city of ilagan fire station · 2020. 7. 22. · blood letting 4 2 -50% consulation - - bp...
TRANSCRIPT
1st Semester CY 2020
CITY OF ILAGAN FIRE STATION
CINSP ANGEL S DIQUIATCO JR, MBA BFPCity Fire Marshal
(COVER PAGE)
(
TABLE OF CONTENTS
I. GENERAL OVERVIEW
A. City Profile
B. Jurisdictional Map
II. ADMINSTRATIVE UPDATES
A. Personnel Administration
Personnel Strength / Rank Profile
Personnel Training Profile
B. Promotion and Recruitment
C. Updates in the Implementation of the Philippine Anti-Drug
Strategy (PADS)
III. LOGISTICAL UPDATES
A. Status of Fire Stations / Substations
Status of Construction of Fire Stations and Buildings
Status of Repair of Fire Stations and Buildings
B. Status of Fire Apparatus, Ambulances, and Service Vehicle
Status of Repair of Fire Apparatus
Status of Repair of Ambulances
Status of Repair of Service Vehicle
IV. OPERATIONAL UPDATES
A. Fire Prevention
B. Fire Suppression
C. Fire Investigation
D. Emergency Medical/Dental and Rescue Services
E. Updates on Non-Fire and Related Responses (BFP Responses
during Typhoons, Earthquakes, Natural and Man-Made Disasters / Calamities,
Pandemics, Terrorists Attacks and Similar Events)
V. BUDGETARY UPDATES
A. Status of Utilization of Funds
VI. PLANS AND PROGRAMS
A. Physical Report of Operations
B. Action Plan
I. GENERAL OVERVIEW
A. CITY PROFILE
Area Profile
B. JURISDICTIONAL MAP
(ENTER HERE YOUR CITY/MUNICIALITY JURISDICTIONAL MAP.)
City No. of
Barangays
Population Land Area
(km 2)
City of IIagan 91 180,000 1,166.26 sq.
km
CITY/MU
NICIPALI
TY
OFFICER NON OFFICER
NUP TOTAL
SSUPT SUPT CINSP SINSP INSP SFO4 SFO3 SFO2 SFO1 FO3 FO2 FO1
ILAGAN 1 1 1 4 5 2 18 32
II. ADMINISTRATIVE UPDATES
A. PERSONNEL ADMINISTRATION
Table IIA-1 PERSONNEL STRENGTH / RANK PROFILE
Table IIA-2 TRAINING PROFILE
CITY/MU
NICIPALIT
Y
OSEC PSOAC PSOBC FOCCFPS
CFAIIC PSBRC FSBC
OTHER
SNONE TOTAL
CITY OF
ILAGAN
1 1 2 4 21
2-
ongoing
FBRC
Training
1 32
IV. OPERATIONAL UPDATES
A. FIRE PREVENTION
STRUCTURAL
CIT
Y O
F ILA
GA
N
assem
bly
ed
uca
tio
na
l
Da
y c
are
He
alt
hc
are
Re
sid
en
tia
l b
oa
rd a
nd
care
De
ten
tio
n a
nd
co
rre
cti
on
al
ho
tel
do
rmit
ori
es
Ap
art
men
tb
uild
ing
Lo
dg
ing
an
d r
oo
min
g
ho
use
Sin
gle
an
d t
wo
fam
ily
dw
ell
ing
un
its
me
rca
nti
le
bu
sin
es
s
Ind
ustr
ial
sto
rag
e
Sp
ec
ial s
tru
ctu
re
No
ns
tru
ctu
ral (
ex v
eh
icle
use
d a
s r
oll
ing
sto
re &
etc
.)
TOTAL 27 14 0 2 0 1 8 1 14 12 0 2,186 530 136 57 6 13
CIT
Y O
F I
LA
GA
N
Bu
ild
ing
Pla
ns
Re
vie
we
d, P
roc
es
sed
, a
nd
Iss
ue
d F
SE
C
FS
IC O
cc
up
an
cy
FS
IC f
or
Bu
sin
es
s
FS
IC I
ss
ue
d f
rom
PE
ZA
FS
IC I
ss
ue
d f
or
Go
ve
rnm
en
t B
ldg
s
To
tal
FS
IC I
ss
ue
d (
Oc
cu
pa
nc
y, B
us
ine
ss
,
PE
ZA
, G
ovt
Bld
gs
)
No
tic
e t
o C
om
ply
Is
su
ed
No
tic
e t
o C
orr
ec
t V
iola
tio
ns
Is
su
ed
Ab
ate
me
nt
Ord
er
Iss
ue
d
RE
CO
MM
EN
DE
D F
OR
ST
OP
PA
GE
OF
OP
ER
AT
ION
S
AM
OU
NT
OF
FIR
E C
OD
E F
EE
S A
SS
ES
SE
D
TOTAL 59 25 2,979 0 5 3,009 6 0 0 0 Php2,474,387.00
NUMBER OF ESTABLISHMENTS INSPECTED PER
CITY/MUNICIPALITY
CITY/MUNICIPALITYas of 2ND Quarter
(previous)
as of 2ND Quarter
(current)Variance
CITY OF ILAGAN 230 167 -27.39%
NUMBER OF ESTABLISHMENTS INSPECTED PER CITY/
MUNICIPALITY
CITY/MUNICIPALIT
Y
as of 1ST Semester
2019
as of 1st
Semester *2020Variance
CITY OF ILAGAN 2,990 3,012 0.74%
NUMBER OF ESTABLISHMENTS INSPECTED PER
CITY/MUNICIPALITY
CITY/MUNICIPALITY as of CY 2019 as of CY *2020 Variance
CITY OF ILAGAN 3,294 3,012 -8.56%
CITY/MUNICIPALITY
2ND QUARTER (Previous Year)
2ND QUARTER (Current Year)
VARIANCE
CITY OF ILAGAN P194,191.00 P198,723.00 2.33%
FIRE CODE FEES COLLECTON AS OF 2ND QUARTER
CITY/MUNICIPALITY 1ST SEMESTER (Previous Year)
1ST SEMESTER (Current Year)
VARIANCE
CITY OF ILAGAN P1,696,287.50 P2,474,387.00 45.87%
FIRE CODE FEES COLLECTON AS OF 1ST SEMESTER
CITY/MUNICIPALITY 2019 (Previous Year) 2020 (Current Year)Jan-June 2020
VARIANCE
CITY OF ILAGAN 2,364,446.04 P2,474,387.00 4.64%
FIRE CODE FEES COLLECTON AS OF 2020
B. FIRE SUPPRESSION
FIRE INCIDENT COMPARATIVE REPORT
KINDS OCCUPANCY
Covering
period
(previous)
Covering
period
(present)
VARIANCE
ST
RU
CT
UR
AL F
IRE
Residential 2 6 200%
Industrial/Factory
Commercial/Mercantile
Storage 1 -
Mixed
Business/Gov't Offices 1 -
Educational 1 -
Institutional
Place of Assembly 1 -
Miscellaneous
TOTAL
NO
N
ST
RU
CT
UR
AL
FIR
E
Grass, Rubbish and Forest Fire 1 3 200%
Motor Vehicle 1 -
Ship/Water Vessel
Aircraft
Locomotive
TOTAL 5 12 140%
AMOUNT OF DAMAGE BASED ON SUBMITTED AFFIDAVIT OF
LOSS3,347,878.00 1,530,000.00 -54%
CA
US
ES
OF
FIR
E
DESCRIPTION
Covering
period
(previous)
Covering
period
(present)
VARIANCE
Electrical connection 1 4 300%
Electrical appliances
Electrical machinery
Spontaneous combustion
Unattended cooking/stove 1 -
Open flame due to
torch/gasera1 1 0%
LPG Explosion
Lighted cigarette butt
Chemicals
Pyrotechniques
Lighted match stick/lighter 1 1 0%
Incendiary
devices/flammable liquid
Lightning
Bomb explosion
Undetermined 2 -
Others 1 5 400%
TOTAL 5 12 140%
C. FIRE INVESTIGATION
FIRE INVESTIGATION COMPARATIVE REPORT
CLA
SS
IFIC
AT
ION
OF
FIR
E
Intentional - -
Accidental fire 5 10 100%
Undetermined - -
Fire cases under
investigation2
TOTAL 5 12 140%
CA
SU
ALT
IES
Fatalities in fire fighter - -
Fatalities in fire civilian - -
Injuries in fire fighter - -
Injuries in fire civilian - -
TOTAL - -
CONTINUATION: FIRE INVESTIGATION COMPARATIVE REPORT
EMERGENCY RESPONSE
ACTIVITIES
Covering
period
(previous
)
Covering
period
(present)
VARIANCE
FIRE INCIDENTS 5 12 140%
RESCUE
OPERATIONAL/DISASTERS-
VEHICULAR ACCIDENTS - 1
MEDICAL CASES - -
TOTAL
NON EMERGENCY RESPONSE
FREE MEDICAL AND DENTAL
SERVICES- -
TT VACCINATION - -
BLOOD LETTING 4 2 -50%
CONSULATION - -
BP MONITORING - -
DRILL CONDUCTED 81 7 -91.35%
OTHERS
TOTAL 89 20 -77.52%
D. EMERGENCY MEDICAL SERVICES AND RESCUE SERVICES
EMS/RESCUE COMPARATIVE REPORT
CITY/MUNICIPALITY OF ILAGAN, ISABELA Total
Household
(BRGY)
Household
Affected
1. Households in disaster/calamity-affected barangays rendered with
assistance
- -
2. Individuals rendered with technical rescue assistance/intervention - -
3. Non-emergency cases rendered with assistance by BFP 20 BARANGAYS
-
-
4. Local, National and International events deployed with BFP
contingents
11 BARANGAYS -
5. LGU's extended with technical trainings by BFP - -
E. UPDATES ON NON-FIRE AND RELATED RESPONSES (BFP RESPONSES DURING TYPHOONS,
EARTHQUAKES, NATURAL AND MAN-MADE DISASTERS / CALAMITIES, PANDEMICS, TERRORISTS
ATTACKS AND SIMILAR EVENTS)
STATUS OF CONSTRUCTION OF FIRE STATION AND BUILDINGS AS OF 2020
III. LOGISTICS UPDATES
I.STATUS OF FIRE STATION/SUBSTATION
REGION 02
DATE
AWARDE
D
BUDGETAMOUNT OF
CONTRACT
PROGRESS OF
CONSTRUCTIO
N (% of
Accomplishme
nt)
DATE OF
COMPLETI
ON
REMARK
S
City of Ilagan Fire
Station 2016 2,625,000.000
1ST PHASE
COMPLETED
100%
BFP
Counterp
art
2nd Phase 95%3rd/4th
quarter
2020
LGU
Counterp
art
STATUS OF REPAIR OF FIRE STATION AND BUILDINGS
As of June 2020
REGION 02
DATE
AWARDE
D
BUDGETAMOUNT OF
CONTRACT
PROGRESS OF
CONSTRUCTIO
N (% of
Accomplishme
nt)
DATE OF
COMPLETI
ON
REMARK
S
City of Ilagan Fire
Station NEGATIVE
STATUS OF REPAIR OF FIRETRUCK
As of June 2020
REGION 02DATE
AWARDEDBUDGET
AMOUNT OF
CONTRACT
PROGRESS
OF
CONSTRUC
TION (% of
Accomplish
ment)
DATE OF
COMPLETIO
N
REMARK
S
City of Ilagan Fire
Station 07
November
2019
Php
365,511.05 Php 360,100.00 80% 06 April 2020
With
approved
temporary
suspensio
n of work
( Due to
COVID-
19
pandemic
lockdown)
B. STATUS OF FIRE APPARATUS, AMBULANCES AND SERVICE VEHICLE
STATUS OF REPAIR OF AMBULANCE
As of June 2020
REGION 02
DATE
AWARDE
D
BUDGET
AMOUNT
OF
CONTRACT
PROGRESS OF
CONSTRUCTION
(% of
Accomplishment)
DATE OF
COMPLETI
ON
REMARK
S
City of Ilagan Fire
StationNEGATIVE
V. BUDGETARY UPDATES
A. Status of Utilization of Funds as of June 2020
UTILIZATION OF 20% FIRE CODE FEES
(FY 2010-2013)
No. Mode of Procurement Date of Procurement Particulars Quantity Unit of Measure AMOUNT
ON PROCESS (INTENDED FOR NEW FIRE STATION BUILDING) 495,223.58
TOTAL
BALANCE 495,223.58
TOTAL
OFFICE2nd QTR
(751) APRIL(755) MAY (755) JUNE(755)TOTAl (755) APRIL(761) MAY(761) JUNE(761)
TOTAL (761)
ILAGAN 5,000.00 3,333.00 3,333.00 3,334.0010,000.00 18,743.88 18,743.88 18,743.88 56,231.64 71,231.64
TOTAL
OFFICE1ST QTR
(751)JANUARY(
755)FEBRUARY
(755)MARCH
(755)TOTAl (755)
JANUARY(761)
FEBRUARY(761)
MARCH(761)
TOTAL (761)
ILAGAN 5,000.00 3,333.00 3,333.00 3,334.0010,000.00 20,601.12 20,601.12 20,601.12 61,803.36 76,803.36
V. BUDGETARY UPDATES
A. Status of Utilization of Funds as of June 2020
VI. PLANS AND PROGRAMS
A. Physical Report of Operation as of June 2020
PHYSICAL REPORT ON OPERATIONS (PRO) CY 2020
As of JUNE 2020
FIRE PREVENTION MANAGEMENT PROGRAM1.Percentage of buildings and establishments inspected covered by Fire Code: BPLO registered, Government owned bldg./structures, and all other privately owned bldgs./structures not requiring FSIC against
total no. of buildings and establishments nationwide.
2. Percentage of Fire Safety Inspection Certificate (FSIC) rated buildings and structure that has not been the cause of fire incident (origin of fire) against total number of FSIC
rated buildings/establishments nationwide
3. Percentage (%) of buildings and establishments inspected within the prescribed time frame (i.e. 3½ days from the receipt of Inspection Order (IO) of the Fire safety Inspector) against total
number of buildings/establishments nationwide.
4. No. of IEC and related activities conducted
MONTHREGISTERED BPLO CY
2019 DATA
NO. OF GOVERNMENT
OWNED BUILDING
PRIVATELY OWNED
BUILDING/ STRUCTURE
NOT REQUIRING FSIC
NON STRUCTURAL
(Motor vehicle, Motor
Banca, Pedicab and the
likes)
TOTAL TARGETS
FOR CY 2020
buildings and
establishments
inspected covered
by Fire Code
FSIC rated buildings and
structure that has not
been the cause of fire
incident (origin of fire)
total number of
FSIC rated
buildings/
establishments
buildings and
establishments inspected
within the prescribed time
frame
FIRE PREVENTION
MANAGEMENT
PROGRAM -
INDICATOR 1
FIRE PREVENTION
MANAGEMENT
PROGRAM -
INDICATOR 2
FIRE PREVENTION
MANAGEMENT
PROGRAM -
INDICATOR 3
FIRE PREVENTION
MANAGEMENT
PROGRAM -
INDICATOR 4
(1) (2) (3) (4) (5) (6)=(2)/(1) (7)=(3)/(4) (8)=(5)/(2) (9)
JANUARY 2213 0 2,213 2,283 2,282 2,282 2,283 103% 100% 100% 3
FEBRUARY 211 241 443 441 441 443 184% 100% 100% 7
MARCH 127 150 98 98 98 98 65% 100% 100% 2
SUB-TOTAL 2,551 0 0 0 2,604 2,824 2,821 2,821 2,824 108% 100% 100% 12
APRIL 64 89 2 2 2 2 2% 100% 100% 0
MAY 63 88 70 68 68 70 80% 100% 100% 0
JUNE 46 66 92 94 94 92 139% 100% 100% 0
SUB-TOTAL 173 0 0 0 243 164 164 164 164 67% 100% 100% 0
JULY 75 100
AUGUST 75 100
SEPTEMBER 63 83
SUB-TOTAL 213 0 0 0 283 0 0 0 0 0% #DIV/0! #DIV/0! 0
OCTOBER 22 52
NOVEMBER 7 32
DECEMBER 3 8
SUB-TOTAL 32 0 0 0 92 0 0 0 0 0% #DIV/0! #DIV/0! 0
TOTAL
2,969 0 0 0 3,222 2,988 2,985 2,985 2,988
93% 100% 100%
12
FIRE AND EMERGENCY MANAGEMENT PROGRAM - Fire Operations Activities
1.Percentage (%) of fire, emergency and rescue calls responded nationwide (fire related) against total number of fire, EMS and rescue calls
2. Percentage (%) of fire calls not exceeding 300,000 estimated property damage out of the total number of fire calls
nationwide
3. Percentage (%) of fire calls and related emergencies responded within seven (7) minutes (from receipt of call until arrival on the fire scene) against total fire and
emergency calls
MONTH
CALLS RESPONDS
FIRE CALLS NOT
EXCEEDING
300,000
WITHIN 7 MINUTES
Fire
Operations
Activities -
INDICATOR 1
Fire
Operations
Activities -
INDICATOR 2
Fire Operations
Activities -
INDICATOR 3FIRE CALLSEMS CALLS
(fire related)
RESCUE CALLS
(fire related)
TOTAL
NUMBER OF
CALLS
FIRE CALLS
RESPONDED
EMS CALLS
RESPONDED
RESCUE CALLS
RESPONDED
TOTAL
NUMBER OF
CALLS
RESPONDED
FIRE EMS
TOTAL
NUMBER OF
FIRE AND EMS
CALLS
RESPONDED
WITHIN 7 MIN.
(1) (2) (3) (4) (5) (6) (7) (8) (9) (10) (11) (12) (13)=(8)/(4) (14)=(9)/(1) (15)=(12)/(1)+(2)
JANUARY 2 0 0 2 2 0 0 2 1 2 0 2 100% 50% 100%
FEBRUARY 3 0 0 3 3 0 0 3 2 1 0 1 100% 67% 33%
MARCH 3 0 0 3 3 0 0 3 3 3 0 3 100% 100% 100%
Sub-total 8 0 0 8 8 0 0 8 6 6 0 6 100% 75% 75%
APRIL 1 0 0 1 1 0 0 1 1 0 0 0 100% 100% 0%
MAY 1 0 0 1 1 0 0 1 1 1 0 0 100% 100% 0%
JUNE 2 0 0 2 2 0 0 2 2 1 0 1 100% 100% 50%
Sub-total 4 0 0 4 4 0 0 4 4 2 0 1 100% 100% 25%
JULY
AUGUST
SEPTEMBER
Sub-total 0 0 0 0 0 0 0 0 0 0 0 0 #DIV/0! #DIV/0! #DIV/0!
OCTOBER
NOVEMBER
DECEMBER
Sub-total 0 0 0 0 0 0 0 0 0 0 0 0 #DIV/0! #DIV/0! #DIV/0!
TOTAL 12 0 0 12 12 0 0 12 10 8 0 7100% 83% 58%
FIRE AND EMERGENCY MANAGEMENT PROGRAM - Non-Fire Response Activities
1. Percentage (%) of households in disaster/calamity-affected barangays rendered with assistance against total households in
disaster/calamity-affected barangays
2.Number of individuals rendered with technical rescue
assistance/intervention
3.Number of Non-emergency cases rendered with assistance by
BFP
4.Number of Local, National and International events deployed with BFP contingents
5. Number of LGUs extended with technical trainings by BFP
MONTHTOTAL HOUSEHOLDS IN DISASTER/
CALAMITY-AFFECTED BARANGAYS
HOUSEHOLDS AFEECTED
RENDERED WITH ASSISTANCE
Non-Fire Response Activities -
INDICATOR 1
Non-Fire Response Activities -
INDICATOR 2
Non-Fire Response Activities -
INDICATOR 3
Non-Fire Response Activities -
INDICATOR 4
Non-Fire Response Activities -
INDICATOR 5
(1) (2) (3)=(2)/(1) (4) (5) (6) (7)
JANUARY 3 1 0
FEBRUARY 1 1 0
MARCH 2 2 0
Sub-total 4 4 0
APRIL 5 1 0
MAY 3 1 0
JUNE 2 1 0
Sub-total
JULY
AUGUST
SEPTEMBER
Sub-total
OCTOBER
NOVEMBER
DECEMBER
Sub-total
TOTAL
FIRE AND EMERGENCY MANAGEMENT PROGRAM - Fire Investigation Activities
1.Percentage (%) fire incidents investigated against total no. of fire incidents responded.
2.Percentage (%) of arson fire cases filed in court against total no. of arson fires.
3.Percentage (%) of fire incidents investigated with SIR submitted against total number of fire incident responded
regionwide.
MONTH
FIRE CALLS RESPONDED FIRE INCIDENTS INVESTIGATED TOTAL NUMBER OF ARSON FIRE ARSON FIRE FILED IN COURTFIRE INCIDENTS INVESTIGATED
WITH SIR
Fire Investigation
Activities - INDICATOR 1
Fire Investigation Activities
- INDICATOR 2
Fire Investigation Activities
- INDICATOR 3
(1) (2) (3) (4) (5) (6)=(2)/(1) (7)=(4)/(3) (8)=(5)/(1)
JANUARY 2 2 0 0 2 100% #DIV/0! 100%
FEBRUARY 3 3 0 0 3 100% #DIV/0! 100%
MARCH 3 3 0 0 3 100% #DIV/0! 100%
Sub-total 8 8 0 0 8 100% #DIV/0! 100%
APRIL 1 1 0 0 1 100% #DIV/0! 100%
MAY 1 1 0 0 1 100% #DIV/0! 100%
JUNE 2 2 0 0 2 100% #DIV/0! 100%
Sub-total 4 4 0 0 4 100% #DIV/0! 100%
TOTAL 12 12 0 0 12
100% #DIV/0! #DIV/0!
ISSUES AND
CONCERNS
ACTION TAKEN BY
REGIONAL OFFICE
ACTION TO BE
REQUESTED FROM NHQ
EXPECTED
OUTPUTTARGET DATE
Acquisition of
new fire truck - - - -
Additional
personnel as
per fire truck
ratio
B. Action Plan as of June 2020
-An increase of 2% in the conduct of Fire safety inspection
ACTION PLAN
As of ______________
City: _______________
PREPARED BY: CERTIFIED CORRECT: NOTED AND APPROVED:
SFO1 WESLEY A AUSTRIACO II SFO1 MARVIN B GALASINAO CINSP ANGEL S DIQUIATCO JR,MBA, BFP