city of gaffney code enforcement demolition€¦ · the work under this contract will consist of...

22
City of Gaffney CODE ENFORCEMENT DEMOLITION Bid Package June 2020

Upload: others

Post on 24-Jan-2021

0 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: City of Gaffney CODE ENFORCEMENT DEMOLITION€¦ · The work under this contract will consist of the demolition of structures as described in the bid documents attached. Bid proposals

City of Gaffney

CODE ENFORCEMENT

DEMOLITION

Bid Package

June 2020

Page 2: City of Gaffney CODE ENFORCEMENT DEMOLITION€¦ · The work under this contract will consist of the demolition of structures as described in the bid documents attached. Bid proposals

1

City of Gaffney

Code Enforcement Demolition

Table of Contents

# of Pages

1. Request for Bids (RFB) 3

2. Bid Form (BF) 1

3. Agreement For Demolition (AFD) 5

4. General Conditions (GC) 4

5. Exhibit A – Specifications (EXA) 3

6. Exhibit B – Location Maps 4

Demolition Location Overview

Demolition Location 1 – 805 S. Limestone Street

Demolition Location 2 – 202 Overbrook Drive

Demolition Location 1 – 102 Cedar Street

Page 3: City of Gaffney CODE ENFORCEMENT DEMOLITION€¦ · The work under this contract will consist of the demolition of structures as described in the bid documents attached. Bid proposals

RFB- 1

REQUEST FOR BIDS

CODE ENFORCEMENT – DEMOLITION OF STRUCTURES The City of Gaffney is soliciting sealed and competitive bids from qualified contractors for the demolition of structures as part of code enforcement. The structures to be demolished are located at the following locations:

805 South Limestone Street (Tax Map No. 082-14-00-063.000)

202 Overbrook Drive (Tax Map No. 081-14-00-009.000)

102 Cedar Street (Tax Map No. 099-07-00-113.001) Sealed bids will be received by the City of Gaffney until 3:00 p.m.ET, on (Thurs, June 11, 2020) from qualified contractors. All bids duly received will be publicly opened and read aloud on the second floor at Gaffney City Hall, located at 201 North Limestone Street, Gaffney South Carolina 29340. Bids will not be accepted after the above date and time. The work under this contract will consist of the demolition of structures as described in the bid documents attached. Bid proposals should be submitted as follows: Submittal: One (1) original of the bid form must be received on or before

3:00 p.m. on Thurs, June 11, 2020. Physical Address: City of Gaffney Attn: Mr. Heath Gregory, Building Inspector 201 N. Limestone Street (second floor) Gaffney, South Carolina 29340 Mark Envelope: “BID – CODE ENFORCEMENT DEMOLITION” (Sealed envelope

must be clearly marked with these words on outside) There will be a mandatory pre-bid meeting for this project at 3:00 p.m. on (Thurs, June 4, 2020). This meeting will be held on the 2nd floor conference room 201 of Gaffney City Hall. If you fail to attend you will not be allowed to bid. Contractor Requirements Bids received after the date and time set for receipt will not be accepted. It is the bidder’s responsibility to ensure timely delivery of their bid. Weather, flight delays, carrier errors and other acts of otherwise excusable neglect are risks allocated to bidders and will not be exempted from deadline requirements. Telegraphic, telephone or facsimile bids will not be accepted. Any offer submitted as a result of this solicitation shall be binding on the offeror for ninety (90) calendar days following the bid opening date. Any bid for which the offeror specifies a shorter acceptance period may be rejected. The owner reserves the right to waive any irregularities, or to reject any or all bids. No bidder may withdraw his/her bid within ninety (90) days after the actual date of the opening thereof.

Page 4: City of Gaffney CODE ENFORCEMENT DEMOLITION€¦ · The work under this contract will consist of the demolition of structures as described in the bid documents attached. Bid proposals

RFB- 2

Bids forms that are not signed will not be accepted as complete and shall not be considered. Bids must be signed in ink (not typed) in the appropriate space(s) by an authorized officer or employee of the bidder. Bids must be submitted on the “Bid Form” provided. Upon receiving the “NOTICE OF AWARD”, the successful bidder has ten (10) business days to submit all required insurance certificates, permits, and licenses. If the Bidder discovers any ambiguity, conflict, discrepancy, omission or other errors in the Bid, Bidder shall immediately notify the City of such error in writing and request modification or clarification of the document. The Bidder is responsible for clarifying any ambiguity, conflict, discrepancy, omission or other error in the Bid or it shall be deemed waived. The successful contractor shall comply with all instructions and shall perform services in a manner commensurate with the highest professional standards by qualified and experienced personnel. The successful bidder will be required to enter into a contract agreement for these services. The agreement will be as provided in this bid package unless otherwise agreed upon by the City and contractor. It shall be the contractor’s responsibility to insure that all work conforms to OSHA requirements and the oral or written instructions pertaining to the safety and protection of all persons in or about the site of the work. The contractor shall be responsible for any damage or injury to any person or property resulting from the contractor’s failure to maintain adequate safeguards against the occurrence of accidents, injuries, or damages at the site of the work. During the performance of the contract, the contractor shall comply with any and all Federal, State or Local laws. Any revisions to the bid request will be issued and distributed as an addendum. Bidders are specifically directed not to contact any other City personnel for meetings, conferences, or technical discussions related to this Bid. Failure to adhere to this policy may be ground for rejection of bids. Offerors are cautioned that any statements made by the contact of City staff persons that materially change any portion of the bid document shall not be relied upon unless subsequently ratified by a formal written amendment to the bid document. This bid request is being issued by the City of Gaffney. Unless otherwise directed, all communication and questions regarding bids must be submitted in written format to the City at the following:

City of Gaffney Attn: Heath Gregory, Building Inspector 201 N. Limestone Street Gaffney, South Carolina 29340 Phone: (864) 487-8500 Email: [email protected] The deadline for written questions is seven calendar days prior to the bid opening.

Page 5: City of Gaffney CODE ENFORCEMENT DEMOLITION€¦ · The work under this contract will consist of the demolition of structures as described in the bid documents attached. Bid proposals

RFB- 3

The right is reserved by the City of Gaffney to reject any or all bids; to waive any informality or irregularity not affected by law; to evaluate, in its absolute discretion, the bids submitted; and to award contract according to the bid which best serves the interest of the City. All costs incurred by the bidder associated with bid preparations and subsequent interviews and/or negotiations, which may or may not lead to the execution of an agreement, shall be borne entirely and exclusively by the bidder. Protest of Solicitation or Award Solicitation – The City of Gaffney allows any prospective bidder, offeror or contractor who is aggrieved in connection with the solicitation of this contract to protest to the City Administrator within fifteen (15) calendar days. Any protest shall be in writing, submitted to the City Administrator, as stated above, and shall set forth the grounds of protest and the relief requested with enough particularity to give notice of the issues to be decided. Award – Any bidder, offeror or contractor who is aggrieved in connection with the intended award or award of this contract should protest to the City Administrator within fifteen (15) calendar days of the date the notification of award is posted in accordance with this policy. Any protest shall be in writing, submitted to the City Administrator, as stated above, and shall set forth the grounds of protest and the relief requested with enough particularity to give notice of the issues to be decided. Proprietary and/or Confidential Information Your proposal or bid is a public document under the South Carolina Freedom of Information Act (FOIA), except as to information that may be treated as confidential as an exception to disclosure under the FOIA. If you cannot agree to this standard, please do not submit your bid or proposal. All information that is to be treated as confidential and/or proprietary must be clearly identified, and each page containing confidential and/or proprietary information, in whole or in part, must be stamped and/or denoted as CONFIDENTIAL, in bold. All information not so noted and identified shall be subject to disclosure by the City. The words “Bidder”, “Offeror”, “Proposer”, “Vendor”, and “Contractor” are used interchangeably throughout this bid, and are used in place of the person, firm, or corporation submitting a bid.

Page 6: City of Gaffney CODE ENFORCEMENT DEMOLITION€¦ · The work under this contract will consist of the demolition of structures as described in the bid documents attached. Bid proposals

BF - 1

BID FORM

CODE ENFORCEMENT DEMOLITIONS

(THIS FORM MUST BE COMPLETED AND SUBMITTED AT BID OPENING)

805 South Limestone St. 202 Overbrook Dr. 102 Cedar St.

Demolition and

Removal of

Structure

$

$

$

TOTAL PROJECT COST $

In compliance with the invitation, the undersigned agrees to furnish any or all items quoted on at

prices as set forth after the item and otherwise specified.

Dated: Signature

Print Name

Title

Company

Address

Phone

.

Email

Page 7: City of Gaffney CODE ENFORCEMENT DEMOLITION€¦ · The work under this contract will consist of the demolition of structures as described in the bid documents attached. Bid proposals

AFD-1

STATE OF SOUTH CAROLINA )

) AGREEMENT FOR DEMOLITION

COUNTY OF CHEROKEE )

THIS AGREEMENT made and entered into on the date last entered hereinafter, by and

between ____________________________, hereinafter referred to as “Contractor”, and the

CITY OF GAFFNEY, hereinafter referred to as “the City” for demolition and clearing of the

property as described in the Request for Bids.

WITNESSETH:

That the parties hereto, for and in consideration of the covenants, premises, and conditions

hereinafter set forth, agree as follows:

1. Statement of Work

The Contractor will furnish all permits, supervision, labor, materials, machinery, tools,

equipment and services to demolish and remove the following building(s) and/or

structure(s) in accordance with this agreement and the bid documents, request for

proposals, plans, specifications, and other referenced documents:

805 South Limestone Street (Tax Map No. 082-14-00-063.000)

202 Overbrook Drive (Tax Map No. 081-14-00-009.000)

102 Cedar Street (Tax Map No. 099-07-00-113.001)

The following documents are attached hereto and designated to be a part of this

Agreement and are incorporated herein:

Request for Bids

Bid Form

General Conditions

Exhibit A – Specifications

Exhibit B – Location Maps

2. Contract Price

The total contract price is $____________ and is shown on the attached Bid Form, which

is made a part of this Agreement. This Bid Form includes detailed costs for each

property.

3. Change Orders

No changes from the original plans, specifications, work write-up, and documents shall

be made, and the City and Contractor shall not agree to any changes or additional work to

be performed, unless specifically approved by written order of the City prior to such

changes or additions.

Each Order shall include in its final form the following:

Page 8: City of Gaffney CODE ENFORCEMENT DEMOLITION€¦ · The work under this contract will consist of the demolition of structures as described in the bid documents attached. Bid proposals

AFD-2

(a) A detailed description of the change in the work.

(b) The Contractor's proposal (if any) or a conformed copy thereof.

(c) A statement that the resulting change shall be performed in accordance with

Contract requirements except as modified by the Change Order.

4. Inspection of Work

The Contractor shall permit the City to inspect all work and/or materials at all times, and

shall remove and replace all defective work and materials at the Contractor's expense

upon notice by the City.

5. Time of Commencement and Completion

The Contractor represents that no work has been performed and no materials have been

delivered to the construction site prior to the execution of this Agreement. The

Contractor shall commence work upon issuance of a Notice to Proceed by the City.

All work as required in accordance with the work write-up, specifications, and

documents, if any, annexed hereto shall be satisfactorily completed by the Contractor

within sixty (60) days after issuance of the proceed Order.

6. Insurance

The Contractor, as well as any subcontractor, shall maintain such insurance as will

protect him from claims under Workers Compensation Acts and other employee benefits

acts, from claims for damages because of bodily injury, including death, and from claims

for damages to property which may arise both out of and during operations under this

Contract, whether such operations be by himself or by any subcontractor or anyone

directly or indirectly employed by either of them. The Contractor shall maintain general

liability insurance as follows: Coverage for bodily injury liability must be $1,000,000

each person and $2,000,000 each occurrence. Property damage liability must be

$1,000,000 each occurrence and $2,000,000 each aggregate. Workers Compensation and

Employer Liability Coverage must comply with statutory requirements. Certificates of

such insurance shall be provided to the City prior to the time work is commenced. The

Contractor shall defend, indemnify and hold harmless the City, its officers and

employees, from liability and claim for damages because of bodily injury, death, property

damage, sickness, disease, or loss and expense arising from Contractor's operations under

this Contract.

7. Accident Prevention

No laborer or mechanic employed in the performance of this contract shall be required to

work in surroundings or under working conditions which are unsanitary, hazardous, or

Page 9: City of Gaffney CODE ENFORCEMENT DEMOLITION€¦ · The work under this contract will consist of the demolition of structures as described in the bid documents attached. Bid proposals

AFD-3

dangerous to his health or safety as determined under construction safety and health

standards promulgated by the Secretary of Labor.

The Contractor shall exercise precaution at all times for the protection of persons and

property, and shall be responsible for all damages to persons or property, either on or off

the site, which occur as a result of his prosecution of the work. The safety provisions of

applicable laws and building construction codes shall be observed, and the Contractor

shall take or cause to be taken such additional safety and health measures as determined

to be reasonably necessary. Machinery, equipment, and all hazards shall be guarded in

accordance with the safety provisions of the Manual of Accident Prevention in

Construction published by the Associated General Contractors of America, Inc., to the

extent that such provisions are not in conflict with applicable laws.

8. Permits and Licenses

All permits and licenses necessary for the completion and execution of this work,

including but not limited to a City business license and demolition permit, shall be

secured and paid for by the Contractor. If the Contractor at any time observes or

discovers that the bid package, plans and/or specifications are at variance with applicable

laws, rules, ordinances, or regulations bearing on the conduct of or materials used in such

work, he shall promptly notify the City in writing. Any necessary changes shall be

adjusted as provided in the Contract for changes in the work. If the Contractor performs

work contrary to such laws, ordinances and/or regulations, he shall bear all costs arising

therefrom.

9. Workmanship

The entire project shall be executed in the best workmanlike manner in accordance with

the specifications, work write-up, and drawings, if any annexed hereto. In addition, all

work shall be performed in accordance with applicable local codes and regulations

whether or not covered by the work write-up, specifications and drawings, if any. The

Contractor shall keep the premises clean and orderly during the course of the work and

remove all debris at the completion of the work. Materials and equipment that have been

removed and replaced as part of the work shall belong to the Contractor, who shall be

responsible for proper disposal.

10. Assignment/Subcontractors

The Contractor shall not assign his rights under this contract without having first obtained

written consent of the City. Further, the Contractor shall not vary from the

subcontractors nor substitute any subcontractor as listed on the bid documents without

having first obtained the written consent of the City. Any request for assignment of this

contract or substitution of subcontractors shall be directed in writing to the City.

Page 10: City of Gaffney CODE ENFORCEMENT DEMOLITION€¦ · The work under this contract will consist of the demolition of structures as described in the bid documents attached. Bid proposals

AFD-4

The Contractor agrees that he is as fully responsible to the City for the acts and omissions

of his subcontractors and of persons either directly or indirectly employed by them, as he

is for the acts and omissions of himself or persons directly employed by him. Nothing

contained in this Agreement shall create any contractual relation between any

subcontractor and the City. The Contractor shall not subcontract any part of the work

under this Contract or permit subcontracted work to be further subcontracted without the

prior written approval of the City.

11. Warranties

The Contractor upon completion of the project shall deliver to the City a written warranty

guaranteeing the work performed for a period of one (1) year from the date of acceptance

by the City of all work required under this contract.

12. Use of Utilities/Cooperation of City

The Contractor shall provide utilities such as lights, water and power, situated at the

project site necessary to the successful completion of the Project. The use of these

facilities, as well as the associated costs, will be the responsibility of the Contractor.

13. Final Payment/Release of Liens

The City shall make final payment to the Contractor within thirty (30) days of receipt of

an invoice for the work. The contractor shall not submit an invoice until after the work is

completed, and only after final inspection and acceptance of all the work to be performed,

and further subject to the condition that final payment shall not be due until the

Contractor has delivered to the City a complete release of all liens or claims for liens

arising out of the contract by the Contractor, subcontractors, laborers, and suppliers of

material.

14. Partial Disbursements

No partial disbursements will be made by the City to the Contractor under this

agreement.

15. Default by Contractor

In the event of default by the Contractor of any of the conditions contained herein, the

City shall have the right to discharge the Contractor from performance of further services,

without waiver of any penalty or other remedy provided by this Agreement or as

provided by law.

16. Non-Liability of the City

The Contractor agrees to hold the City harmless for any damages arising out of the

undertaking and execution of this Agreement.

Page 11: City of Gaffney CODE ENFORCEMENT DEMOLITION€¦ · The work under this contract will consist of the demolition of structures as described in the bid documents attached. Bid proposals

AFD-5

17. Entire Contract

This Agreement, including documents incorporated by reference herein, represents the

entire contract between the parties hereto, and no prior, simultaneous, or subsequent

Agreements shall be binding unless executed in writing by the parties hereto.

WITNESS OUR HANDS AND SEALS ON THE DATES SET FORTH BELOW.

Contractor:__________________________

Dated:

BY: ____________________ _

Its:

ATTEST: Printed Name: ______

CITY OF GAFFNEY (SEAL)

Dated:

BY:

Its: City Administrator

ATTEST: Printed Name: James R. Taylor ______

Page 12: City of Gaffney CODE ENFORCEMENT DEMOLITION€¦ · The work under this contract will consist of the demolition of structures as described in the bid documents attached. Bid proposals

GC - 1

GENERAL CONDITIONS

1. DEFAULT: In case of default by the Contractor, the City reserves the right to

purchase any or all items in default in the open market, charging the Contractor

with any excessive costs. Should such charge be assessed, no subsequent bids of

the defaulting Contractor will be considered until the assessed charge has been

satisfied.

2. NON-APPROPRIATION: Any contract entered into by the City resulting from

this bid invitation shall be subject to cancellation without damages or further

obligation when funds are not appropriated or otherwise made available to

support continuation of performance in a subsequent fiscal period or appropriated

year.

3. INDEMNIFICATIONS: The Contractor agrees to indemnify any save harmless

the City of Gaffney and all City officers, agents and employees from claims,

suits, actions, damages and costs of every name and description, arising out of or

resulting form the use of any materials furnished by the Contractor, provided that

such liability is not attributable to negligence on the part of the City or failure of

the City to use the materials in the manner outlined by the Contractor in

descriptive literature or specifications submitted with the Contractor’s bid.

4. CONTRACT ADMINISTRATION: Questions or problems arising after award

of this contract shall be directed to the City Administrator. Copies of all

correspondence concerning this contract shall be sent to the City of Gaffney, 201

North Limestone Street, Gaffney, SC 29340. All change orders must be

authorized in writing by the City Administrator. The City of Gaffney shall not be

bound to any change in the original contract unless approved in writing by the

City Administrator.

5. FORCE MAJEURE: The Contractor shall not be liable for any excess costs if

the failure to perform the contract arises out of causes beyond the control and

without fault or negligence of the Contractor. Such causes may include, but not

restricted to, acts of God or of the public enemy, acts of the Government in either

its sovereign or contractual capacity, fires, epidemics, quarantine restrictions,

strikes, freight embargoes, and unusually severe weather; but in every case the

failure to perform must be beyond the control and without the fault or negligence

of the Contractor. The Contractor shall not be liable for any excess costs if the

failure to perform is caused by default of a subcontractor if such default arises

out of causes beyond the control of both the Contractor and subcontractor, unless

the supplies or services to be furnished by the subcontractor were obtainable

from other sources in sufficient time to permit the contract to meet the required

delivery schedule.

6. PUBLICITY RELEASES: Contractor agrees not to refer to award of this

contract in commercial advertising in such a manner as to state or imply that the

Page 13: City of Gaffney CODE ENFORCEMENT DEMOLITION€¦ · The work under this contract will consist of the demolition of structures as described in the bid documents attached. Bid proposals

GC - 2

products or services provided are endorsed or preferred by the City. The

Contactor shall not have the right to include the City’s name in its published list

of customers without prior approval of the City. With regard to news releases,

only the name of the City, type and duration of contract may be used and then

only with prior approval of the City. The Contractor also agrees not to publish,

or cite in any form, any comments or quotes from the City staff.

7. QUALITY OF PRODUCT: Unless otherwise indicated in this bid it is

understood and agreed that any items offered or shipped on this bid shall be new

and in first class condition unless otherwise indicated herein.

8. S.C. LAW CLAUSE: Upon award of a contract under this bid, the person,

partnership, association or corporation to whom the award is made must comply

with the laws of South Carolina which require such person or entity to be

authorized and/or licensed to do business with this State. Notwithstanding the

fact that applicable statutes may exempt or exclude the successful bidder from

requirements that it be authorized and/or licensed to business in this State, by

submission of this signed bid, the bidder agrees to subject himself to the

jurisdiction and process of the courts of the State of South Carolina as to all

matters and disputes arising or to arise under the control and the performance

thereof, including any questions as to the liability for taxes, licenses, or fees

levied by the State.

9. ASSIGNMENT: No contract or its provisions may be assigned, sublet, or

transferred without the written consent of the City of Gaffney.

10. AFFIRMATIVE ACTION: The successful bidder will take affirmative action in

complying with all Federal and State requirements concerning fair employment

and treatment of all employees, without regard or discrimination by reason of

race, color, religion, sex, national origin or physical handicap.

11. BIDDING CONDITION OF PRICE: All bid prices submitted shall remain

effective for a minimum period of 90 days, unless otherwise stated. The City

reserves the right to make additional purchases at the submitted bid prices, during

the specified period.

12. S.C. SALES TAX: A sales tax will be added to all orders; however lump sum

bids shall include sales tax in bid price unless otherwise noted. By submission of

a signed bid, you are certifying, under penalties of perjury, that you comply

with section 12-54-1020(B) of the SC Code of Laws 1976, as amended, relating

to payment of any applicable taxes. This will certify to the City your

compliance.

13. BID REQUIREMENTS: Bid requirements on the materials and equipment

specified are not intended to be restrictive to potential bidders, but indicate the

Page 14: City of Gaffney CODE ENFORCEMENT DEMOLITION€¦ · The work under this contract will consist of the demolition of structures as described in the bid documents attached. Bid proposals

GC - 3

required features for satisfactory performance. The City of Gaffney will

determine if minor deviations from these features are acceptable.

14. DEVIATIONS FROM SPECIFICATIONS: Any deviation from specifications

indicated herein must be clearly pointed out; otherwise, it will be considered that

items offered are in strict compliance with these specifications, and successful

bidder will be held responsible therefore. Deviations must be explained in detail

on separate attached sheet(s). The listing of deviations, if any, is required but

will not be construed as waiving any requirements of the specifications.

Deviations found in the evaluation of the bid and not listed may be cause for

rejection. Bidders offering substitute or equal items must provide information

sufficient enough to determine acceptability of item offered.

15. CONTRACT: This bid and submitted documents, when properly accepted by the

City of Gaffney, along with a written purchase order and signed contract form,

shall constitute a contract equally binding between the successful offeror and the

City of Gaffney. No different or additional terms will become a part of this

contract, with the exception of a Change Order.

16. CHANGE ORDERS: No oral statement of any person shall modify or otherwise

change, or affect the terms, conditions or specifications stated in the resulting

contract. All change orders to the contract will be made in writing by the City of

Gaffney.

17. AMENDMENTS: All amendments to and interpretations of this solicitation

shall be in writing and issued by the City of Gaffney. The City of Gaffney shall

not be legally bound by any amendment or interpretation that is not in writing.

18. BID EVALUATION: Bids received will be evaluated by the City Administrator

or his designee. Factors to be considered during the evaluation process include,

but are not limited to, cost, qualifications, reputation and dependability of the

Contractor.

19. ARBITRATION: Under no circumstances and with no exception will the City of

Gaffney act as arbitrator between the Contractor and any subcontractor.

20. SHIPPING: All deliveries shall be shipped F.O.B. point Destination-freight

prepaid, the seller pays and bears all freight charges; collect shipments will not

be accepted. It is agreed by the parties hereto that delivery by the Contractor to

the common carrier does not constitute delivery to the City. Any claim for loss

or damage shall be between the Contractor and the carrier.

21. “OR APPROVED EQUAL”: Certain processes, types of equipment or kinds of

material are described in the specifications and/or on the drawings by means of

trade/brand names and catalog numbers. In each instance where this occurs, it is

understood and inferred that such description is followed by the words “or

Page 15: City of Gaffney CODE ENFORCEMENT DEMOLITION€¦ · The work under this contract will consist of the demolition of structures as described in the bid documents attached. Bid proposals

GC - 4

approved equal”. Such method of description is intended merely as a means of

establishing a standard of comparability. However, the Owner reserves the right

to select the items which, in the judgment of the Owner, are best suited to the

needs of the Owner based on price, quality, service, availability and other relative

factors. Bidders must indicate brand name, model, model number, size, type,

weight, color, etc., of the item bid, if not exactly the same as the item specified.

Vendor’s stock number or catalog number is not sufficient to meet this

requirement. If any bidder desires to furnish an item different from the

specifications, vendor shall submit along with the bid, the information, data,

pictures, designs, cuts, etc., of the material they plan to furnish so as to enable the

Owner to compare the material specified; and, such material shall be given due

consideration. The Owner reserves the right to insist upon, and receive items as

specified if the submitted items do not meet the Owner’s standards for

acceptance.

22. ALTERNATE BIDS: Bidders wishing to submit an alternate for consideration

that does not meet the City’s specifications (or approved deviations), must submit

their proposal as an alternate bid.

Page 16: City of Gaffney CODE ENFORCEMENT DEMOLITION€¦ · The work under this contract will consist of the demolition of structures as described in the bid documents attached. Bid proposals

EXA - 1

EXHIBIT A – SPECIFICATIONS

1. Unless otherwise required, submit only one copy of the bid.

2. Bids, amendments thereto or withdrawal requests received after the time advertised for

bid opening will be void regardless of when they are mailed.

3. Address and mark bids as indicated in the notice.

4. The City reserves the right to reject any and all bids and to waive all technicalities.

5. All services, materials, and products offered must be guaranteed to meet the

requirements of the specifications indicated, given, and referred to.

6. Prices bid must be based upon payment in thirty (30) days. Discounts for payment in

less than thirty (30) days will not be considered in making award.

7. Unless otherwise indicated, prices must be firm for ninety (90) days.

8. The right is reserved in case tie bids are received to make award as considered to be

most advantageous to the City.

9. Successful bidder/contractor and any subcontractor must have a City of Gaffney

business license prior to any site activities.

10. Successful bidder/contractor must obtain a demolition permit and business license

from the City and comply with all other state and local requirements.

11. All demolition must meet SC DHEC regulations and requirements.

12. The entire demolition project shall be complete within sixty (60) days of the execution

of an Agreement and the issuance of the Notice of Award.

13. The Contractor shall not close or obstruct roadways, sidewalks, drainage, hydrants, or

flow of potable water or sanitary sewer systems except as specifically allowed by the

specifications. Prior to initiating any closure of obstruction allowed by the

specifications, the Contractor shall notify the City and comply with their requirements.

Where pedestrian and /or driver safety is endangered in the area of demolition work or

removal work, use traffic barricades with flashing lights. Contractor shall be

responsible for protecting all right-of-way infrastructures (streets, sidewalks, curbing,

etc.) from damage, and shall be responsible for replacement of same, if damaged, at no

cost to the City.

14. It is the Contractor’s responsibility to contact all utility providers, for each structure

separately, to confirm that all services have been disconnected prior to executing any

work. Under no circumstances shall demolition of or interruption of service by an

Page 17: City of Gaffney CODE ENFORCEMENT DEMOLITION€¦ · The work under this contract will consist of the demolition of structures as described in the bid documents attached. Bid proposals

EXA - 2

existing utility occur prior to the authorized removal of that utility from service.

Should an unauthorized or accidental interruption of service occur before intended or

approved, the Contractor shall provide repairs to restore service as necessary in an

expedient manner per utility service provider.

15. Contractor shall remove all structures, foundations, footings, concrete slabs, utilities,

tree roots and stumps (except protected trees), debris, undergrowth, etc. to the

satisfaction of the City, and backfill as necessary to provide positive drainage on the

site. Contractor shall also provide erosion control measures as required to prevent

sediments from impacting adjacent property.

16. All disturbed ground shall be fine graded, seeded and strawed. The work shall not be

considered complete until the site is stabilized and grass is growing on at least 75% of

disturbed area.

17. Trees designated by the City to be protected shall not be removed or damaged.

Contractor must coordinate this designation with the City prior to any site activities.

18. Receipts and landfill disposal tickets must be presented to the City upon request.

19. Conduct demolition to minimize interference with adjacent structures. Cease

operations immediately if adjacent structures appear to be in danger. Notify the City.

Do not resume operations until directed by the City. Conduct operations with

minimum interference to public or private accesses. Maintain protected egress and

access at all times.

20. Prevent the spread of dust and debris and avoid the creation of a nuisance or hazard in

the surrounding area. Sprinkle work with water to minimize dust. Provide hoses and

water connections for this purpose. Do not use water if it results in hazardous or

objectionable conditions such as but not limited to, ice, flooding, or pollution.

21. Except where otherwise noted, all materials removed and not reused shall become the

property of the Contractor and shall be removed from the project site. Title to the

materials resulting from demolition, and materials to be removed, is vested in the

Contractor upon issue of a Notice to Proceed by City. City shall not be responsible for

the condition, loss of, or damage to such property after Notice to Proceed. Materials

shall not be sold or viewed by prospective purchasers on the site.

22. Work should be scheduled between the hours of 7:00 a.m. and 5:00 p.m. Monday

through Friday. The Contractor and City must agree on other times.

23. The successful bidder shall indemnify and save harmless the City of Gaffney and all

city officials, agents, and employees, from all suits or claims of any character brought

by reason of infringing on any patent trade mark, or copyright.

Page 18: City of Gaffney CODE ENFORCEMENT DEMOLITION€¦ · The work under this contract will consist of the demolition of structures as described in the bid documents attached. Bid proposals

EXA - 3

24. Contractor shall not commence work under this contact until he has obtained all

insurance required hereunder and such insurance has been approved by the City of

Gaffney, nor shall the Contractor allow any subcontractor to commence work on his

subcontract until all similar insurance required of the subcontractor has been obtained

and approved. Approval of the insurance by the City of Gaffney shall not relive or

decrease the liability of the Contractor hereunder.

Compensation and Employer’s Liability Insurance: The Contractor shall take out and

maintain, during the life of the contract, the workmen’s Compensation and Employer’s

Liability Insurance for all of his employees to be engaged in work on the project under

this contract, and in case any such work is sublet, the contractor shall require the

subcontractor similarly to provide Workmen’s Compensation and Employer’s

Liability Insurance for all of the latter’s employees to be engaged in such work.

Bodily Injury and Property Damage Liability Insurance: The Contractor shall take out

and maintain, during the life of this contract, such Bodily Injury Liability and Property

Damage Liability Insurance, and Automobile Bodily Injury Liability and Property

Liability Insurance, as shall protect him and any subcontractor performing work

covered by this contract from claims for damages for personal injury, including

accidental death, as well as from claims from property damage, which may arise from

operations under this contract, whether such operations be by himself or by any

subcontractors or by anyone directly or indirectly employed by either of them, and the

amounts of such insurance shall be no less than:

Bodily Injury Liability Insurance in an amount not less than two million

dollars ($2,000,000.00) per occurrence and one million dollars ($1,000,000.00)

for each person for injuries, including wrongful death on any one person.

Property Damage Insurance in an amount not less than one million dollars

($1,000,000.00) per occurrence and two million dollars ($2,000,000.00) each

aggregate.

The City, its officers and employees shall be named as an “additional insured”

in the automobile and General Liability policies, and it shall be stated on the

Insurance Certificate with the provision that this coverage “is primary to all

other coverage the City may possess.”

Page 19: City of Gaffney CODE ENFORCEMENT DEMOLITION€¦ · The work under this contract will consist of the demolition of structures as described in the bid documents attached. Bid proposals

0 0.50.25Mi

±Coordinate System: NAD 1983 StatePlane South Carolina FIPS 3900 Feet

Demolition Location Overview

CherokeeCounty

£¤29

£¤29

§̈¦85

Overbrook Dr

Overbrook Dr

EO'NealStEO'NealSt

WO'NealSt

WO'NealSt

W Buford St

W Buford St

CollegeDr

CollegeDr

ERutledgeAve

ERutledgeAve

S Johnson St

S Johnson St

E Buford St

E Buford St

Holland St

Holland StThom

pson St

Thom

pson St

UnionSt

UnionSt

EastJrH

ighSch

oolRd

EastJrH

ighSch

oolRd

W

RutledgeAve

W

RutledgeAve

Beltline

Rd

Beltline

Rd

Leadmine St

Leadmine St

Hetty

HillS

t

Hetty

HillS

t

Leadm

ineRd

Leadm

ineRd

EFrederickSt

EFrederickSt

CorrySt

CorrySt

NLimestone

St

NLimestone

St

WilkinsvilleHwy

WilkinsvilleHwy

ProvidenceRd

ProvidenceRd

BoilingSpringsHwy

BoilingSpringsHwy

WFloyd

BakerB

lvd

WFloyd

BakerB

lvd

ChesneeHwy

ChesneeHwy

S Logan St

S Logan St

N Logan St

N Logan St

WFrederickSt

WFrederickSt

Pacolet

Hwy

Pacolet

Hwy

E Floyd Baker Blvd

E Floyd Baker Blvd

S Limestone St

S Limestone St

Shelby

Hwy

Shelby

Hwy

Hyatt St

Hyatt St

UnionHwy

UnionHwy

EXIT 95EXIT 95

EXIT 92EXIT 92

CherokeeAv

eChero

keeAve

OldGeo

rgiaHwy

OldGeo

rgiaHwy

N Granard St

N Granard St

SGr

anardSt

SGr

anardSt

Demo Location 1

805 S. Limestone St.

Demo Location 2

202 Overbrook Dr.

Demo Location 3

102 Cedar St.

City of GaffneySite Parcel

Gaffney City Limits

Map prepared by City of Gaffney, Community Development, GIS | Updated: 5/15/2020

Tax parcel data provided courtesy of Cherokee County, SC

2020

Page 20: City of Gaffney CODE ENFORCEMENT DEMOLITION€¦ · The work under this contract will consist of the demolition of structures as described in the bid documents attached. Bid proposals

0 10050Feet

±Coordinate System: NAD 1983 StatePlane South Carolina FIPS 3900 Feet

Tax Map Number:082-14-00-063.000

Address:805 S. Limestone StreetGaffney, SC 29340

Demolition Location 1!(

!(

!(

!(

!(

!(

!(

!(

!(

!(

!( !(!(

!(

!(

!(

!(

!(

!(

!(

!(

!(

!(

!(

!(

!(

!(

!(

!(

UV150

UV150

UV105

W Nott St

W Nott St

S Petty St

S Petty St

S Petty St

S Petty St

Sleep Easy Aly

Sleep Easy Aly

Sleep Easy Aly

Sleep Easy Aly

Corry St

Corry St

Corry St

Corry St

Corry St

Corry St

ENottSt

ENottSt

E Nott St

E Nott St

ENottSt

ENottSt

S Limestone St

S Limestone St

S Limestone St

S Limestone St

Corry St

Corry St

1100

709

800

903

1005

102

905

714

801

803

805104

810

807

900

1000

809

1010

101902

904

901

715

803

717

804

801103

711

!( Address Points

Site Parcel

Parcels

Map prepared by City of Gaffney, Community Development, GIS | Updated: 5/15/2020

Tax parcel data and 2016 aerial imagery provided courtesy of Cherokee County, SC

City of Gaffney

Page 21: City of Gaffney CODE ENFORCEMENT DEMOLITION€¦ · The work under this contract will consist of the demolition of structures as described in the bid documents attached. Bid proposals

0 10050Feet

±Coordinate System: NAD 1983 StatePlane South Carolina FIPS 3900 Feet

Tax Map Number:081-14-00-009.000

Address:202 Overbrook DriveGaffney, SC 29341

Demolition Location 2

!(

!(

!(

!(

!(

!(

!(

!(

!(

!(

!(

!(

!(

!(!(

!(

!(

!(

!(

!(

!(

!(

!(

!(

!(

!(

!(

!(

!(

!(

!(

!(

!(

!(

!(

!(

!(

!(

!(

!(

!(

!(

W Sm

ith St

W Sm

ith St

W Sm

ith St

W Sm

ith St

W Sm

ith St

W Sm

ith St

WSm

ithSt

WSm

ithSt

Hampton Ave

Hampton Ave

Hampton Ave

Hampton Ave

Overbr

ook Dr

Overbr

ook Dr

Overbr

ook Dr

Overbr

ook Dr

204

202

205

207

209

823

821

210

212

1005UNITA

1005UNITB

1005UNITC

1005UNITD1005

UNITE

1007

1009

903

110UNITB

110UNITA

200

206

208UNITD

208UNITC

208UNITB

208UNITA

210

203

201

211

213

213

211

209817UNITB

817UNITA

901

905

110

110UNITC

110UNITE

1015

!( Address Points

Site Parcel

Parcels

Map prepared by City of Gaffney, Community Development, GIS | Updated: 5/15/2020

Tax parcel data and 2016 aerial imagery provided courtesy of Cherokee County, SC

City of Gaffney

Page 22: City of Gaffney CODE ENFORCEMENT DEMOLITION€¦ · The work under this contract will consist of the demolition of structures as described in the bid documents attached. Bid proposals

0 10050Feet

±Coordinate System: NAD 1983 StatePlane South Carolina FIPS 3900 Feet

Tax Map Number:099-07-00-113.001

Address:102 Cedar StreetGaffney, SC 29340

Demolition Location 3

!(

!(

!(

!(

!(

!( !(

!(

!(

!(

!(

!(

!(

!(

!(

!(

!(

!(!(

!(

!(

!(

!(

!(

!(

!(

!(

!(

!(

!(!(

!(

!(

!(

!(

!(

!(!(!(

!(

!(

!(

!(

!(

!(

!(

!(

!(

!(

!(

!(

!(

!(

!(

!(

!( !(

!( !(

!(Be

echSt

BeechSt

Walnut St

Walnut St

Beech St

Beech St

Oak St

Oak St

Filbert StFilbert St

BeechS

t

BeechS

t

Oak

StOak

St

Beech St

Beech St

CedarS

tCed

arSt

Cherry S

tChe

rry St

Walnut St

Walnut St

Filbert StFilbert St

Beech St

Beech St

Beech St

Beech St

Cedar St

Cedar St

Cedar St

Cedar St

Oak St

Oak St

Oak St

Oak St

Cherry

St

Cherry

St

Cherry S

tCher

ry St

Cherry S

tChe

rry St

CherrySt

CherryS

t

Oak

StOak

St

Oak St

Oak St

Cedar St

Cedar St

Cedar S

tCed

ar St

Birch St

Birch St

BirchSt

BirchS

t

Birch St

Birch St

204202

302

105

500

117 302

200

114

306

501103

305

306

500

502

503

118304

116

507

506

109

107

401

305

304

407102

408105

403

307 500

301

402

503400

308

3081/2

501

406

102

205

104

203

204

301

203

300

201

301

300

303

202

409 505

103 504

!( Address Points

Site Parcel

Parcels

Map prepared by City of Gaffney, Community Development, GIS | Updated: 5/15/2020

Tax parcel data and 2016 aerial imagery provided courtesy of Cherokee County, SC

City of Gaffney