City of London
Veterans Memorial Parkway ExtensionHuron Street to Clarke Road
City of London
AGENDA
1) Project History
2) Roadway and Streetscape
3) Construction Staging
4) Schedule
5) Questions
• 1996 EA completed to extend Airport Road from Oxford Street to Clarke Road
• 2008 EA completed to widen and grade separate Veterans Memorial Parkway (VMP) from Highway 401 to Clarke Road
• Property negotiations between land owners and City of London for extension of VMPto Clarke Road
• Stantec retained by City (Jan 2016) to undertake preliminary and detail design, and tendering to extend VMPbetween Huron Street and Clarke Road
Project History
• The previous 2008 EA alignment was refined during the project’s preliminary design phase to better match to the existing Clarke Road alignment
• Clarke Road Widening Environmental Assessment completed in 2019 to confirm future VMP alignment
Previous Alignment
Refined Alignment
VMP aligned to match into future Clarke Road widening to four lanes.
Project History
Roadway – VMP Extension
Roadway – VMP / Clarke / FCA
Roadway – VMP / Huron
• Two lane rural cross section for VMPsimilar to VMP south of Huron Street
• Right-of-way incorporates ultimate 100 m width (where property permits) to protect corridor
• Future additional lanes are being considered now to minimize future throwaway costs
• Permits ditches instead of a storm sewer system to contribute to storm runoff quantity and quality control
Roadway - Cross Section
Goal: To create an extension of Veterans Memorial
Parkway that carries on the original intent of the parkway, to honour Canadian Veterans, as well as to provide native habitat where possible.
Objectives: Create a wave of red fall coloured trees to
signify remembrance. Use native trees where possible to integrate
with Fanshawe Conservation Area and support native species.
Implement native grasses and wildflowers where possible to create pollinator habitat.
Accentuate intersections with flowering trees.
Legend:
Deciduous Trees
Deciduous Trees with Red Fall Colour
Flowering Deciduous Trees
Coniferous Trees
Existing Trees To Remain
Seed Restoration
Streetscape Concept
Anticipated Spring/Summer 2020
Construction Construct new VMP Corridor
Between Huron Street and Clarke Road
Construct new drainage channel and new stormwater management pond
Traffic Existing conditions, all lanes are
open on Clarke Road and Huron Street
Access maintained at all entrances along Huron Street and Clarke Road including Fanshawe Conservation Area Entrance
Construction Stage 1
Anticipated Summer 2020
Traffic VMP will be closed from Oxford
Street to Huron Street with traffic detours for 6 weeks
Huron Street at VMP to be reduced to one lane, alternating traffic on granular surface
Construction Reconstruct Huron Street and
existing VMP Temporary widening on Clarke
Road in preparation for Stage 3
Construction Stage 2
Veterans Memorial Parkway will be closed from Oxford Street to Huron Street for 6 weeks.
A temporary road closure to through traffic is required during construction due to the grade raise required on Huron Street.
The temporary road closure will also shorten the overall duration of construction.
Access for residents and emergency services will be maintained during construction.
Advance signage and variable message signs will be used to alert the public.
Detour Route – Stage 2Anticipated Summer 2020
Traffic Huron Street will be open
VMP will be open from Fanshawe Conservation Area Entrance south
Clarke Road will be open north and south with traffic shifted at Fanshawe conservation Area Entrance
Access to Fanshawe Conservation Area via Clarke Road to Huron Street to New VMP Extension
Single lane flagging on Fanshawe Conservation Area Entrance as required to tie in new entrance
Construction Construct north tie-in of VMP to
Clarke Road
Anticipated Summer/Fall 2020
Construction Stage 3
Anticipated Summer/Fall 2020
Construction Stage 3 – FCA Entrance
Anticipated Fall 2020
Construction Construct tie-in of Clarke Road/VMP
intersection with existing Clarke Road
Removal of Old Clarke Road/Fanshawe Conservation Area Entrance
Construction Stage 4
Traffic Clarke Road traffic detoured along
new VMP extension to Huron Street
Huron Street and VMP will be open
Clarke Road north of Ted Early Park will be closed
Ted Earley Park and Bulk Water Station access will be maintained
Access for residents and emergency services will be maintained during construction.
Advance signage and variable message signs will be used to alert the public.
Detour Route – Stage 4Anticipated Fall 2020
MILESTONE TIMEFRAME
PUBLIC INFORMATION CENTRE OCTOBER 16, 2019
PUBLIC INPUT OCTOBER 30, 2019
FINALIZE DESIGN NOVEMBER-DECEMBER 2019
TENDER ADVERTISING JANUARY 2020
TENDER AWARD / CONSTRUCTION START APRIL 2020
Schedule
Questions?