Page 1: City of Glendale Community Development Fee Schedule€¦ · Plan Review of Phased Designs for New Construction and Additions (foundation only, shell building, etc.). Projects built

City of Glendale

Community Development

Fee Schedule

  Effective May 10, 2019  

City of Glendale User Page 2 4/24/2019

Page 2: City of Glendale Community Development Fee Schedule€¦ · Plan Review of Phased Designs for New Construction and Additions (foundation only, shell building, etc.). Projects built

3

4-5

6

Building Safety Permit Fees 7-9

9

14

14-16

16

17

18-20

21-23

24-25

26-33

34-35

Planning Fees

Transportation Services Fees

Fire Department Services Fees

Utility Services Fees

Building Safety Backflow/Misc./Inspection Fees

Building Safety Fee General Notes

Table of Contents

Building Safety Administrative Fees

Building Safety Table 3A (Building Permit Fees)

Building Safety Residential Fees

Building Safety Commercial Fees

Building Safety Sign/Fence Fees

Engineering Fees

Building Safety Table 3B (Building Valuation Chart)

City of Glendale User Page 3 4/24/2019

Page 3: City of Glendale Community Development Fee Schedule€¦ · Plan Review of Phased Designs for New Construction and Additions (foundation only, shell building, etc.). Projects built

BUILDING SAFETY

Miscellaneous fees are those fees that do not fall under the plan review or inspection areas. These fees

are generally based on an hourly rate but may be set on standard administrative costs for providing

service.

FEE GENERAL NOTES

Building Plan Review Fees

Building Permit Fees

Miscellaneous Fees

Building inspections are financed by building permit fees. Permit fees for new buildings, additions, and

pools are based on the valuation (total construction costs) of the buildings or structure. The

determination of the value or valuation will be made on the basis of the Building Valuation Data

published in the International Code Council Building Safety Journal and by other valuation criteria

approved by the Building Official. Other types of permits have fees based on the amount of time

estimated to inspect the project until completion.

Plan review fees pay for the evaluation of plans to determine compliance with adopted codes and

ordinances. These fees are based on a percentage of the calculated building permit fee with a minimum

charge for each application. Payment of the plan review fee is in addition to the building permit fee and

is non-refundable after plans are accepted and the review is started.

In addition to the basic level of inspection services offered, additional inspection services are available

through prior arrangement with the Building Safety Department and with payment of the appropriate

fee. These services include after-hours, weekend or holiday inspections, re-inspections, optional (not

required) inspections and requests for time-specific inspections.

City of Glendale User Page 4 4/24/2019

Page 4: City of Glendale Community Development Fee Schedule€¦ · Plan Review of Phased Designs for New Construction and Additions (foundation only, shell building, etc.). Projects built

Permit Faxing (charged once, faxed in or out) $12.66

$38.01

$3.78 per page

$122.88 plus printing costs

Record Retention Fee (commercial, residential, T.I. plans) 1% of permit ($10 min.)

20% of permit ($50 min.)

50% of original permit

100% of new permit fees

Work prior to issuance of permit. 200% of new permit fees

$122.88 per hr. (2 hr. min.)

$122.88 per hr. (2 hr. min.)

$122.88 per hr. (3 hr. min.)

$126.62 (for 3 years)

$316.86

$443.60

$122.88 per hr. (1 hr. min.)

Permit Record Change (incl. address change)

Plan Reproduction Fee

Refund of Permit Fee (no inspections made)

Single Family Residential

Request for modifications or alternate materials and methods per Section 104 of the City of Glendale Ordinance

must first be made to the Assistant Director, who will conduct the initial review.

Initial Review/Structural

Initial Review/Non-Structural

Expired Permits:

Plan Reproduction Fee (8.5 x 11 and 11 x 17)

Renewal of Approval

Renewals prior to expiration

Renewals after expiration

Permits expire by limitation and become null and void if the work authorized by the permit has not commenced

within 180 days from the date of the permit, or any permit shall expire 180 days after the last approved

inspection. (See section 105.5 of the 2018 International Building Code and City of Glendale Ordinance).

Lot Combination, Building Code Covenant and Use Agreement,

Non-Build Easement Requests

General Services:

BUILDING SAFETY

Board of Appeals

Non-Single Family

ADMINISTRATIVE FEES

Requests for Code Modifications or Formal Interpretations from

Building Official

Appeals/Modifications/Formal Interpretations:

City of Glendale User Page 5 4/24/2019

Page 5: City of Glendale Community Development Fee Schedule€¦ · Plan Review of Phased Designs for New Construction and Additions (foundation only, shell building, etc.). Projects built

$122.88 per hr. (1 hr. min.)

$122.88 per hr. (1 hr. min.)

$760.50

100% of plan review fee per

building75% of permit based on valuation

of submittal

75% of permit based on valuation

of submittal times three (3)

$122.88 per hr. (1 hr. min.)

$122.88 per hr. (2 hr. min.)

$122.88 per hr. (1 hr. min.)

$122.88 per hr. (2 hr. min.)

Included in original permit fee

$531.22 for a max. of 30 days

$1,062.46 for an additional 30 days

$2,124.94 for an additional 30 days

Initial Plan Review Application

Investigation

Administration

Appeal to Hearing Officer

Plan Review of Phased Designs for New Construction and Additions (foundation only, shell building, etc.).

Projects built with phased or partial permits require significantly more coordination time for the plan review and

inspection process than do projects built under a single permit.

It is expected that no project shall exceed 90 days operation under a Temporary Certificate of Occupancy.

 Should a third or subsequent extension occur, the fee will double that of the previous extension.  For example,

the third extension would be $4,249.82, the fourth extension would be $8,499.64, etc.  

Second 30 day extension of TCO

Building Safety Pre-Plan Submittal Meeting

First Temporary Certificate of Occupancy (TCO)

Certificate of Occupancy

Damaged Buildings:

Phased Submittals:

Revisions - (Plan review of changes made to approved plans

either before or after permit is issued. Revisions that expand

the scope of a permit require a new permit and fees.)

P.A.S.S. (Permits and Safety Sequence)

Staff Consultation and Research

Deferred Submittals

Subsequent Plan Review Submittals (for each phase)

First 30 day extension of TCO

Certificate of Occupancy:

Optional Plan Review Services:

City of Glendale User Page 6 4/24/2019

Page 6: City of Glendale Community Development Fee Schedule€¦ · Plan Review of Phased Designs for New Construction and Additions (foundation only, shell building, etc.). Projects built

Change of Occupancy or Use: (Requires both of the following)

$122.88 per hr. (2 hr. min.)

$114.35 per hr. (2 hr. min.)

Copy of Certificate of Occupancy $76.60 per copy

$114.35

75% of permit fee (min. $122.88)

75% of permit fee (min. $122.88) +

$61.44 per EA additional

elevation or change to

building footprint

75% of the electrical permit fee

(min. $122.88)

75% of the plumbing permit fee

(min. $122.88)

75% of the mechanical permit fee

(min. $122.88)

$61.44 per permit

$122.88 per hr. (1 hr. min.)

$61.44 per plan

$122.88 per hr. (1 hr. min.) Revisions

that expand the scope of a

permit require new permit and

fees.

$122.88 per hr. (2 hr. min.)

75% of the building permit fee

(min. $122.88)

75%  of the electric permit fee

(min. $122.88)

75% of the plumbing permit fee

(min. $122.88)

Plumbing Plan Review

Electrical Plan Review

Plan review fees are due when the permit application is submitted. For combination permits, plan review fees

for electrical, mechanical, and plumbing reviews will be collected at the time of permitting.

Certificate of Occupancy: Tenant Space - no work

Plan Review

Inspection

Annual Renewal of Standard Plans

Base Plan plus variations

Electrical Plan Review

Custom Home, Remodel, Room Addition Plans:

RESIDENTIAL FEES

Standard Plans:

Base Plan Only-Building

Plumbing Plan Review

Mechanical Plan Review

Third or Subsequent Review of Plans

Site Plan Review

Building Plan Review

Plan Review Fees:

Revisions - Plan review of changes made to approved plans

before or after permit issued

Truss Calculation Review - Truss package submitted separately

from building permit plans or revisions to the truss package are

required after permit is issued.

City of Glendale User Page 7 4/24/2019

Page 7: City of Glendale Community Development Fee Schedule€¦ · Plan Review of Phased Designs for New Construction and Additions (foundation only, shell building, etc.). Projects built

75% of the mechanical permit fee

(min. $122.88)

$122.88 per hr. (1 hr. min.)

$122.88 per hr. (1 hr. min.) Revisions

that expand the scope of a

permit require new permit and

fees.$122.88 per hr. (2 hr. min.)

Based on value, see Table 3A

Per structure $59.01 per structure

$29.79

$38.64

$78.75

$114.35 per request

$152.10

$38.64

$6.00 EA

$0.06 SF

Base Permit Fee

Electrical Clearance - (Inspection not included w/Electrical

permits) When required by utility company to energize

service

Permit fees are based on the valuation of the project, or portion of the project represented by each separate

permit. Valuation of the work shall be the estimated cost as determined by the Building Official based on

nationally recognized standards and shall include the value of materials, labor, overhead, and profit. See Table

3B (which is the valuation chart) to determine the value of the project. Fees for all permits will be collected at

the time of permitting.

Per building

Building Permit:

Mechanical Plan Review

Revisions - (Plan review of changes made to approved plans

before or after permit issued.)

Electric Permit:

Third or Subsequent Review of Plans

Electrical Service - 200A or less

Demolition Permit:

Sub panels

Appliances - 1 HP or less- dishwasher, cook tops, ranges, wall

a/c, washing machines, garbage disposals, water heaters,

clothes dryers, space heaters, trash compacters

Livable Floor Area

Truss Calculation Review - Truss package submitted separately

from building permit plans or revisions to the truss package are

required after permit is issued.

Permit Fees:

Temporary Power Meter Installation

Electrical Service - over 200A

City of Glendale User Page 8 4/24/2019

Page 8: City of Glendale Community Development Fee Schedule€¦ · Plan Review of Phased Designs for New Construction and Additions (foundation only, shell building, etc.). Projects built

$1.36 EA

$0.89 EA

$1.36 EA

$0.89 EA

$23.04 EA

$29.79

$13.48

$13.48

$18.76

$23.04

$9.19 EA

$9.19 EA

$13.48

$13.48

$32.24

$13.48 EA

$17.35

$122.88 ($61.44 for 1/2 hr.)

$57.00 per permit

$152.01 per unit

$114.35 per unit

$29.79

$11.78 EA

$31.23

$6.00 100 LF (100 FT min.)

$6.00 100 LF (100 FT min.)

$15.58

Gas Piping:

Plumbing Permit:

Evaporative Coolers

Appliance Vents

100K BTU or less

Furnaces:

Piggy-backed HVAC (w/evap)

Miscellaneous equipment/appliances

Exhaust Hoods

Site Plan Review

Vent Fans

Water Piping

Sewer

Fixtures

Base Permit Fee

Installation

Plan Review

over 100K BTU

Repairs/additions to existing equipment

Electrical Upgrade/New Service

Base Permit Fee

Lighting Fixtures:

Additional fixtures

First 20 fixtures

Mechanical Permit:

Receptacles/Switches/Outlets:First 20 fixtures

Air Handlers

Miscellaneous

Additional fixtures

Water Heater

Drainage Piping

Mobile Home Plan Review and Permit Fees:

All-in-one HVAC

City of Glendale User Page 9 4/24/2019

Page 9: City of Glendale Community Development Fee Schedule€¦ · Plan Review of Phased Designs for New Construction and Additions (foundation only, shell building, etc.). Projects built

$7.78

$1.36 EA

$114.35 per request

$18.76 EA

$12.41 EA

75% of the building permit fee

(min. $122.88)

75% of the electrical permit fee

(min. $122.88)

75% of the plumbing permit fee

(min. $122.88)

75% of the mechanical permit fee

(min. $122.88)

$57.00 per permit

$122.88 per hr. (1 hr. min.)

$122.88 per hr. (1 hr. min.) Revisions

that expand the scope of a

permit require new permit and

fees.$122.88 per hr. (2 hr. min.)

$122.88 per hr. (1 hr. min.) Revisions

that expand the scope of a

permit require new permit and

fees.

Third or Subsequent Review of Plans

Site Plan Review - For previously approved standards -carports,

retaining walls, and bus shelters

Truss Calculation Review - When truss package is submitted

separate from building permit plans or revisions to truss

package are required after permit is issued

Electrical Plan Review

Plumbing Plan Review

Mechanical Plan Review

Plan Review Services Not Otherwise Listed - Plan review of

changes made to approved plans before or after permit issued

Revisions - Plan review of changes made to approved plans

before or after permit issued

Plan Review Fees:

COMMERCIAL FEES

Miscellaneous equipment/appliances

each additional outlet

5 outlets or less

Lawn Sprinkler System-(includes backflow device)

Gas Clearance - (Inspection not included with

Mechanical/Plumbing permits) When required by utility

company to establish service

Building Plan Review

Plan review fees are due when the permit application is submitted. For combination permits, plan review fees

for electrical, mechanical, and plumbing reviews will be collected at the time of permitting.

City of Glendale User Page 10 4/24/2019

Page 10: City of Glendale Community Development Fee Schedule€¦ · Plan Review of Phased Designs for New Construction and Additions (foundation only, shell building, etc.). Projects built

$114.35

$126.73 per structure

Based on value, see Table 3A

$152.10

$29.79

$15.58

$59.01

$38.64

$78.75

$114.35 per hr. (3 hr. min.)

$114.35 per request

$114.35 per request

$6.00 EA

$15.58 EA

$1.36 EA

$0.89 EA

Gas Clearance - (At a single site address) When required by

utility company to establish service

Demolition Permit

Appliances:

Permit fees are based on the valuation of the project, or portion of the project represented by each separate

permit. Valuation of the work shall be the estimated cost as determined by the Building Official based on

nationally recognized standards and shall include the value of materials, labor, overhead, and profit. See Table

3B (which is the valuation chart) to determine the value of the project. Fees for all permits will be collected at

the time of permitting.

200A or less

Building Permit

More than 1 HP

First 20 fixtures

Additional fixtures

Distribution System - In addition to pole or pedestal fee

construction sites, decorative lights, Christmas tree lots,

pumpkin patches, etc.

201A-999A

over 1000A

Electrical Permit:

Permit Fees:

Minimum Commercial Permit Fee

Less than 1 HP

Temporary Power:

Meter Installation

Power Pole or Pedestal

Base Permit Fee

Electrical Service:

Electrical Clearance - (At a single site address) When required

by utility company to energize service

Receptacles/Switches/Outlets:

City of Glendale User Page 11 4/24/2019

Page 11: City of Glendale Community Development Fee Schedule€¦ · Plan Review of Phased Designs for New Construction and Additions (foundation only, shell building, etc.). Projects built

$1.37 EA

$0.89 EA

$1.36 EA

$1.36 EA

$6.00 EA

$15.58 EA

$31.17 EA

$62.74 EA

$94.41 EA

$9.19 EA 100 LF

$29.50 EA

$0.058 SF

$59.01

$18.76 EA

$23.04 EA

$18.76 EA

$18.76 EA

$32.24 EA

$32.24 EA

$18.76 EA

$23.04 EA

$17.35 EA

$13.48 EA

$22.60 EA

$13.48 EA

Air Handlers:

1 HP or less

more than 10 HP less than 50 HP

Suspended, Recessed, Floor Mounted

Base Permit Fee

Piggy-back HVAC (w/evap)

over 100K BTU

Repairs/additions to existing equip.

Less than 10,000 CFM

More than 10,000 CFM

Evaporative Coolers

over 100K BTU

Mechanical Permit:

Theatrical-type

Pole or platform mounted

more than 100 HP

more than 50 HP less than 100 HP

Floor Furnace

100K BTU or less

Livable Floor Area

First 20 fixtures

Additional fixtures

Power Apparatus:

Furnaces and All-in-One HVAC (Package Units):

more than 1 HP less than 10 HP

Miscellaneous

Bus ways, each 100 LF

Multi-Family Residential Only:

Ventilation and Exhaust:

Heat Pump - Split System

100K BTU or less

Lighting Fixtures:

City of Glendale User Page 12 4/24/2019

Page 12: City of Glendale Community Development Fee Schedule€¦ · Plan Review of Phased Designs for New Construction and Additions (foundation only, shell building, etc.). Projects built

$9.19 EA

$13.48 EA

$177.06 EA

$13.48 EA

$13.48 EA

$9.19 EA

$13.48 EA

$13.48 EA

$18.38 EA

$18.38 EA

$34.38 EA

$47.21 EA

$70.26 EA

$117.42 EA

$13.48

$6.00 per 100 LF (100 FT min.)

$59.01

$12.41 EA

$31.23

$0.74 per LF ($40.62min.)

$76.04 plus $0.30/LF

$361.24 plus $0.10/LF

$25.21 EA

$12.41 EA

$6.00 per 100 LF (100 FT min.)

$6.00 per 100 LF (100 FT min.)

$15.37 EA

$7.78

$1.36 EAover 5 outlets

Compensation Air Circulation System

> 15 HP and ≤ 30 HP or > 500K and < 1,000,000 BTU/h

1-100 FT

Water Piping

Drainage Piping

Water Heater

Gas Piping:

101-1,000 FT

>30 HP and ≤ 50 HP or ≤ 1,000,000 BTU/h and <1,750,000

BTU/h

Boilers/Compressors/Absorption Systems:

Incinerators, Commercial and Industrial

≤ 3 HP or 100K BTU/h

Appliance Vents

Type I

Type II

Refrigeration Evaporators

Vent/Exhaust Fan

Product Conveying Exhaust System

Refrigeration Condensors

Private Sewer Collector:

5 outlets or less

Fixtures

Base Permit Fee

Miscellaneous equipment/appliances

Sewer

Chilled/Hot Water Piping (Hydronic)

over 1,000 FT

Exhaust Hoods:

>50 HP or ≤ 1,750,000 BTU/h

Plumbing Permit:

Waste Pretreatment Interceptor

Roof Drains (inside bldg)

> 3 HP but ≤ 15 HP or > 100K and < 500K

City of Glendale User Page 13 4/24/2019

Page 13: City of Glendale Community Development Fee Schedule€¦ · Plan Review of Phased Designs for New Construction and Additions (foundation only, shell building, etc.). Projects built

$18.76 EA

$15.58

$82.37 per device

$12.41 EA

$57.00 per permit

$57.00 per permit

75% of total permit

$62.74

$115.65

$77.00

$77.00

$38.33

Building Permit:

Spas/Hot Tubs

Site Plan Review

Secondary Barrier

Public Pool

Private Spa

Plan Review

Above Ground

Atmospheric Type Vacuum Breaker

Based on value, see Table 3A

Backflow Devices not Atmospheric:

Based on value, see Table 3A

Based on value, see Table 3A

In Ground

Electrical Permit

Plumbing Permit:

Public Spa

Miscellaneous equipment/appliances

Lawn Sprinkler System - (includes backflow device)

Swimming Pools and Spa Permits:

Private Pool

City of Glendale User Page 14 4/24/2019

Page 14: City of Glendale Community Development Fee Schedule€¦ · Plan Review of Phased Designs for New Construction and Additions (foundation only, shell building, etc.). Projects built

75% of building permit fee (1/2 hr.

min. @ $61.44)

Building Permit:

$76.04 per sign

$76.04 per sign

$31.67 per occasion (10 days)

$31.67 per sign

$76.04 per sign

$114.35 per sign

$76.04 per sign

Based on value, see Table 3A

$114.35 add per sign

$50.00 per pole

$76.04 per sign

$122.88 ($61.44 min. for 1/2 hr.)

$0.12 per SF

$0.12 per SF

$0.19 per SF

$82.37 per site

$82.37 per device

$72.42 per hydrant

75% of permit

$253.49

$29.79 EA

$9.19 EA

Backflow Prevention:

Annual Processing Fee

Permanent Commercial Sign:

With Electric

No Electric

Electric Permit

Perimeter residential subdivision walls

Construction/Development Sign

Flag Poles

Subdivision Advertising/Directional Sign

Billboards:

Electrical Permit (includes generator)

Plan Review

Sign Plan Review

Permit Fee

Carnivals and Circus Events:

Hydrant Backflow Permit

Miscellaneous Permits:

Rides, Displays

Fence walls over 6 FT in height

Retaining walls of any height

Building Permit

Fence/Wall Permits:

Sign Permits:

EMB Fee

With Electric

Face Change Only

Promo. Pennants, Balloons, Banners, Displays

Structural Plan Review

Building Permit:

City of Glendale User Page 15 4/24/2019

Page 15: City of Glendale Community Development Fee Schedule€¦ · Plan Review of Phased Designs for New Construction and Additions (foundation only, shell building, etc.). Projects built

$9.19 EA

75% of permit

$190.13

$29.79 EA

$9.19 EA

$9.19 EA

$126.73

$190.13 ($95.06 EA additional)

$316.86

Inspections Outside of Normal Business Hours:$141.65 per hr. (2 hr. min.)

$141.65 per hr. (3 hr. min.)

$114.35

$114.35 EA inspection (2 hr. min.)

$114.35 per hr. (1 hr. min.)

$114.35

Haunted Houses/Amusements:

Re-Inspections

Shopping Mall Events

Weekdays

Plan Review

System Lighting/Booths

Saturdays, Sundays, Holidays

Electrical Permit (includes generator)

Investigations

Spray Booths

Building Permit

Special Events

Inspections of Buildings to be Relocated

Inspections:

Inspections

Rides, Displays

System Lighting/Booths

City of Glendale User Page 16 4/24/2019

Page 16: City of Glendale Community Development Fee Schedule€¦ · Plan Review of Phased Designs for New Construction and Additions (foundation only, shell building, etc.). Projects built

$1,000,001.00 and up

Valuation chart on the following page has been updated in accordance with

Buiding Standards Magazine or as published. Current publication utilized is

August 2018-

TABLE 3A BUILDING PERMIT FEES

$500,001.00 to $1,000,000.00

$50,001.00 to $100,000.00

$7090.16 for the first $1,000,000.00 plus $4.62 for each

additional $1,000.00 or fraction thereof.

$494.66 for the first $25,000.00 plus $12.78 for each additional

$1,000.00, or fraction thereof, to and including $50,000.00.

$814.16 for the first $50,000.00 plus $8.86 for each additional

$1,000.00 or fraction thereof, to and including $100,000.00.

$86.64 for the first $2,000.00 plus $17.74 for each additional

$1,000.00, or fraction thereof, to and including $25,000.00.

$4085.16 for the first $500,000.00 plus $6.01 for each

additional $1,000.00 or fraction thereof, to and including

$1,000,000.00.

$1257.16 for the first $100,000.00 plus $7.07 for each

additional $1,000.00 or fraction thereof, to and including

$500,000.00.

$29.79

Total Valuation

29.79 for the first $500.00 plus $3.85for each additional

$100.00, or fraction thereof, to and including $2,000.00

$25,001.00 to $50,000.00

Fee

$1.00 to $500.00

$501.00 to $2,000.00

$2,001.00 to $25,000.00

$100,001.00 to $500,000.00

City of Glendale User Page 17 4/24/2019

Page 17: City of Glendale Community Development Fee Schedule€¦ · Plan Review of Phased Designs for New Construction and Additions (foundation only, shell building, etc.). Projects built

TABLE 3B

City of Glendale User Page 18 4/24/2019

Page 18: City of Glendale Community Development Fee Schedule€¦ · Plan Review of Phased Designs for New Construction and Additions (foundation only, shell building, etc.). Projects built

$358.88 per sheet

$358.88 per sheet

$358.88 per sheet

$358.88 per sheet

$358.88 per sheet

$358.88 per sheet

$358.88 per sheet

$358.88 per sheet

$35.86

$358.88 per review

$358.88

$358.88 per review

$1,102.59

$126.73

$0.51 SY

$57.00 EA

$0.30 LF

$0.37 SF

$0.08 SF

$31.67 EA

$31.67 EA

$253.49 EA

$126.73 EACatch Basin/Scuppers

Sidewalk Ramps

Driveway - Commercial

Driveway - Residential

Second Review

Plan Review, Grading, Drainage and SWPPP:

Sidewalk

Valley Gutter

Right of Way Permit:

Paving

Third Plan Review

Revisions

PERMIT FEES

First Review

Curb and Gutter

Manholes/Water Valve Adjustment

Third or Subsequent Review

First Plan Review

Second Plan Review

Base Fee

Minor Land Division

Minor Land Division

Drainage Report Review:

First Plan Review

ENGINEERING FEES

Construction Drawings (Civil):

Revisions

Second Plan Review

Third or Subsequent Review

Owner Occupied Single-Family Residence Fee (10% of plan

review fee)

PLAN REVIEW FEES

City of Glendale User Page 19 4/24/2019

Page 19: City of Glendale Community Development Fee Schedule€¦ · Plan Review of Phased Designs for New Construction and Additions (foundation only, shell building, etc.). Projects built

$126.73

$63.38 EA

$1.25 LF

$0.99 LF

$1.25 LF

$1.25 LF

$57.00 EA

$443.60 EA

Base Fee $126.73

$0.51 SY

$126.73 EA

$57.00 EA

$1.23 LF

$221.79 EA

$0.74 LF

$0.51 LF

$12.66 EA

$152.01 EA

$57.00 EA

$0.95 SY

$190.13 per sheet

$126.73 per sheet

$190.13 per sheet

$126.73 per sheet

$633.74 annually

$221.79

Sewer Line Trench

Dry Utility Permit:

Storm Drain/Private Irrigation (12" and larger)

Paving (on site)

Grading and Drainage Permit:

Public Water, Sewer and Storm Drain Permit:

Wet Taps

Storm Drain Trench

Irrigation (12" and larger)

Manholes

Hydrant Flow Test

Catch Basin/Scuppers (private)

Manholes/Drywells (private)

Pits

Seal Coat

First Plan Review

Man Holes

Utility Cabinet 30" and above in height

Trench (R/W) Paved

Trench (R/W) Unpaved

Emergency Permits:

Second Plan Review

Emergency Permit Asphalt Restoration

Base Fee

Revisions

Emergency Permit Annual Fee

Third or Subsequent Review

Base Fee

Water Line Trench

City of Glendale User Page 20 4/24/2019

Page 20: City of Glendale Community Development Fee Schedule€¦ · Plan Review of Phased Designs for New Construction and Additions (foundation only, shell building, etc.). Projects built

$106.23 per hr.

$141.65 per hr.

$83.23 per hr. (EA inspection)

$316.86

50% of current fee

100% of current fee

ADMINISTRATIVE FEES

Investigation Fee-Work Done w/o Permit

PERMIT TIME EXTENSION OR REINSTATEMENT:

Inspection Services - Overtime

Inspection Services

After 180 days of expiration or termination

Re-Inspection

Within 180 days of expiration or termination

City of Glendale User Page 21 4/24/2019

Page 21: City of Glendale Community Development Fee Schedule€¦ · Plan Review of Phased Designs for New Construction and Additions (foundation only, shell building, etc.). Projects built

$204.21

$144.00

$84.99

$84.99

$217.21

$534.77

$534.77

$524.14

$417.88

$417.88

$276.24

$4,221.57 plus $112.14 per acre

$2,115.50 plus $112.14 per acre

$4,221.57

$2,115.50

$2,276.05 plus $112.14 per acre

$3,409.36 plus $112.14 per acre

$2,276.05 plus $112.14 per acre

$3,409.36 plus $112.14 per acre

$4,542.67 plus $112.14 per acre

General Plan Amendments:

Multiple Residence Districts

Minor Map Amendment

Major Text Amendment

Single Residence Districts

Rezoning:

Board of Adjustment appealed to Superior Court

Zoning Administration:

Major Map Amendment

PLANNING FEES

All Other Districts

Planning Director decision appealed to Board of Adjustment

Planning Commission action appealed to City Council

Zoning or Interpretation Letter

Continuance at the request of applicant

Continuances:

Construction Trailers/Manufactured Buildings

Zoning Verification Letter

Residential Administrative Relief

Seasonal Sales/Temporary Events

Overlay Districts (PRD, AIO, SCO, HP)

Minor Text Amendment

Planned Area Development (PAD) District

Commercial Administrative Relief

Administrative Review

Appeals:

City of Glendale User Page 22 4/24/2019

Page 22: City of Glendale Community Development Fee Schedule€¦ · Plan Review of Phased Designs for New Construction and Additions (foundation only, shell building, etc.). Projects built

$1,133.30

$4,221.57 any length of text, section

or topic

$1,057.74

$2,110.78

$1,138.03 plus $112.14 per acre

$1,704.68 plus $112.14 per acre

$1,138.03 plus $112.14 per acre

$1,704.68 plus $112.14 per acre

$854.70 plus $29.51 per lot

$875.93 plus $112.14 per acre

$1,605.49 plus $112.14 per acre

$1,709.40 plus $29.51 per lot

$368.29

$2,871.03 plus $29.51 per lot

$2,510.97

$1,171.07

$417.88

$4,181.41

General Plan Amendment - Major

Rezoning Overlay Districts (PRD, AIO, SCO, HP)

Zoning Ordinance Text Amendment

Appeal to City Council

Rezoning Single Family Districts

Rezoning Multiple Residence Districts

All Others

Conditional Use Permit as a Result of Unauthorized

Construction/Installation

Preliminary Plat

Rezoning Planned Area Development (PAD) District

Concurrent Review Processes:

General Plan Amendment - Minor

Amendment to any Approved Stipulation

Conditional Use Permits:

Design Review

Convenience Use

Development Master Plan

Final Plat

Preliminary Plat

Preliminary Plat Time Extension

Subdivisions:

City of Glendale User Page 23 4/24/2019

Page 23: City of Glendale Community Development Fee Schedule€¦ · Plan Review of Phased Designs for New Construction and Additions (foundation only, shell building, etc.). Projects built

$221.91

$1,558.28

$413.16 single residence

$2,337.42 all others

$112.14

$112.14

$248.12

$248.12

$148.72

$557.20

$59.01

$2,627.82

$87.35

$658.73

$1,751.89 plus $112.14 per acre

$30.11 per lot

$358.88 per sheet

$358.88 per sheet

$358.88 per sheet

$358.88 per sheet

$443.60 EA

$0.04 SF

Preapplications:

Group Homes:

First Plan Review

Second Plan Review

Third or Subsequent Review

Revisions

Sprinkled Area in Right-of-Way

Third and Subsequent Reviews of Application

Planner Consultation

Single Residence

Site Reservation

Variances:

Site Reservation

Variance as a Result of Unauthorized Construction/Installation

Design Review - Major

Planner Pre-application

Site Review

All Others

Variance as a Result of Unauthorized Construction/Installation

Design Review-Single Family Home Product

Landscape Irrigation Permit:

Design Review as a result of Unauthorized

Construction/Installation

Site Review

Design Review - Minor

Medical Marajuana Facilities:

Design Review:

Design Review Waiver Letter

50% of initial (base) fee

Team Pre-application

Base Fee

Construction Drawings (Landscaping):

Miscellaneous:

City of Glendale User Page 24 4/24/2019

Page 24: City of Glendale Community Development Fee Schedule€¦ · Plan Review of Phased Designs for New Construction and Additions (foundation only, shell building, etc.). Projects built

$358.88 per sheet

$358.88 per sheet

$358.88 per sheet

$358.88 per sheet

$47.21 EA pole

$47.21 per submittal

$23.60 per submittal

$47.21 per submittal

$590.27

$147.57 per lane, per day, up to 1/2

mile

$88.53 per lane, per day, up to 1/4

mile

$88.53 per day, up to 1/4 mile

$88.53 per day, 1 block

$88.53 per day

$1,770.79

$1,180.53

$1,180.53

$1,180.53

$1,180.53

$590.27

Restricting traffic at a signalized intersection without active

work occurring and an off-duty Glendale and/or sworn Police

Officer or Maricopa County Sheriff in uniform not present

Violating restrictions, limits, times, and locations of the

Barricade Use permit

Temporary Traffic Control Device Installation and Removal

Certification

Street Light

Residential Streets

First Plan Review

Traffic Engineering Plan Reviews:

Third Plan Review

Second Plan Review

Construction Inspection:

First Plan Review

Restricting traffic during peak hours without authorization of

the City's Transportation Director or designee

Alley Closure

Revisions

Arterial Streets

Collector Streets

Failing to correct or cure violations within the time period

stated in a warning notice

Plan Review, Traffic Control:

Barricade Manual Violations (Civil Sanctions):Presenting an imminent risk of death or injury to the public

within public right-of-way

Restricting roadway without proper certification, a barricade

permit and an approved traffic control plan for more than thirty

minutes

Sidewalk Closure

Third Plan Review

Barricaded Lane Restrictions:

Second Plan Review

TRANSPORTATION SERVICE FEES:

City of Glendale User Page 25 4/24/2019

Page 25: City of Glendale Community Development Fee Schedule€¦ · Plan Review of Phased Designs for New Construction and Additions (foundation only, shell building, etc.). Projects built

$590.27

$590.27

$295.11

$295.11

$295.11

$295.11

$13,647.25 per year

Leaving advance-warning signs facing traffic after restriction

has been removed, per direction

Leaving traffic control in the right-of-way twenty-four (24)

hours after Barricade Use Permit has expired

Rendering a Bus Stop inaccessible without relocating it or

making other accommodations

Missing or improper advanced-warning signs

Civil sanctions doubled. In addition, the City may double any civil sanction under this article

up to a maximum amount of two thousand five hundred dollars ($2500.00) for continuing

violations within a twenty-four (24) hour period. Each calendar day shall be considered a

separate period for the purposes of issuing civil sanctions.

Missing or improper use of barricades and channelizing devices

Use of unacceptable quality of traffic control as shown in the

City of Phoenix Barricade Manual

Annual Utility Permit

City of Glendale User Page 26 4/24/2019

Page 26: City of Glendale Community Development Fee Schedule€¦ · Plan Review of Phased Designs for New Construction and Additions (foundation only, shell building, etc.). Projects built

Access Gates:$317.32

$317.32

$317.32 (min. fee)

$0.053 SF

$0.018 SF

$94.42

$317.32

$237.99

$347.54 $623.31

See New Installation above

$317.32

$339.99

$237.99

Note: Each riser will be calculated as a separate system. No system can exceed 52,000 SF

Alternative surface Fire Apparatus Access Roads Install/Modify

Automatic Sprinkler System - Modification:

For each floor level above or below the grade floor level, add

1 - 20 heads

First 10,000 SF

Automatic Sprinkler System - New Installation

Access: To install or modify access gates across a fire

apparatus access road, OR to modify any fire apparatus access

road or fire lane, OR to modify firefighter pedestrian access

into a facility or premises.

Area over 10,000 SF

For each in-rack storage system add

Exception: There shall be no permit fee for installing a 13-D residential sprinkler system in a Group R,

Division 3 Occupancy that is not used for commercial purposes such as, but not limited to, assisted living or

group home use.

Modifications not requiring changing or adding sprinkler heads

Fire Service Mains:

First 200 FT

21 - 100 heads101 - 500 heads

System modifications over 500 heads shall be considered new

systems.

Each additional 200 FT, or fraction thereof

FIRE DEPARTMENT FEES

Automatic Fire Protection Systems:

CONSTRUCTION PERMITS

City of Glendale User Page 27 4/24/2019

Page 27: City of Glendale Community Development Fee Schedule€¦ · Plan Review of Phased Designs for New Construction and Additions (foundation only, shell building, etc.). Projects built

$94.42 EA

$94.42

$317.32

$317.32

Fire Pumps: $793.29

$634.64

$317.32

$475.97

$396.64

$317.32

$317.32

$158.63

$158.63

$317.32

$158.63

$317.32

$317.32 > 50 gallons - Installation

Single system

Modifications not requiring a pump test

Private fire hydrants, remove from service use or operation.

Private Hydrants

Modifications, per hydrant

Automatic Hood Systems:

Single pump

Each additional 1 - 4 outlets, add

Modification

Battery Systems

Each additional pump

Piping modifications

Clean Agent, Dry Chemical, Carbon Dioxide, and Other Special Extinguishing

Systems:

1 - 10 outlets

Modifications requiring a pump test

1 - 5,000 SF

Standpipes:

Modification, each system

Note: Small booster pumps may be permitted as part of other systems. The multiple pump advantage shall be

applied when plans are submitted and work is performed concurrently.

Each additional system

Each additional 5,000 SF or fraction thereof

City of Glendale User Page 28 4/24/2019

Page 28: City of Glendale Community Development Fee Schedule€¦ · Plan Review of Phased Designs for New Construction and Additions (foundation only, shell building, etc.). Projects built

$515.63

$769.70

$362.65

$94.42

$317.32

$33.05

$515.63

$769.70

$362.65

$94.42

Fire Protection System Monitoring $237.99

$634.64

$317.32

Fire Alarm System - New Installation:

Installation includes cylinder and all piping, valves and related

equipment.

Up to 10,000 SF

1 - 10 devices

Each additional device over 10

SF of area covered by alarm system:

For each floor level above or below the grade floor level, add

Fire Alarm System - Modification:

Note: Devices shall include, but not be limited to, all initiating and signaling devices such as pull stations,

smoke and heat detectors, and audible and visual alarms.

Up to 10,000 SF

10,001 - 52,000 SF

Fire Protection System Monitoring

Each additional 52,000 SF or fraction thereof

For each floor level above or below the grade floor level, add

10,001 - 52,000 SF

SF of area covered by alarm system:

Each additional 52,000 SF or fraction thereof

Fire Alarm Panel - Installation Only:

Compressed Gas Systems:

Compressed Gas System, Modification. If the work performed

involves more than 50% of the system, the fees for a new

installation shall apply.

City of Glendale User Page 29 4/24/2019

Page 29: City of Glendale Community Development Fee Schedule€¦ · Plan Review of Phased Designs for New Construction and Additions (foundation only, shell building, etc.). Projects built

$793.29

$396.64

$475.97

$475.97

$317.32

$317.32

$317.32

$475.97

$317.32

$317.32

$475.97

$317.32

$475.97

$317.32

$317.32

$317.32

$793.29

$475.97

$317.32

$317.32

$475.97

$317.32

$317.32

Industrial Oven Installation

First tank

Fire Fighter Breathing Air Systems:

Modification

Tank Installation-first tank

Installation

Flammable/Combustible Liquids

Abandon a tank in place

Systems with fixed fire protection equipment, add

Hazardous Materials Liquid Tank: Modifications

Tanks with fixed fire protection systems, add

Modifications

Tanks installed in a vault, add

Install, repair, close, abandon, or modify any facility or area

Hazardous Materials:

Tanks installed in a vault, add

Tank Installation-each additional tank

Liquefied Petroleum Gases:

Modify

Flammable/Combustible Liquid Tanks

Cryogenic Fluid Systems:

Install

Industrial Oven Installation

Tank removal, per tank

Each additional tank

Tank removal, per tank

To install, construct or alter equipment, plants, terminals, wells,

refineries, distilleries and similar faculties where flammable

and combustible liquids are produced, processed, transported,

stored, dispensed or used.

Tanks with fixed fire protection systems, add

LP-Gas system installation:

LPG System - Modification, each system:

City of Glendale User Page 30 4/24/2019

Page 30: City of Glendale Community Development Fee Schedule€¦ · Plan Review of Phased Designs for New Construction and Additions (foundation only, shell building, etc.). Projects built

$475.97

$317.32

$317.32

$351.30

$158.63

$94.42

$94.42 annually

$634.64 temporary

$94.42

$94.42

$317.32

$317.32

$317.32

$317.32

$475.97

$793.29

$94.42

$475.97

Single

Each Additional

Each additional on the same site

Tents, Canopies, and Other Membrane Structures:

Multiple:

Modification, each

Covered Mall buildings

Aerosol Products

Carnivals and Fairs, See Outdoor Assembly Events

See Construction Permit Section: To maintain lead acid battery

systems and VRLA battery systems > 50 gallons

Compressed Gasses - Storage, use, and handling > permit

amounts

To use open flame producing equipment in a mall

Amusement buildings, to operate a special amusement building:

Place or construct temporary structures

Amusement buildings, to operate a special amusement building:

Dry Cleaning Plants

Battery Systems - Installation

Spraying or dipping:

To change to a more hazardous fluid

Exhibits and Trade Shows

ExplosivesManufacture, storage, sale or use of explosives, explosive material,

or blasting agents, fireworks or pyrotechnic special effect materials

Greater than 50,000 SF

Aggregate Area Used:

1 - 5,000 SF

5,001 - 50,000 SF

Cars in Malls, see Vehicle Display

Cryogenic Fluids, See Hazardous Materials

OPERATIONAL PERMITS

Installation of spray booths, rooms, areas, or dip tanks

First

Blasting fee for the use, handling and storage of explosives used

primarily for construction or demolition, 30-day permit

City of Glendale User Page 31 4/24/2019

Page 31: City of Glendale Community Development Fee Schedule€¦ · Plan Review of Phased Designs for New Construction and Additions (foundation only, shell building, etc.). Projects built

$951.95

$158.63 per hr. standby fee (2 hr. min.)

$951.95

$158.63 per hr. standby fee (2 hr. min.)

$94.42 annually

$237.99

$237.99

$203.03 annually

$203.03 annually

$94.42 annually

$237.99

$203.03 annually

$94.42

$94.42 permanent

$317.32 temporary

$94.42

$317.32 $94.42

$158.63

$317.32

$317.32

$94.42

$951.95

$158.63 per hr. standby fee (2 hr. min.)

$94.42

$1,110.61

$475.97

$317.32

$94.42

Pump-over or pump-out storage tanks

First show

Flame Effects Material: Use and Handling:

Repeat shows at same site

Cryogenic fluids > quantities in Table 105.6.11.

Storage, use and handling > the permit amounts for hazardous

materials in Tables 105.6.9, 105.6.11, or 105.6.20. (For F/C

liquids see above)

Storage, use and handling of Class I, II, III - A Liquids

Organic coatings: manufacturing > 1 gallon per day

Repeat shows at same site

Special events, extension of premises, each occurrence

Spraying and dipping operations

Fireworks, Outdoor Displays

LP Gases:

Repeat shows at same site

Special events, Major (as defined in

www.glendaleaz.com/fire/special_event_handbook.cfm)

Storage use and handling > 25 pounds

Organic coatings: Manufacturing > 1 gallon per day, See

Hazardous Materials

Pump over or pump out storage tanks

To operate a temporary vehicle fueling station

First show

HPM to store, handle or use HPM materials

Storage and use

Special Events

Hazardous Materials:

Outdoor assembly events, carnivals, fair, festivals, etc.

Pyroxylin plastics:

Open Burning

Open flames or torches in a hazardous fire area

Temporary use of LPG inside buildings

Magnesium: processing > 10 pounds

Hot work operations, temporary

Hot work operations, permanent

High piled storage > 500 SF

Special events, Minor (as defined in

www.glendaleaz.com/fire/special_event_handbook.cfm)

Place of assembly, to operate a Group A

Pyrotechnic Special Effects: Use and handling:

First show

Flammable and Combustible Liquids

City of Glendale User Page 32 4/24/2019

Page 32: City of Glendale Community Development Fee Schedule€¦ · Plan Review of Phased Designs for New Construction and Additions (foundation only, shell building, etc.). Projects built

$94.42

$158.63 per hr. (2 hr. min.)

$158.63 per hr. (2 hr. min.)

$7.51 per bed ($158.63 min.)

$158.63

$317.32

$236.09 OR the original permit fee

(whichever is less)

$330.84

$165.42

$55.13

$158.63 per hour (1 hr. min.)

300% of permit fee

$47.23 (non-refundable)

$158.63 per hr. (2 hr. min.)

$158.63 per hr. (1 hr. min.)

300% of permit fee

$158.63 per hr. (2 hr. min.)

50% of current permit fee

100% of current permit fee

Plan Review Application fee: Due upon submittal, non-

refundable (Applies to all plan reviews)

Inspection Fees:

4 Year Inspections:

Inspections requested for other than normal duty hours: Mon.

thru Fri. 7am to 4pm

Vehicle Display: The display of liquid or gas fired vehicles

or equipment inside a Group A, M, or Covered Mall

building, except automotive dealership showrooms.

Third Review and subsequent reviews (Applies to all plan

reviews)

Renewal of expired permit:

Existing building inspection fee, shall be assessed for each

additional inspection after two follow up inspections

Child and Adult day-care

Hospitals, group homes, nursing care, supervisory care,

behavior health, assisted living. The fee schedule is based on

the number of licensed beds as determined by the licensing

agency.

Inspection Fees:

Annual Inspections:

2 Year Inspections:

Greater than 50

Stand by Fee

Construction inspection fee, shall be assessed for each

additional inspection after two follow up inspections

Operating without a permit (Applies to all permits)

After 180 days of expiration

Expedited plan review (Applies to all plan reviews and

includes P.A.S.S. projects

Licensed for 50 or less

Minimum plan review fee when none of the above apply

(Applies to all plan reviews)

Within 180 days of expiration

Revisions (Applies to all plan reviews)

City of Glendale User Page 33 4/24/2019

Page 33: City of Glendale Community Development Fee Schedule€¦ · Plan Review of Phased Designs for New Construction and Additions (foundation only, shell building, etc.). Projects built

$9.51

$4.88 plus $.91 per page after 1st

page

$475.97

$793.29

$158.63 or fraction thereof (min.

$79.32)

$158.63 or fraction thereof (min. 1 hr.)

Fire/EMS field incident reports

Records research for specific information, per address

Staff consultation and research

Alternate means and methods or code modification requests.

Fee due upon submittal of request.

Photographs (CD)

Technical Report Review

Operational Service Fees:

City of Glendale User Page 34 4/24/2019

Page 34: City of Glendale Community Development Fee Schedule€¦ · Plan Review of Phased Designs for New Construction and Additions (foundation only, shell building, etc.). Projects built

$126.73

$221.80

$506.99

$633.75

$1,901.26

$2,788.53

$5,070.02

$9,686.26

$95.06 plus $1693.55 deposit

$96.59 $60.19

$127.59

$2,281.48

$1,204.12

$126.73 per visit, after 2 initial visits

$236.07

Marker Ball Inspection Fee

Permit for non-significant industrial users that have the

potential to damage the sewer and treatment plant

infrastructure.

Non-Significant Industrial User 'B Level' Permit Annual Maintenance Fee:

Annual Permit Maintenance Fee:

Grease Interceptor Re-Inspection Fee:

Service Line Relocate Fee up to 13 FT

UTILITY SERVICES FEES

Non-Significant Industrial User 'B Level' Permit Application Fee:

6 inch

4 inch

Hydrant Install/Relocate Fee

8 inch

Permit for significant industries that have the potential to

damage the sewer and treatment plant infrastructure.

Annual maintenance to help defray the costs of monitoring,

inspections, enforcement actions and preparation of reports.

Fee to encourage compliance with grease interceptor pumping

requirements for restaurants and businesses that are required to

maintain grease interceptors to prevent entry of grease and oil

into the sewer system.

Significant Industrial User Permit Application Fee:

1 inch to 3/4 inch Fitting Fee

PERMIT AND INSPECTION FEES:

Meter Size

WATER METER FEES:

3 inch

1 inch

2 inch

1.5 inch

0.75 inch

City of Glendale User Page 35 4/24/2019

Page 35: City of Glendale Community Development Fee Schedule€¦ · Plan Review of Phased Designs for New Construction and Additions (foundation only, shell building, etc.). Projects built

$188.85

$188.85

$93.68 issuance

$157.70 per riser, after 2 initial tests

$23.60

$53.10

$27.96

$76.73

$17.72

$35.41

$76.73

$76.73

$1.17

$23.60

1.50%

$200.00

$250.00

$300.00

Lien Fee $22.30

$70.81

$118.02

$23.60

Deposit Fees:

Disconnect Notice

Fee intended to provide incentive to contractors to properly

flush and prepare water lines constructed to serve new

development. Failure to prepare the lines results in repeated

testing by the Water Quality Lab and increased costs.

Meter Field Test - 1 1/2" and larger

Other Property Types - Up to 1 1/2 meter

Other Property Types - 2" and larger meter

Meter Test Fees:Meter Bench Test - 1" and smaller

Meter Bench Test - 1 1/2" and larger

After Hour Reconnect

Delinquent Account Fee (Previously Delinquent Collection Fee)

General Fees:New Account

Residential Meter (single family)

Unauthorized Use

Collection Agency Referral

Insufficient Fund Check

Annual maintenance fee for compliance inspections of

restaurants and others that are required to maintain grease

interceptors to prevent entry of oil and grease into the sewer

system and to minimize odor complaints.

Miscellaneous Field Visit

Door Tag

Broken Meter Lock

Late Charge (On Past Due Balance)

Meter Tampering

Water Main Re-Test Fee:

Annual maintenance fee to help defray the costs of monitoring,

inspections, and enforcement actions of non-significant

industrial users.

Temporary Permit or Manhole Entry Permit:

Maintenance fee to defray costs of permitting and inspections.

Grease Bearing Waste Discharger Fee:

Refer to Glendale City Code, Chapter 2 Article1, Sec

2.4

City of Glendale User Page 36 4/24/2019

Page 36: City of Glendale Community Development Fee Schedule€¦ · Plan Review of Phased Designs for New Construction and Additions (foundation only, shell building, etc.). Projects built

City of Glendale User Page 37 4/24/2019

Page 37: City of Glendale Community Development Fee Schedule€¦ · Plan Review of Phased Designs for New Construction and Additions (foundation only, shell building, etc.). Projects built

Table 3B

Group

IA IB IIA IIB IIIA IIIB IV VA VB

A-1 Assembly, theaters, w/stage

244.21 236.18 230.55 221.01 207.82 201.82 214.02 189.83 182.71

A-1 Assembly, theaters w/out

stage 223.45 215.42 209.80 200.25 187.31 181.32 193.26 169.33 162.21

A-2 Assembly, nightclubs 190.08 184.73 180.34 172.99 163.33 158.82 166.99 147.83 142.92

A-2 Assembly, restaurants,

bars, banquet halls 189.08 183.73 178.34 171.99 161.33 157.82 165.99 145.83 141.92

A-3 Assembly, churches 224.47 216.44 210.82 201.27 189.73 183.73 194.28 171.74 164.62

A-3 Assembly, general,

community halls, libraries,

museums 188.77 180.74 174.11 165.57 151.59 146.63 158.58 133.64 127.52

A-4 Assembly, arenas 222.45 214.42 207.80 199.25 185.31 180.32 192.26 167.33 161.21

B Business 195.88 188.76 182.90 173.98 159.08 153.13 167.31 139.76 133.67

B Business – shell 156.70 151.01 146.32 139.19 127.26 122.50 133.85 111.81 106.94

B Business – tenant

improvement

39.18 37.75 36.58 34.80 31.82 30.63 33.46 27.95 26.73

E Educational 207.44 200.32 195.11 186.22 173.62 164.85 179.83 151.63 147.30

F-1 Factory and industrial,

moderate hazard 115.30 109.99 103.87 99.84 89.72 85.56 95.69 73.79 69.57

F-2 Factory and industrial, low

hazard 114.30 108.99 103.87 98.84 89.72 84.56 94.69 73.79 68.57

H-1 High Hazard, explosives 107.85 102.54 97.43 92.40 83.50 78.33 88.25 67.57 N.P.

H-234 High Hazard 107.85 102.54 97.43 92.40 83.50 78.33 88.25 67.57 62.34

H-5 HPM 195.88 188.76 182.90 173.98 159.08 153.13 167.31 139.76 133.67

I-1 Institutional, supervised

environment 194.98 188.36 182.90 175.20 161.40 157.01 175.29 144.58 140.08

I-2 Institutional, hospitals 327.69 320.57 314.72 305.80 289.87 0.00 299.12 270.56 N.P.

I-3 Institutional, restrained 222.66 215.54 209.69 200.77 187.11 180.16 194.09 167.80 159.71

I-4 Institutional, day care

facilities 194.98 188.36 182.90 175.20 161.40 157.01 175.29 144.58 140.08

M Mercantile 141.54 136.19 130.80 124.45 114.24 110.73 118.45 98.74 94.83

M Mercantile – shell 113.23 108.95 104.64 99.56 91.39 88.58 94.76 78.99 75.86

M Mercantile – tenant

improvement

28.31 27.24 26.16 24.89 22.85 22.15 23.69 19.75 18.97

R-1 Residential, hotels 196.81 190.20 184.74 177.03 162.97 158.58 177.13 146.15 141.65

R-2 Residential, multiple family 165.05 158.44 152.98 145.27 132.00 127.61 145.37 115.18 110.68

R-3 Residential, one- and two-

family 154.04 149.85 145.98 142.32 137.11 133.50 139.93 128.29 120.75

R-4 Residential, care/assisted

living facilities 194.98 188.36 182.90 175.20 161.40 157.01 175.29 144.58 140.08

S-1 Storage, moderate hazard 106.85 101.54 95.43 91.40 81.50 77.33 87.25 65.57 61.34

S-2 Storage, low hazard 105.85 100.54 95.43 90.40 81.50 76.33 86.25 65.57 60.34

S-2.1 Public Parking Garage 55.82 55.82 55.82 55.82 N.P. N.P. 55.82 N.P. N.P.

Type of Construction

I-2 Institutional, nursing homes 227.45 220.33 214.47 205.56 191.65 N.P. 198.88 172.34 N.P.

U Utility, miscellaneous 83.66 79.00 74.06 70.37 63.47

c.        For shell buildings other than B or M occupancies, use 80% of the sq. ft. values provided.

d.        Tenant Improvements for other than B and M occupancies, use 20% of sq. ft. values provided.

e.        N.P. = not permitted

The Valuation chart is provided by the International Code Council and published in The Building Safety Journal annually.

59.32 67.24 50.19 47.80

a.        Private Garages use Utility, miscellaneous

b.        Unfinished basements (all use group) = $22.45 per sq. ft.

City of Glendale User Page 17

Page 38: City of Glendale Community Development Fee Schedule€¦ · Plan Review of Phased Designs for New Construction and Additions (foundation only, shell building, etc.). Projects built

Table 3B

City of Glendale User Page 17

Page 39: City of Glendale Community Development Fee Schedule€¦ · Plan Review of Phased Designs for New Construction and Additions (foundation only, shell building, etc.). Projects built

Occupancy Type Type of Construction Current Valuation 2009 Multiplier/ Fees Proposed Valuation 2014 Multiplier Fees Additional Revenue Generation

M Mercantile IB 55,068,000.00$ 423,288.00$ 76,206,000.00$ 592,106.00$ 168,818.00$

R-3 Residential, one &

two-family VB 200,433.70$ 3,231.50$ 216,830.00$ 3458.47 226.97$

M Mercantile IIB 7,139,150.00$ 58,438.00$ 8,178,700.00$ 67,105.00$ 8,667.00$

B Business IIB 4,583,600.00$ 38,983.00$ 5,290,000.00$ 44,812.00$ 5,829.00$

I.2 Institutional, Hospitals IIB 13,220,130.00$ 104,729.00$ 14,536,060.00$ 114,747.00$ 10,018.00$

Page 40: City of Glendale Community Development Fee Schedule€¦ · Plan Review of Phased Designs for New Construction and Additions (foundation only, shell building, etc.). Projects built

Additional Revenue Generation