $8,000 1.000 $8,000Chain Link Fence 1,300 LF $50 1.000 $65,000

Total, Div. 02000 $5,519,800

3 CONCRETE

Sidewalk outside of fence 115 CY $700 1.000 $80,500Segmental Retaining Wall 3,400 SF $40 1.000 $136,000

Total, Div. 03000 $216,500

4 MASONRY

NoneT l Di 04000 $0Total, Div. 04000 $0

5 METALS

NoneTotal, Div. 05000 $0

6 WOOD AND PLASTICS

NoneTotal, Div. 06000 $0

7 THERMAL AND MOISTURE PROTECTION

NoneTotal, Div. 07000 $0

8 DOORS AND WINDOWS

NoneTotal, Div. 08000 $0

9 FINISHES9 FINISHES

NoneTotal, Div. 09000 $0

10 SPECIALITIES

NoneTotal, Div 10000 $0

11 EQUIPMENT

NoneTotal, Div. 11000 $0

File: Package 1 - Conceptual Design Cost Estimate.xlsxTab: 2 ‐ Site Work

Page 3 of 6

Page 18: City of Sunnyvale · Culvert and Temporary Bypass $7,007,000 : $7,300,000 . Subtotal $17,924,000 . ... Includes installation of a new box culvert to replace the storm drainage volume

PRELIMINARY COST ESTIMATE - PACKAGE 1 - SITE PREPARATION

PROJECT : PRIMARY TREATMENT DESIGN LOCATION FACTOR: 1.000CITY OF SUNNYVALE ESTIMATED MIDPOINT OF CONSTRUCTION : 1/15/2016

JOB # : COST ESTIMATE PREPARATION DATE : 8/26/2014

LOCATION : SUNNYVALE, CA BY : RN/MPELEMENT # : 2 REVIEWED BY: DHELEMENT : SITE WORK

DIVISION DESCRIPTION QUAN UNIT UNIT COSTLOCATION FACTOR SUBTOTAL TOTAL

12 FURNISHING

NoneTotal, Div. 12000 $0

13 SPECIAL CONSTRUCTION

NNoneTotal, Div. 13000 $0

14 CONVEYING SYSTEMS

NoneTotal, Div. 14000 $0

15 MECHANICAL

NoneTotal Div 15000 $0Total, Div. 15000 $0

16 ELECTRICAL

Access gate electrical/security gate/key pad 1 LS $20,000 1.000 $20,000Total, Div. 16000 $20,000

17 INSTRUMENTATION

Access gate instrumentation 1 LS $2,500 1.000 $2,500$2,500

Total, Div. 17000 $0

SUBTOTAL $5,758,800

Estimating Contingency 25% $1,439,700SUBTOTAL $7,198,500

Sales Tax on 50% of Subtotal Above 8.75% $314,934SUBTOTAL $7,513,434

General Conditions 10% $751,343SUBTOTAL $8 264 778SUBTOTAL $8,264,778

General Contractor Overhead and Profit 13% $1,074,421SUBTOTAL $9,339,199

Escalation to Mid-Point (at 3% Annual Inflation Rate) 4% $391,433

ELEMENT CONSTRUCTION COST $9,731,000

File: Package 1 - Conceptual Design Cost Estimate.xlsxTab: 2 ‐ Site Work

Page 4 of 6

Page 19: City of Sunnyvale · Culvert and Temporary Bypass $7,007,000 : $7,300,000 . Subtotal $17,924,000 . ... Includes installation of a new box culvert to replace the storm drainage volume

PRELIMINARY COST ESTIMATE - PACKAGE 1 - SITE PREPARATION

PROJECT : PRIMARY TREATMENT DESIGN LOCATION FACTOR: 1.000CITY OF SUNNYVALE ESTIMATED MIDPOINT OF CONSTRUCTION : 1/15/2016

JOB # : COST ESTIMATE PREPARATION DATE : 8/26/2014

LOCATION : SUNNYVALE, CA BY : RN/MPELEMENT # : 3 REVIEWED BY: DHELEMENT : CULVERT AND TEMPORARY BYPASS

DIVISION DESCRIPTION QUAN UNIT UNIT COSTLOCATION FACTOR SUBTOTAL TOTAL

2 SITEWORK

Excavation down from elevation 109 17,102 CY $7 1.000 $119,714Sheet Piles 35,860 SF $29 1.000 $1,039,940

Dewatering (during temporary bypass PS and Culvert construction) 1 LS $100,000 1.000 $100,000Temporary Rerouting SD pipes from Culvert Sides 1 LS $40 000 1 000 $40 000Temporary Rerouting SD pipes from Culvert Sides 1 LS $40,000 1.000 $40,000Backfill over Culvert 13,480 CY $8 1.000 $107,840Export Dirt 3,622 CY $18 1.000 $65,196168" x 84" Culvert aggregate base 543 CY $46 1.000 $24,993

Total, Div. 02000 $1,497,683

3 CONCRETE

168" x 84" precast, double barrel concrete culvert (mtrl to site) 815 LF $800 1.000 $652,000Box Culvert Installation 1 LS $270,000 1.000 $270,000Culvert Headwall 40 CY $1,200 1.000 $48,000Culvert Headwall 40 CY $1,200 1.000 $48,000Miscellaneous Concrete 1 LS $10,000 1.000 $10,000Bypass Pump Station Structure 1 LS $200,000 1.000 $200,000

Total, Div. 03000 $1,180,000

4 MASONRY

None

Total, Div. 04000 $0

5 METALS

Miscellaneous Metals 1 LS $5,000 1.000 $5,000

Total, Div. 05000 $5,000

6 WOOD AND PLASTICS

None

Total Div 06000 $0Total, Div. 06000 $0

7 THERMAL AND MOISTURE PROTECTION

None

Total, Div. 07000 $0

8 DOORS AND WINDOWS

NoneTotal, Div. 08000 $0, $0

9 FINISHES

Painting and Protective Coating 1 LS $7,500 1.000 $7,500Total, Div. 09000 $7,500

10 SPECIALITIES

Signs, Identification, Stenciling and Tagging System 1 LS $5,000 1.000 $5,000

Total, Div 10000 $5,000

File: Package 1 - Conceptual Design Cost Estimate.xlsxTab: 3 ‐ Culvert and Bypass

Page 5 of 6

Page 20: City of Sunnyvale · Culvert and Temporary Bypass $7,007,000 : $7,300,000 . Subtotal $17,924,000 . ... Includes installation of a new box culvert to replace the storm drainage volume

PRELIMINARY COST ESTIMATE - PACKAGE 1 - SITE PREPARATION

PROJECT : PRIMARY TREATMENT DESIGN LOCATION FACTOR: 1.000CITY OF SUNNYVALE ESTIMATED MIDPOINT OF CONSTRUCTION : 1/15/2016

JOB # : COST ESTIMATE PREPARATION DATE : 8/26/2014

LOCATION : SUNNYVALE, CA BY : RN/MPELEMENT # : 3 REVIEWED BY: DHELEMENT : CULVERT AND TEMPORARY BYPASS

DIVISION DESCRIPTION QUAN UNIT UNIT COSTLOCATION FACTOR SUBTOTAL TOTAL

11 EQUIPMENT

Installation of bypass pump station and piping, and removal 1 LS $266,758 1.000 $266,758Standby temp. bypass pumping rental during wet weather season 8 mon. $121,071 1.000 $968,571Fuel for pump 65,000 gal $5 1.000 $325,000

Total, Div. 11000 $1,560,329

12 FURNISHING

NoneTotal, Div. 12000 $0

13 SPECIAL CONSTRUCTION

NoneTotal, Div. 13000 $0

14 CONVEYING SYSTEMS14 CONVEYING SYSTEMS

Connect culvert to 72" CMP and existing ForeBay pump station 1 LS $25,000 1.000 $25,000

Total, Div. 14000 $25,000

15 MECHANICAL

Existing STD pipe connections to new culvert 4 EA $7,500 1.000 $30,000Connect existing 12" SD to culvert 1 EA $10,000 1.000 $10,000

Total, Div. 15000 $40,00016 ELECTRICAL

NoneTotal, Div. 16000

17 INSTRUMENTATION

NoneTotal, Div. 17000

SUBTOTAL $4 320 513SUBTOTAL $4,320,513

Estimating Contingency 25% $1,080,128SUBTOTAL $5,400,641

Sales Tax on 50% of Subtotal Above 8.75% $236,278SUBTOTAL $5,636,919

General Conditions 10% $563,692SUBTOTAL $6,200,611

General Contractor Overhead and Profit 13% $806 079General Contractor Overhead and Profit 13% $806,079SUBTOTAL $7,006,690

Escalation to Mid-Point (at 3% Annual Inflation Rate) 4% $293,671

ELEMENT CONSTRUCTION COST $7,300,000

File: Package 1 - Conceptual Design Cost Estimate.xlsxTab: 3 ‐ Culvert and Bypass

Page 6 of 6

Page 21: City of Sunnyvale · Culvert and Temporary Bypass $7,007,000 : $7,300,000 . Subtotal $17,924,000 . ... Includes installation of a new box culvert to replace the storm drainage volume

Design Information Memorandum No. 12 PACKAGE 2 – HEADWORKS AND PSTS

November 2014 - FINAL pw://Carollo/Documents/Client/CA/Sunnyvale/9265A10/DIMs/DIM 12-Construction Cost Estimate.docx

Page 22: City of Sunnyvale · Culvert and Temporary Bypass $7,007,000 : $7,300,000 . Subtotal $17,924,000 . ... Includes installation of a new box culvert to replace the storm drainage volume
Page 23: City of Sunnyvale · Culvert and Temporary Bypass $7,007,000 : $7,300,000 . Subtotal $17,924,000 . ... Includes installation of a new box culvert to replace the storm drainage volume

PROJECT : CITY OF SUNNYVALE

PRIMARY TREATMENT DESIGN

PRELIMINARY COST ESTIMATE - PACKAGE 2 - HEADWORKS AND PSTS ESTIMATED MIDPOINT OF CONSTRUCTION : 11/3/2017

JOB # : 9265A.10 COST ESTIMATE PREPARATION DATE : 8/28/2014ELEMENT : SUMMARY OF CONSTRUCTION COSTS BY : MK/RN/MP

Midpoint of Construction: 11/3/2017Rate of Annual Inflation: 3%Estimating Contingency: 25%

Sales Tax: 8.75%General Conditions: 10%

Contractor Overhead and Profit: 13%

ELEMENT # DESCRIPTION TOTAL

1 PAVING, GRADING, YARD PIPING, AND YARD STRUCTURES $12,724,000

2 SCREENING FACILITY $8,319,000

3 GRIT & SCREENINGS HANDLING FACILITY $3,589,000

4 INFLUENT PUMP STATION $9,561,000

5 GRIT BASINS $7,043,000

6 PRIMARY SEDIMENTATION TANKS $16,634,000

7 CEPT FACILITY $1,198,000

8 ODOR CONTROL FACILITY $2,787,000

9 HEADWORKS ELECTRICAL BUILDING $2,926,000

10 SWITCHGEAR BUILDING AND ELECTRICAL & INSTRUMENTATION SYSTEM $4,274,000

11 STANDBY GENERATOR $1,878,000

12 EXHAUST HEAT RECOVERY $1,819,000

13 TUNNEL SYSTEM $4,285,000

14 PE PIPELINE FROM PLANT TO PONDS $0

Total Estimated Construction Cost = $77,037,000

File: Package 2 - Conceptual Design Cost Estimate.xlsTab: Summary

Page 1 of 37

Page 24: City of Sunnyvale · Culvert and Temporary Bypass $7,007,000 : $7,300,000 . Subtotal $17,924,000 . ... Includes installation of a new box culvert to replace the storm drainage volume
Page 25: City of Sunnyvale · Culvert and Temporary Bypass $7,007,000 : $7,300,000 . Subtotal $17,924,000 . ... Includes installation of a new box culvert to replace the storm drainage volume

PRELIMINARY COST ESTIMATE - PACKAGE 2 - HEADWORKS AND PSTS

PROJECT : PRIMARY TREATMENT DESIGN LOCATION FACTOR: 1.000

CITY OF SUNNYVALE ESTIMATED MIDPOINT OF CONSTRUCTION : 11/3/2017

JOB # : 9265A.10 COST ESTIMATE PREPARATION DATE : 8/28/2014

LOCATION : SUNNYVALE, CA BY : RN

ELEMENT # : 1 REVIEWED BY: DH

ELEMENT : PAVING, GRADING, YARD PIPING, AND YARD STRUCTURES KC

DIVISION DESCRIPTION QUAN UNIT UNIT COST

LOCATION

FACTOR SUBTOTAL TOTAL

2 SITEWORK

Excavations

60" PI 178 CY $17 1.000 $2,971

60" PE 4990 CY $17 1.000 $83,383

42" FA 15 CY $17 1.000 $25536" FA 227 CY $17 1.000 $3,791

30" PI 241 CY $17 1.000 $4,023

24" STD 267 CY $17 1.000 $4,45624" FA 78 CY $17 1.000 $1,30018" STD 519 CY $17 1.000 $8,664

16" FA 6 CY $17 1.000 $102

12" TD 948 CY $17 1.000 $15,844

12" STD 954 CY $17 1.000 $15,943

12" SD 948 CY $17 1.000 $15,844

UW, PW, SA 1800 CY $17 1.000 $30,078

66" SS' 2396 CY $17 1.000 $40,030

66" SS Manholes 62 CY $17 1.000 $1,040

Pipe Embedment

60" PI 80 CY $40 1.000 $3,203

60" PE 1620 CY $40 1.000 $64,782

42" FA 7 CY $40 1.000 $291

36" FA 116 CY $40 1.000 $4,638

30" PI 130 CY $40 1.000 $5,205

24" STD 110 CY $40 1.000 $4,398

24" FA 40 CY $40 1.000 $1,60424" FA 40 CY $40 1.000 $1,604

18" STD 226 CY $40 1.000 $9,059

16" FA 3 CY $40 1.000 $133

12" TD 332 CY $40 1.000 $13,290

12" STD 334 CY $40 1.000 $13,373

12" SD 332 CY $40 1.000 $13,290

66" SS' 694 CY $40 1.000 $27,768

UW, PW, SA 700 CY $40 1.000 $28,000

Backfill

60" PI 53 CY $28 1.000 $1,478

60" PE 365 CY $28 1.000 $10,114

42" FA 4 CY $28 1.000 $113

36" FA 65 CY $28 1.000 $1,796

30" PI 74 CY $28 1.000 $2,052

24" STD 133 CY $28 1.000 $3,695

24" FA 26 CY $28 1.000 $719

18" STD 259 CY $28 1.000 $7,184

16" FA 2 CY $28 1.000 $62

12" TD 593 CY $28 1.000 $16,421

12" STD 596 CY $28 1.000 $16,523

12" SD 593 CY $28 1.000 $16,421

UW, PW, SA 1100 CY $28 1.000 $30,481

66" SS' 1497 CY $28 1.000 $41,488

Hauling Excavated Material

60" PI 124 CY $11 1.000 $1,369

60" PE 2494 CY $11 1.000 $27,434

42" FA 11 CY $11 1.000 $123

36" FA 162 CY $11 1.000 $1,782

30" PI 166 CY $11 1.000 $1,826

24" STD 133 CY $11 1.000 $1,467

24" FA 52 CY $11 1.000 $570

18" STD 259 CY $11 1.000 $2,852

16" FA 4 CY $11 1.000 $43

12" TD 356 CY $11 1.000 $3,911

12" STD 358 CY $11 1.000 $3,936

File: Package 2 - Conceptual Design Cost Estimate.xlsTab: 1

Page 2 of 37

Page 26: City of Sunnyvale · Culvert and Temporary Bypass $7,007,000 : $7,300,000 . Subtotal $17,924,000 . ... Includes installation of a new box culvert to replace the storm drainage volume

PRELIMINARY COST ESTIMATE - PACKAGE 2 - HEADWORKS AND PSTS

PROJECT : PRIMARY TREATMENT DESIGN LOCATION FACTOR: 1.000

CITY OF SUNNYVALE ESTIMATED MIDPOINT OF CONSTRUCTION : 11/3/2017

JOB # : 9265A.10 COST ESTIMATE PREPARATION DATE : 8/28/2014

LOCATION : SUNNYVALE, CA BY : RN

ELEMENT # : 1 REVIEWED BY: DH

ELEMENT : PAVING, GRADING, YARD PIPING, AND YARD STRUCTURES KC

DIVISION DESCRIPTION QUAN UNIT UNIT COST

LOCATION

FACTOR SUBTOTAL TOTAL

12" SD 356 CY $11 1.000 $3,911

66" SS' 898 CY $11 1.000 $9,882

Site Clearing and Grubbing 1 LS $20,000 1.000 $20,000

AC Paving including Subgrade 164000 SF $3 1.000 $492,000

AB Road 22000 SF $1.50 1.000 $33,000

Finish Grading 1 LS $15,000 1.000 $15,000

Groundwater Dewatering 1 LS $100,000 1.000 $100,000

Utility Potholing 1 LS $30,000 1.000 $30,000

Relocate Existing Utilities for utilidor / piping 1 LS $50,000 1.000 $50,000

Bollards 50 EA $1,600 1.000 $80,000

66" SS Shoring 9,240 SF $29 1.000 $267,960

Miscellaneous shoring 3,200 SF $29 1.000 $92,800

Jacking Pit 1 LS $120,000 1.000 $120,000

Receiving Pit 1 LS $60,000 1.000 $60,000

Ground Improvements for 72" Casing Installations 180 LF $1,000 1.000 $180,000

6' tall Chain Link Fence (Baylands to PE Distribution Box) 600 LF $35 1.000 $21,000

24' wide Access Gate 1 EA $7,500 1.000 $7,500

24' wide Construction Access Gate 1 EA $7,500 1.000 $7,500

Total, Div. 02000 $2,201,167

3 CONCRETE

Influent Junction Box 1 LS $200,000 1.000 $200,000

PE Junction Manhole 1 LS $75,000 1.000 $75,000

PE Junction Box 1 LS $200,000 1.000 $200,000

66" SS Manholes 2 EA $45,000 1.000 $90,000

60" PE Manholes for Tunneling 2 EA $75,000 1.000 $150,00060" PE Manholes for Tunneling 2 EA $75,000 1.000 $150,000

Storm Drain Manholes 12 EA $8,000 1.000 $96,000

Catch Basins 12 EA $3,500 1.000 $42,000

Curb and Gutter 1400 LF $35 1.000 $49,000

Valley Gutter 30 LF $60 1.000 $1,800

Miscellaneous Concrete 1 LS $10,000 1.000 $10,000

Miscellaneous Sidewalks 1 LS $40,000 1.000 $40,000

Total, Div. 03000 $953,800

4 MASONRY

None

Total, Div. 04000 $0

5 METALS

Miscellaneous Metals 1 LS $20,000 1.000 $20,000

Total, Div. 05000 $20,000

6 WOOD AND PLASTICS

None

Total, Div. 06000 $0

7 THERMAL AND MOISTURE PROTECTION

None

Total, Div. 07000 $0

8 DOORS AND WINDOWS

File: Package 2 - Conceptual Design Cost Estimate.xlsTab: 1

Page 3 of 37

Page 27: City of Sunnyvale · Culvert and Temporary Bypass $7,007,000 : $7,300,000 . Subtotal $17,924,000 . ... Includes installation of a new box culvert to replace the storm drainage volume

PRELIMINARY COST ESTIMATE - PACKAGE 2 - HEADWORKS AND PSTS

PROJECT : PRIMARY TREATMENT DESIGN LOCATION FACTOR: 1.000

CITY OF SUNNYVALE ESTIMATED MIDPOINT OF CONSTRUCTION : 11/3/2017

JOB # : 9265A.10 COST ESTIMATE PREPARATION DATE : 8/28/2014

LOCATION : SUNNYVALE, CA BY : RN

ELEMENT # : 1 REVIEWED BY: DH

ELEMENT : PAVING, GRADING, YARD PIPING, AND YARD STRUCTURES KC

DIVISION DESCRIPTION QUAN UNIT UNIT COST

LOCATION

FACTOR SUBTOTAL TOTAL

None

Total, Div. 08000 $0

9 FINISHES

Painting and Protective Coating 1 LS $10,000 1.000 $10,000

Total, Div. 09000 $10,000

10 SPECIALTIES

Signs, Identification, Stenciling and Tagging System 1 LS $15,000 1.000 $15,000

Total, Div 10000 $15,000

11 EQUIPMENT

None

Total, Div. 11000 $0

12 FURNISHING

None

Total, Div. 12000 $0

13 SPECIAL CONSTRUCTION13 SPECIAL CONSTRUCTION

Temporary Bypass Pumping 1 LS $200,000 1.000 $200,000

Total, Div. 13000 $200,000

14 CONVEYING SYSTEMS

None

Total, Div. 14000 $0

15 MECHANICAL

72" Casing Pipes (60" PE and Future Piping) 360 LF $2,400 1.000 $864,000

66" SS (RCP) 231 LF $528 1.000 $121,968

60" PI (RCP/Steel) 60 LF $480 1.000 $28,800

60" PE (RCP/Steel) 1350 LF $480 1.000 $648,000

42" FA (FRP) 35 LF $280 1.000 $9,800

36" FA (FRP) 175 LF $200 1.000 $35,000

30" PI (DIP) 200 LF $240 1.000 $48,000

24" STD (PVC) 200 LF $192 1.000 $38,400

24" FA (FRP) 100 LF $150 1.000 $15,000

18" STD (PVC) 540 LF $144 1.000 $77,760

16" FA (FRP) 10 LF $100 1.000 $1,000

12" TD (PVC) 800 LF $96 1.000 $76,800

12" STD (PVC) 805 LF $96 1.000 $77,280

12" SD (PVC) 800 LF $96 1.000 $76,800

Potable Water Yard Piping 1400 LF $70 1.000 $98,000

Utility Water Yard Piping 2000 LF $80 1.000 $160,000

Service Air Piping 1 LS $25,000 1.000 $25,000

6" Grit Slurry Piping 200 LF $200 1.000 $40,000

6" Primary Sludge and Scum Piping (Heat Traced) 650 LF $200 1.000 $130,000

Pipe Fittings, Valves, Couplings (5% of sum of piping LF costs) 1 LS $129,000 1.000 $129,000

Miscellaneous Piping 4" and Smaller 1 LS $20,000 1.000 $20,000

Miscellaneous Drain Piping 1 LS $20,000 1.000 $20,000

File: Package 2 - Conceptual Design Cost Estimate.xlsTab: 1

Page 4 of 37

Page 28: City of Sunnyvale · Culvert and Temporary Bypass $7,007,000 : $7,300,000 . Subtotal $17,924,000 . ... Includes installation of a new box culvert to replace the storm drainage volume

PRELIMINARY COST ESTIMATE - PACKAGE 2 - HEADWORKS AND PSTS

PROJECT : PRIMARY TREATMENT DESIGN LOCATION FACTOR: 1.000

CITY OF SUNNYVALE ESTIMATED MIDPOINT OF CONSTRUCTION : 11/3/2017

JOB # : 9265A.10 COST ESTIMATE PREPARATION DATE : 8/28/2014

LOCATION : SUNNYVALE, CA BY : RN

ELEMENT # : 1 REVIEWED BY: DH

ELEMENT : PAVING, GRADING, YARD PIPING, AND YARD STRUCTURES KC

DIVISION DESCRIPTION QUAN UNIT UNIT COST

LOCATION

FACTOR SUBTOTAL TOTAL

Total, Div. 15000 $2,740,608

16 ELECTRICAL

Conduit/Ductbanks 1 LS $1,000,000 1.000 $1,000,000

Total, Div. 16000 $1,000,000

17 INSTRUMENTATION

None

Total, Div. 17000 $0

SUBTOTAL $7,140,575

Estimating Contingency 25% $1,785,144

SUBTOTAL $8,925,719

Sales Tax on 50% of Subtotal Above 8.75% $390,500

SUBTOTAL $9,316,220

General Conditions 10% $931,622

SUBTOTAL $10,247,842

General Contractor Overhead and Profit 13% $1,332,219General Contractor Overhead and Profit 13% $1,332,219

SUBTOTAL $11,580,061

Escalation to Mid-Point (at 3% Annual Inflation Rate) 9.88% $1,144,175

ELEMENT CONSTRUCTION COST $12,724,000

Note: No cost included for off-site PE pipe installation or rehabilitation

File: Package 2 - Conceptual Design Cost Estimate.xlsTab: 1

Page 5 of 37

Page 29: City of Sunnyvale · Culvert and Temporary Bypass $7,007,000 : $7,300,000 . Subtotal $17,924,000 . ... Includes installation of a new box culvert to replace the storm drainage volume

PRELIMINARY COST ESTIMATE - PACKAGE 2 - HEADWORKS AND PSTS

PROJECT : PRIMARY TREATMENT DESIGN LOCATION FACTOR: 1.163

CITY OF SUNNYVALE ESTIMATED MIDPOINT OF CONSTRUCTION : 11/3/2017

JOB # : 9265A.10 COST ESTIMATE PREPARATION DATE : 8/28/2014

LOCATION : SUNNYVALE, CA BY : MK

ELEMENT # : 2 REVIEWED BY: KR

ELEMENT : SCREENING FACILITY JW

DIVISION DESCRIPTION QUAN UNIT UNIT COST

LOCATION

FACTOR SUBTOTAL TOTAL

2 SITEWORK

Site Cleaning and Preparation 1 LS $5,000 1.000 $5,000

Cat 235 Trackhoe 1.50CY Bucket, Class C (Hard Digging), 0-20' D 4,264 CY $4.27 1.163 $21,169Native Pipe Bed & Zone/Confined Structure Backfill, Class A 986 CY $28 1.163 $31,682ABC 103 CY $56 1.000 $5,76820 CY Dump Truck, 30 Miles/Round Trip 4,058 CY $13 1.163 $63,412Sheet Piling, 38#/SF To 40' Deep, Pulled & Salvaged (Pits Only) 8,773 SF $29 1.163 $295,887

Total, Div. 02000 $422,918

3 CONCRETE

30" STRUCTURAL FLAT MAT ON GRADE 310 CY $500 1.163 $180,265

30" STRAIGHT WALL >8' HIGH 1108 CY $584 1.163 $752,256

12" ELEVATED SLAB, 21'-26' HIGH 91 CY $545 1.163 $57,727

Class C Fill or Grouting Allowance 1 LS $40,000 1.000 $40,000

Total, Div. 03000 $1,030,248

4 MASONRY

None

Total, Div. 04000 $0

5 METALS

Aluminum Treadplate 345 SF $56 1.163 $22,607

Total, Div. 05000 $22,607

6 WOOD AND PLASTICS

T-Lock Lining 14,663 SF $21 1.000 $314,934

Total, Div. 06000 $314,934

7 THERMAL AND MOISTURE PROTECTION

None

Total, Div. 07000 $0

8 DOORS AND WINDOWS

None

Total, Div. 08000 $0

9 FINISHES

Mechanical Coating Allowance 1 LS $5,000 1.000 $5,000

Total, Div. 09000 $5,000

10 SPECIALTIES

None

Total, Div. 10000 $0

11 EQUIPMENT

File: Package 2 - Conceptual Design Cost Estimate.xlsTab: 2

Page 6 of 37

Page 30: City of Sunnyvale · Culvert and Temporary Bypass $7,007,000 : $7,300,000 . Subtotal $17,924,000 . ... Includes installation of a new box culvert to replace the storm drainage volume

PRELIMINARY COST ESTIMATE - PACKAGE 2 - HEADWORKS AND PSTS

PROJECT : PRIMARY TREATMENT DESIGN LOCATION FACTOR: 1.163

CITY OF SUNNYVALE ESTIMATED MIDPOINT OF CONSTRUCTION : 11/3/2017

JOB # : 9265A.10 COST ESTIMATE PREPARATION DATE : 8/28/2014

LOCATION : SUNNYVALE, CA BY : MK

ELEMENT # : 2 REVIEWED BY: KR

ELEMENT : SCREENING FACILITY JW

DIVISION DESCRIPTION QUAN UNIT UNIT COST

LOCATION

FACTOR SUBTOTAL TOTAL

Slide Plate 3 EA $6,000 1.000 $18,000

Bar Screen Channel Inlet Gate, 48"x100", Motorized Operator 4 EA $33,389 1.163 $155,324

Bar Screen Channel Outlet Gate, 48"x100", Motorized Operator 4 EA $33,389 1.163 $155,324

Bypass Channel Inlet Gate, 48"x100", Motorized Operator 1 EA $33,389 1.163 $38,831

Bypass Channel Outlet Gate, 48"x100", Motorized Operator 1 EA $33,389 1.163 $38,831

(4) Chain-Drive Multi Rake Bar Screens and (2) Auger Type with

Wash Tub Screenings Washer/Compactor with Sprays 1 EA $1,596,000 1.000 $1,596,000

Total, Div. 11000 $2,002,311

12 FURNISHING

None

Total, Div. 12000 $0

13 SPECIAL CONDITIONS

None

Total, Div. 13000 $0

14 CONVEYING SYSTEMS

Shaftless Screw Screenings Conveyor 1 EA $241,500 1.000 $241,500

Total, Div. 14000 $241,500Total, Div. 14000 $241,500

15 MECHANICAL

Allowance for Foul Air Duct 1 LS $20,000 1.000 $20,000

Total, Div. 15000 $20,000

16 ELECTRICAL

Electrical Allowance (Percentage of Div. 1 - 15) 10% $405,952

Total, Div. 16000 $405,952

17 INSTRUMENTATION

Instrumentation Allowance (Percentage of Div. 1 - 15) 5% $202,976

Total, Div. 17000 $202,976

SUBTOTAL $4,668,445

Estimating Contingency 25% $1,167,111

SUBTOTAL $5,835,557

Sales Tax on 50% of Subtotal Above 8.75% $255,306

SUBTOTAL $6,090,862

General Conditions 10% $609,086

SUBTOTAL $6,699,949

General Contractor Overhead and Profit 13% $870,993

SUBTOTAL $7,570,942

Escalation to Mid-Point (at 3% Annual Inflation Rate) 9.88% $748,051

File: Package 2 - Conceptual Design Cost Estimate.xlsTab: 2

Page 7 of 37

Page 31: City of Sunnyvale · Culvert and Temporary Bypass $7,007,000 : $7,300,000 . Subtotal $17,924,000 . ... Includes installation of a new box culvert to replace the storm drainage volume

PRELIMINARY COST ESTIMATE - PACKAGE 2 - HEADWORKS AND PSTS

PROJECT : PRIMARY TREATMENT DESIGN LOCATION FACTOR: 1.163

CITY OF SUNNYVALE ESTIMATED MIDPOINT OF CONSTRUCTION : 11/3/2017

JOB # : 9265A.10 COST ESTIMATE PREPARATION DATE : 8/28/2014

LOCATION : SUNNYVALE, CA BY : MK

ELEMENT # : 2 REVIEWED BY: KR

ELEMENT : SCREENING FACILITY JW

DIVISION DESCRIPTION QUAN UNIT UNIT COST

LOCATION

FACTOR SUBTOTAL TOTAL

ELEMENT CONSTRUCTION COST $8,319,000

File: Package 2 - Conceptual Design Cost Estimate.xlsTab: 2

Page 8 of 37

Page 32: City of Sunnyvale · Culvert and Temporary Bypass $7,007,000 : $7,300,000 . Subtotal $17,924,000 . ... Includes installation of a new box culvert to replace the storm drainage volume

PRELIMINARY COST ESTIMATE - PACKAGE 2 - HEADWORKS AND PSTS

PROJECT : PRIMARY TREATMENT DESIGN LOCATION FACTOR: 1.163

CITY OF SUNNYVALE ESTIMATED MIDPOINT OF CONSTRUCTION : 11/3/2017

JOB # : 9265A.10 COST ESTIMATE PREPARATION DATE : 8/28/2014

LOCATION : SUNNYVALE, CA BY : MK

ELEMENT # : 3 REVIEWED BY: KR

ELEMENT : GRIT & SCREENINGS HANDLING FACILITY JW

DIVISION DESCRIPTION QUAN UNIT UNIT COST

LOCATION

FACTOR SUBTOTAL TOTAL

2 SITEWORK

Site Cleaning and Preparation 1 LS $5,000 1.000 $5,000

Cat 235 Trackhoe 1.50CY Bucket, Class C (Hard Digging), 0-20' D 201 CY $4.27 1.163 $998Native Pipe Bed & Zone/Confined Structure Backfill, Class A 47 CY $28 1.163 $1,510ABC 77 CY $56 1.000 $4,31220 CY Dump Truck, 30 Miles/Round Trip 280 CY $13 1.163 $4,375

Total, Div. 02000 $16,195

3 CONCRETE

8" FLAT NON-FORMED S.O.G. 25 CY $500 1.163 $14,538

18" STRUCTURAL FLAT MAT ON GRADE 92 CY $500 1.163 $53,498

6" FLAT NON-FORMED SLAB ON GRADE 9 CY $500 1.163 $5,234

12" STRAIGHT WALL >8' HIGH 253 CY $962 1.163 $283,091

12" ELEVATED SLAB TO 20' 59 CY $480 1.163 $32,964

24" W X 24" D CONC BEAM 10 CY $774 1.163 $9,002

Class C Fill or Grouting Allowance 1 LS $100,000 1.000 $100,000

Total, Div. 03000 $498,325

4 MASONRY

None

Total, Div. 04000 $0

5 METALS5 METALS

Metal Canopy 481 SF $120 1.163 $67,128

Aluminum Grating, 2" 468 SF $56 1.163 $30,666

Aluminum Stairs, Including Railing and Supports 80 RSR $561 1.163 $52,217

Aluminum OSHA Handrail 71 LF $75 1.163 $6,234

Steel Deck, 3" X 16 Ga. 1591 SF $7 1.163 $12,923

Discharge Chute 3 EA $5,000 1.000 $15,000

Three 10'x10' Roof Hatches and One 4'x4' Roof Hatch (Aluminum) 316 SF $56 1.163 $20,429

Total, Div. 05000 $204,598

6 WOOD AND PLASTICS

None

Total, Div. 06000 $0

7 THERMAL AND MOISTURE PROTECTION

3-1/4" R-20.00 Composite Board Roof Insulation 1,591 SF $4 1.163 $8,308

Neoprene, Fully Adhered With Adhesive, Polychloroprene 1,591 SF $7 1.163 $13,322

Total, Div. 07000 $21,630

8 DOORS AND WINDOWS

7/0 X 7/0 X 1.75" NO LABEL DOUBLE HOLLOW METAL DOOR

W/FRAME & HDWRE 1 EA $1,645 1.163 $1,913

3/0 X 7/0 X 1.75" NO LABEL SINGLE HOLLOW METAL DOOR

W/FRAME & HDWRE 3 EA $853 1.163 $2,974

10'-0" X 12'-0" Roll-Up Overhead Door, Chain Lift, 22 Gauge

Galvanized Steel/Aluminum 2 EA $2,820 1.163 $6,559

Electric Door Operator For Chain Lift Roll-Up Overhead Door, No

Wiring 2 EA $1,740 1.163 $4,047

File: Package 2 - Conceptual Design Cost Estimate.xlsTab: 3

Page 9 of 37

Page 33: City of Sunnyvale · Culvert and Temporary Bypass $7,007,000 : $7,300,000 . Subtotal $17,924,000 . ... Includes installation of a new box culvert to replace the storm drainage volume

PRELIMINARY COST ESTIMATE - PACKAGE 2 - HEADWORKS AND PSTS

PROJECT : PRIMARY TREATMENT DESIGN LOCATION FACTOR: 1.163

CITY OF SUNNYVALE ESTIMATED MIDPOINT OF CONSTRUCTION : 11/3/2017

JOB # : 9265A.10 COST ESTIMATE PREPARATION DATE : 8/28/2014

LOCATION : SUNNYVALE, CA BY : MK

ELEMENT # : 3 REVIEWED BY: KR

ELEMENT : GRIT & SCREENINGS HANDLING FACILITY JW

DIVISION DESCRIPTION QUAN UNIT UNIT COST

LOCATION

FACTOR SUBTOTAL TOTAL

Total, Div. 08000 $15,494

9 FINISHES

Mechanical Coating Allowance (Percentage of Div. 15) 1% $1,483

Total, Div. 09000 $1,483

10 SPECIALTIES

None

Total, Div. 10000 $0

11 EQUIPMENT

Auger Type Screenings Washer/Compactor with Sprays (Screening

Equipment Quote Included in Area 2) 0 EA - - -

Screenings Rotating Tipping Trough 2 EA $24,000 1.000 $48,000

CONANDA Fine Grit Washer 1 EA $630,000 1.000 $630,000

Ventilation Fans 2 LS $2,000 1.000 $8,000

Odor Control Fans at PST 4 EA $3,000 1.000 $6,000

Total, Div. 11000 $692,000

12 FURNISHING

NoneNone

Total, Div. 12000 $0

13 SPECIAL CONDITIONS

None

Total, Div. 13000 $0

14 CONVEYING SYSTEMS

None

Total, Div. 14000 $0

15 MECHANICAL

8" FLG CLDI PIPE IN BLDG 61 LF $84 1.163 $5,978

8" X 8" CLDI MJ TEE OR WYE 2 EA $1,741 1.163 $4,050

8" 45° 125# CLDI FXF ELL 6 EA $730 1.163 $5,091

10" FLG CLDI PIPE IN BLDG 20 LF $110 1.163 $2,549

Allowance for Foul Air Duct 1 LS $20,000 1.000 $20,000

Additional Piping Allowance 1 LS $75,000 1.000 $75,000

Pipe Support Allowance (Percentage of Div. 15) 5% $112,668 $5,633

HVAC Allowance for Electrical Room 1 EA $30,000 1.000 $30,000

Total, Div. 15000 $148,301

16 ELECTRICAL

Electrical Allowance (Percentage of Div. 1 - 15) 10% $159,803

Total, Div. 16000 $159,803

17 INSTRUMENTATION

File: Package 2 - Conceptual Design Cost Estimate.xlsTab: 3

Page 10 of 37

Page 34: City of Sunnyvale · Culvert and Temporary Bypass $7,007,000 : $7,300,000 . Subtotal $17,924,000 . ... Includes installation of a new box culvert to replace the storm drainage volume

PRELIMINARY COST ESTIMATE - PACKAGE 2 - HEADWORKS AND PSTS

PROJECT : PRIMARY TREATMENT DESIGN LOCATION FACTOR: 1.163

CITY OF SUNNYVALE ESTIMATED MIDPOINT OF CONSTRUCTION : 11/3/2017

JOB # : 9265A.10 COST ESTIMATE PREPARATION DATE : 8/28/2014

LOCATION : SUNNYVALE, CA BY : MK

ELEMENT # : 3 REVIEWED BY: KR

ELEMENT : GRIT & SCREENINGS HANDLING FACILITY JW

DIVISION DESCRIPTION QUAN UNIT UNIT COST

LOCATION

FACTOR SUBTOTAL TOTAL

PLC Cabinet 1 EA $176,400 $176,400

Instrumentation Allowance (Percentage of Div. 1 - 15) 5% $79,901

Total, Div. 17000 $256,301

SUBTOTAL $2,014,132

Estimating Contingency 25% $503,533

SUBTOTAL $2,517,664

Sales Tax on 50% of Subtotal Above 8.75% $110,148

SUBTOTAL $2,627,812

General Conditions 10% $262,781

SUBTOTAL $2,890,594

General Contractor Overhead and Profit 13% $375,777

SUBTOTAL $3,266,371

Escalation to Mid-Point (at 3% Annual Inflation Rate) 9.88% $322,736

ELEMENT CONSTRUCTION COST $3,589,000

File: Package 2 - Conceptual Design Cost Estimate.xlsTab: 3

Page 11 of 37

Page 35: City of Sunnyvale · Culvert and Temporary Bypass $7,007,000 : $7,300,000 . Subtotal $17,924,000 . ... Includes installation of a new box culvert to replace the storm drainage volume

PRELIMINARY COST ESTIMATE - PACKAGE 2 - HEADWORKS AND PSTS

PROJECT : PRIMARY TREATMENT DESIGN LOCATION FACTOR: 1.163

CITY OF SUNNYVALE ESTIMATED MIDPOINT OF CONSTRUCTION : 11/3/2017

JOB # : 9265A.10 COST ESTIMATE PREPARATION DATE : 8/28/2014

LOCATION : SUNNYVALE, CA BY : MK

ELEMENT # : 4 REVIEWED BY: KR

ELEMENT : INFLUENT PUMP STATION JW

DIVISION DESCRIPTION QUAN UNIT UNIT COST

LOCATION

FACTOR SUBTOTAL TOTAL

2 SITEWORK

Site Cleaning and Preparation 1 LS $5,000 1.000 $5,000

Cat 235 Trackhoe 1.50CY Bucket, Class C (Hard Digging), 0-20' D 7,518 CY $4.27 1.163 $37,324Native Pipe Bed & Zone/Confined Structure Backfill, Class A 1,432 CY $28 1.163 $46,013ABC 179 CY $56 1.000 $10,02420 CY Dump Truck, 30 Miles/Round Trip 7,518 CY $13 1.163 $117,479Sheet Piling, 38#/SF To 40' Deep, Pulled & Salvaged (Pits Only) 8,760 SF $29 1.163 $295,449

Total, Div. 02000 $511,289

3 CONCRETE

30" STRUCTURAL FLAT MAT ON GRADE 987 CY $500 1.163 $573,941

24" STRAIGHT WALL >8' HIGH 40 CY $650 1.163 $30,234

30" STRAIGHT WALL >8' HIGH 1014 CY $584 1.163 $688,437

12" STRAIGHT WALL >8' HIGH 116 CY $962 1.163 $129,797

12" ELEVATED SLAB, 33'-38' HIGH 120 CY $590 1.163 $82,302

6" FLAT NON-FORMED SLAB ON GRADE 7 CY $500 1.163 $4,071

Pump Pads 7 CY $337 1.163 $2,874

Total, Div. 03000 $1,511,655

4 MASONRY

None

Total, Div. 04000 $0Total, Div. 04000 $0

5 METALS

Checkered Aluminum Plate 1,913 LB $56 1.163 $125,121

Aluminum OSHA Handrail 628 LF $75 1.163 $55,138

Aluminum Stairs, Including Railing and Supports 98 RSR $561 1.163 $63,966

Steel Deck, 3" X 16 Ga. 370 SF $7 1.163 $3,004

Total, Div. 05000 $247,229

6 WOOD AND PLASTICS

T-Lok Lining 5,128 SF $21 1.000 $110,142

Total, Div. 06000 $110,142

7 THERMAL AND MOISTURE PROTECTION

3-1/4" R-20.00 Composite Board Roof Insulation 370 SF $4 1.163 $1,931

Neoprene, Fully Adhered With Adhesive, Polychloroprene 370 SF $7 1.163 $3,097

Total, Div. 07000 $5,028

8 DOORS AND WINDOWS

3/0 X 7/0 X 1.75" NO LABEL SINGLE HOLLOW METAL DOOR

W/FRAME & HDWRE 4 EA $853 1.163 $3,966

Total, Div. 08000 $3,966

9 FINISHES

Mechanical Coating Allowance (Percentage of Div. 15) 1% $8,890

Total, Div. 09000 $8,890

File: Package 2 - Conceptual Design Cost Estimate.xlsTab: 4

Page 12 of 37

Page 36: City of Sunnyvale · Culvert and Temporary Bypass $7,007,000 : $7,300,000 . Subtotal $17,924,000 . ... Includes installation of a new box culvert to replace the storm drainage volume

PRELIMINARY COST ESTIMATE - PACKAGE 2 - HEADWORKS AND PSTS

PROJECT : PRIMARY TREATMENT DESIGN LOCATION FACTOR: 1.163

CITY OF SUNNYVALE ESTIMATED MIDPOINT OF CONSTRUCTION : 11/3/2017

JOB # : 9265A.10 COST ESTIMATE PREPARATION DATE : 8/28/2014

LOCATION : SUNNYVALE, CA BY : MK

ELEMENT # : 4 REVIEWED BY: KR

ELEMENT : INFLUENT PUMP STATION JW

DIVISION DESCRIPTION QUAN UNIT UNIT COST

LOCATION

FACTOR SUBTOTAL TOTAL

10 SPECIALTIES

None

Total, Div. 10000 $0

11 EQUIPMENT

Dry-Pit Submersible Non-clog Pumps 6 EA $161,850 1.000 $971,100

Wet Well Inlet Gates - SST, Downward Opening, 108x90, Motorized

Operator 3 EA $67,612 1.000 $202,836

Compartment Isolation Gates - SST, Downward Opening, 108x66,

Motorized Operator 2 EA $49,582 1.000 $99,164

Pump Intake Gates, 33x33, Motorized Operator 6 EA $13,254 1.000 $79,525

Sump Pumps 2 EA $6,000 1.000 $12,000

Ventilation Fans 6 LS $2,000 1.000 $8,000

Odor Control Fans at PST 2 EA $3,000 1.000 $6,000

Total, Div. 11000 $1,378,626

12 FURNISHING

None

Total, Div. 12000 $0

13 SPECIAL CONDITIONS13 SPECIAL CONDITIONS

None

Total, Div. 13000 $0

14 CONVEYING SYSTEMS

None

Total, Div. 14000 $0

15 MECHANICAL

30" FLG CLDI PIPE IN BLDG 150 LF $648 1.163 $113,127

20" FXF CAST IRON PLUG VALVE W/HANDWHEEL OP 6 EA $7,071 1.163 $49,342

16"- 125# DI FXF CHECK VALVE 6 EA $33,320 1.163 $232,508

20" FLG CLDI PIPE IN BLDG 78 LF $296 1.163 $26,820

20" 90° 125# CLDI FXF ELL 9 EA $5,423 1.163 $56,766

30" 90° 125# CLDI FXF ELL 5 EA $11,393 1.163 $66,249

30"X24" 125# CLDI FXF CONCENTRIC RDCR 6 EA $12,523 1.163 $87,388

30" Square to Round Transition 6 EA $20,000 1.163 $139,560

20"X18" 125# CLDI FXF CONCENTRIC RDCR 6 EA $7,043 1.163 $49,145

Pump Reducing Intake Elbow 6 EA $6,000 1.163 $41,868

Allowance for Foul Air Duct 1 LS $20,000 1.000 $20,000

Pipe Support Allowance (Percentage of Div. 15) 5% $6,186

Total, Div. 15000 $888,959

16 ELECTRICAL

Electrical Allowance (Percentage of Div. 1 - 15) 10% $466,578

Total, Div. 16000 $466,578

17 INSTRUMENTATION

File: Package 2 - Conceptual Design Cost Estimate.xlsTab: 4

Page 13 of 37

Page 37: City of Sunnyvale · Culvert and Temporary Bypass $7,007,000 : $7,300,000 . Subtotal $17,924,000 . ... Includes installation of a new box culvert to replace the storm drainage volume

PRELIMINARY COST ESTIMATE - PACKAGE 2 - HEADWORKS AND PSTS

PROJECT : PRIMARY TREATMENT DESIGN LOCATION FACTOR: 1.163

CITY OF SUNNYVALE ESTIMATED MIDPOINT OF CONSTRUCTION : 11/3/2017

JOB # : 9265A.10 COST ESTIMATE PREPARATION DATE : 8/28/2014

LOCATION : SUNNYVALE, CA BY : MK

ELEMENT # : 4 REVIEWED BY: KR

ELEMENT : INFLUENT PUMP STATION JW

DIVISION DESCRIPTION QUAN UNIT UNIT COST

LOCATION

FACTOR SUBTOTAL TOTAL

Instrumentation Allowance (Percentage of Div. 1 - 15) 5% $233,289

Total, Div. 17000 $233,289

SUBTOTAL $5,365,649

Estimating Contingency 25% $1,341,412

SUBTOTAL $6,707,062

Sales Tax on 50% of Subtotal Above 8.75% $293,434

SUBTOTAL $7,000,496

General Conditions 10% $700,050

SUBTOTAL $7,700,545

General Contractor Overhead and Profit 13% $1,001,071

SUBTOTAL $8,701,616

Escalation to Mid-Point (at 3% Annual Inflation Rate) 9.88% $859,768

ELEMENT CONSTRUCTION COST $9,561,000

File: Package 2 - Conceptual Design Cost Estimate.xlsTab: 4

Page 14 of 37

Page 38: City of Sunnyvale · Culvert and Temporary Bypass $7,007,000 : $7,300,000 . Subtotal $17,924,000 . ... Includes installation of a new box culvert to replace the storm drainage volume

PRELIMINARY COST ESTIMATE - PACKAGE 2 - HEADWORKS AND PSTS

PROJECT : PRIMARY TREATMENT DESIGN LOCATION FACTOR: 1.163

CITY OF SUNNYVALE ESTIMATED MIDPOINT OF CONSTRUCTION : 11/3/2017

JOB # : 9265A.10 COST ESTIMATE PREPARATION DATE : 8/28/2014

LOCATION : SUNNYVALE, CA BY : MK

ELEMENT # : 5 REVIEWED BY: KR

ELEMENT : GRIT BASINS JW

DIVISION DESCRIPTION QUAN UNIT UNIT COST

LOCATION

FACTOR SUBTOTAL TOTAL

2 SITEWORK

Site Cleaning and Preparation 1 LS $5,000 1.000 $5,000

Cat 235 Trackhoe 1.50CY Bucket, Class C (Hard Digging), 0-20' D 2,111 CY $4.27 1.163 $10,480Native Pipe Bed & Zone/Confined Structure Backfill, Class A 972 CY $28 1.163 $31,232ABC 136 CY $56 1.000 $7,61620 CY Dump Truck, 30 Miles/Round Trip 1,529 CY $13 1.163 $23,893Sheet Piling, 38#/SF To 40' Deep, Pulled & Salvaged (Pits Only) 4,620 SF $29 1.163 $155,819

Total, Div. 02000 $234,040

3 CONCRETE

30" STRUCTURAL FLAT MAT ON GRADE 158 CY $500 1.163 $91,877

18" STRUCTURAL FLAT MAT ON GRADE 4 CY $500 1.163 $2,326

12" STRUCTURAL FLAT MAT ON GRADE 57 CY $500 1.163 $33,146

18" STRAIGHT WALL >8' HIGH 212 CY $753 1.163 $185,585

12" STRAIGHT WALL >8' HIGH 359 CY $962 1.163 $401,698

12" ELEVATED SLAB TO 20' 200 CY $480 1.163 $111,741

Class C Fill/Grouting 1 LS $30,000 1.000 $30,000

Total, Div. 03000 $856,373

4 MASONRY

None

Total, Div. 04000 $0

5 METALS

Checkered Aluminum Plate 1,790 LB $56 1.163 $117,076

Aluminum OSHA Handrail 480 LF $75 1.163 $42,143

Aluminum Stairs, Including Railing and Supports 88 RSR $561 1.163 $57,439

Total, Div. 05000 $216,659

6 WOOD AND PLASTICS

T-Lok Lining 12,721 SF $21 1.000 $273,223

Total, Div. 06000 $273,223

7 THERMAL AND MOISTURE PROTECTION

None

Total, Div. 07000 $0

8 DOORS AND WINDOWS

None

Total, Div. 08000 $0

9 FINISHES

Mechanical Coating Allowance (Percentage of Div. 15) 1% $3,662

Total, Div. 09000 $3,662

10 SPECIALTIES

None

File: Package 2 - Conceptual Design Cost Estimate.xlsTab: 5

Page 15 of 37

Page 39: City of Sunnyvale · Culvert and Temporary Bypass $7,007,000 : $7,300,000 . Subtotal $17,924,000 . ... Includes installation of a new box culvert to replace the storm drainage volume

PRELIMINARY COST ESTIMATE - PACKAGE 2 - HEADWORKS AND PSTS

PROJECT : PRIMARY TREATMENT DESIGN LOCATION FACTOR: 1.163

CITY OF SUNNYVALE ESTIMATED MIDPOINT OF CONSTRUCTION : 11/3/2017

JOB # : 9265A.10 COST ESTIMATE PREPARATION DATE : 8/28/2014

LOCATION : SUNNYVALE, CA BY : MK

ELEMENT # : 5 REVIEWED BY: KR

ELEMENT : GRIT BASINS JW

DIVISION DESCRIPTION QUAN UNIT UNIT COST

LOCATION

FACTOR SUBTOTAL TOTAL

Total, Div. 10000 $0

11 EQUIPMENT

Stop Plates 2 EA $6,000 1.000 $12,000

Eutek HeadCell Grit Vortex System 1 EA $669,600 1.000 $669,600

Grit Pumps 6 EA $61,427 1.000 $368,565

Pump Gallery Sump Pump 1 EA $6,000 1.000 $6,000

42"x108" Influent Channel Gates 3 EA $36,060 1.000 $108,179

48"x72" Bypass Gate 1 EA $24,040 1.000 $24,040

54"x108" Effluent Gates 3 EA $40,567 1.000 $121,702

Automatic Sampler 1 EA $9,600 1.000 $9,600

Odor Control Fans at PST 2 EA $3,000 1.000 $6,000

Total, Div. 11000 $1,325,686

12 FURNISHING

None

Total, Div. 12000 $0

13 SPECIAL CONDITIONS

None

Total, Div. 13000 $0Total, Div. 13000 $0

14 CONVEYING SYSTEMS

None

Total, Div. 14000 $0

15 MECHANICAL

6" FLG CLDI PIPE IN BLDG 185 LF $66 1.163 $14,190

4" FLG CLDI PIPE IN BLDG 275 LF $45 1.163 $14,516

8"X 6" 125# CLDI FXF ECCENTRIC RDCR 6 EA $1,218 1.163 $8,498

6" FXF CAST IRON PLUG VALVE W/HANDWHEEL OP 12 EA $1,024 1.163 $14,293

4" FXF CAST IRON PLUG VALVE W/HANDWHEEL OP 24 EA $740 1.163 $20,654

4"- 200 PSI CI FXF SWING CHECK VALVE 6 EA $1,221 1.163 $8,517

4" Fca Above Ground 6 EA $496 1.163 $3,464

8" Fca Above Ground 9 EA $952 1.163 $9,963

30" FLG CLDI PIPE IN BLDG 126 LF $648 1.163 $95,027

30" 90° 125# CLDI FXF ELL 6 EA $11,393 1.163 $79,499

84" Astm C-76 Class V Rcp In Open Trench 10 LF $376 1.163 $4,377

Allowance for Foul Air Duct 1 LS $20,000 1.000 $20,000

Additional 20% Piping Allowance 20% $58,600

Pipe Support Allowance (Percentage of Div. 15) 5% $14,650

Total, Div. 15000 $366,249

16 ELECTRICAL

Electrical Allowance (Percentage of Div. 1 - 15) 10% $327,589

Total, Div. 16000 $327,589

17 INSTRUMENTATION

Instrumentation Allowance (Percentage of Div. 1 - 15) 5% $163,795

Flowmeter-Magnetic 30" 3 EA $53,085 1.163 $185,215

File: Package 2 - Conceptual Design Cost Estimate.xlsTab: 5

Page 16 of 37

Page 40: City of Sunnyvale · Culvert and Temporary Bypass $7,007,000 : $7,300,000 . Subtotal $17,924,000 . ... Includes installation of a new box culvert to replace the storm drainage volume

PRELIMINARY COST ESTIMATE - PACKAGE 2 - HEADWORKS AND PSTS

PROJECT : PRIMARY TREATMENT DESIGN LOCATION FACTOR: 1.163

CITY OF SUNNYVALE ESTIMATED MIDPOINT OF CONSTRUCTION : 11/3/2017

JOB # : 9265A.10 COST ESTIMATE PREPARATION DATE : 8/28/2014

LOCATION : SUNNYVALE, CA BY : MK

ELEMENT # : 5 REVIEWED BY: KR

ELEMENT : GRIT BASINS JW

DIVISION DESCRIPTION QUAN UNIT UNIT COST

LOCATION

FACTOR SUBTOTAL TOTAL

Total, Div. 17000 $349,010

SUBTOTAL $3,952,491

Estimating Contingency 25% $988,123

SUBTOTAL $4,940,613

Sales Tax on 50% of Subtotal Above 8.75% $216,152

SUBTOTAL $5,156,765

General Conditions 10% $515,677

SUBTOTAL $5,672,442

General Contractor Overhead and Profit 13% $737,417

SUBTOTAL $6,409,859

Escalation to Mid-Point (at 3% Annual Inflation Rate) 9.88% $633,330

ELEMENT CONSTRUCTION COST $7,043,000

File: Package 2 - Conceptual Design Cost Estimate.xlsTab: 5

Page 17 of 37

Page 41: City of Sunnyvale · Culvert and Temporary Bypass $7,007,000 : $7,300,000 . Subtotal $17,924,000 . ... Includes installation of a new box culvert to replace the storm drainage volume

PRELIMINARY COST ESTIMATE - PACKAGE 2 - HEADWORKS AND PSTS

PROJECT : PRIMARY TREATMENT DESIGN LOCATION FACTOR: 1.000

CITY OF SUNNYVALE ESTIMATED MIDPOINT OF CONSTRUCTION : 11/3/2017

JOB # : 9265A.10 COST ESTIMATE PREPARATION DATE : 8/28/2014

LOCATION : SUNNYVALE, CA BY : MP

ELEMENT # : 6 REVIEWED BY: CO

ELEMENT : PRIMARY SEDIMENTATION TANKS DH

DIVISION DESCRIPTION QUAN UNIT UNIT COST

LOCATION

FACTOR SUBTOTAL TOTAL

2 SITEWORK

Site Cleaning and Preparation 1 LS $5,000 1.000 $5,000

Excavation 11600 CY $7 1.000 $81,200

Backfilling and Compaction 2,700 CY $10 1.000 $27,000

Aggregate Base under Foundation 1,200 CY $56 1.000 $67,200

Dirt Hauling, 30 miles, round trip 8,900 CY $11 1.000 $97,900

Sheet Piling 4,300 SF $29 1.000 $124,700

Misc. Site Work 1 LS $50,000 1.000 $50,000

Total, Div. 02000 $453,000

3 CONCRETE

Slab on Grade 1500 CY $707 1.000 $1,060,955

Thick Wall (>8" thick) 1100 CY $926 1.000 $1,019,045

Elevated Slab 300 CY $999 1.000 $299,831

Beam 20 CY $999 1.000 $19,989

Column 3 CY $926 1.000 $2,779

Pipe Encasement 24 CY $488 1.000 $11,717

Misc. Concrete (Lean Concrete) 1 LS $40,000 1.000 $40,000

Side Walk and Misc. Pads 40 CY $634 1.000 $25,371

Total, Div. 03000 $2,479,687

4 MASONRY

None

Total, Div. 04000 $0

5 METALS

Handrail 1,600 LF $80 1.000 $128,000

Odor Control Cover 7,300 SF $120 1.000 $876,000

Roof Hatches 100 SF $150 1.000 $15,000

Aluminum Stairs 100 VLF $200 1.000 $20,000

Current Construction for Future Odor Control Cover to Entire PSTs 1 LS $100,000 1.000 $100,000

Misc. Metals 1 LS $50,000 1.000 $50,000

Total, Div. 05000 $1,189,000

6 WOOD AND PLASTICS

T-Lock Lining 11,200 SF $21 1.000 $240,555

Inlet Flocculating Baffles 1 LS $120,000 1.000 $120,000

Mid Tank Baffles 1 LS $180,000 1.000 $180,000

Sludge Hopper Canopy 1 LS $100,000 1.000 $100,000

Effluent Launders 108 LF $80 1.000 $8,640

V-notch weirs 216 LF $120 1.000 $25,920

Misc. Wood and Plastics 1 LS $50,000 1.000 $50,000

Total, Div. 06000 $725,115

7 THERMAL AND MOISTURE PROTECTION

Pump Gallery 1 LS $30,000 1.000 $30,000

Total, Div. 07000 $30,000

8 DOORS AND WINDOWS

Single Door 2 EA $1,900 1.000 $3,800

File: Package 2 - Conceptual Design Cost Estimate.xlsTab: 6

Page 18 of 37

Page 42: City of Sunnyvale · Culvert and Temporary Bypass $7,007,000 : $7,300,000 . Subtotal $17,924,000 . ... Includes installation of a new box culvert to replace the storm drainage volume

PRELIMINARY COST ESTIMATE - PACKAGE 2 - HEADWORKS AND PSTS

PROJECT : PRIMARY TREATMENT DESIGN LOCATION FACTOR: 1.000

CITY OF SUNNYVALE ESTIMATED MIDPOINT OF CONSTRUCTION : 11/3/2017

JOB # : 9265A.10 COST ESTIMATE PREPARATION DATE : 8/28/2014

LOCATION : SUNNYVALE, CA BY : MP

ELEMENT # : 6 REVIEWED BY: CO

ELEMENT : PRIMARY SEDIMENTATION TANKS DH

DIVISION DESCRIPTION QUAN UNIT UNIT COST

LOCATION

FACTOR SUBTOTAL TOTAL

Double Door 1 EA $3,600 1.000 $3,600

Total, Div. 08000 $7,400

9 FINISHES

Painting and Protective Coating 1 LS $30,000 1.000 $30,000

Air Compression

Painting and Protective Coatings 1 LS $7,000 1.000 $7,000

Total, Div. 09000 $37,000

10 SPECIALTIES

Signs, Identification, Stenciling and Tagging System 1 LS $25,000 1.000 $25,000

Total, Div. 10000 $25,000

11 EQUIPMENT

Chain and Flight Sludge Collector 6 EA $100,000 1.000 $600,000

Ducking/Tilting Trough Skimmer 6 EA $40,000 1.000 $240,000

Scum Pump 4 EA $37,000 1.000 $148,000

Sludge Pump 9 EA $31,000 1.000 $279,000

Sump Pump 1 EA $6,000 1.000 $6,000

Pre-aeration Blowers 2 EA $112,000 1.000 $224,000

Ventilation Fans 4 LS $2,000 1.000 $8,000Ventilation Fans 4 LS $2,000 1.000 $8,000

Odor Control Fans at PST 2 EA $3,000 1.000 $6,000

Dampers 1 LS $4,000 1.000 $4,000

Ductwork and Accessories 1 LS $20,000 1.000 $20,000

Primary Influent Gates - 2' x 3' 18 EA $13,100 1.000 $235,800

Primary Effluent Gates - 3' x 3' 6 EA $14,400 1.000 $86,400

Primary Effluent Channel Gates - 66" x 66" 2 EA $30,000 1.000 $60,000

Stop Plates and Guide - 2' x 5' (Primary Influent Gates) 18 EA $3,000 1.000 $54,000

Stop Plates and Guide - 3' x 5' (Primary Effluent Gates) 6 EA $3,500 1.000 $21,000

Stop Plates and Guide - 5' x 10' (Primary Influent Channel) 2 EA $10,000 1.000 $20,000

Stop Plates and Guide - 4' x 8' (Primary Effluent Channel) 2 EA $7,000 1.000 $14,000

Gate Operators 42 EA $7,500 1.000 $315,000

Misc. Equipment 1 LS $100,000 1.000 $100,000

Air Compression

Rotary Screw Non-lubricated Air Compressors (Duty/Standby) 2 EA $7,500 1.000 $15,000

Includes Packaged Control Panel

Air Receiver 1 EA $1,000 1.000 $1,000

Refrigerant Air Dryer 1 EA $1,000 1.000 $1,000

Desiccant Air Dryer 1 EA $700 1.000 $700

Auto Drain Valves 3 EA $200 1.000 $600

Total, Div. 11000 $2,459,500

12 FURNISHING

None

Total, Div. 12000 $0

13 SPECIAL CONSTRUCTION

None

Total, Div. 13000 $0

14 CONVEYING SYSTEMS

File: Package 2 - Conceptual Design Cost Estimate.xlsTab: 6

Page 19 of 37

Page 43: City of Sunnyvale · Culvert and Temporary Bypass $7,007,000 : $7,300,000 . Subtotal $17,924,000 . ... Includes installation of a new box culvert to replace the storm drainage volume

PRELIMINARY COST ESTIMATE - PACKAGE 2 - HEADWORKS AND PSTS

PROJECT : PRIMARY TREATMENT DESIGN LOCATION FACTOR: 1.000

CITY OF SUNNYVALE ESTIMATED MIDPOINT OF CONSTRUCTION : 11/3/2017

JOB # : 9265A.10 COST ESTIMATE PREPARATION DATE : 8/28/2014

LOCATION : SUNNYVALE, CA BY : MP

ELEMENT # : 6 REVIEWED BY: CO

ELEMENT : PRIMARY SEDIMENTATION TANKS DH

DIVISION DESCRIPTION QUAN UNIT UNIT COST

LOCATION

FACTOR SUBTOTAL TOTAL

Monorail and Crane 1 LS $50,000 1.000 $50,000

Total, Div. 14000 $50,000

15 MECHANICAL

Primary influent and Effluent Pipes (Connections & 5 ft from Structure) 1 LS $250,000 1.000 $250,000

Sludge Piping and Valving 1 LS $80,000 1.000 $80,000

Scum Piping and Valving 1 LS $50,000 1.000 $50,000

Pre-aeration Air Piping 1 LS $50,000 1.000 $50,000

Sludge & Scum Pre-heating 1 LS $80,000 1.000 $80,000

Air Diffusers 1 LS $38,000 1.000 $38,000

Misc. Piping 1 LS $50,000 1.000 $50,000

Air Compression

Air Piping 1 LS $5,000 1.000 $5,000

Air Valves 1 LS $500 1.000 $500

Pipe Supports 1 LS $2,000 1.000 $2,000

Total, Div. 15000 $605,500

16 ELECTRICAL

Electrical Allowance (Percentage of Div. 1 - 15) 10% $806,120

Total, Div. 16000 $806,120

17 INSTRUMENTATION

PLC Cabinet 1 EA $176,400 1.000 $176,400

Communications Cabinet 1 EA $15,960 1.000 $15,960

Instrumentation and Controls 1 LS $275,000 1.000 $275,000

Total, Div. 17000 $467,360

SUBTOTAL $9,334,682

Estimating Contingency 25% $2,333,671

SUBTOTAL $11,668,353

Sales Tax on 50% of Subtotal Above 8.75% $510,490

SUBTOTAL $12,178,843

General Conditions 10% $1,217,884

SUBTOTAL $13,396,728

General Contractor Overhead and Profit 13% $1,741,575

SUBTOTAL $15,138,302

Escalation to Mid-Point (at 3% Annual Inflation Rate) 9.88% $1,495,749

ELEMENT CONSTRUCTION COST $16,634,000

File: Package 2 - Conceptual Design Cost Estimate.xlsTab: 6

Page 20 of 37

Page 44: City of Sunnyvale · Culvert and Temporary Bypass $7,007,000 : $7,300,000 . Subtotal $17,924,000 . ... Includes installation of a new box culvert to replace the storm drainage volume

PRELIMINARY COST ESTIMATE - PACKAGE 2 - HEADWORKS AND PSTS

PROJECT : PRIMARY TREATMENT DESIGN LOCATION FACTOR: 1.000

CITY OF SUNNYVALE ESTIMATED MIDPOINT OF CONSTRUCTION : 11/3/2017

JOB # : 9265A.10 COST ESTIMATE PREPARATION DATE : 8/28/2014

LOCATION : SUNNYVALE, CA BY : MP

ELEMENT # : 7 REVIEWED BY: CO

ELEMENT : CEPT FACILITY DH

DIVISION DESCRIPTION QUAN UNIT UNIT COST

LOCATION

FACTOR SUBTOTAL TOTAL

2 SITEWORK

Site Cleaning and Preparation 1 LS $2,000 1.000 $2,000

Excavation 130 CY $7 1.000 $910

Backfilling and Compaction 41 CY $10 1.000 $410

Aggregate Base under Foundation 62 CY $56 1.000 $3,472

Dirt Hauling, 30 miles, round trip 89 CY $11 1.000 $979

Total, Div. 02000 $7,771

3 CONCRETE

Slab on Grade 100 CY $707 1.000 $70,730

Thick Wall (>8" thick) 12 CY $926 1.000 $11,117

Side Walk and Misc. Pads 1 LS $15,000 1.000 $15,000

Misc. Concrete 1 LS $5,000 1.000 $5,000

Total, Div. 03000 . $101,847

4 MASONRY

None

Total, Div. 04000 $0

5 METALS

Stairs, landing and handrails 1 LS $15,000 1.000 $15,000

Metal Canopy 700 SF $120 1.000 $84,000

Total, Div. 05000 $99,000

6 WOOD AND PLASTICS

FRP grating 90 SF $30 1.000 $2,700

Total, Div. 06000 $2,700

7 THERMAL AND MOISTURE PROTECTION

Thermal and Moisture Protection 1 LS $5,000 1.000 $5,000

Total, Div. 07000 $5,000

8 DOORS AND WINDOWS

None

Total, Div. 08000 $0

9 FINISHES

Painting and Protective Coating 1 LS $25,000 1.000 $25,000

Total, Div. 09000 $25,000

10 SPECIALTIES

Signs, Identification, Stenciling and Tagging System 1 LS $5,000 1.000 $5,000

Misc. Specialties (ESEW, etc.) 1 LS $15,000 1.000 $15,000

Total, Div. 10000 $20,000

File: Package 2 - Conceptual Design Cost Estimate.xlsTab: 7

Page 21 of 37

Page 45: City of Sunnyvale · Culvert and Temporary Bypass $7,007,000 : $7,300,000 . Subtotal $17,924,000 . ... Includes installation of a new box culvert to replace the storm drainage volume

PRELIMINARY COST ESTIMATE - PACKAGE 2 - HEADWORKS AND PSTS

PROJECT : PRIMARY TREATMENT DESIGN LOCATION FACTOR: 1.000

CITY OF SUNNYVALE ESTIMATED MIDPOINT OF CONSTRUCTION : 11/3/2017

JOB # : 9265A.10 COST ESTIMATE PREPARATION DATE : 8/28/2014

LOCATION : SUNNYVALE, CA BY : MP

ELEMENT # : 7 REVIEWED BY: CO

ELEMENT : CEPT FACILITY DH

DIVISION DESCRIPTION QUAN UNIT UNIT COST

LOCATION

FACTOR SUBTOTAL TOTAL

11 EQUIPMENT

Ferric Chloride Storage Tank, 5,000 gal 2 EA $15,000 1.000 $30,000

Polymer Tote, 100 gal 2 EA $1,500 1.000 $3,000

Ferric Chloride Metering Pump Skid 1 EA $12,000 1.000 $12,000

Polymer Blending and Activation Unit 1 EA $16,000 1.000 $16,000

Polymer Metering Pump Skid 1 EA $10,000 1.000 $10,000

Total, Div. 11000 $71,000

12 FURNISHING

None

Total, Div. 12000 $0

13 SPECIAL CONDITIONS

None

Total, Div. 13000 $0

14 CONVEYING SYSTEMS

None

Total, Div. 14000 $0Total, Div. 14000 $0

15 MECHANICAL

All Piping and Valving 1 LS $100,000 1.000 $100,000

Total, Div. 15000 $100,000

16 ELECTRICAL

Electrical 1 LS $40,000 1.000 $40,000

Total, Div. 16000 $40,000

17 INSTRUMENTATION

Instrumentation and Controls 1 LS $200,000 1.000 $200,000

Total, Div. 17000 $200,000

SUBTOTAL $672,318

Estimating Contingency 25% $168,080

SUBTOTAL $840,398

Sales Tax on 50% of Subtotal Above 8.75% $36,767

SUBTOTAL $877,165

General Conditions 10% $87,717

SUBTOTAL $964,882

General Contractor Overhead and Profit 13% $125,435

SUBTOTAL $1,090,316

Escalation to Mid-Point (at 3% Annual Inflation Rate) 9.88% $107,729

File: Package 2 - Conceptual Design Cost Estimate.xlsTab: 7

Page 22 of 37

Page 46: City of Sunnyvale · Culvert and Temporary Bypass $7,007,000 : $7,300,000 . Subtotal $17,924,000 . ... Includes installation of a new box culvert to replace the storm drainage volume

PRELIMINARY COST ESTIMATE - PACKAGE 2 - HEADWORKS AND PSTS

PROJECT : PRIMARY TREATMENT DESIGN LOCATION FACTOR: 1.000

CITY OF SUNNYVALE ESTIMATED MIDPOINT OF CONSTRUCTION : 11/3/2017

JOB # : 9265A.10 COST ESTIMATE PREPARATION DATE : 8/28/2014

LOCATION : SUNNYVALE, CA BY : MP

ELEMENT # : 7 REVIEWED BY: CO

ELEMENT : CEPT FACILITY DH

DIVISION DESCRIPTION QUAN UNIT UNIT COST

LOCATION

FACTOR SUBTOTAL TOTAL

ELEMENT CONSTRUCTION COST $1,198,000

File: Package 2 - Conceptual Design Cost Estimate.xlsTab: 7

Page 23 of 37

Page 47: City of Sunnyvale · Culvert and Temporary Bypass $7,007,000 : $7,300,000 . Subtotal $17,924,000 . ... Includes installation of a new box culvert to replace the storm drainage volume

PRELIMINARY COST ESTIMATE - PACKAGE 2 - HEADWORKS AND PSTS

PROJECT : PRIMARY TREATMENT DESIGN LOCATION FACTOR: 1.000

CITY OF SUNNYVALE ESTIMATED MIDPOINT OF CONSTRUCTION : 11/3/2017

JOB # : 9265A.10 COST ESTIMATE PREPARATION DATE : 8/28/2014

LOCATION : SUNNYVALE, CA BY : THK

ELEMENT # : 8 REVIEWED BY: BK

ELEMENT : ODOR CONTROL FACILITY DH

DIVISION DESCRIPTION QUAN UNIT UNIT COST

LOCATION

FACTOR SUBTOTAL TOTAL

2 SITEWORK

Excavation 120 CY $7 1.000 $840

Aggregate Base under Foundation 40 CY $56 1.000 $2,240

Backfilling and Compaction 80 CY $10 1.000 $800

Dirt Hauling, 30 miles, round trip 40 CY $11 1.000 $440

Total, Div. 02000 $4,320

3 CONCRETE

Slab on Grade 70 CY $707 1.000 $49,511

Tank Pads 10 CY $634 1.000 $6,343

Fan Pads 2 CY $634 1.000 $1,269

Total, Div. 03000 $57,122

4 MASONRY

None

Total, Div. 04000 $0

5 METALS

Miscellaneous Metals 1 LS $3,000 1.000 $3,000

Total, Div. 05000 $3,000

6 WOOD AND PLASTICS

None

Total, Div. 06000 $0

7 THERMAL AND MOISTURE PROTECTION

None

Total, Div. 07000 $0

8 DOORS AND WINDOWS

None

Total, Div. 08000 $0

9 FINISHES

Painting 1 LS $7,500 1.000 $7,500

Total, Div. 09000 $7,500

10 SPECIALTIES

None

Total, Div. 10000 $0

11 EQUIPMENT

Packaged Bioscrubber 3 EA $450,000 1.000 $1,350,000

Includes:

Scrubber Tank

Blowers

Control Panel

Water Panel

Piping and Valves Between Panel and Scrubber

Nutrient Feed Pumps and Tank

Initial Nutrients

Material Installation

Total, Div. 11000 $1,350,000

File: Package 2 - Conceptual Design Cost Estimate.xlsTab: 8

Page 24 of 37

Page 48: City of Sunnyvale · Culvert and Temporary Bypass $7,007,000 : $7,300,000 . Subtotal $17,924,000 . ... Includes installation of a new box culvert to replace the storm drainage volume

PRELIMINARY COST ESTIMATE - PACKAGE 2 - HEADWORKS AND PSTS

PROJECT : PRIMARY TREATMENT DESIGN LOCATION FACTOR: 1.000

CITY OF SUNNYVALE ESTIMATED MIDPOINT OF CONSTRUCTION : 11/3/2017

JOB # : 9265A.10 COST ESTIMATE PREPARATION DATE : 8/28/2014

LOCATION : SUNNYVALE, CA BY : THK

ELEMENT # : 8 REVIEWED BY: BK

ELEMENT : ODOR CONTROL FACILITY DH

DIVISION DESCRIPTION QUAN UNIT UNIT COST

LOCATION

FACTOR SUBTOTAL TOTAL

12 FURNISHING

None

Total, Div. 12000 $0

13 SPECIAL CONDITIONS

None

Total, Div. 13000 $0

14 CONVEYING SYSTEMS

None

Total, Div. 14000 $0

15 MECHANICAL

46" FRP Duct 18 LF $300 1.000 $5,400

32" FRP Duct 16 LF $190 1.000 $3,040

FRP Tees 2 EA $2,000 1.000 $4,000

FRP Elbows 4 EA $1,400 1.000 $5,600

Flexible Duct Connection 6 EA $400 1.000 $2,400

FRP Dampers 3 EA $500 1.000 $1,500

Drain Piping and Fittings 1 LS $10,000 1.000 $10,000

Miscellaneous Piping, Valves, Utility Station 1 LS $5,000 1.000 $5,000

Pipe Supports 1 LS $5,000 1.000 $5,000

Total, Div. 15000 $41,940Total, Div. 15000 $41,940

16 ELECTRICAL

Electrical (Power to manufacturer panels) 1 LS $50,000 1.000 $50,000

Total, Div. 16000 $50,000

17 INSTRUMENTATION

Instrumentation (Remote monitoring to SCADA) 1 LS $50,000 1.000 $50,000

Total, Div. 17000 $50,000

SUBTOTAL $1,563,882

Estimating Contingency 25% $390,971

SUBTOTAL $1,954,853

Sales Tax on 50% of Subtotal Above 8.75% $85,525

SUBTOTAL $2,040,378

General Conditions 10% $204,038

SUBTOTAL $2,244,416

General Contractor Overhead and Profit 13% $291,774

SUBTOTAL $2,536,190

Escalation to Mid-Point (at 3% Annual Inflation Rate) 9.88% $250,590

ELEMENT CONSTRUCTION COST $2,787,000

File: Package 2 - Conceptual Design Cost Estimate.xlsTab: 8

Page 25 of 37

Page 49: City of Sunnyvale · Culvert and Temporary Bypass $7,007,000 : $7,300,000 . Subtotal $17,924,000 . ... Includes installation of a new box culvert to replace the storm drainage volume

PRELIMINARY COST ESTIMATE - PACKAGE 2 - HEADWORKS AND PSTS

PROJECT : PRIMARY TREATMENT DESIGN LOCATION FACTOR: 1.163

CITY OF SUNNYVALE ESTIMATED MIDPOINT OF CONSTRUCTION : 11/3/2017

JOB # : 9265A.10 COST ESTIMATE PREPARATION DATE : 8/28/2014

LOCATION : SUNNYVALE, CA BY : MK

ELEMENT # : 9 REVIEWED BY: KR

ELEMENT : HEADWORKS ELECTRICAL BUILDING JW

DIVISION DESCRIPTION QUAN UNIT UNIT COST

LOCATION

FACTOR SUBTOTAL TOTAL

2 SITEWORK

Site Cleaning and Preparation 1 LS $2,000 1.000 $2,000

Cat 235 Trackhoe 1.50CY Bucket, Class C (Hard Digging), 0-20' D 160 CY $4.27 1.163 $794Native Pipe Bed & Zone/Confined Structure Backfill, Class A 41 CY $28 1.163 $1,317ABC 44 CY $56 1.000 $2,46420 CY Dump Truck, 30 Miles/Round Trip 195 CY $13 1.163 $3,047

Total, Div. 02000 $9,623

3 CONCRETE

12" STRUCTURAL FLAT MAT ON GRADE 50 CY $500 1.163 $29,075

Total, Div. 03000 $29,075

4 MASONRY

Standard Concrete Block, 8" 283 SF $17 1.163 $5,696

Standard Concrete Block, 12" 2,547 SF $20 1.163 $57,894

Seismic Reinforcement Adder 2,547 SF $1 1.163 $4,194

Full Grout (All cells) 2,830 SF $1 1.163 $4,147

Pilaster Adder 283 SF $82 1.163 $26,994

Total, Div. 04000 $98,925

5 METALS

Structural Steel Shapes & Plates - Sub (ALLOWANCE) 1 EA $10,000 1.000 $10,000

Steel Deck, 3" X 16 Ga. 1,200 SF $7 1.163 $9,747

Aluminum Stairs, Including Railing and Supports 28 RSR $561 1.163 $18,276

Total, Div. 05000 $38,023

6 WOOD AND PLASTICS

None

Total, Div. 06000 $0

7 THERMAL AND MOISTURE PROTECTION

3-1/4" R-20.00 Composite Board Roof Insulation 1,200 SF $4 1.163 $6,266

Neoprene, Fully Adhered With Adhesive, Polychloroprene 1,200 SF $7 1.163 $10,048

Total, Div. 07000 $16,315

8 DOORS AND WINDOWS

7/0 X 7/0 X 1.75" NO LABEL DOUBLE HOLLOW METAL DOOR

W/FRAME & HDWRE 1 EA $1,645 1.163 $1,913

3/0 X 7/0 X 1.75" NO LABEL SINGLE HOLLOW METAL DOOR

W/FRAME & HDWRE 3 EA $853 1.163 $2,974

Total, Div. 08000 $4,888

9 FINISHES

None

Total, Div. 09000 $0

10 SPECIALTIES

File: Package 2 - Conceptual Design Cost Estimate.xlsTab: 9

Page 26 of 37

Page 50: City of Sunnyvale · Culvert and Temporary Bypass $7,007,000 : $7,300,000 . Subtotal $17,924,000 . ... Includes installation of a new box culvert to replace the storm drainage volume

PRELIMINARY COST ESTIMATE - PACKAGE 2 - HEADWORKS AND PSTS

PROJECT : PRIMARY TREATMENT DESIGN LOCATION FACTOR: 1.163

CITY OF SUNNYVALE ESTIMATED MIDPOINT OF CONSTRUCTION : 11/3/2017

JOB # : 9265A.10 COST ESTIMATE PREPARATION DATE : 8/28/2014

LOCATION : SUNNYVALE, CA BY : MK

ELEMENT # : 9 REVIEWED BY: KR

ELEMENT : HEADWORKS ELECTRICAL BUILDING JW

DIVISION DESCRIPTION QUAN UNIT UNIT COST

LOCATION

FACTOR SUBTOTAL TOTAL

None

Total, Div. 10000 $0

11 EQUIPMENT

None

Total, Div. 11000 $0

12 FURNISHING

None

Total, Div. 12000 $0

13 SPECIAL CONDITIONS

Alarm and Security System 1 EA $30,000 1.000 $30,000

Total, Div. 13000 $30,000

14 CONVEYING SYSTEMS

None

Total, Div. 14000 $0Total, Div. 14000 $0

15 MECHANICAL

HVAC Allowance 1 EA $35,000 1.000 $35,000

Total, Div. 15000 $35,000

16 ELECTRICAL

Allowance for Electrical Equipment 1 LS $1,000,000 $1,000,000

Total, Div. 16000 $1,000,000

17 INSTRUMENTATION

PLC Cabinet 2 EA $176,400 $352,800

Communications Cabinet 1 EA $15,960 $15,960

Instrumentation Allowance (Percentage of Div. 1 - 15) 5% $11,342

Total, Div. 17000 $380,102

SUBTOTAL $1,641,951

Estimating Contingency 25% $410,488

SUBTOTAL $2,052,439

Sales Tax on 50% of Subtotal Above 8.75% $89,794

SUBTOTAL $2,142,233

General Conditions 10% $214,223

SUBTOTAL $2,356,456

General Contractor Overhead and Profit 13% $306,339

SUBTOTAL $2,662,796

Escalation to Mid-Point (at 3% Annual Inflation Rate) 9.88% $263,099

File: Package 2 - Conceptual Design Cost Estimate.xlsTab: 9

Page 27 of 37

Page 51: City of Sunnyvale · Culvert and Temporary Bypass $7,007,000 : $7,300,000 . Subtotal $17,924,000 . ... Includes installation of a new box culvert to replace the storm drainage volume

PRELIMINARY COST ESTIMATE - PACKAGE 2 - HEADWORKS AND PSTS

PROJECT : PRIMARY TREATMENT DESIGN LOCATION FACTOR: 1.163

CITY OF SUNNYVALE ESTIMATED MIDPOINT OF CONSTRUCTION : 11/3/2017

JOB # : 9265A.10 COST ESTIMATE PREPARATION DATE : 8/28/2014

LOCATION : SUNNYVALE, CA BY : MK

ELEMENT # : 9 REVIEWED BY: KR

ELEMENT : HEADWORKS ELECTRICAL BUILDING JW

DIVISION DESCRIPTION QUAN UNIT UNIT COST

LOCATION

FACTOR SUBTOTAL TOTAL

ELEMENT CONSTRUCTION COST $2,926,000

File: Package 2 - Conceptual Design Cost Estimate.xlsTab: 9

Page 28 of 37

Page 52: City of Sunnyvale · Culvert and Temporary Bypass $7,007,000 : $7,300,000 . Subtotal $17,924,000 . ... Includes installation of a new box culvert to replace the storm drainage volume

PRELIMINARY COST ESTIMATE - PACKAGE 2 - HEADWORKS AND PSTS

PROJECT : PRIMARY TREATMENT DESIGN LOCATION FACTOR: 1.163

CITY OF SUNNYVALE ESTIMATED MIDPOINT OF CONSTRUCTION : 11/3/2017

JOB # : 9265A.10 COST ESTIMATE PREPARATION DATE : 8/28/2014

LOCATION : SUNNYVALE, CA BY : MK

ELEMENT # : 10 REVIEWED BY: KR

ELEMENT : SWITCHGEAR BUILDING AND ELECTRICAL & INSTRUMENTATION SYSTEM JW

DIVISION DESCRIPTION QUAN UNIT UNIT COST

LOCATION

FACTOR SUBTOTAL TOTAL

2 SITEWORK

Site Cleaning and Preparation 1 LS $2,000 1.000 $2,000

Cat 235 Trackhoe 1.50CY Bucket, Class C (Hard Digging), 0-20' D 241 CY $4.27 1.163 $1,196Native Pipe Bed & Zone/Confined Structure Backfill, Class A 50 CY $28 1.163 $1,607ABC 78 CY $56 1.000 $4,36820 CY Dump Truck, 30 Miles/Round Trip 323 CY $13 1.163 $5,047

Total, Div. 02000 $14,218

3 CONCRETE

12" STRUCTURAL FLAT MAT ON GRADE 78 CY $500 1.163 $45,357

Total, Div. 03000 $45,357

4 MASONRY

Standard Concrete Block, 8" 1,288 SF $17 1.163 $25,924

Standard Concrete Block, 12" 2,966 SF $20 1.163 $67,418

Seismic Reinforcement Adder 2,966 SF $1 1.163 $4,884

Full Grout (All cells) 4,254 SF $1 1.163 $6,234

Pilaster Adder 330 SF $82 1.163 $31,477

Total, Div. 04000 $135,937

5 METALS5 METALS

Structural Steel Shapes & Plates - Sub (ALLOWANCE) 1 EA $10,000 1.000 $10,000

Steel Deck, 3" X 16 Ga. 2,117 SF $7 1.163 $17,196

Aluminum Stairs, Including Railing and Supports 28 RSR $561 1.163 $18,276

Total, Div. 05000 $45,472

6 WOOD AND PLASTICS

None

Total, Div. 06000 $0

7 THERMAL AND MOISTURE PROTECTION

3-1/4" R-20.00 Composite Board Roof Insulation 2,117 SF $4 1.163 $11,055

Neoprene, Fully Adhered With Adhesive, Polychloroprene 2,117 SF $7 1.163 $17,727

Total, Div. 07000 $28,782

8 DOORS AND WINDOWS

7/0 X 7/0 X 1.75" NO LABEL DOUBLE HOLLOW METAL DOOR

W/FRAME & HDWRE 1 EA $1,645 1.163 $1,913

3/0 X 7/0 X 1.75" NO LABEL SINGLE HOLLOW METAL DOOR

W/FRAME & HDWRE 7 EA $853 1.163 $6,940

Total, Div. 08000 $8,853

9 FINISHES

None

Total, Div. 09000 $0

File: Package 2 - Conceptual Design Cost Estimate.xlsTab: 10

Page 29 of 37

Page 53: City of Sunnyvale · Culvert and Temporary Bypass $7,007,000 : $7,300,000 . Subtotal $17,924,000 . ... Includes installation of a new box culvert to replace the storm drainage volume

PRELIMINARY COST ESTIMATE - PACKAGE 2 - HEADWORKS AND PSTS

PROJECT : PRIMARY TREATMENT DESIGN LOCATION FACTOR: 1.163

CITY OF SUNNYVALE ESTIMATED MIDPOINT OF CONSTRUCTION : 11/3/2017

JOB # : 9265A.10 COST ESTIMATE PREPARATION DATE : 8/28/2014

LOCATION : SUNNYVALE, CA BY : MK

ELEMENT # : 10 REVIEWED BY: KR

ELEMENT : SWITCHGEAR BUILDING AND ELECTRICAL & INSTRUMENTATION SYSTEM JW

DIVISION DESCRIPTION QUAN UNIT UNIT COST

LOCATION

FACTOR SUBTOTAL TOTAL

10 SPECIALTIES

None

Total, Div. 10000 $0

11 EQUIPMENT

None

Total, Div. 11000 $0

12 FURNISHING

None

Total, Div. 12000 $0

13 SPECIAL CONDITIONS

Alarm and Security System 1 EA $30,000 1.000 $30,000

Total, Div. 13000 $30,000

14 CONVEYING SYSTEMS

None

Total, Div. 14000 $0

15 MECHANICAL

HVAC Allowance 1 EA $50,000 1.000 $50,000

Total, Div. 15000 $50,000

16 ELECTRICAL

Allowance for Electrical Equipment 1 LS $1,500,000 $1,500,000

Total, Div. 16000 $1,500,000

17 INSTRUMENTATION

HMI Hardware and Software 1 EA $327,600 $327,600

HMI Development Hardware and Software 1 EA $176,400 $176,400

Server Room UPS 1 EA $20,160 $20,160

Instrumentation Allowance (Percentage of Div. 1 - 15) 5% $15,431

Total, Div. 17000 $539,591

SUBTOTAL $2,398,210

Estimating Contingency 25% $599,553

SUBTOTAL $2,997,763

Sales Tax on 50% of Subtotal Above 8.75% $131,152

SUBTOTAL $3,128,915

General Conditions 10% $312,891

SUBTOTAL $3,441,806

General Contractor Overhead and Profit 13% $447,435

SUBTOTAL $3,889,241

File: Package 2 - Conceptual Design Cost Estimate.xlsTab: 10

Page 30 of 37

Page 54: City of Sunnyvale · Culvert and Temporary Bypass $7,007,000 : $7,300,000 . Subtotal $17,924,000 . ... Includes installation of a new box culvert to replace the storm drainage volume

PRELIMINARY COST ESTIMATE - PACKAGE 2 - HEADWORKS AND PSTS

PROJECT : PRIMARY TREATMENT DESIGN LOCATION FACTOR: 1.163

CITY OF SUNNYVALE ESTIMATED MIDPOINT OF CONSTRUCTION : 11/3/2017

JOB # : 9265A.10 COST ESTIMATE PREPARATION DATE : 8/28/2014

LOCATION : SUNNYVALE, CA BY : MK

ELEMENT # : 10 REVIEWED BY: KR

ELEMENT : SWITCHGEAR BUILDING AND ELECTRICAL & INSTRUMENTATION SYSTEM JW

DIVISION DESCRIPTION QUAN UNIT UNIT COST

LOCATION

FACTOR SUBTOTAL TOTAL

Escalation to Mid-Point (at 3% Annual Inflation Rate) 9.88% $384,279

ELEMENT CONSTRUCTION COST $4,274,000

File: Package 2 - Conceptual Design Cost Estimate.xlsTab: 10

Page 31 of 37

Page 55: City of Sunnyvale · Culvert and Temporary Bypass $7,007,000 : $7,300,000 . Subtotal $17,924,000 . ... Includes installation of a new box culvert to replace the storm drainage volume

PRELIMINARY COST ESTIMATE - PACKAGE 2 - HEADWORKS AND PSTS

PROJECT : PRIMARY TREATMENT DESIGN LOCATION FACTOR: 1.163

CITY OF SUNNYVALE ESTIMATED MIDPOINT OF CONSTRUCTION : 11/3/2017

JOB # : 9265A.10 COST ESTIMATE PREPARATION DATE : 8/28/2014

LOCATION : SUNNYVALE, CA BY : MK

ELEMENT # : 11 REVIEWED BY: KR

ELEMENT : STANDBY GENERATOR JW

DIVISION DESCRIPTION QUAN UNIT UNIT COST

LOCATION

FACTOR SUBTOTAL TOTAL

2 SITEWORK

Cat 235 Trackhoe 1.50CY Bucket, Class C (Hard Digging), 0-20' D 176 CY $4.27 1.163 $874Native Pipe Bed & Zone/Confined Structure Backfill, Class A 56 CY $28 1.163 $1,799ABC 48 CY $56 1.000 $2,68820 CY Dump Truck, 30 Miles/Round Trip 202 CY $13 1.163 $3,157

Total, Div. 02000 $8,518

3 CONCRETE

24" STRUCTURAL FLAT MAT ON GRADE 80 CY $500 1.163 $46,520

Total, Div. 03000 $46,520

4 MASONRY

None

Total, Div. 04000 $0

5 METALS

None

Total, Div. 05000 $0

6 WOOD AND PLASTICS6 WOOD AND PLASTICS

None

Total, Div. 06000 $0

7 THERMAL AND MOISTURE PROTECTION

None

Total, Div. 07000 $0

8 DOORS AND WINDOWS

None

Total, Div. 08000 $0

9 FINISHES

None

Total, Div. 09000 $0

10 SPECIALTIES

None

Total, Div. 10000 $0

11 EQUIPMENT

None

Total, Div. 11000 $0

File: Package 2 - Conceptual Design Cost Estimate.xlsTab: 11

Page 32 of 37

Page 56: City of Sunnyvale · Culvert and Temporary Bypass $7,007,000 : $7,300,000 . Subtotal $17,924,000 . ... Includes installation of a new box culvert to replace the storm drainage volume

PRELIMINARY COST ESTIMATE - PACKAGE 2 - HEADWORKS AND PSTS

PROJECT : PRIMARY TREATMENT DESIGN LOCATION FACTOR: 1.163

CITY OF SUNNYVALE ESTIMATED MIDPOINT OF CONSTRUCTION : 11/3/2017

JOB # : 9265A.10 COST ESTIMATE PREPARATION DATE : 8/28/2014

LOCATION : SUNNYVALE, CA BY : MK

ELEMENT # : 11 REVIEWED BY: KR

ELEMENT : STANDBY GENERATOR JW

DIVISION DESCRIPTION QUAN UNIT UNIT COST

LOCATION

FACTOR SUBTOTAL TOTAL

12 FURNISHING

None

Total, Div. 12000 $0

13 SPECIAL CONDITIONS

None

Total, Div. 13000 $0

14 CONVEYING SYSTEMS

None

Total, Div. 14000 $0

15 MECHANICAL

Piping Allowance 1 EA $20,000 1.000 $20,000

Total, Div. 15000 $20,000

16 ELECTRICAL

Standby Generator 1 EA 708,780$ 1.000 708,780$

Fuel Tanks 1 EA 250,000$ 1.000 250,000$ Fuel Tanks 1 EA 250,000$ 1.000 250,000$

Total, Div. 16000 $958,780

17 INSTRUMENTATION

Miscellaneous Instrumentation - Generator and Fuel Tank 1 EA $20,000 1.000 $20,000

Total, Div. 17000 $20,000

SUBTOTAL $1,053,818

Estimating Contingency 25% $263,454

SUBTOTAL $1,317,272

Sales Tax on 50% of Subtotal Above 8.75% $57,631

SUBTOTAL $1,374,903

General Conditions 10% $137,490

SUBTOTAL $1,512,393

General Contractor Overhead and Profit 13% $196,611

SUBTOTAL $1,709,004

Escalation to Mid-Point (at 3% Annual Inflation Rate) 9.88% $168,859

ELEMENT CONSTRUCTION COST $1,878,000

File: Package 2 - Conceptual Design Cost Estimate.xlsTab: 11

Page 33 of 37

Page 57: City of Sunnyvale · Culvert and Temporary Bypass $7,007,000 : $7,300,000 . Subtotal $17,924,000 . ... Includes installation of a new box culvert to replace the storm drainage volume

PRELIMINARY COST ESTIMATE - PACKAGE 2 - HEADWORKS AND PSTS

PROJECT : PRIMARY TREATMENT DESIGN LOCATION FACTOR: 1.000

CITY OF SUNNYVALE ESTIMATED MIDPOINT OF CONSTRUCTION : 11/3/2017

JOB # : 9265A.10 COST ESTIMATE PREPARATION DATE : 8/28/2014

LOCATION : SUNNYVALE, CA BY : THK

ELEMENT # : 12 REVIEWED BY: DH

ELEMENT : EXHAUST HEAT RECOVERY

NOTE:

DIVISION DESCRIPTION QUAN UNIT UNIT COST

LOCATION

FACTOR SUBTOTAL TOTAL

2 SITEWORK

Sitework 1 LS $10,000 1.000 $10,000

Total, Div. 02000 $10,000

3 CONCRETE

Concrete Slab/Miscellaneous Concrete 1 LS $10,000 1.000 $10,000

Equipment Pads 1 LS $1,000 1.000 $1,000

Total, Div. 03000 $11,000

4 MASONRY

None

Total, Div. 04000 $0

5 METALS

Miscellaneous metals 1 LS $20,000 1.000 $20,000

Total, Div. 05000 $20,000

6 WOOD AND PLASTICS

NoneNone

Total, Div. 06000 $0

7 THERMAL AND MOISTURE PROTECTION

None

Total, Div. 07000 $0

8 DOORS AND WINDOWS

None

Total, Div. 08000 $0

9 FINISHES

Painting and Protective Coatings (Piping and Equipment) 1 LS $15,000 1.000 $15,000

Total, Div. 09000 $15,000

10 SPECIALTIES

None

Total, Div. 10000 $0

11 EQUIPMENT

Exhaust Heat Recovery 1 LS $350,000 1.000 $350,000

Total, Div. 11000 $350,000

12 FURNISHING

File: Package 2 - Conceptual Design Cost Estimate.xlsTab: 12

Page 34 of 37

Page 58: City of Sunnyvale · Culvert and Temporary Bypass $7,007,000 : $7,300,000 . Subtotal $17,924,000 . ... Includes installation of a new box culvert to replace the storm drainage volume

PRELIMINARY COST ESTIMATE - PACKAGE 2 - HEADWORKS AND PSTS

PROJECT : PRIMARY TREATMENT DESIGN LOCATION FACTOR: 1.000

CITY OF SUNNYVALE ESTIMATED MIDPOINT OF CONSTRUCTION : 11/3/2017

JOB # : 9265A.10 COST ESTIMATE PREPARATION DATE : 8/28/2014

LOCATION : SUNNYVALE, CA BY : THK

ELEMENT # : 12 REVIEWED BY: DH

ELEMENT : EXHAUST HEAT RECOVERY

NOTE:

DIVISION DESCRIPTION QUAN UNIT UNIT COST

LOCATION

FACTOR SUBTOTAL TOTAL

None

Total, Div. 12000 $0

13 SPECIAL CONDITIONS

None

Total, Div. 13000 $0

14 CONVEYING SYSTEMS

None

Total, Div. 14000 $0

15 MECHANICAL

Exhaust Heat Recovery Piping 1 LS $50,000 1.000 $50,000

Miscellaneous Equipment, Piping, Fittings and Valves 1 LS $145,000 1.000 $145,000

Total, Div. 15000 $195,000

16 ELECTRICAL

Electrical 1 LS $120,000 1.000 $120,000

Total, Div. 16000 $120,000Total, Div. 16000 $120,000

17 INSTRUMENTATION

Controls Improvements 1 EA $300,000 1.000 $300,000

Total, Div. 17000 $300,000

SUBTOTAL $1,021,000

Estimating Contingency 25% $255,250

SUBTOTAL $1,276,250

Sales Tax on 50% of Subtotal Above 8.75% $55,836

SUBTOTAL $1,332,086

General Conditions 10% $133,209

SUBTOTAL $1,465,295

General Contractor Overhead and Profit 13% $190,488

SUBTOTAL $1,655,783

Escalation to Mid-Point (at 3% Annual Inflation Rate) 9.88% $163,601

ELEMENT CONSTRUCTION COST $1,819,000

File: Package 2 - Conceptual Design Cost Estimate.xlsTab: 12

Page 35 of 37

Page 59: City of Sunnyvale · Culvert and Temporary Bypass $7,007,000 : $7,300,000 . Subtotal $17,924,000 . ... Includes installation of a new box culvert to replace the storm drainage volume

PRELIMINARY COST ESTIMATE - PACKAGE 2 - HEADWORKS AND PSTS

PROJECT : PRIMARY TREATMENT DESIGN LOCATION FACTOR: 1.000

CITY OF SUNNYVALE ESTIMATED MIDPOINT OF CONSTRUCTION : 11/3/2017

JOB # : 9265A.10 COST ESTIMATE PREPARATION DATE : 8/28/2014

LOCATION : SUNNYVALE, CA BY : RN

ELEMENT # : 13 REVIEWED BY: DH

ELEMENT : TUNNEL SYSTEM KC

DIVISION DESCRIPTION QUAN UNIT UNIT COST

LOCATION

FACTOR SUBTOTAL TOTAL

2 SITEWORK

Excavations

8' x 8' Tunnel 6000 CY $7 1.000 $144,000

Backfill

8' x 8' Tunnel 3000 CY $10 1.000 $30,000

Hauling Excavated Material

8' x 8' Tunnel 3000 CY $11 1.000 $33,000

Total, Div. 02000 $207,000

3 CONCRETE

8' x 8' Tunnel 650 LF $2,500 1.000 $1,625,000

Total, Div. 03000 $1,625,000

4 MASONRY

None

Total, Div. 04000 $0

5 METALS

Stairs to Tunnels 3 LS $120,000 1.000 $360,000

Total, Div. 05000 $360,000

6 WOOD AND PLASTICS

None

Total, Div. 06000 $0

7 THERMAL AND MOISTURE PROTECTION

None

Total, Div. 07000 $0

8 DOORS AND WINDOWS

None

Total, Div. 08000 $0

9 FINISHES

None

Total, Div. 09000 $0

10 SPECIALTIES

None

Total, Div. 10000 $0

11 EQUIPMENT

File: Package 2 - Conceptual Design Cost Estimate.xlsTab: 13

Page 36 of 37

Page 60: City of Sunnyvale · Culvert and Temporary Bypass $7,007,000 : $7,300,000 . Subtotal $17,924,000 . ... Includes installation of a new box culvert to replace the storm drainage volume

PRELIMINARY COST ESTIMATE - PACKAGE 2 - HEADWORKS AND PSTS

PROJECT : PRIMARY TREATMENT DESIGN LOCATION FACTOR: 1.000

CITY OF SUNNYVALE ESTIMATED MIDPOINT OF CONSTRUCTION : 11/3/2017

JOB # : 9265A.10 COST ESTIMATE PREPARATION DATE : 8/28/2014

LOCATION : SUNNYVALE, CA BY : RN

ELEMENT # : 13 REVIEWED BY: DH

ELEMENT : TUNNEL SYSTEM KC

DIVISION DESCRIPTION QUAN UNIT UNIT COST

LOCATION

FACTOR SUBTOTAL TOTAL

None

Total, Div. 11000 $0

12 FURNISHING

None

Total, Div. 12000 $0

13 SPECIAL CONSTRUCTION

None

Total, Div. 13000 $0

14 CONVEYING SYSTEMS

None

Total, Div. 14000 $0

15 MECHANICAL

Pipe Supports in Tunnel 650 LF $150 1.000 $97,500

Tunnel Drainage Pumps and piping 1 LS $25,000 1.000 $25,000

Total, Div. 15000 $122,500

16 ELECTRICAL

Allowance for Lighting 1 LS $30,000 1.000 $30,000

Allowance for Ventilation 1 LS $30,000 1.000 $30,000

Total, Div. 16000 $60,000

17 INSTRUMENTATION

Allowance for Instrumentation 1 LS $30,000 1.000 $30,000

Total, Div. 17000 $30,000

SUBTOTAL $2,404,500

Estimating Contingency 25% $601,125

SUBTOTAL $3,005,625

Sales Tax on 50% of Subtotal Above 8.75% $131,496

SUBTOTAL $3,137,121

General Conditions 10% $313,712

SUBTOTAL $3,450,833

General Contractor Overhead and Profit 13% $448,608

SUBTOTAL $3,899,442

Escalation to Mid-Point (at 3% Annual Inflation Rate) 9.88% $385,287

ELEMENT CONSTRUCTION COST $4,285,000

File: Package 2 - Conceptual Design Cost Estimate.xlsTab: 13

Page 37 of 37

Page 61: City of Sunnyvale · Culvert and Temporary Bypass $7,007,000 : $7,300,000 . Subtotal $17,924,000 . ... Includes installation of a new box culvert to replace the storm drainage volume

Design Information Memorandum No. 12 PACKAGE 3 – DEMOLITION AND SITE RESTORATION

November 2014 - FINAL pw://Carollo/Documents/Client/CA/Sunnyvale/9265A10/DIMs/DIM 12-Construction Cost Estimate.docx

Page 62: City of Sunnyvale · Culvert and Temporary Bypass $7,007,000 : $7,300,000 . Subtotal $17,924,000 . ... Includes installation of a new box culvert to replace the storm drainage volume
Page 63: City of Sunnyvale · Culvert and Temporary Bypass $7,007,000 : $7,300,000 . Subtotal $17,924,000 . ... Includes installation of a new box culvert to replace the storm drainage volume

PROJECT : CITY OF SUNNYVALE

PRIMARY TREATMENT DESIGNPRELIMINARY COST ESTIMATE - PACKAGE 3 - DEMOLITION AND SITE RESTORATION ESTIMATED MIDPOINT OF CONSTRUCTION : 9/21/2019

JOB # : 9265A.10 COST ESTIMATE PREPARATION DATE : 8/28/2014ELEMENT : SUMMARY OF CONSTRUCTION COSTS BY : MK/KR

Rate of Annual Inflation: 3%Estimating Contingency: 25%

Sales Tax: 8.75%General Conditions: 10%

Contractor Overhead and Profit: 13%

ELEMENT # DESCRIPTION TOTAL

1 SITE DEMOLITION $2,780,000

Total Estimated Construction Cost = $2,780,000

File: Package 3 - Conceptual Design Cost Estimate.xlsTab: Summary

Page 1 of 4

Page 64: City of Sunnyvale · Culvert and Temporary Bypass $7,007,000 : $7,300,000 . Subtotal $17,924,000 . ... Includes installation of a new box culvert to replace the storm drainage volume
Page 65: City of Sunnyvale · Culvert and Temporary Bypass $7,007,000 : $7,300,000 . Subtotal $17,924,000 . ... Includes installation of a new box culvert to replace the storm drainage volume

PRELIMINARY COST ESTIMATE - PACKAGE 3 - DEMOLITION AND SITE RESTORATION

PROJECT : PRIMARY TREATMENT DESIGN LOCATION FACTOR: 1.163

CITY OF SUNNYVALE ESTIMATED MIDPOINT OF CONSTRUCTION : 9/21/2019

JOB # : 9265A.10 COST ESTIMATE PREPARATION DATE : 8/28/2014

LOCATION : SUNNYVALE, CA BY : MK/KR

ELEMENT # : 1 REVIEWED BY: JW

ELEMENT : SITE DEMOLITION

DIVISION DESCRIPTION QUAN UNIT UNIT COST

LOCATION

FACTOR SUBTOTAL TOTAL

2 SITEWORK

Auxiliary Pump Station

Earthwork Allowance 1 LS $200,000 1.000 $200,000

DEMO LARGE CONCRETE BUILDING 27720 CF $2.00 1.163 $64,477

Offhaul concrete demo 1027 CY $20.00 1.000 $20,533

Remove EquipmentInfluent Sampler 1 EA $2,000 1.000 $2,000

Influent Sluice Gate 1 EA $2,000 1.000 $2,000

Bar Screen 1 EA $10,000 1.000 $10,000Influent Pumps 2 EA $10,000 1.000 $20,000Flow Meter 2 EA $2,000 1.000 $4,000

Dewatering Sump Pump 1 EA $2,000 1.000 $2,000

Grinder Flush Water Valve 1 EA $2,000 1.000 $2,000

Influent Sampler Pump 1 EA $2,000 1.000 $2,000

Remove Piping

30" Influent Pump Discharge 20 LF $79 1.163 $1,840

48" Influent Pipe 23 LF $128 1.163 $3,417

24" Pump Discharge 60 LF $63 1.163 $4,390

Remove Electrical Equipment and Wiring 1 LS $10,000 1.000 $10,000

Primary Control Building

Remove Equipment EA 1.000 $0

Engines 3 $20,000 1.000 $60,000

90 Degree Drives 3 $5,000 1.000 $15,00090 Degree Drives 3 $5,000 1.000 $15,000

Influent Pumps 3 $10,000 1.000 $30,000

Air Blowers and Appurtenances (Silencing Intakes) 3 $10,000 1.000 $30,000

In-channel Grinders 2 $10,000 1.000 $20,000

In-channel Grinder Hydraulic System 1 $10,000 1.000 $10,000

Sludge Pumps 2 $5,000 1.000 $10,000

Screenings Pump 1 $5,000 1.000 $5,000

Heat Recovery System 1 $20,000 1.000 $20,000

Water Softening System 1 $5,000 1.000 $5,000

Boilers and Boiler Stacks 2 $10,000 1.000 $20,000

Repair Roof at Boiler Stack 1 $5,000 1.000 $5,000

Sluice Gates 2 $5,000 1.000 $10,000

Sluice Gate Hydraulic System 1 $5,000 1.000 $5,000

Air Compressors 2 $5,000 1.000 $10,000

Jib Cranes 2 $5,000 1.000 $10,000

Remove Piping LF

Allowance 1 LS $100,000 1.000 $100,000

Remove Electrical Equipment and Wiring 1 LS $30,000 1.000 $30,000

Primary Sedimentation Tanks

Remove Equipment EA 1.000 $0

Raw Sludge Pumps 10 $5,000 1.000 $50,000

Sedimentation Scum Removers 10 $5,000 1.000 $50,000

Sedimentation Cross Collectors 9 $5,000 1.000 $45,000

Sedimentation Longitudinal Collectors 10 $10,000 1.000 $100,000

Sedimentation Tank Drain Valves 10 $1,000 1.000 $10,000

Grit Removal Pumps 10 $5,000 1.000 $50,000

Grit Removal Pump Discharge Control Valves 10 $1,000 1.000 $10,000

Preaeration Air Diffusers in Tanks 10 $2,000 1.000 $20,000

Preaeration Tank Drain Valves 10 $1,000 1.000 $10,000

Preaeration Tank Slide Gates 10 $2,000 1.000 $20,000

Preaeration Tank Air Flowmeters 10 $500 1.000 $5,000

Effluent Launders 20 $1,000 1.000 $20,000

Effluent Slide Gates 20 $1,000 1.000 $20,000

Sedimentation Gallery Exhaust Fan 2 $2,000 1.000 $4,000

File: Package 3 - Conceptual Design Cost Estimate.xlsTab: 1

Page 2 of 4

Page 66: City of Sunnyvale · Culvert and Temporary Bypass $7,007,000 : $7,300,000 . Subtotal $17,924,000 . ... Includes installation of a new box culvert to replace the storm drainage volume

PRELIMINARY COST ESTIMATE - PACKAGE 3 - DEMOLITION AND SITE RESTORATION

PROJECT : PRIMARY TREATMENT DESIGN LOCATION FACTOR: 1.163

CITY OF SUNNYVALE ESTIMATED MIDPOINT OF CONSTRUCTION : 9/21/2019

JOB # : 9265A.10 COST ESTIMATE PREPARATION DATE : 8/28/2014

LOCATION : SUNNYVALE, CA BY : MK/KR

ELEMENT # : 1 REVIEWED BY: JW

ELEMENT : SITE DEMOLITION

DIVISION DESCRIPTION QUAN UNIT UNIT COST

LOCATION

FACTOR SUBTOTAL TOTAL

Influent Gates 27 $1,000 1.000 $27,000

Scum Removal Air Blower 3 $5,000 1.000 $15,000

Scum Ejector 4 $5,000 1.000 $20,000

Influent Channel Slide Gates 3 $2,000 1.000 $6,000

Effluent Channel Slide Gates 10 $2,000 1.000 $20,000

Remove Piping LF

Allowance 1 LS $100,000 1.000 $100,000

Remove Electrical Equipment and Wiring 1 LS $30,000 1.000 $30,000

Landscaping Allowance 1 LS $100,000 1.000 $100,000

Total, Div. 02000 $1,475,657

3 CONCRETE

None

Total, Div. 03000 $0

4 MASONRY

None

Total, Div. 04000 $0

5 METALS5 METALS

None

Total, Div. 05000 $0

6 WOOD AND PLASTICS

None

Total, Div. 06000 $0

7 THERMAL AND MOISTURE PROTECTION

None

Total, Div. 07000 $0

8 DOORS AND WINDOWS

None

Total, Div. 08000 $0

9 FINISHES

None

Total, Div. 09000 $0

10 SPECIALITIES

None

Total, Div 10000 $0

File: Package 3 - Conceptual Design Cost Estimate.xlsTab: 1

Page 3 of 4

Page 67: City of Sunnyvale · Culvert and Temporary Bypass $7,007,000 : $7,300,000 . Subtotal $17,924,000 . ... Includes installation of a new box culvert to replace the storm drainage volume

PRELIMINARY COST ESTIMATE - PACKAGE 3 - DEMOLITION AND SITE RESTORATION

PROJECT : PRIMARY TREATMENT DESIGN LOCATION FACTOR: 1.163

CITY OF SUNNYVALE ESTIMATED MIDPOINT OF CONSTRUCTION : 9/21/2019

JOB # : 9265A.10 COST ESTIMATE PREPARATION DATE : 8/28/2014

LOCATION : SUNNYVALE, CA BY : MK/KR

ELEMENT # : 1 REVIEWED BY: JW

ELEMENT : SITE DEMOLITION

DIVISION DESCRIPTION QUAN UNIT UNIT COST

LOCATION

FACTOR SUBTOTAL TOTAL

11 EQUIPMENT

None

Total, Div. 11000 $0

12 FURNISHING

None

Total, Div. 12000 $0

13 SPECIAL CONSTRUCTION

None

Total, Div. 13000 $0

14 CONVEYING SYSTEMS

None

Total, Div. 14000 $0

15 MECHANICAL

None

Total, Div. 15000 $0

16 ELECTRICAL

None

$0

Total, Div. 16000

17 INSTRUMENTATION

None

Total, Div. 17000 $0

SUBTOTAL $1,475,657

Estimating Contingency 25% $368,914

SUBTOTAL $1,844,571

Sales Tax on 50% of Subtotal Above 8.75% $80,700

SUBTOTAL $1,925,271

General Conditions 10% $192,527

SUBTOTAL $2,117,798

General Contractor Overhead and Profit 13% $275,314

SUBTOTAL $2,393,112

Escalation to Mid-Point (at 3% Annual Inflation Rate) 16.16% $386,783

ELEMENT CONSTRUCTION COST $2,780,000

File: Package 3 - Conceptual Design Cost Estimate.xlsTab: 1

Page 4 of 4