city of new westminster · wally carter p.eng address: web engineering ltd. 4173 dawson street,...

90
Owner: City of New Westminster Contract Administrator: WEB Engineering Ltd. July 2013 CITY OF NEW WESTMINSTER Engineering Department Contract Documents For Contract NWIT-13-23 2013 Capital Pavement Program

Upload: others

Post on 19-Jun-2020

16 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: CITY OF NEW WESTMINSTER · Wally Carter P.Eng Address: WEB Engineering Ltd. 4173 Dawson Street, Burnaby, B.C. V5C 4B3 Phone: 604-294-8588 Fax: 604-294-8580 2.0 Tender Documents 2.1

Owner: City of New Westminster

Contract Administrator: WEB Engineering Ltd.

July 2013

CITY OF NEW WESTMINSTER Engineering Department

Contract Documents For Contract NWIT-13-23 2013 Capital Pavement Program

Page 2: CITY OF NEW WESTMINSTER · Wally Carter P.Eng Address: WEB Engineering Ltd. 4173 Dawson Street, Burnaby, B.C. V5C 4B3 Phone: 604-294-8588 Fax: 604-294-8580 2.0 Tender Documents 2.1

TC - PAGE 1 UNIT PRICE CONTRACT

MMCD (2000)

City of New Westminster

PROJECT TENDER DOCUMENT

2013 Capital Pavement Program CONTRACT NWIT-13-23

Table of Contents

Table of Contents ........................................................................................................................... TC-Page 1

Invitation to Tender...................................................................................................................... INV-Page 1

Instructions to Tenderers: Part I .....................................................................................IT PART I-Page 1-6 Instructions to Tenderers: Part II (MMCD) ...................................................................... (Not Reproduced)

Form of Tender ........................................................................................................................... FT-Page 1-3 Appendix 1 - Schedule of Quantities & Prices ............................................................................. 4-9 Appendix 2 - Preliminary Construction Schedule ......................................................................... 10 Appendix 3 - Experience of Superintendent and Project Manager ................................................ 11 Appendix 4 - Comparable Work Experience ................................................................................. 12 Appendix 5 - Subcontractors ......................................................................................................... 13 Appendix 6 – Force Account Labour Rates ................................................................................... 14 Appendix 7 – Declaration: Living Wage Employer ...................................................................... 15 Appendix 8 – Tenderer’s Plant ...................................................................................................... 16

Agreement ................................................................................................................................ AGT-Page 1-4 Schedule 1 - Schedule of Contract Documents ................................................................................ 5 Schedule 2 - List of Contract Drawings ........................................................................................... 6

General Conditions (MMCD) ............................................................................................ (Not Reproduced) Specifications (MMCD) ..................................................................................................... (Not Reproduced)

Supplementary General Conditions ....................................................................................... SGC-Page 1-14

Supplementary Specifications ................................................................................................ SS Page 1 – 13

Standard Detail Drawings (MMCD) .................................................................................. (Not Reproduced)

Page 3: CITY OF NEW WESTMINSTER · Wally Carter P.Eng Address: WEB Engineering Ltd. 4173 Dawson Street, Burnaby, B.C. V5C 4B3 Phone: 604-294-8588 Fax: 604-294-8580 2.0 Tender Documents 2.1

City of New Westminster 2013 Capital Pavement Program

Contract NWIT-13-23

INVITATION TO TENDERERS

NWIT-13-23 Invitation to Tender

Contract: 2013 Capital Pavement Program Reference No.: Contract NWIT-13-23 ( OWNER’S CONTRACT REFERENCE NO. ) The Owner invites tenders for: Repaving and reconstruction of approximately 32,600 square meters of roadway with approximately 2700 tonnes of 12.5mm Superpave, 4600 tonnes of 19.0mm Superpave, 1900 tonnes of UC #1 and 2500 tonnes of LC #1 asphalt, 6700 tonnes of base gravel, 9500 tonnes of sub-base gravel, full depth milling, pavement patching and pavement marking, all within the City of New Westminster. Copies of the Contract Documents are available on or after July 4, 2013, for download from the City of New Westminster’s Purchasing site at: http://www.newwestcity.ca/business/bid_opportunities/request_for_bids__proposals_-_open.php A tender shall be accompanied by a Bid Bond (or Certified Cheque) in the amount of ten percent (10%) of the Tender Price. The successful tenderer will be required to provide a Performance and Labour and Material Payment Bond each in the amount of fifty percent (50%) of the Tender Price. An Agreement of Surety to bond shall accompany the tender submitted. Technical inquires regarding this tender may be directed to Wally Carter P.Eng, WEB Engineering Ltd. 604. 294.8588. The lowest or any Tender may not necessarily be accepted and the City will not be responsible for any cost incurred by the Tenderer in preparing the Tender. Tender award will be contingent on budget approval from the Corporation of the City of New Westminster council. If the value of the contract(s) resulting from this invitation to tender exceeds the thresholds stipulated in Annex 502.4 of the Agreement on Internal Trade, then all provisions of the Agreement on Internal Trade will apply. The City’s language in its procurement documents shall be English. Tenders are scheduled to close at: Tender Closing Time: 3:00, pm local time Tender Closing Date: July 25, 2013 at: Information Desk Attention: Purchasing Manager City of New Westminster 511 Royal Avenue New Westminster, B.C. V3L 1H9 The City will not open Tenders in Public.

Page 4: CITY OF NEW WESTMINSTER · Wally Carter P.Eng Address: WEB Engineering Ltd. 4173 Dawson Street, Burnaby, B.C. V5C 4B3 Phone: 604-294-8588 Fax: 604-294-8580 2.0 Tender Documents 2.1

INSTRUCTIONS TO TENDERERS Instructions to Tender, Part I

Page 5: CITY OF NEW WESTMINSTER · Wally Carter P.Eng Address: WEB Engineering Ltd. 4173 Dawson Street, Burnaby, B.C. V5C 4B3 Phone: 604-294-8588 Fax: 604-294-8580 2.0 Tender Documents 2.1

City of New Westminster 2013 Capital Pavement Program

Contract NWIT-13-23 INSTRUCTIONS TO TENDERERS - PART I

NWIT-13-23 Instruct Tenderer

PAGE IT1

(TO BE READ WITH “INSTRUCTIONS TO TENDERERS - PART II” CONTAINED IN THE EDITION OF THE PUBLICATION “MASTER MUNICIPAL CONSTRUCTION DOCUMENTS” SPECIFIED IN ARTICLE 2.2 BELOW)

City of New Westminster (the “Owner”) Contract: 2013 Capital Pavement Program Reference #. NWIT-13-23 1.0 Introduction 1.1 These Instructions apply to and govern the preparation of tenders for this

Contract. The Contract is generally for the following work:

Repaving and reconstruction of approximately 32,600 square meters of roadway with approximately 2700 tonnes of 12.5mm Superpave, 4600 tonnes of 19.0mm Superpave, 1900 tonnes of UC #1 and 2500 tonnes of LC #1 asphalt, 6700 tonnes of base gravel, 9500 tonnes of sub-base gravel, full depth milling, pavement patching and pavement marking, all within the City of New Westminster.

1.2 Direct all inquiries regarding the Contract to: Wally Carter P.Eng Address: WEB Engineering Ltd. 4173 Dawson Street, Burnaby, B.C. V5C 4B3 Phone: 604-294-8588 Fax: 604-294-8580 2.0 Tender Documents

2.1 The tender documents which a Tenderer should review to prepare a Tender consist of all of the Contract Documents listed in Schedule 1 entitled “Schedule of Contract Documents”. Schedule 1 is attached to the Agreement which is included as part of the Tender package. The Contract Documents include the drawings listed in Schedule 2 to the Agreement, entitled “List of Contract Drawings”.

2.2 A portion of the Contract Documents are included by reference. Copies of these

documents have not been included with the tender package. These documents are the Instructions to Tenderers - Part II, General Conditions, Specifications and Standard Detail Drawings. They are those contained in the publication entitled “Master Municipal Construction Documents - General Conditions, Specifications and Standard Detail Drawings”. Refer to Schedule 1 to the Agreement or, if not specified in Schedule 1, then the applicable edition shall be the most recent

Page 6: CITY OF NEW WESTMINSTER · Wally Carter P.Eng Address: WEB Engineering Ltd. 4173 Dawson Street, Burnaby, B.C. V5C 4B3 Phone: 604-294-8588 Fax: 604-294-8580 2.0 Tender Documents 2.1

City of New Westminster 2013 Capital Pavement Program

Contract NWIT-13-23 INSTRUCTIONS TO TENDERERS - PART I

NWIT-13-23 Instruct Tenderer

PAGE IT2

edition as of the date of the Tender Closing Date. All sections of this publication are by reference included in the Contract Documents.

Copies of the Master Municipal Construction Document ( Gold Edition) can be obtained at:

Support Services Unlimited #102 – 211 Columbia Street Vancouver BC V6A 2R5 604 681-0295 2.3 Any additional information made available to tenderers prior to the Tender

Closing Time by the Owner or representative of the Owner, such as geotechnical reports or as-built plans, which is not expressly included in Schedule 1 or Schedule 2 to the Agreement, is not included in the Contract Documents. Such additional information is made available to tenderers who shall make their own judgment about its reliability, accuracy, completeness and relevance to the Contract, and neither the Owner nor any representative of the Owner makes any guarantee or representation that the additional information is reliable, accurate, complete, or relevant.

3.0 Submission of Tenders 3.1 Original Tenders must be submitted in a sealed envelope, clearly marked on the

outside with the above Contract Title and Reference No., and must be received by the office of:

City of New Westminster – Purchasing Department on or before: Tender Closing Time: 3:00, pm local time Tender Closing Date: July 25, 2013 at Address: Main Information Desk 511 Royal Avenue City of New Westminster, BC. V3L 1H9 3.2 Late Tenders will not be accepted or considered, and will be returned unopened.

3.3 Facsimile, electronic mail, or other unsealed bids will not be accepted. 3.4 The City will not open this tender in Public

Page 7: CITY OF NEW WESTMINSTER · Wally Carter P.Eng Address: WEB Engineering Ltd. 4173 Dawson Street, Burnaby, B.C. V5C 4B3 Phone: 604-294-8588 Fax: 604-294-8580 2.0 Tender Documents 2.1

City of New Westminster 2013 Capital Pavement Program

Contract NWIT-13-23

INSTRUCTIONS TO TENDERERS - PART I

NWIT-13-23 Instruct Tenderer

PAGE IT3

4.0 Additional Instructions to Tenderers 4.1 The following terms are additional to the terms and conditions contained in the

MMCD Instructions to Tenderers – Part II: Tender Requirements 5

5.2 Delete Instructions to Tenderers – Part II, Paragraph 5.2 and substitute the following:

A tender must be accompanied by tender security (“Bid Security”) in the form of: 5.2.1 a bid bond issued by a surety licensed to carry on the business of

suretyship in British Columbia in a form satisfactory to the Owner in an amount equal to 10% of the Tender Price; or

5.2.2 cash, bank draft or letter of credit in a form satisfactory to the

Owner in an amount equal to 10% of the Tender Price. 5.3 add or amend the following: 5.3.3 Appendix 3 – name and brief description of the previous

experience of the Superintendent and the Project Manager the tenderer will use for the Work.

5.3.6 Appendix 6 – Schedule of Force Account Labour and Equipment

Rates. Insert the hourly rates for labour and Equipment including allowances for taxes, assessments, benefits, tools, overhead and profit.

5.3.7 Appendix 7 – Declaration – Living Wage Employer 5.3.8 Appendix 8 – Tenderer’s Plant Prices 10 add or amend the following: 10.1 The Tender Price will represent the entire cost excluding GST

taxes to the Owner of the complete Work based on the estimated quantities in the Schedule of Quantities and Prices of the Form of Tender. Notwithstanding the generalities of the above, tenderers shall include in the tendered prices (including unit prices, lump sum prices, or other forms of pricing) sufficient amounts to cover;

10.4 If a tenderer has omitted to enter a price for an item of Work set

out in the tender, unless the tender indicates to the contrary, the tenderer shall be deemed to have allowed elsewhere in the tender for the cost to carry out that item of Work and no increase in the contract price shall be allowed on account of such omission.

Page 8: CITY OF NEW WESTMINSTER · Wally Carter P.Eng Address: WEB Engineering Ltd. 4173 Dawson Street, Burnaby, B.C. V5C 4B3 Phone: 604-294-8588 Fax: 604-294-8580 2.0 Tender Documents 2.1

City of New Westminster 2013 Capital Pavement Program

Contract NWIT-13-23

INSTRUCTIONS TO TENDERERS - PART I

NWIT-13-23 Instruct Tenderer

PAGE IT4

Taxes 11 add or amend the following; 11.1 The tendered prices shall cover all taxes and assessments of any

kind payable with respect to the Work, but shall not include GST taxes. GST taxes shall be listed as a separate item as required by GC 19.2.

Award 15.1 Amendment to 15.1 of the Instructions to Tenderers Part II (Award) of

the MMCD replacing paragraph after 15.1.6

In exercising its discretion, the Owner will have regard to the information provided by the tenderer in the Appendices to the Form of Tender as described under IT5.3, and may also have regard to any information obtained by the Owner in evaluating such tender information, as well as the Owner's previous experience, if any, with the tenderer. In exercising its discretion the Owner may consider, but is not limited to, the following criteria in addition to the Tender Price:

a) the proven experience of the Tenderer, and any listed

subcontractors to do the Work; b) the Tenderer's ability to complete the Work within the

Preliminary Construction Schedule;

c) the Tenderer's ability to work effectively with the Owner, its consultants and representatives.;

d) the Tenderer's ability to manage and do the work effectively

using the named superintendent and submitted contractors and subcontractors;

e) the Tenderer's history on other projects including with respect to

quality of work, changes in the work, force account work, and the contract administration costs of the Owner

f) the nature of any legal proceedings undertaken by the Tenderer,

or any officer or director of the Tenderer or affiliate of the Tenderer, directly (or indirectly through another corporation) against the Owner within the previous five years of the Invitation to Tenders

g) Litigation and ongoing unresolved claims. In a addition to any other provision of this tender document, and

without limiting the City’s discretion under any other provision of this tender document, the City may, in its absolute discretion, reject a tender if;

Page 9: CITY OF NEW WESTMINSTER · Wally Carter P.Eng Address: WEB Engineering Ltd. 4173 Dawson Street, Burnaby, B.C. V5C 4B3 Phone: 604-294-8588 Fax: 604-294-8580 2.0 Tender Documents 2.1

City of New Westminster 2013 Capital Pavement Program

Contract NWIT-13-23

INSTRUCTIONS TO TENDERERS - PART I

NWIT-13-23 Instruct Tenderer

PAGE IT5

(i) the Tenderer, or any officer or director of the Tenderer, is or has been engaged directly or indirectly in a legal action against the City in relation to any matter; or

(ii) the Tenderer has current unresolved extra work claims totaling in excess of $100,000.00 beyond 90 days of contract substantial completion for any construction project with the City.

In determining whether or not to reject a tender under this

section, the City will consider whether the litigation or unresolved extra work claim is likely to affect the Tenderer ‘s ability to work with the City, its employees, consultants and representatives and whether the City’s experience with the Tenderer indicates an unusual risk the City will incur increased staff and legal costs in the administration of the contract if awarded to the Tenderer.

In no event shall the Owner be liable for the Tenderer's costs of preparing and submitting a tender, which shall be done by the Tenderer at its sole risk.

15.2 Replace 15.2 of the Instructions to Tenderers Part II (Award) with the

following: 15.2.1 Tenderers will not be permitted to alter or amend tendered prices

included in a tender after the Tender Closing Time. 15.2.2 The Owner has a limited budget for this Contract. Projects may

be added or deleted with appropriate adjustments to estimated quantities in the Schedule of Quantities and Prices so that the Tender Price is within the Owner’s budget. If, prior to award of the Contract the Owner identifies changes the Owner wishes to make, the changes, at the sole discretion of the Owner, may be made prior to award of the of the Contract. Alternatively, the Owner may award the Contract as tendered and delete work after award. In such case, Supplementary General Condition 9.4, Valuation of Changes shall apply.

4.2 Living Wage Policy add the following;

Effective January 1st, 2011, the City of New Westminster became a “Living Wage Employer”. As such, the City has established a Living Wage Policy that requires all firms that are contracted by the City to provide services on City premises, to pay their employees, who perform said service on City property, A Living Wage as calculated by the Living Wage for Families Campaign. The figure for 2013 for the Lower Mainland is $19.62 per hour, assuming no benefits are provided by the employer.

Page 10: CITY OF NEW WESTMINSTER · Wally Carter P.Eng Address: WEB Engineering Ltd. 4173 Dawson Street, Burnaby, B.C. V5C 4B3 Phone: 604-294-8588 Fax: 604-294-8580 2.0 Tender Documents 2.1

City of New Westminster 2013 Capital Pavement Program

Contract NWIT-13-23

INSTRUCTIONS TO TENDERERS - PART I

NWIT-13-23 Instruct Tenderer

PAGE IT6

In order to determine an employee’s hourly rate with benefits the Living Wage for Families has created a Living Wage Calculator to assist with this determination. Please access the following website to determine your compatibility. http://livingwageforfamilies.ca/calculator/ The City includes in all its competitive bid documents a Declaration referencing the City’s expectations with regards to compliance of the Policy. This Declaration can be found in Appendix 7 – Declaration – Living Wage Employer of these documents. Completion and submission of the Declaration is required prior to contract award. In evaluating submissions, the City intends to rely on the Declaration provided by a Respondent and shall have no obligation or duty to investigate the truthfulness of the Declaration. Please review the City’s Living Wage Policy for further information. http://www.newwestcity.ca/business/living_wage_employer.php

Page 11: CITY OF NEW WESTMINSTER · Wally Carter P.Eng Address: WEB Engineering Ltd. 4173 Dawson Street, Burnaby, B.C. V5C 4B3 Phone: 604-294-8588 Fax: 604-294-8580 2.0 Tender Documents 2.1

FORM OF TENDER WITH APPENDICIES Form of Tender Appendix 1: Schedule of Quantities and Prices Appendix 2: Preliminary Construction Schedule Appendix 3: Experience of Superintendent and Project Manager Appendix 4: Comparable Work Experience Appendix 5: Subcontractors Appendix 6: Force Account Labour and Equipment Rates Appendix 7: Declaration – Living Wage Employer Appendix 8: Tenderer's Plant

Page 12: CITY OF NEW WESTMINSTER · Wally Carter P.Eng Address: WEB Engineering Ltd. 4173 Dawson Street, Burnaby, B.C. V5C 4B3 Phone: 604-294-8588 Fax: 604-294-8580 2.0 Tender Documents 2.1

FT - PAGE 1 UNIT PRICE CONTRACT

Tenderer’s Initials __________

MMCD (2000)

Form of Tender ( FOR USE WHEN UNIT PRICES FORM THE BASIS OF PAYMENT - TO BE USED ONLY WITH THE GENERAL CONDITIONS AND OTHER STANDARD DOCUMENTS OF THE UNIT PRICE MASTER MUNICIPAL CONSTRUCTION DOCUMENTS. ) City of New Westminster ( NAME OF OWNER ) Contract: 2013 Capital Pavement Program

Reference No. Contract NWIT-13-23 TO OWNER:

1 WE, THE UNDERSIGNED:

1.1 have received and carefully reviewed all of the Contract Documents, including the Instructions to Tenderers, the specified edition of the "Master Municipal Construction Documents - General Conditions, Specifications and Standard Detail Drawings" and the following Addenda:

( ADDENDA, IF ANY )

1.2 have full knowledge of the Place of the Work, and the Work required; and

1.3 have complied with the Instructions to Tenderers; and

2 ACCORDINGLY WE HEREBY OFFER:

2.1 to perform and complete all of the Work and to provide all the labour, equipment and

material all as set out in the Contract Documents, in strict compliance with the Contract Documents; and

2.2 to achieve Substantial Performance of the Work in Section A within

10 Weeks from the Commencement Date; and ( WORK DURATION OR DATE )

2.3 to do the Work for the price, which is the sum of the products of the actual quantities

incorporated into the Work and the appropriate unit prices set out in Appendix 1, the "Schedule of Quantities and Prices", plus any lump sums or specific prices and adjustment amounts as provided by the Contract Documents. For the purposes of tender comparison, our offer is to complete the Work in Section A for the "Tender Price" in the sum of

__________________________________________________________________________________________________ Dollars ( $__________________________________)

as set out on Appendix 1 of this Form of Tender. Our Tender Price is based on the estimated quantities listed in the Schedule of Quantities and Prices, and includes GST.

Page 13: CITY OF NEW WESTMINSTER · Wally Carter P.Eng Address: WEB Engineering Ltd. 4173 Dawson Street, Burnaby, B.C. V5C 4B3 Phone: 604-294-8588 Fax: 604-294-8580 2.0 Tender Documents 2.1

FT - PAGE 2 UNIT PRICE CONTRACT

Tenderer’s Initials __________

MMCD (2000)

3 WE CONFIRM:

3.1 that we understand and agree that the quantities as listed in the Schedule of Quantities and Prices are estimated, and that the actual quantities will vary.

3.2 that we understand and agree that the Owner is in no way obligated to accept this

Tender.

4 WE CONFIRM:

4.1 that the following Appendices are attached to and form a part of this tender:

4.1.1 the Appendices as required by paragraph 5.3 of the Instructions to Tenderers – Part I and Part II; and

4.1.2 the Bid Security as required by paragraph 5.2 of the Instructions to Tenderers -

Part I. 5 WE AGREE:

5.1 that this tender will be irrevocable and open for acceptance by the Owner for a period of

60 calendar days from the day following the Tender Closing Date and Time, even if the tender of another tenderer is accepted by the Owner. If within this period the Owner delivers a written notice ("Notice of Award") by which the Owner accepts our tender we will:

5.1.1 provide Declaration of Living Wage Employer as required before award 5.1.2 within 10 Days of receipt of the written Notice of Award deliver to the Owner:

a) a Performance Bond and a Labour and Material Payment Bond, each in

the amount of 50% of the Contract Price, covering performance of the Work including the Contractor’s obligations during the Maintenance Period and in a form acceptable to the Owner. The Labour and Material Payment Bond must be a Broad Form Bond, protecting all companies with a direct contract with the Principal or any Sub-Contractor of the Principal;

b) a Construction Schedule, as provided by GC 4.6.1;

c) a “clearance letter” indicating that the tenderer is in WSBC compliance;

d) a copy of the insurance policies as specified in GC 24 indicating that all

such insurance coverage is in place and;

Page 14: CITY OF NEW WESTMINSTER · Wally Carter P.Eng Address: WEB Engineering Ltd. 4173 Dawson Street, Burnaby, B.C. V5C 4B3 Phone: 604-294-8588 Fax: 604-294-8580 2.0 Tender Documents 2.1

FT - PAGE 3 UNIT PRICE CONTRACT

Tenderer’s Initials __________

MMCD (2000)

5.1.3 within 2 Days of receipt of written "Notice to Proceed", or such longer time as

may be otherwise specified in the Notice to Proceed, commence the Work (the “Commencement Date”); and

5.1.4 sign the Contract Documents as required by GC 2.1.2.

6 WE AGREE:

6.1 that, if we receive written Notice of Award of this Contract and, contrary to paragraph 5

of this Form of Tender, we:

6.1.1 fail or refuse to deliver the documents as specified by paragraph 5.1.2 of this Form of Tender; or

6.1.2 fail or refuse to commence the Work as required by the Notice to Proceed,

then such failure or refusal will be deemed to be a refusal by us to enter into the Contract and the Owner may, on written notice to us, award the Contract to another party. We further agree that, as full compensation on account of damages suffered by the Owner because of such failure or refusal, the Bid Security shall be forfeited to the Owner, in an amount equal to the face value of the Bid Security.

7 OUR ADDRESS is as follows:

Phone: Fax: Email Address: Attention:

This Tender is executed this day of , 2013.

Contractor:

(FULL LEGAL NAME OF CORPORATION, PARTNERSHIP OR INDIVIDUAL)

(AUTHORIZED SIGNATORY AND CORPORATE SEAL)

(AUTHORIZED SIGNATORY)

Page 15: CITY OF NEW WESTMINSTER · Wally Carter P.Eng Address: WEB Engineering Ltd. 4173 Dawson Street, Burnaby, B.C. V5C 4B3 Phone: 604-294-8588 Fax: 604-294-8580 2.0 Tender Documents 2.1

FT - PAGE 4 UNIT PRICE CONTRACT

Tenderer’s Initials __________

MMCD (2000)

Form of Tender - Appendix 1 Contract NWIT-13-23

2013 Capital Pavement Program SCHEDULE OF QUANTITIES AND PRICES (See paragraph 5.3.1 of the Instructions to Tenderers - Part II)

(All prices and Quotations including the Contract Price shall include all Taxes, but shall not include GST. GST shall be shown separately.)

Page 16: CITY OF NEW WESTMINSTER · Wally Carter P.Eng Address: WEB Engineering Ltd. 4173 Dawson Street, Burnaby, B.C. V5C 4B3 Phone: 604-294-8588 Fax: 604-294-8580 2.0 Tender Documents 2.1

FT-PAGE5

Section A : 6th Ave., 6th St., Royal Ave.

DESCRIPTION UNIT QUANTITY UNIT PRICE AMOUNT

4.2 Common Excavation cu.m 8,250.0 $ $

4.4 Subgrade Preparation sq.m. 9,900.0 $ $

4.5 Saw Cut lin.m 915.0 $ $

4.6 Sub-Base (SS 13 ) tonne 9,550.0 $ $

4.7 Base (SS 13 ) tonne 5,700.0 $ $

4.9 Tack Coat litre 8,100.0 $ $

4.10 Asphalt Pavement - WMA (SS 10 , SS 11 and SS 19).1 12.5 mm Superpave tonne 2,700.0 $ $.2 19.0 mm Superpave tonne 4,600.0 $ $

4.13 Replace/Adjust Manhole/Utility Cover (SS 8).1 Manhole Adjustment - Frame

& Cover each 22.0 $ $.2 Manhole Frame and Cover

Replacement each 13.0 $ $.3 Supply & Install New MR-6 Style

water valve box each 9.0 $ $.4 Adjust water valve box each 30.0 $ $.5 Adjust FortisBC Gas valve box each 1.0 $ $.7 Adjust Metro Vancouver Manhole or valve each 1.0 $ $

4.16 Milling Existing Asphalt Pavement (SS 9).2 Full Depth Milling sq. m 5,875.0 $ $.3 Strip milling (butt joint), 50mm depth sq. m 400.0 $ $

4.21 Replace Traffic Loop Detector (SS 12) each 13.0 $ $

Streetworks and Paving

SCHEDULE OF QUANTITIES AND PRICES

Form of Tender - Appendix 1

CONTRACT NWIT-13-232013 Capital Pavement Program

CITY OF NEW WESTMINSTER

Tenderer's Initials____________

Page 17: CITY OF NEW WESTMINSTER · Wally Carter P.Eng Address: WEB Engineering Ltd. 4173 Dawson Street, Burnaby, B.C. V5C 4B3 Phone: 604-294-8588 Fax: 604-294-8580 2.0 Tender Documents 2.1

FT-PAGE6

Section A : 6th Ave., 6th St., Royal Ave.

DESCRIPTION UNIT QUANTITY UNIT PRICE AMOUNT

Streetworks and Paving

SCHEDULE OF QUANTITIES AND PRICES

Form of Tender - Appendix 1

CONTRACT NWIT-13-232013 Capital Pavement Program

CITY OF NEW WESTMINSTER

4.24 Permanent Pavement Marking (SS 14).1 Thermoplastic Markings

.1 Double Yellow Line lin.m 150.0 $ $

.2 Single Line (Solid / Broken) lin.m 2,325.0 $ $

.3 Stop Bars lin.m 73.0 $ $

.4 Cross Walk lin.m 255.0 $ $

.5 3.0m wide Zebra Cross Walk per lin.m road width lin.m 14.0 $ $

.6 Arrows / Symbols each 6.0 $ $

.7 Painted Median with Thermoplastic Cross Hatching sq.m 95.0 $ $

4.33 Compact and Proof Roll road gravel layer sq.m 9,900.0 $ $

4.45 Test Pit over existing Metro Vancouver's Water Mainor Sewer Main (SS 18) - (Provisional) each 4.0 $ $

TOTAL FOR SECTION A : Streetworks and Paving $

Tenderer's Initials____________

Page 18: CITY OF NEW WESTMINSTER · Wally Carter P.Eng Address: WEB Engineering Ltd. 4173 Dawson Street, Burnaby, B.C. V5C 4B3 Phone: 604-294-8588 Fax: 604-294-8580 2.0 Tender Documents 2.1

FT-PAGE7

Section B : 8th Ave. (Provisional Work)

DESCRIPTION UNIT QUANTITY UNIT PRICE AMOUNT

4.2 Common Excavation cu.m 750.0 $ $

4.5 Saw Cut lin.m 30.0 $ $

4.7 Base (SS 13 ) tonne 1,025.0 $ $

4.9 Tack Coat litre 5,500.0 $ $

4.10 Asphalt Pavement - WMA (SS 10 , SS 11 and SS 19).3 Upper Course #1 tonne 1,900.0 $ $.4 Lower Course #1 tonne 2,500.0 $ $.6 Asphalt Driveways tonne 15.0 $ $

4.13 Replace/Adjust Manhole/Utility Cover (SS 8).1 Manhole Adjustment - Frame

& Cover each 8.0 $ $.2 Manhole Frame and Cover

Replacement each 13.0 $ $.3 Supply & Install New MR-6 Style

water valve box each 11.0 $ $.4 Adjust water valve box each 4.0 $ $.6 Adjust Tel / Hydro / NW Electrical Vault Cover each 6.0 $ $.7 Adjust Metro Vancouver Manhole or valve each 6.0 $ $.9 Adjust Survey Monument frame & cover each 1.0 $ $

4.16 Milling Existing Asphalt Pavement (SS 9).1 Surface Milling, LT 80mm sq. m 790.0 $ $.2 Full Depth Milling sq. m 8,650.0 $ $.3 Strip milling (butt joint), 50mm depth sq. m 270.0 $ $

4.17 Pavement Patching (SS 17).1 Greater than 125mm

.1 Area less than 5 sq. m sq. m 6.0 $ $

.2 Area more than or Equalto 5 sq. m sq. m 160.0 $ $

4.21 Replace Traffic Loop Detector (SS 12) each 21.0 $ $

Streetworks and Paving

SCHEDULE OF QUANTITIES AND PRICES

Form of Tender - Appendix 1

CONTRACT NWIT-13-23

2013 Capital Pavement Program

CITY OF NEW WESTMINSTER

Tenderer's Initials____________

Page 19: CITY OF NEW WESTMINSTER · Wally Carter P.Eng Address: WEB Engineering Ltd. 4173 Dawson Street, Burnaby, B.C. V5C 4B3 Phone: 604-294-8588 Fax: 604-294-8580 2.0 Tender Documents 2.1

FT-PAGE8

Section B : 8th Ave. (Provisional Work)

DESCRIPTION UNIT QUANTITY UNIT PRICE AMOUNT

Streetworks and Paving

SCHEDULE OF QUANTITIES AND PRICES

Form of Tender - Appendix 1

CONTRACT NWIT-13-23

2013 Capital Pavement Program

CITY OF NEW WESTMINSTER

4.24 Permanent Pavement Marking (SS 14).1 Thermoplastic Markings

.1 Double Yellow Line lin.m 50.0 $ $

.2 Single Line (Solid / Broken) lin.m 1,075.0 $ $

.3 Stop Bars lin.m 82.0 $ $

.4 Cross Walk lin.m 225.0 $ $

.5 3.0m wide Zebra Cross Walk per lin.m road width lin.m 21.0 $ $

.6 Arrows / Symbols each 12.0 $ $

.7 Painted Median with Thermoplastic Cross Hatching sq.m 165.0 $ $

4.33 Compact and Proof Roll road gravel layer sq.m 12,800.0 $ $

4.44 Pre-duct road crossing for TeraSpan Fibre Optic Cable (SS 15).1 Supply and install 25mm conduit lin.m 52.0 $ $.2 Install Junction Box supplied by TeraSpan each 4.0 $ $

4.45 Test Pit over existing Metro Vancouver's Water Mainor Sewer Main (SS 18) - (Provisional) each 11.0 $ $

TOTAL FOR SECTION B (Provisional Work) : Streetworks and Paving $

Tenderer's Initials____________

Page 20: CITY OF NEW WESTMINSTER · Wally Carter P.Eng Address: WEB Engineering Ltd. 4173 Dawson Street, Burnaby, B.C. V5C 4B3 Phone: 604-294-8588 Fax: 604-294-8580 2.0 Tender Documents 2.1

FT - PAGE 9 UNIT PRICE CONTRACT

Tenderer’s Initials __________

MMCD (2000)

Form of Tender - Appendix 1

Contract NWIT-13-23

2013 Capital Pavement Program SCHEDULE OF QUANTITIES AND PRICES (See paragraph 5.3.1 of the Instructions to Tenderers - Part II)

(All prices and Quotations including the Contract Price shall include all Taxes, but shall not include GST. GST shall be shown separately.)

TENDER SUMMARY

SECTION A : Streetworks & Paving for 6th Ave., 6th St., Royal Ave. .............................$_________________ GST (Section A) ................................................$_________________ TOTAL TENDER PRICE (Section A) ................................................$_________________ (Insert this Price in the Form of Tender 2.3) SECTION B (PROVISIONAL) : Streetworks & Paving for 8th Ave. ................................................$_________________ GST (Section B) ................................................$_________________ TOTAL TENDER PRICE (Section B) ................................................$_________________ SECTION A + SECTION B : Streetworks & Paving (Section A + Section B) .........................................$_________________ GST (Section A + Section B) ................................................$_________________ TOTAL TENDER PRICE (Section A + Section B) ..................................$_________________ It is understood that Section B is Provisional Work and may or may not be awarded. It is understood the City has the right to compare tenders based on Section A alone or Sections A and B combined for all tenders at its full discretion and contingent to available funding.

Page 21: CITY OF NEW WESTMINSTER · Wally Carter P.Eng Address: WEB Engineering Ltd. 4173 Dawson Street, Burnaby, B.C. V5C 4B3 Phone: 604-294-8588 Fax: 604-294-8580 2.0 Tender Documents 2.1

FT - PAGE 10 UNIT PRICE CONTRACT

Tenderer’s Initials __________

MMCD (2000)

Form of Tender - Appendix 2 Contract NWIT-13-23

2013 Capital Pavement Program PRELIMINARY CONSTRUCTION SCHEDULE (See paragraph 5.3.2 of the Instructions to Tenderers - Part II) INDICATE SCHEDULE WITH BAR CHART WITH MAJOR ITEM DESCRIPTIONS AND TIME

MILESTONE DATES

ACTIVITY

CONSTRUCTION SCHEDULE

1

2

3 4 5 6 7 8 9 10

11

12

13

14

15 16

Page 22: CITY OF NEW WESTMINSTER · Wally Carter P.Eng Address: WEB Engineering Ltd. 4173 Dawson Street, Burnaby, B.C. V5C 4B3 Phone: 604-294-8588 Fax: 604-294-8580 2.0 Tender Documents 2.1

FT - PAGE 11 UNIT PRICE CONTRACT

Tenderer’s Initials __________

MMCD (2000)

Form of Tender - Appendix 3

Contract NWIT-13-23

2013 Capital Pavement Program EXPERIENCE OF SUPERINTENDENT AND PROJECT MANAGER (See paragraph 5.3.3 of the Instructions to Tenderers - Part I & II) Name / Title: _______________________________________________________________

Experience:

Dates: Project Name: Responsibility:

References:

Dates: Project Name: Responsibility:

References:

Name / Title: _______________________________________________________________

Experience:

Dates: Project Name: Responsibility:

References:

Dates: Project Name: Responsibility:

References:

Page 23: CITY OF NEW WESTMINSTER · Wally Carter P.Eng Address: WEB Engineering Ltd. 4173 Dawson Street, Burnaby, B.C. V5C 4B3 Phone: 604-294-8588 Fax: 604-294-8580 2.0 Tender Documents 2.1

FT - PAGE 12 UNIT PRICE CONTRACT

Tenderer’s Initials __________

MMCD (2000)

Form of Tender - Appendix 4 Contract NWIT-13-23

2013 Capital Pavement Program COMPARABLE WORK EXPERIENCE (See paragraph 5.3.4 of the Instructions to Tenderers - Part II)

PROJECT

OWNER/ CONTRACT NAME

PHONE NUMBER

WORK DESCRIPTION

VALUE ($)

Page 24: CITY OF NEW WESTMINSTER · Wally Carter P.Eng Address: WEB Engineering Ltd. 4173 Dawson Street, Burnaby, B.C. V5C 4B3 Phone: 604-294-8588 Fax: 604-294-8580 2.0 Tender Documents 2.1

FT - PAGE 13 UNIT PRICE CONTRACT

Tenderer’s Initials __________

MMCD (2000)

Form of Tender - Appendix 5 Contract NWIT-13-23

2013 Capital Pavement Program SUBCONTRACTORS (See paragraph 5.3.5 of the Instructions to Tenderers - Part II)

TENDER ITEM

TRADE SUBCONTRACTOR NAME

PHONE NUMBER

Page 25: CITY OF NEW WESTMINSTER · Wally Carter P.Eng Address: WEB Engineering Ltd. 4173 Dawson Street, Burnaby, B.C. V5C 4B3 Phone: 604-294-8588 Fax: 604-294-8580 2.0 Tender Documents 2.1

FT - PAGE 14 UNIT PRICE CONTRACT

Tenderer’s Initials __________

MMCD (2000)

Form of Tender - Appendix 6 Contract NWIT-13-23

2013 Capital Pavement Program FORCE ACCOUNT LABOUR AND EQUIPMENT RATES (See paragraph 5.3.6 of the Instructions to Tenderers - Part I)

Labour and Equipment

Hourly Rate

Overtime Rate

Page 26: CITY OF NEW WESTMINSTER · Wally Carter P.Eng Address: WEB Engineering Ltd. 4173 Dawson Street, Burnaby, B.C. V5C 4B3 Phone: 604-294-8588 Fax: 604-294-8580 2.0 Tender Documents 2.1

FT - PAGE 15 UNIT PRICE CONTRACT

Tenderer’s Initials __________

MMCD (2000)

Form of Tender - Appendix 7 Contract NWIT-13-23

2013 Capital Pavement Program

Declaration – Living Wage Employer (See paragraph 5.3.7 of the Instructions to Tenderers - Part I & paragraph 4.2 of the Additional Instruction to Tenderers – Part

I)

I, ______________________ as a duly authorized signing officer of Company: ________________________ Address: _________________________ _________________________ _________________________, confirm that all employees and sub-contractors under our contract with the City as outlined below, are paid not less than the “Living Wage” as calculated by the Living Wage for Families Campaign. I understand that this requirement extends only to those employees and sub-contractors’ employees that perform work while on City premises and property for the durations in excess of one continuous hour per occasion. I understand that the City will conduit audits if and when notification of the breach of this compliance is received by the City. I understand that in the event any breach of this declaration is found to be true, the City reserves the right to cancel its contract without penalty at any time once said authentication of the breach is made. Contract Name: ______________________________ Authorized Signatory: Dated: __________________________ _______________________

Page 27: CITY OF NEW WESTMINSTER · Wally Carter P.Eng Address: WEB Engineering Ltd. 4173 Dawson Street, Burnaby, B.C. V5C 4B3 Phone: 604-294-8588 Fax: 604-294-8580 2.0 Tender Documents 2.1

FT - PAGE 16 UNIT PRICE CONTRACT

Tenderer’s Initials __________

MMCD (2000)

Form of Tender - Appendix 8 Contract NWIT-13-23

2013 Capital Pavement Program

TENDERER’S PLANT (See paragraph 5.3.8 of the Instructions to Tenderers - Part I )

The Tenderer agrees that the minimum availability of plant and equipment will be as listed and that no changes, additions or deletions will be made to this plant and equipment without approval of the Contract Administrator. The Tenderer shall list the plant and equipment he proposes to use on the Work: Plant Under Tenderer’s Control: Plant to be Rented: Plant to be Purchased:

Page 28: CITY OF NEW WESTMINSTER · Wally Carter P.Eng Address: WEB Engineering Ltd. 4173 Dawson Street, Burnaby, B.C. V5C 4B3 Phone: 604-294-8588 Fax: 604-294-8580 2.0 Tender Documents 2.1

AGREEMENT

Agreement Schedule 1 -- Schedule of Contract Documents Schedule 2 -- List of Drawings

Page 29: CITY OF NEW WESTMINSTER · Wally Carter P.Eng Address: WEB Engineering Ltd. 4173 Dawson Street, Burnaby, B.C. V5C 4B3 Phone: 604-294-8588 Fax: 604-294-8580 2.0 Tender Documents 2.1

AGT - PAGE 1 UNIT PRICE CONTRACT

MMCD (2000)

Agreement Between Owner and Contractor THIS AGREEMENT made in duplicate this day of , 2013.

Contract: 2013 Capital Pavement Program Reference No. Contract NWIT-13-23

BETWEEN:

The City of New Westminster (the "Owner")

AND:

( NAME AND OFFICE ADDRESS OF CONTRACTOR)

(the "Contractor")

The Owner and the Contractor agree as follows: ARTICLE 1 THE WORK - START/COMPLETION DATES 1.1 The Contractor will perform all Work and provide all labour, equipment and material and do all things strictly as required by the Contract Documents. 1.2 The Contractor will commence the Work in accordance with the Notice to Proceed. The Contractor will proceed with the Work diligently, will perform the Work generally in accordance with the construction schedules as required by the Contract Documents and will achieve Substantial Performance of the Work in Section A on or before 10 Weeks subject to the provisions of the Contract Documents for adjustments to the Contract Time. 1.3 Time shall be of the essence of the Contract.

Page 30: CITY OF NEW WESTMINSTER · Wally Carter P.Eng Address: WEB Engineering Ltd. 4173 Dawson Street, Burnaby, B.C. V5C 4B3 Phone: 604-294-8588 Fax: 604-294-8580 2.0 Tender Documents 2.1

AGT - PAGE 2 UNIT PRICE CONTRACT

MMCD (2000)

ARTICLE 2 CONTRACT DOCUMENTS 2.1 The "Contract Documents" consist of the documents listed or referred to in Schedule 1, entitled "Schedule of Contract Documents", which is attached and forms a part of this Agreement, and includes any and all additional and amending documents issued in accordance with the provisions of the Contract Documents. All of the Contract Documents shall constitute the entire Contract between the Owner and the Contractor. 2.2 The Contract supersedes all prior negotiations, representations or agreements, whether written or oral, and the Contract may be amended only in strict accordance with the provisions of the Contract Documents. ARTICLE 3 CONTRACT PRICE 3.1 The price for the Work ("Contract Price") shall be the sum in Canadian dollars of the following:

3.1a) the product of the actual quantities of the items of Work listed in the Schedule of Quantities and Prices which are incorporated into or made necessary by the Work and the unit prices listed in the Schedule of Quantities and Prices; plus

3.1b) all lump sums, if any, as listed in the Schedule of Quantities and Prices, for items relating to

or incorporated into the Work; plus

3.1c) any adjustments, including any payments owing on account of Changes and agreed to Extra Work, approved in accordance with the provisions of the Contract Documents.

3.2 The Contract Price shall be the entire compensation owing to the Contractor for the Work and this compensation shall cover and include all profit and all costs of supervision, labour, material, equipment, overhead, financing, and all other costs and expenses whatsoever incurred in performing the Work. ARTICLE 4 PAYMENT 4.1 Subject to applicable legislation and the provisions of the Contract Documents, the Owner shall make payments to the Contractor. 4.2 If the Owner fails to make payments to the Contractor as they become due in accordance with the terms of the Contract Documents then interest calculated at 0% per annum over the prime commercial lending rate of the Royal Bank of Canada on such unpaid amounts shall also become due and payable until payment. Such interest shall be calculated and added to any unpaid amounts monthly. ARTICLE 5 RIGHTS AND REMEDIES 5.1 The duties and obligations imposed by the Contract Documents and the rights and remedies available thereunder shall be in addition to and not a limitation of any duties, obligations, rights and remedies otherwise imposed or available by law. 5.2 Except as specifically set out in the Contract Documents, no action or failure to act by the Owner, Contract Administrator or Contractor shall constitute a waiver of any of the parties' rights or duties afforded under the Contract, nor shall any such action or failure to act constitute an approval of or acquiescence in any breach under the Contract.

Page 31: CITY OF NEW WESTMINSTER · Wally Carter P.Eng Address: WEB Engineering Ltd. 4173 Dawson Street, Burnaby, B.C. V5C 4B3 Phone: 604-294-8588 Fax: 604-294-8580 2.0 Tender Documents 2.1

AGT - PAGE 3 UNIT PRICE CONTRACT

MMCD (2000)

ARTICLE 6 NOTICES 6.1 Communications among the Owner, the Contract Administrator and the Contractor, including all written notices required by the Contract Documents, may be delivered by hand, or by fax, or by pre-paid registered mail to the addresses as set out below: The Owner:

City of New Westminster 511 Royal Avenue New Westminster, V3L 1H9

Fax: (604) 527-4564 Attention: Roger Emanuels, A.Sc.T. The Contractor:

Fax: Attention:

The Contract Administrator:

WEB Engineering Ltd. 4173 Dawson Street Burnaby, BC V5C 4B3 Fax: 604.294.8580 Attention: Wally Carter P.Eng

6.2 A communication or notice that is addressed as above shall be considered to have been received:

6.2a) immediately upon delivery, if delivered by hand; or

6.2b) immediately upon transmission if sent and received by fax; or

6.2c) after 5 Days from date of posting if sent by registered mail. 6.3 The Owner or the Contractor may, at any time, change its address for notice by giving written notice to the other at the address then applicable. Similarly if the Contract Administrator changes its address for notice then the Owner will give or cause to be given written notice to the Contractor. 6.4 The sender of a notice by fax assumes all risk that the fax will be received properly, and the provisions of paragraph 12.5 of the Instructions to Tenderers apply to the sender. ARTICLE 7 GENERAL 7.1 This Contract shall be construed according to the laws of British Columbia. 7.2 The Contractor shall not, without the express written consent of the Owner, assign this Contract, or any portion of this Contract.

Page 32: CITY OF NEW WESTMINSTER · Wally Carter P.Eng Address: WEB Engineering Ltd. 4173 Dawson Street, Burnaby, B.C. V5C 4B3 Phone: 604-294-8588 Fax: 604-294-8580 2.0 Tender Documents 2.1

AGT - PAGE 4 UNIT PRICE CONTRACT

MMCD (2000)

7.3 The headings included in the Contract Documents are for convenience only and do not form part of this Contract and will not be used to interpret, define or limit the scope or intent of this Contract or any of the provisions of the Contract Documents. 7.4 A word in the Contract Documents in the singular includes the plural and, in each case, vice versa. 7.5 This agreement shall endure to the benefit of and be binding upon the parties and their successors, executors, administrators and assigns. IN WITNESS WHEREOF the parties hereto have executed this Agreement the day and year first written above. Contractor: (FULL LEGAL NAME OF CORPORATION, PARTNERSHIP OR INDIVIDUAL) (AUTHORIZED SIGNATORY) (AUTHORIZED SIGNATORY) Owner: (FULL LEGAL NAME OF OWNER) (AUTHORIZED SIGNATORY) (AUTHORIZED SIGNATORY)

Page 33: CITY OF NEW WESTMINSTER · Wally Carter P.Eng Address: WEB Engineering Ltd. 4173 Dawson Street, Burnaby, B.C. V5C 4B3 Phone: 604-294-8588 Fax: 604-294-8580 2.0 Tender Documents 2.1

AGT - PAGE 5 UNIT PRICE CONTRACT

MMCD (2000)

Schedule 1 Schedule of Contract Documents (INCLUDE IN LIST ALL DOCUMENTS INCLUDING, IF ANY, SUPPLEMENTARY GENERAL CONDITIONS, SUPPLEMENTARY SPECIFICATIONS, SUPPLEMENTARY STANDARD DETAIL DRAWINGS)

2013 Capital Pavement Program Contract NWIT-13-23

The following is an exact and complete list of the Contract Documents, as referred to in Article 2.1 of the Agreement. NOTE: The documents noted with "*" are contained in the "Master Municipal Construction Documents -

General Conditions, Specifications and Standard Detail Drawings", Gold edition dated January, 2000. All sections of this publication are included in the Contract Documents.

1 Agreement, including all Schedules; 2 Supplementary General Conditions, if any; 3 General Conditions*; 4 Supplementary Specifications, if any; 5 Specifications*; 6 Supplementary Standard Detail Drawings, if any; 7 Standard Detail Drawings*; 8 Executed Form of Tender, including all Appendices; 9 Contract Drawings listed in Schedule 2 to the Agreement -"List of Contract Drawings"; 10 Instructions to Tenderers - Part I; 11 Instructions to Tenderers - Part II*; 12 The following Addenda: Addendum 1

Page 34: CITY OF NEW WESTMINSTER · Wally Carter P.Eng Address: WEB Engineering Ltd. 4173 Dawson Street, Burnaby, B.C. V5C 4B3 Phone: 604-294-8588 Fax: 604-294-8580 2.0 Tender Documents 2.1

AGT - PAGE 6 UNIT PRICE CONTRACT

MMCD (2000)

Schedule 2 List of Contract Drawings (COMPLETE LISTING OF ALL DRAWINGS, PLANS AND SKETCHES THAT ARE PART OF THE CONTRACT DOCUMENTS)

2013 Capital Pavement Program Contract NWIT-13-23

TITLE

DRAWING NO.

REV NO.

COVER SHEET

Road Works – Eighth Avenue : Sixth Street to STA. 22+640 1696-R-701 1

Road Works – Eighth Avenue : STA. 22+640 to McBride Boulevard 1696-R-702 1

Road Works – Sixth Avenue : Sixth Street to Fifth Street 1696-R-1001 1

Road Works – Royal Avenue : Fourth Street to Second Street 1696-R-1101 1

Road Works – Royal Avenue : Second Street to Dufferin Street 1696-R-1102 1

Road Works – Sixth Street : Tenth Avenue to Eighth Avenue 1696-R-501 1

Page 35: CITY OF NEW WESTMINSTER · Wally Carter P.Eng Address: WEB Engineering Ltd. 4173 Dawson Street, Burnaby, B.C. V5C 4B3 Phone: 604-294-8588 Fax: 604-294-8580 2.0 Tender Documents 2.1

SUPPLEMENTARY GENERAL CONDITIONS Supplementary General Conditions

Page 36: CITY OF NEW WESTMINSTER · Wally Carter P.Eng Address: WEB Engineering Ltd. 4173 Dawson Street, Burnaby, B.C. V5C 4B3 Phone: 604-294-8588 Fax: 604-294-8580 2.0 Tender Documents 2.1

City of New Westminster 2013 Capital Pavement Program

Contract NWIT-13-23

SUPPLEMENTARY GENERAL CONDITIONS

These Supplementary General Conditions must be read in conjunction with the General Conditions contained in the Master Municipal Construction Documents, Volume II, 1996( rev. April 2000)

Page SGC 1

TABLE OF CONTENTS Page 1 Definitions ............................................................................................................. SGC 2 4 Contractor ............................................................................................................ SGC 2 4.3 Protection of Work, Property and the Public ...................................... SGC 2 4.6 Hours of Work ..................................................................................... SGC 4 4.12 Inspections ............................................................................................ SGC 5 4.14 Final Cleanup ....................................................................................... SGC 5 4.17 Survey Layout and As-Constructed Information ................................ SGC 5 4.18 No Road Closure Allowed ................................................................... SGC 5 4.19 City Industrial Health and Safety Program ......................................... SGC 6 9 Valuation of Changes and Extra Work ........................................................... SGC 6 9.4 Quantity Variations .............................................................................. SGC 6 20 Laws, Notice, Permits and Fees.......................................................................... SGC 6 20.2.3 Notice of FortisBC Gas Relocation Work .......................................... SGC 6 20.5.1 Notice to Residents and Businesses .................................................... SGC 7 21 Workers’ Compensation ..................................................................................... SGC 7 21.2 Contractor is Prime Contractor ............................................................ SGC 7 24 Insurance ........................................................................................................... SGC 12 24.1 Required Insurance ............................................................................ SGC 12 25 Maintenance Period ........................................................................................... SGC 13 25.1 Correction of Defects ......................................................................... SGC 13 25.2 Commencement of Maintenance Period ........................................... SGC 14

Page 37: CITY OF NEW WESTMINSTER · Wally Carter P.Eng Address: WEB Engineering Ltd. 4173 Dawson Street, Burnaby, B.C. V5C 4B3 Phone: 604-294-8588 Fax: 604-294-8580 2.0 Tender Documents 2.1

City of New Westminster 2013 Capital Pavement Program

Contract NWIT-13-23

SUPPLEMENTARY GENERAL CONDITIONS

These Supplementary General Conditions must be read in conjunction with the General Conditions contained in the Master Municipal Construction Documents, Volume II, 1996( rev. April 2000)

Page SGC 2

DEFINITIONS 1

1.65 “(amend clause X.XX as follows)” preceding a supplementary

clause means this clause provides additional information or restrictions to the referenced clause in the Master Municipal Construction Documents, Volume II.

1.66 “(add new clause X.XX as follows)” preceding a supplementary

clause means this clause provides additional requirements or information not found in the Master Municipal Construction Documents, Volume II.

1.67 “(delete clause X.XX and replace as follows)” preceding a supplementary clause means this clause replaces the referenced clause in the Master Municipal Construction Documents, Volume II in its entirety.

CONTRACTOR 4

Protection of Work,

Property and the Public

4.3 4.3.7 (add new clause 4.3.7 as follows) The Contractor shall locate, mark and protect from damage or disturbance, any and all stakes, survey pins, monuments and markers at the Place of the Work. All survey stakes, pins, monuments or markers that, in the opinion of the Owner, have been damaged or disturbed shall be made good following construction by a registered B.C. Land Surveyor at the Contractor’s expense. 4.3.8 (add new clause 4.3.8 as follows) The Contractor shall conduct his operations so as to cause the minimum obstruction and inconvenience to traffic and to places of business and residences adjacent to the Place of Work. No greater quantity of work shall be undertaken at any one time than can be properly conducted with due regard to the rights and interests of the public as may be determined by the Contract Administrator. The Contractor is to provide safe, satisfactory and convenient means of approach and entrance to adjoining lanes, driveways,

Page 38: CITY OF NEW WESTMINSTER · Wally Carter P.Eng Address: WEB Engineering Ltd. 4173 Dawson Street, Burnaby, B.C. V5C 4B3 Phone: 604-294-8588 Fax: 604-294-8580 2.0 Tender Documents 2.1

City of New Westminster 2013 Capital Pavement Program

Contract NWIT-13-23

SUPPLEMENTARY GENERAL CONDITIONS

These Supplementary General Conditions must be read in conjunction with the General Conditions contained in the Master Municipal Construction Documents, Volume II, 1996( rev. April 2000)

Page SGC 3

buildings and property both for vehicles and pedestrians wherever necessary in the opinion of the Contract Administrator. For this purpose he shall construct and maintain suitable and safe platforms, approaches, structures, bridges, diversions or other works. Where traffic must cross open trenches, the Contractor shall provide suitable bridges. Where trenches have been backfilled or where road improvements are incomplete, the Contractor shall take any steps necessary to prevent potholes or other traffic hazards. Where the Contract Administrator so instructs or where Contract Specifications so require, the Contractor shall provide temporary asphalt patching of such hazards. During all phases of the operation the Contractor shall take precautions to abate nuisance caused by mud or dust by clean-up, sweeping, sprinkling with water, or other means as necessary to accomplish results satisfactory to the Contract Administrator. The Contractor shall take care to prevent spillage on streets over which hauling is done and the Contractor shall immediately clean up any such spillage or debris deposited on streets due to his operations. The Contractor shall not deposit any material upon any street, sidewalk, boulevard, or other property, without the Contract Administrator’s or the Owner’s permission, nor shall he allow the same to remain longer than necessary. All surplus spoil and rubbish and other waste material shall be removed from the site so that the area of work is cleaned up and restored to as clean a condition as it was before the Contract started, within four days of the Contract Administrator’s written request so to do, failing which the Owner may carry out the work or have the work carried out by others and recover the costs from the Contractor or may deduct the cost from any monies due or that may become due to the Contractor. The Contractor, during the progress of the Work, shall make adequate provision to accommodate the normal traffic along streets and highways immediately adjacent to or crossing the Work so as to cause the minimum of inconvenience to the general public.

Page 39: CITY OF NEW WESTMINSTER · Wally Carter P.Eng Address: WEB Engineering Ltd. 4173 Dawson Street, Burnaby, B.C. V5C 4B3 Phone: 604-294-8588 Fax: 604-294-8580 2.0 Tender Documents 2.1

City of New Westminster 2013 Capital Pavement Program

Contract NWIT-13-23

SUPPLEMENTARY GENERAL CONDITIONS

These Supplementary General Conditions must be read in conjunction with the General Conditions contained in the Master Municipal Construction Documents, Volume II, 1996( rev. April 2000)

Page SGC 4

The Contractor shall give due notice to local police and fire department prior to beginning construction and shall comply in all respects with their requirements. The Contractor shall comply with the requirements of the appropriate authority concerned with closure of streets or highways and shall post proper notices and/or signals, and provide necessary barriers, guards, lights, flagmen or watchmen as may be necessary for proper maintenance of traffic and protection of persons and property from injury or damage. All costs involved in respect of the above requirements will be deemed to be included in the Contract Price. Where existing streets or roads are not available as detours, all traffic shall be permitted to pass through the Work with as little inconvenience and delay as possible unless otherwise provided or authorized. If half the street only is under improvement, the other half shall be conditioned and maintained as detour. Where construction is to be carried out on highways or properties other than those of the Owner it shall be the responsibility of the Contractor to familiarize himself with the requirements of the owners or controllers of these properties which pertain to traffic safety or control of the construction operation and to carry out his work in accordance with these requirements.

Hours of Work

4.6 4.6.7 (add new clause 4.6.7 as follows)

Hours of work are regulated by the City’s Construction Noise Bylaw. The Contractor shall not schedule work that will require inspection beyond an eight-hour day without the Contract Administrator’s prior approval. Any extra cost incurred by the Owner for work done outside of normal office hours may be deducted from the Contractor’s monthly payments. On the infrequent occasion that the Contractor finds it necessary to work on Saturday, Sunday or Statutory Holiday, he shall obtain the Engineer’s approval forty eight (48) hours in advance. Work on Sundays or Statutory Holidays will also require City approval, with minimum two weeks notice. The Contractor shall also be

Page 40: CITY OF NEW WESTMINSTER · Wally Carter P.Eng Address: WEB Engineering Ltd. 4173 Dawson Street, Burnaby, B.C. V5C 4B3 Phone: 604-294-8588 Fax: 604-294-8580 2.0 Tender Documents 2.1

City of New Westminster 2013 Capital Pavement Program

Contract NWIT-13-23

SUPPLEMENTARY GENERAL CONDITIONS

These Supplementary General Conditions must be read in conjunction with the General Conditions contained in the Master Municipal Construction Documents, Volume II, 1996( rev. April 2000)

Page SGC 5

charged a working day and will be charged the overtime inspection costs incurred by the Owner. Such costs shall be deducted from monthly progress payments.

Inspections 4.12 4.12.1 (delete clause 4.12.1 and replace as follows)

The Owner will pay for the cost of any testing required under this contract or ordered by the Contract Administrator. The Contractor shall furnish at his expense any labour, equipment, and materials required to obtain representative samples of materials or workmanship incorporated into the Work. Where tests or inspections reveal workmanship or materials not in compliance with contract specifications, the Contractor shall pay for the cost of all additional tests ordered by the Contract Administrator to verify acceptability of corrected work. Extensions to the Contract Time shall not be allowed for any delay occasioned by the above requirement.

Final Cleanup 4.14 4.14 (amend clause 4.14 as follows)

All streets affected by work shall be power swept and made dirt, gravel and grit free.

Survey Layout and

As-Constructed Information

4.17 4.17.1 (add new clause 4.17.1 as follows) The Contractor is responsible for all survey required for construction layout and for record drawings associated with this contract. The Contractor shall be responsible for recording of all field survey information pertaining to the as-constructed drawings, including wye locations, depths and locations of service connections, valve and hydrant locations, etc. The Contractor shall provide, at no charge, a completed set of legible, marked-up as-constructed prints to the Contract Administrator on completion of the Work. The Contractor shall provide any additional information as requested to enable the Contractor Administrator to prepare and submit as-constructed record drawings to the Municipality or the Owner for their records.

No Road Closure

Allowed

4.18 4.18.1 (add new clause 4.18.1 as follows) Total road closure in this Contract will not be allowed. Minimum single lane traffic in both directions must be maintained at all times, and proper traffic control standards shall be enforced. On streets where construction is to take place, the Contractor will be required to post signs at each end of the project warning motorists

Page 41: CITY OF NEW WESTMINSTER · Wally Carter P.Eng Address: WEB Engineering Ltd. 4173 Dawson Street, Burnaby, B.C. V5C 4B3 Phone: 604-294-8588 Fax: 604-294-8580 2.0 Tender Documents 2.1

City of New Westminster 2013 Capital Pavement Program

Contract NWIT-13-23

SUPPLEMENTARY GENERAL CONDITIONS

These Supplementary General Conditions must be read in conjunction with the General Conditions contained in the Master Municipal Construction Documents, Volume II, 1996( rev. April 2000)

Page SGC 6

to expect delays and advising alternative routes should be used.

City Industrial Health

and Safety Program

4.19

4.19 (add new clause 4.19 as follows) 4.19.1 All contractors working for the City of New Westminster are required to be aware of the City’s Industrial Health and Safety Program. It is the Contractor / Subcontractor’s responsibility to perform the job in compliance with the City’s safety standards. The Contractor / Subcontractor is responsible for the compliance of all employees for whom he is primarily responsible, with all WSBC Industrial Health and Safety Regulations, as well as all other applicable Regulations. 4.19.2 As a Contractor / Subcontractor signing a contract with the City, you are agreeing that your Company, Management Staff, Supervisory Staff and workers will comply with our Industrial Health and Safety Program. This is binding while you are on any City work site. 4.19.3 An infraction not immediately corrected, as directed by the contracting City Department, will result in the Contractor / Subcontractor being advised of a breach of contract and advised of action, which will be taken. It must be definitely established that all workers on the job, including all Subcontractor’s employees, are informed of our safety program. Copies of the City’s Industrial Health and Safety Program may be obtained at Engineering Operations, 901 – 1st Street.

VALUATION OF CHANGES AND EXTRA WORK

9 9.4 (delete GC 9.4.1 and substitute the following) 9.4.1 The Contractor shall hold firm all unit prices submitted in

the Schedule of Quantities and Prices regardless of the increase or decrease in quantities.

LAWS, NOTICE,

PERMITS AND FEES

20

20.2 (add new clause 20.2.3 as follows) 20.2.3 The Contractor shall give FortisBC Gas three weeks notice and shall allow two weeks for any relocation work when crossing a FortisBC Gas line.

Page 42: CITY OF NEW WESTMINSTER · Wally Carter P.Eng Address: WEB Engineering Ltd. 4173 Dawson Street, Burnaby, B.C. V5C 4B3 Phone: 604-294-8588 Fax: 604-294-8580 2.0 Tender Documents 2.1

City of New Westminster 2013 Capital Pavement Program

Contract NWIT-13-23

SUPPLEMENTARY GENERAL CONDITIONS

These Supplementary General Conditions must be read in conjunction with the General Conditions contained in the Master Municipal Construction Documents, Volume II, 1996( rev. April 2000)

Page SGC 7

Notice to Residents and Businesses

20.5.1 (add new clause 20.5.1 as follows) The Contractor shall supply copies of letters advising affected residents and business premises. The Contractor shall be responsible for delivering these letters no sooner than seven days and no later than two days before the start of construction.

Workers’ Compensation

21

Contractor is Prime Contractor

21.2 21.2 (delete 21.2 and replace with the following) The Contractor agrees that it shall, at its own expense, procure and carry or cause to be procured and carried and paid for, full Workers’ Compensation Board coverage for itself and all workers, employees, servants and others engaged in or upon any work or service which is the subject of this contract. The Contractor agrees that the Owner has the unfettered right to set off the amount of the unpaid premiums and assessments for such Workers’ Compensation Board coverage against any monies owing by the Owner to the Contractor. The Owner shall have the right to withhold payment under this contract until the Workers’ Compensation Board premiums, assessments or penalties in respect of work done or service performed in fulfilling this contract have been paid in full.

The Contractor agrees that it is the “Prime Contractor” for the purposes of the Workers’ Compensation Board Occupational Health and Safety Regulation for the Province of British Columbia. The Contractor shall have a safety program that meets the requirements of the Workers’ Compensation Board, shall provide first aid services, and shall ensure that all Workers’ Compensation safety rules and regulations are observed during performance of this contract, not only by the Contractor but by all subcontractors, workers, material personnel and others engaged in the performance of this contract. Prior to commencement of construction, the Contractor shall complete and file a “Construction Notice of Project” with the Workers’ Compensation Board and shall

Page 43: CITY OF NEW WESTMINSTER · Wally Carter P.Eng Address: WEB Engineering Ltd. 4173 Dawson Street, Burnaby, B.C. V5C 4B3 Phone: 604-294-8588 Fax: 604-294-8580 2.0 Tender Documents 2.1

City of New Westminster 2013 Capital Pavement Program

Contract NWIT-13-23

SUPPLEMENTARY GENERAL CONDITIONS

These Supplementary General Conditions must be read in conjunction with the General Conditions contained in the Master Municipal Construction Documents, Volume II, 1996( rev. April 2000)

Page SGC 8

provide a copy of the same to the Contract Administrator confirming that the Contractor shall be the Prime Contractor responsible for coordination of safety and health under 20.2 - Notice of Project; 20.3 - Coordination of Multiple Employer The Contractor shall provide the Owner with the Contractor’s Workers’ Compensation Board registration number and letter from the Workers’ Compensation Board confirming that the Contractor is registered in good standing with the Workers’ Compensation Board and that all assessments have been paid to the date thereof prior to the Owner having any obligation to pay monies under this contract. The Contractor shall appoint a designated, qualified Coordinator to ensure the coordination of Health and Safety activities for the work locations, provide assurance of a written safety program in accordance with the Occupational Health & Safety Regulation, and to conduct weekly toolbox safety meetings and monthly formal safety meetings. The safety program, all written safe work procedures and site maps are to be available at the work site prior to the commencement of the work.

The Contractor shall indemnify the Owner and hold harmless the Owner from all manner of claims, demands, costs, losses, sanctions and penalties and proceedings arising out of, or in any way related to, unpaid Workers’ Compensation Board assessments owing from any person or corporation engaged in the performance of this contract or arising out of or in any way related to the failure to observe safety rules, regulations and practices of the Workers’ Compensation Board, including penalties levied by the Workers’ Compensation Board. Occupational Health and Safety The Contractor and its employees and the Contractor’s sub-contractors and their employees shall conform to all current occupational health and safety laws, by-laws, or regulations of the Province of British Columbia including any regulations requiring installation or adoption of safety devices or appliances. The Owner may, on twenty-four (24) hours written

Page 44: CITY OF NEW WESTMINSTER · Wally Carter P.Eng Address: WEB Engineering Ltd. 4173 Dawson Street, Burnaby, B.C. V5C 4B3 Phone: 604-294-8588 Fax: 604-294-8580 2.0 Tender Documents 2.1

City of New Westminster 2013 Capital Pavement Program

Contract NWIT-13-23

SUPPLEMENTARY GENERAL CONDITIONS

These Supplementary General Conditions must be read in conjunction with the General Conditions contained in the Master Municipal Construction Documents, Volume II, 1996( rev. April 2000)

Page SGC 9

notice to the Contractor, suspend the work hereunder immediately as a result of failure to install such devices or because the conditions of immediate danger exist that would be likely to result in injury to any person. Such suspension will continue until the default or failure is corrected.

Without limiting the generality of any other indemnities granted by the Contractor herein, the Contractor shall indemnify and save harmless the Owner against any loss or expense or penalty suffered or incurred by the Owner by reason of failure of the Contractor, its agents or employees, or any sub-contractors of the Contractor, its agents or employees to comply or ensure compliance with the health and safety laws, by-laws and regulations mentioned above. Further, the Contractor warrants that it will not produce or discharge in any manner or form, directly or indirectly, chemicals or toxic substances and that all vehicles and equipment used will not pose a hazard to, or harm or adversely affect anyone coming into contact with them and covenants and agrees to provide the Owner with an environmental plan (where applicable), acceptable to the City of New Westminster, which plan shall outline the procedures to be followed by the Contractor to prevent the production or discharge of chemicals or toxic substances into the environment.

(a) The Contractor shall provide all his work in such a manner that it ensures safety, of the public and in accordance with the safety regulations of the Workers' Compensation Board.

(b) It is required that the Contractor understands and

undertakes to comply with all the W.C.B. Industrial Health and Safety Regulations for hazardous materials and substances namely, the new "Workplace Hazardous Materials Information Systems (WHMIS)" Regulations.

If you are unfamiliar with the Industrial Health and Safety Regulations covering hazardous materials and substances, in particular the WHMIS regulations, or if you are uncertain as to how they relate to the work you are performing for the City of

Page 45: CITY OF NEW WESTMINSTER · Wally Carter P.Eng Address: WEB Engineering Ltd. 4173 Dawson Street, Burnaby, B.C. V5C 4B3 Phone: 604-294-8588 Fax: 604-294-8580 2.0 Tender Documents 2.1

City of New Westminster 2013 Capital Pavement Program

Contract NWIT-13-23

SUPPLEMENTARY GENERAL CONDITIONS

These Supplementary General Conditions must be read in conjunction with the General Conditions contained in the Master Municipal Construction Documents, Volume II, 1996( rev. April 2000)

Page SGC 10

New Westminster on its premises/work site, we suggest you call the W.C.B. Head Office in Richmond during normal business hours - (8:30 a.m. - 4:30 p.m., Monday to Friday).

WHMIS INFORMATION RESEARCH AND STANDARDS DEPARTMENT W.C.B. Occupational Safety and Health Division 6951 Westminster Highway Richmond, BC V7C 1C6

APPENDIX “F” - RISK, HEALTH AND SAFETY (Responsibilities of Contractors) The City of New Westminster strives to maintain a safe work environment for employees and contractors and insists upon the enforcement of safe practices and procedures in all premises and in all work activities. It is essential that all contractors and their employees and subcontractors perform in the same manner. As a contractor to the City of New Westminster, you are expected to conform to the requirements of the Workers’ Compensation Act, the WCB Occupational Health and Safety Regulation and to all federal, provincial and local laws and regulations. Any City of New Westminster employee has the authority to order an unsafe act to cease or to have an unsafe piece of equipment removed from the premises or, in extreme situations, to shut down a job entirely. The following information is provided as typical City of New Westminster requirements, but does not relieve the contractor from complying with all applicable local, provincial and federal laws, regulations and bylaws. PERSONNEL 1. You are expected to inform your employees of any potential

hazard in the workplace and advise of appropriate action to be taken should a hazard be found or a fire or accident occur.

2. Contractors shall restrict persons invited on the premises to employees only. No families or friends are permitted.

Page 46: CITY OF NEW WESTMINSTER · Wally Carter P.Eng Address: WEB Engineering Ltd. 4173 Dawson Street, Burnaby, B.C. V5C 4B3 Phone: 604-294-8588 Fax: 604-294-8580 2.0 Tender Documents 2.1

City of New Westminster 2013 Capital Pavement Program

Contract NWIT-13-23

SUPPLEMENTARY GENERAL CONDITIONS

These Supplementary General Conditions must be read in conjunction with the General Conditions contained in the Master Municipal Construction Documents, Volume II, 1996( rev. April 2000)

Page SGC 11

3. The contractor shall advise the Owner of any on-site accidents

involving the contractor’s employees, or injuries to others caused by the contractor’s business.

GENERAL SAFETY RULES

1. Horseplay, gambling and the use of alcohol or narcotics will not be tolerated.

2. Orderliness and good housekeeping are basic requirements and must be maintained at all times.

3. Any equipment, which could create a hazard, must be

maintained in good condition.

4. Restricted and controlled products shall be labelled, used and stored in accordance with the associated regulations, e.g. WHMIS.

5. Contractors shall use a regular system of inspections to

detect and correct hazardous conditions, safety violations and unsafe working practices on the job site.

6. Contractors shall ensure their employees utilize proper

safety equipment and clothing as required for job site activities.

7. Contractors must follow and have on site proper written

safe work procedures for hazardous work, e.g. confined space entry, lockout, excavations and shoring, etc.

8. All ladders must be of an approved type and length.

Unacceptable ladders must be removed immediately from the premises.

9. All vehicles and equipment on City property must be kept

in safe mechanical condition at all times, and be operated only by persons with a valid driver’s license and/or proper training and qualifications.

10. Contractors shall not operate any equipment, valves,

Page 47: CITY OF NEW WESTMINSTER · Wally Carter P.Eng Address: WEB Engineering Ltd. 4173 Dawson Street, Burnaby, B.C. V5C 4B3 Phone: 604-294-8588 Fax: 604-294-8580 2.0 Tender Documents 2.1

City of New Westminster 2013 Capital Pavement Program

Contract NWIT-13-23

SUPPLEMENTARY GENERAL CONDITIONS

These Supplementary General Conditions must be read in conjunction with the General Conditions contained in the Master Municipal Construction Documents, Volume II, 1996( rev. April 2000)

Page SGC 12

switches, etc., which are part of the District’s operation, unless specific permission is received from the Owner representative.

11. Accumulation of oily rags, combustible refuse or similar

fire hazards will not be tolerated. Your safety record and attitude are important criteria used to judge your qualification for future bidding on contracts with the City of New Westminster. You can help ensure employee safety and your eligibility for future business with the Owner if you exhibit and practice a “Safe Word - Safe District” attitude.

INSURANCE 24

Required Insurance

24.1 24.1 (amend 24.1 as follows) In addition to the MMCD insurance requirements, the Contractor shall also comply with the following requirements, which will take precedence. 24.1.1 The Contractor shall insure and keep insured while this contract is in force, with such companies and on such forms as are acceptable to the Owner, at the Contractor’s expense. Comprehensive General Liability Insurance covering premises and operations liability; Contractor’s Contingency Liability with respect to the operations of Subcontractor’s Completed Operations Liability, Contractual Liability and Non-Owned Automobile Liability Insurance. “(replace 24.1.1 (a) with the following) The limits of liability for Personal Injury and Property Damage combined shall be for not less than $5,000,000 each occurrence. “(add to 24.1.1 (b) as follows)” The Owner shall be added as an additional named insured under the Comprehensive General Liability. A Cross Liability Clause shall be made part of the Comprehensive General Liability Insurance.

Page 48: CITY OF NEW WESTMINSTER · Wally Carter P.Eng Address: WEB Engineering Ltd. 4173 Dawson Street, Burnaby, B.C. V5C 4B3 Phone: 604-294-8588 Fax: 604-294-8580 2.0 Tender Documents 2.1

City of New Westminster 2013 Capital Pavement Program

Contract NWIT-13-23

SUPPLEMENTARY GENERAL CONDITIONS

These Supplementary General Conditions must be read in conjunction with the General Conditions contained in the Master Municipal Construction Documents, Volume II, 1996( rev. April 2000)

Page SGC 13

“(add new 24.1.7 as follows)” All policies shall provide that they cannot be cancelled, lapsed, or materially changed without at least thirty (30) days notice to the Owner by Registered Mail. Prior to commencement of any work hereunder, the Contractor shall file with the Owner a certificate of insurance for each policy required. All such insurance shall be maintained until final completion of the work including the making good of faulty work or materials, except that coverage for completed operations liability shall in any event be maintained for twelve (12) months from date of final acceptance. Should the contractor neglect to obtain and/or maintain insurance as aforesaid, or deliver such policy or policies to the Owner, then the Owner shall obtain and/or maintain such insurance and the Contractor hereby appoints the Owner its true and lawful attorney to do all things necessary for this purpose. All monies expended by the Owner for Insurance premiums under the provisions of this clause shall be charged to the Contractor. 24.1.8 “(add new clause 24.1.8 as follows)” The Contractor shall ensure the following are additional named insured under this contract: City of New Westminster All Sub-Contractors WEB Engineering Ltd.

MAINTENANCE

PERIOD 25

Correction of Defects

25.1

25.1.4 (add new clause 25.1.4 as follows) The Owner is authorized to make repairs to defects or deficiencies if, ten days after giving written notice, the Contractor has failed to make or undertake with due diligence the required repairs. However, in the case of emergency where, in the opinion of the Owner, delay is not reasonable, repairs may be made without notice being sent to the Contractor. All expenses incurred by the Owner in connection with repairs made pursuant to GC 25 shall be paid by the Contractor and may be deducted from the Maintenance Security, or other holdbacks. The Contractor shall

Page 49: CITY OF NEW WESTMINSTER · Wally Carter P.Eng Address: WEB Engineering Ltd. 4173 Dawson Street, Burnaby, B.C. V5C 4B3 Phone: 604-294-8588 Fax: 604-294-8580 2.0 Tender Documents 2.1

City of New Westminster 2013 Capital Pavement Program

Contract NWIT-13-23

SUPPLEMENTARY GENERAL CONDITIONS

These Supplementary General Conditions must be read in conjunction with the General Conditions contained in the Master Municipal Construction Documents, Volume II, 1996( rev. April 2000)

Page SGC 14

promptly pay any shortfall.

Commencement of Maintenance

Period

25.2 25.2.2 (add new clause 25.2.2 as follows) All warranties under this Contract commence from the date of Substantial Performance of the Contract, regardless of whether any Subcontractor achieves Substantial Performance of its Subcontract prior to Substantial Performance of the Contract as a whole.

Page 50: CITY OF NEW WESTMINSTER · Wally Carter P.Eng Address: WEB Engineering Ltd. 4173 Dawson Street, Burnaby, B.C. V5C 4B3 Phone: 604-294-8588 Fax: 604-294-8580 2.0 Tender Documents 2.1

SUPPLEMENTARY SPECIFICATIONS Supplementary Specifications

Page 51: CITY OF NEW WESTMINSTER · Wally Carter P.Eng Address: WEB Engineering Ltd. 4173 Dawson Street, Burnaby, B.C. V5C 4B3 Phone: 604-294-8588 Fax: 604-294-8580 2.0 Tender Documents 2.1

City of New Westminster 2013 Capital Pavement Program

Contract NWIT-13-23

SUPPLEMENTARY SPECIFICATIONS

NWIT-13-23 SSP Page SS 1

TABLE OF CONTENTS SS 1 Scope of Work SS 2 Contract Time SS 3 Definitions SS 4 Temporary No Parking SS 5 Photographic Records SS 6 Cellular Phone for Site Inspector SS 7 Storm Water Quality Protection SS 8 Replace and Adjust Manhole Cover SS 9 Cold Milling: Milling Operation SS 10 Asphalt Pavement Unit Price Adjustment SS 11 Superpave Asphalt Mix and Paving SS 12 Traffic Loop Detector Replacement SS 13 Crushed Granular Subbase and Granular Base SS 14 Permanent Pavement Markings SS 15 Fibre Optic Cable SS 16 Traffic Management Plan SS 17 Pavement Patching SS 18 Test Holes along existing Metro Vancouver Mains (Provisional) SS 19 Warm Mix Asphalt (WMA) APPENDICIES: A: Construction Work Restrictions B: List of Possible Projects C: Metro Testing Core Reports

Page 52: CITY OF NEW WESTMINSTER · Wally Carter P.Eng Address: WEB Engineering Ltd. 4173 Dawson Street, Burnaby, B.C. V5C 4B3 Phone: 604-294-8588 Fax: 604-294-8580 2.0 Tender Documents 2.1

City of New Westminster 2013 Capital Pavement Program

Contract NWIT-13-23

SUPPLEMENTARY SPECIFICATIONS

NWIT-13-23 SSP Page SS 2

SS 1 Scope of Work

This Contract involves road works which includes road reconstruction, pavement patching, asphalt milling, and paving on various streets in the City of New Westminster. These works are funded under the Capital Works Program.

A List of Possible Projects with a Preliminary Pavement Strategy (based on limited visual and sub-surface information) for each is appended to these Supplementary Specifications. The Engineer will confirm pavement strategies in the field prior to commencement of work. Field adjustments to strategies during construction can be expected as subsurface information is reviewed.

Projects may be added, deleted or modified by the City without penalty. The Construction schedule will need to be flexible to allow coordination with other projects.

SS 2 Contract Time

The Work under Section A of this Contract shall be completed no later than 10 Weeks from the Commencement Date.

SS 3 Definitions

In these Supplementary Specifications, unless the context otherwise requires, “Section” means section of the Specifications or the Conditions of Contract. “Item” means item of the Schedule of Quantities and Prices.

SS 4 Temporary No Parking

Add new clause 1.4.5 to Section 01570 1.4, Control of Public Traffic.

.5 Where it is necessary to temporarily disrupt on-street parking for construction, .1 distribute 48-hour advance notice to residents. .2 supply and erect temporary “no-parking” signs. .3 do not impound parked vehicles unless instructed to do so by police or

by-law officer. .4 vehicles may be towed at Contractor’s risk and expense to a nearby

location. Inform registered owner as soon as possible as to the location of vehicle. Do not charge vehicle recovery or towing fees to vehicle owner.

Page 53: CITY OF NEW WESTMINSTER · Wally Carter P.Eng Address: WEB Engineering Ltd. 4173 Dawson Street, Burnaby, B.C. V5C 4B3 Phone: 604-294-8588 Fax: 604-294-8580 2.0 Tender Documents 2.1

City of New Westminster 2013 Capital Pavement Program

Contract NWIT-13-23

SUPPLEMENTARY SPECIFICATIONS

NWIT-13-23 SSP Page SS 3

SS 5 Photographic Records

Add the following to Section 01721 – 1.7; Recording Actual Site Conditions. .5 The Contractor shall have dated photos of each site taken prior to starting

work on the project. Compile photos into binders or provide on digital compact disks for the project records. Provide copy of the photos to the Contract Administrator.

SS 6 Cellular Phone for Site Inspector

Add the following new clause to Section 01535 – 1.8 Temporary Telephone. .2 The Contractor shall provide a cellular telephone for the exclusive use of

the Site Inspector until all Work under this Contract is completed. All costs associated with the phone are the responsibility of the Contractor.

SS 7 Storm Water Quality Protection

Prior to either asphalt milling or application of asphaltic tack coat, install a piece of filter fabric (catchbasin sock) between the catchbasin grate and frame so that foreign materials (asphalt millings, liquid tack coat, asphalt, etc) do not enter the catchbasin during construction. Where construction is adjacent open watercourses, install silt fences, check dams and hay bales (as appropriate) to control silt from worksite. There is no separate payment for this work.

Page 54: CITY OF NEW WESTMINSTER · Wally Carter P.Eng Address: WEB Engineering Ltd. 4173 Dawson Street, Burnaby, B.C. V5C 4B3 Phone: 604-294-8588 Fax: 604-294-8580 2.0 Tender Documents 2.1

City of New Westminster 2013 Capital Pavement Program

Contract NWIT-13-23

SUPPLEMENTARY SPECIFICATIONS

NWIT-13-23 SSP Page SS 4

SS 8 Replace And Adjust Manhole Cover ( Item 4.13 )

.1 Adjust manhole covers to finished paving grades.

.2 Cast Iron Riser Rings are not permitted.

.3 Measurement for payment per following descriptions:

Frame and Cover Adjustment (Item 4.13.1)

Remove existing cast iron frame and cover, concrete / brick risers. Clean concrete doughnut to remove all old mortar. Add new IPEX “Lifesaver” PE risers. Re-install cast iron frame and cover to meet new grade, profile and cross-fall. If required, add ladder rungs to suit Worksafe BC Requirements (Ladder rungs not included in unit price).

Frame and Cover Replacement (Item 4.13.2)

Remove existing cast iron frame and cover, concrete / brick risers. Clean concrete doughnut to remove all old mortar. Add new IPEX “Lifesaver” PE risers and Muller AJ633 Adjustable Frame and Cover to new grades. If required, add ladder rungs to suit Worksafe BC Requirements (Ladder rungs not included in unit price).

Payment will be made at the unit price bid for each manhole modified as described above.

Page 55: CITY OF NEW WESTMINSTER · Wally Carter P.Eng Address: WEB Engineering Ltd. 4173 Dawson Street, Burnaby, B.C. V5C 4B3 Phone: 604-294-8588 Fax: 604-294-8580 2.0 Tender Documents 2.1

City of New Westminster 2013 Capital Pavement Program

Contract NWIT-13-23

SUPPLEMENTARY SPECIFICATIONS

NWIT-13-23 SSP Page SS 5

SS 9 Cold Milling: Milling Operation (Item 4.16)

MMCD Section 02574 is modified by addition of the following to sub-section 3.4, Milling Operation The following applies to all asphalt milling including surface milling and full depth milling listed under Schedule of Quantities and Prices item 4.16. .7 All manhole rims, valve covers, utility cover lids, wheelchair letdowns,

and butt joints to adjacent road sections must have a temporary asphalt ramp from the top of existing road to the milled surface of sufficient length to prevent damage to vehicular and / or pedestrian traffic. The ramps are to be removed immediately prior to paving.

.8 For surface milling operations, pavement patch or repair any section

where gravel base is exposed (break-through) prior to end of working day and opening road to traffic.

.9 For full depth milling operation, at least asphalt base lift prior to end of

working day and opening road to traffic, unless approved otherwise by the City.

.10 The Contractor may mill asphalt over areas to be excavated to facilitate

the work. There will be no separate measurement for this work under Item 4.16. Measurement and Payment to be included in Common Excavation.

SS 10 Asphalt Pavement Unit Price Adjustment (Item 4.10)

The Contractor or the Owner may request adjustment of the unit prices submitted for Asphalt Pavement (Schedule of Quantities and Prices Item 4.10) if the Composite Rack Posting (CRP) varies by more than 5.0% from Tender Closing Date to the time the asphalt paving is actually performed. The CRP is a composite of the available Rack Postings for PG 64-22 FOB Langley BC. Requests for asphalt pavement unit price adjustment must be made prior to commencing asphalt paving. Payment for asphalt paving performed prior to a request for price adjustment will be made at the unit price submitted in Schedule

Page 56: CITY OF NEW WESTMINSTER · Wally Carter P.Eng Address: WEB Engineering Ltd. 4173 Dawson Street, Burnaby, B.C. V5C 4B3 Phone: 604-294-8588 Fax: 604-294-8580 2.0 Tender Documents 2.1

City of New Westminster 2013 Capital Pavement Program

Contract NWIT-13-23

SUPPLEMENTARY SPECIFICATIONS

NWIT-13-23 SSP Page SS 6

of Quantities and Prices Item 4.10 plus any previous adjustments made under this Supplementary Specification (Project). Unit prices submitted under Item 4.10 will be increased or decreased as applicable using the following formula: Adjustment = (CRP work - CRP tender) x AC volume

Adjustment amount in dollars per tonne the unit price is modified CRP work is the CRP at the time paving is performed CRP tender is the CRP at the Tender Closing Date AC volume is the mixture design percent asphalt content, by volume

SS 11 Superpave Asphalt Mix And Paving ( Item 4.10)

1.0 General Add new clause 1.0.2 and new clause 1.03

.2 This Section applies to mix Superpave designs for “design traffic load of 3 to less than 30 million ESAL”. If a higher design traffic is specified, the publication “Superpave Level 1 Mix Design – Superpave Series No. 2 (SP-2)” must be used.

.3 All mix to be Warm Mix Asphalt (WMA). Maximum 10% RAP

permitted in WMA mixes. 1.2 References Add new clause 1.2.2

.2 “Superpave Level 1 Mix Design – Superpave Series No. 2 (SP-2)” and C-SHRP Technical brief # 17.

2.0 Products Replace Section 2.0 with: 2.1 Materials

.1 Mineral Aggregates as described in Chapter 3 of “Superpave Level 1 Mix Design – Superpave Series No. 2 (SP-2)”

.2 Asphalt cement to meet or exceed Performance Grade PG 62 -22.

Submit test results confirming conformance with the PG specification.

Page 57: CITY OF NEW WESTMINSTER · Wally Carter P.Eng Address: WEB Engineering Ltd. 4173 Dawson Street, Burnaby, B.C. V5C 4B3 Phone: 604-294-8588 Fax: 604-294-8580 2.0 Tender Documents 2.1

City of New Westminster 2013 Capital Pavement Program

Contract NWIT-13-23

SUPPLEMENTARY SPECIFICATIONS

NWIT-13-23 SSP Page SS 7

2.2 Mix Design

.1 Design of mix to follow Level 1 procedures as published in the current edition of Asphalt Institute Manual SP -2, Superpave Level 1 Mix Design. All procedures of Chapter 5 of the above mentioned publication are required, including Moisture Sensitivity.

.2 Provide gradation curve based on the results of at least five ( 5 )

samples for each aggregate type ( or stockpile ). .3 Superpave Design Gyratory Compactive effort to be based on

following criteria , unless modified by the Engineer: Number of Gyrations Initial 8 Design 100 Maximum 160

3.0 Execution 3.1 Plant and Mixing Requirements

.4 Mixing Tolerances Replace Clause 3.3.4 with:

.1 During plant production, the gradation of the asphalt mix aggregate shall be tested. Samples shall be obtained at the plant both prior to and after the addition of asphalt cement. Test results shall be made available within three ( 3 ) hours of sampling.

.2 During plant production, the mixture properties shall be within the

following tolerances of the design : Mixture Property Tolerance Asphalt Content 0.3 % Air Voids 1.0 % Voids filled with asphalt, % 65 - 75 Dust Proportion 0.6 - 1.2

.3 The Owner will conduct Quality Assurance testing. Quality Assurance

testing may be conducted at the hot mix plant. The Contractor shall provide 100 amp single phase 250 volt power outlet receptacle and space within 15 meters of the receptacle for mobile test equipment.

Page 58: CITY OF NEW WESTMINSTER · Wally Carter P.Eng Address: WEB Engineering Ltd. 4173 Dawson Street, Burnaby, B.C. V5C 4B3 Phone: 604-294-8588 Fax: 604-294-8580 2.0 Tender Documents 2.1

City of New Westminster 2013 Capital Pavement Program

Contract NWIT-13-23

SUPPLEMENTARY SPECIFICATIONS

NWIT-13-23 SSP Page SS 8

.11 Production Quality Control Plan Add new Clause 3.1.11

.1 A Production Quality Control Plan ( PQCP ) shall be submitted to the Engineer at least 7 days prior to paving. No paving will be permitted until the PQCP has been approved. As a minimum the PQCP shall include :

(a) monitoring procedures for stockpiles plant aggregate gradation

and consistency (b) asphalt cement content (b) tests required and frequency for Quality Control (c) time frame for test results during paving

.2 The Contractor shall employ qualified personnel, including at least

one certified technician to implement and oversee the PQCP.

3.6 Compaction Replace Clause 3.6.1 with:

.1 Roll asphalt continuously to density between 91.0% and 96.0% of the maximum theoretical density. Ninety percent ( 90% ) of a minimum five ( 5 ) samples shall meet this criteria. In addition, no individual test can be less than 89.0%.

.2 The Contractor is responsible for Quality Control. A Construction

Quality Control Plan ( CQCP ) shall be submitted to the Engineer 7 days prior to paving.

As a minimum, the CQCP shall include full details of:

(a) the paving equipment (b) number of trucks (c) rate of placement (d) contemplated rolling patterns (e) testing for control of density

3.7 Joints Add New Clause 3.7.1.4:

.4 Feather joints are not permitted. Construct butt joints at all locations

where meeting existing pavement. Surface milling for preparing butt

Page 59: CITY OF NEW WESTMINSTER · Wally Carter P.Eng Address: WEB Engineering Ltd. 4173 Dawson Street, Burnaby, B.C. V5C 4B3 Phone: 604-294-8588 Fax: 604-294-8580 2.0 Tender Documents 2.1

City of New Westminster 2013 Capital Pavement Program

Contract NWIT-13-23

SUPPLEMENTARY SPECIFICATIONS

NWIT-13-23 SSP Page SS 9

joints will be paid separately under item 4.16 b). Butt joint locations are not shown on the Contract drawings. The location of all butt joints shall be determined by the Contractor.

SS 12 Traffic Loop Detector Replacement (Item 4.21)

This item does not apply to loops for new or upgraded traffic signals nor replacement loops for signal upgrades. This item applies only to traffic signal loop detectors that need to be replaced as a result of asphalt milling, pavement patching, or excavation for utility installation where new signals or upgrades are not occurring. For loops as defined above: .1 The Contractor shall reference the loop type(s) and location(s) prior to

commencing work. The Contractor shall notify Traffic Operations Department 48 hours prior to disrupting loops. Install detector loops prior to final overlay. Also notify Traffic Operations Department immediately after repaving and reconnection of loops.

SS 13 Crushed Granular Sub-base and Granular Base( Item 4.6, 4.7 )

Delete Section 02223 - 3.5.3 Backfill Materials and replace with the following: .2 Trench Backfill Material to be Crushed Granular Sub-base Delete Section 02224 – 2.2 Specified Materials and replace with the following: .1 Subgrade Fill to be 100 mm Pit Run Gravel .2 Sub-base for road construction shall be Crushed Granular Sub-base. Replace Section 02226 – 2.9.1, Crushed Granular Sub-base with the following: .1 To be quarried rock, 100% fractured to 75 mm minus by mechanical

means with no rounded sands or aggregates to following gradations. (Note: Table on Page 02226-6 unchanged)

Replace Section 02226 – 2.10.1, Granular Base, with the following: .1 To be quarried rock, 100% fractured to 19 mm minus by mechanical

means with no rounded sands or aggregates to following gradations. (Note: Table on Page 02226-7 unchanged)

Page 60: CITY OF NEW WESTMINSTER · Wally Carter P.Eng Address: WEB Engineering Ltd. 4173 Dawson Street, Burnaby, B.C. V5C 4B3 Phone: 604-294-8588 Fax: 604-294-8580 2.0 Tender Documents 2.1

City of New Westminster 2013 Capital Pavement Program

Contract NWIT-13-23

SUPPLEMENTARY SPECIFICATIONS

NWIT-13-23 SSP Page SS 10

SS 14 Permanent Pavement Markings ( Item 4.24 )

All permanent pavement markings to be thermoplastic markings. Lane lines on new pavement to be extruded thermoplastic. Delete Section 02580 – 1.2 , Scope, and replace with the following: .1 Survey referencing all existing traffic control / pavement markings prior

to commencing work, survey layout and installation of new markings with paint or thermoplastic material as directed by Contract Administrator. Markings may include crosswalks, symbols, lettering, stop bars, lane and edge lines, or related markings.

Delete Section 02580 – 1.5.2 and .3, Measurement and Payment, and replace with the following: .2 Payment for permanent pavement markings will be made at the

applicable unit rate per material classification listed in the Schedule of Quantities and Prices. Measurement of lines will be by lineal meter between intersections, stop bars, or curbs. Dashed, skip, or broken lines will be measured as a continuous line without considering breaks. For cross hatching for painted medians, the entire median area will be measured in square meters. Zebra Cross Walks will be measured from pavement edge to pavement edge perpendicular to direction of vehicle traffic.

.3 Payment for permanent pavement markings includes:

.1 Survey referencing existing pavement markings prior to conducting work

.2 Survey layout of replacement permanent pavement markings

.3 Installation of temporary pavement makings until permanent markings are installed.

.4 Removal of Temporary pavement markings and devices after permanent markings are in place.

.5 Construction of permanent pavement markings with paint or thermoplastic material as directed by Contract Administrator

.6 All traffic control, scheduling and co-ordination to complete the temporary and permanent pavement markings.

Page 61: CITY OF NEW WESTMINSTER · Wally Carter P.Eng Address: WEB Engineering Ltd. 4173 Dawson Street, Burnaby, B.C. V5C 4B3 Phone: 604-294-8588 Fax: 604-294-8580 2.0 Tender Documents 2.1

City of New Westminster 2013 Capital Pavement Program

Contract NWIT-13-23

SUPPLEMENTARY SPECIFICATIONS

NWIT-13-23 SSP Page SS 11

SS 15 Fibre Optic Cable (Item 4.44)

TeraSpan Networks Inc. has a private fibre optics network that could be impacted by works under this contract. Where the cable is encountered during construction, steps shall be taken to have the cable relocated to a new conduit. This work must be carefully coordinated by the Contractor with TeraSpan. The Owner is not responsible for any delays resulting from this work. The Contractor shall: .1 Contact Tera Span at 604-255-8711 and arrange for work to commence .2 supply and install conduit .3 install junction boxes provided by TeraSpan Networks Inc. Measurement for payment of Junction Boxes as each installed. Measurement for payment of supply and install conduit by lineal meter. All cutting of cable, splicing and installation of cable in conduits by TeraSpan Networks Inc.

SS 16 Traffic Management Plan

The Contractor shall provide a traffic management plan including proposed traffic diversions, location of flaggers and signage. The plan must be approved by the Owner. Electronic Changeable Message Boards will be required for busy arterial/collector roads. For the Royal Avenue Project, Electronic Changeable Message Boards must be placed in position a minimum of two weeks before starting work to advise motorists of the upcoming works. A minimum of 8 Electronic Changeable Message Boards will be required. The Owner will issue a Highway Use permit permitting parking outside of construction hours. There is no separate payment for providing a traffic management plan.

Page 62: CITY OF NEW WESTMINSTER · Wally Carter P.Eng Address: WEB Engineering Ltd. 4173 Dawson Street, Burnaby, B.C. V5C 4B3 Phone: 604-294-8588 Fax: 604-294-8580 2.0 Tender Documents 2.1

City of New Westminster 2013 Capital Pavement Program

Contract NWIT-13-23

SUPPLEMENTARY SPECIFICATIONS

NWIT-13-23 SSP Page SS 12

SS 17 Pavement Patching (Item 4.17)

1.0 General .1 Definition

Section SS 17 refers to those patching of existing pavement requiring removal of full depth of existing asphalt concrete and repaving with new hot-mix asphalt Concrete Paving (Section 02512) where the following conditions are met:

a) the width of the patch is less than 2.0 meters, AND b) the total area of the patch is less than 500.0 square meters. Repairs to granular base and / or subbase may also be required. All other repairs will be paid at applicable unit rates for asphalt milling and hot mix asphalt concrete paving.

.2 Measurement and Payment .1 Pavement Patching will be paid for on the basis of square meters per

re-installed asphalt depth and size range classification in the Schedule of Quantities and Prices.

.2 Base or subgrade repairs will be measured separately as excavation

and granular materials as appropriate.

2.0 Execution .1 Where possible, Pavement Patching to be completed after surface milling. .2 Contractor to provide materials and traffic control for layout of sections to

be patched as identified by Contract Administrator. .3 Minimum thickness of asphalt patch to be 75 mm. A thicker patch may be

required by the Contract Administrator.

Page 63: CITY OF NEW WESTMINSTER · Wally Carter P.Eng Address: WEB Engineering Ltd. 4173 Dawson Street, Burnaby, B.C. V5C 4B3 Phone: 604-294-8588 Fax: 604-294-8580 2.0 Tender Documents 2.1

City of New Westminster 2013 Capital Pavement Program

Contract NWIT-13-23

SUPPLEMENTARY SPECIFICATIONS

NWIT-13-23 SSP Page SS 13

SS 18 Test Holes along existing Metro Vancouver Mains (Provisional) (Item 4.45) This item applies only to works occurring over and/or near existing Metro Vancouver Water/Sewer Mains. Test holes will be required to confirm the location of the existing Metro Vancouver Water/Sewer Mains. Payment for this item shall be measured for each test hole completed. Payment shall include saw cutting pavement or concrete, excavation with a Hydro-Vac truck, disposal of surplus excavated materials, backfill with approved bedding material, backfill with approved imported granular backfill material, all traffic control, recording the location of the existing main, co-ordinating works with Metro Vancouver personal, all temporary and/or permanent surface restoration and all other works and materials necessary to complete the installation of the test hole.

SS 19 Warm Mix Asphalt (WMA) (Item 4.10) Warm Mix Asphalt (WMA) is required for all projects in this contract. Maximum 10% RAP permitted in WMA mixes.

Page 64: CITY OF NEW WESTMINSTER · Wally Carter P.Eng Address: WEB Engineering Ltd. 4173 Dawson Street, Burnaby, B.C. V5C 4B3 Phone: 604-294-8588 Fax: 604-294-8580 2.0 Tender Documents 2.1

City of New Westminster 2013 Capital Pavement Program

Contract NWIT-13-23

Appendix A – Work Hour Restrictions

NWIT-13-23 SSP

ID# Street / Intersection

Location Work Hours Allowed

208 8th Avenue (Provisional) : 6th Street to McBride Blvd 9:00 a.m. to 3:00 p.m. 222 6th Avenue : 6th Street to 5th Street 7:00 a.m. to 5:00 p.m. 229 Royal Avenue : 4th Street to Dufferin Street 7:00 a.m. to 3:00 p.m. for East Bound

Lanes 9:00 a.m. to 3:00 p.m. for West Bound Lanes

229 Royal Avenue : Dufferin Street to Pattullo Bridge On Ramp

During scheduled closure of Pattullo Bridge by Translink

232 6th Street : 8th Avenue to 10th Avenue 7:00 a.m. to 5:00 p.m.

* Hours or work subject to change based on site constraints and are to be approved by

the City Engineer.

Page 65: CITY OF NEW WESTMINSTER · Wally Carter P.Eng Address: WEB Engineering Ltd. 4173 Dawson Street, Burnaby, B.C. V5C 4B3 Phone: 604-294-8588 Fax: 604-294-8580 2.0 Tender Documents 2.1

City of New Westminster 2013 Capital Pavement Program

Contract NWIT-13-23

Appendix B – List of Projects

NWIT-13-23 SSP

COMPLETE LIST OF POSSIBLE PROJECTS (with preliminary pavement strategies) ID# Street/

Intersection

Location Preliminary Strategy Existing A/C

Depth 208 8th Avenue :

(Provisional) 6th Street to 4th Street 4th Street to Sta. 22+729 Sta. 22+729 to Colborne St. Colborne St. to McBride Blvd

Full Depth Mill asphalt and base gravels to depths ranging from 120mm to 150mm. Proof roll and over excavate failed areas. Install base gravels as required and repave with 70mm, 50mm asphalt lifts. Excavate road down 180mm. Proof roll and over excavate failed areas. Install 60mm thick base gravel layer and repave with 70mm, 50mm asphalt lifts. Full Depth Mill asphalt and base gravels to depths ranging from 120mm to 150mm. Proof roll and over excavate failed areas. Install base gravels as required and repave with 70mm, 50mm asphalt lifts. East Bound Lanes 

Curb  Lane  ‐  Full Depth Mill asphalt and base gravels to 120mm depth. Proof roll and over excavate failed areas. Repave with 70mm, 50mm asphalt lifts. 

Thru & Turn Lanes – Surface Mill asphalt to 50mm depth. Pavement Patching as required. Repave with 50mm asphalt lift. 

 West Bound Lanes 

Full Depth Mill asphalt and base gravels to 120mm depth. Proof roll and over excavate failed areas. Repave with 70mm, 50mm asphalt lifts.

110mm

to 150mm

75mm to

165mm

90mm to

150mm

80mm

190mm

80mm to

115mm

Page 66: CITY OF NEW WESTMINSTER · Wally Carter P.Eng Address: WEB Engineering Ltd. 4173 Dawson Street, Burnaby, B.C. V5C 4B3 Phone: 604-294-8588 Fax: 604-294-8580 2.0 Tender Documents 2.1

City of New Westminster 2013 Capital Pavement Program

Contract NWIT-13-23

Appendix B – List of Projects

NWIT-13-23 SSP

ID# Street/ Intersection

Location Preliminary Strategy Existing A/C

Depth 222 6th Avenue : 6th Street to Sta. 12+520

Sta. 12+520 to 5th Street

Excavate road down 725mm. Rebuild road with 450mm thick sub-base gravel layer and 150mm thick base gravel layer. Repave with 75mm, 50mm asphalt lifts. Full Depth Mill asphalt and road gravels to 115mm depth. Proof roll subgrade and over excavate as required. Repave with 65mm, 50mm asphalt lifts.

N/A

N/A

229 Royal Ave. : 4th St. to Sta. 11+70 (EB Lanes) 4th St. to Sta. 12+55 (WB Lanes) Sta. 11+70 to Sta. 15+30 (EB Lanes) Sta. 12+55 to Sta. 14+80 (WB Lanes) Sta. 15+30 to Pattullo Bridge On Ramp (EB Lanes) Sta. 14+80 to Dufferin St (WB Lanes)

Thru & Turn Lanes: Excavate road down 350mm. Rebuild road with 200mm thick base gravel layer. Repave with 100mm, 50mm asphalt lifts. Parking Lanes: Full Depth Mill asphalt and road gravels to 100mm depth. Proof roll subgrade and over excavate as required. Repave with 50mm, 50mm asphalt lifts.  Thru & Turn Lanes: Excavate road down 750mm. Rebuild road with 450mm thick sub-base gravel layer and 150mm thick base gravel layer. Repave with 100mm, 50mm asphalt lifts  Parking Lanes: Full Depth Mill asphalt and road gravels to 100mm depth. Proof roll subgrade and over excavate as required. Repave with 50mm, 50mm asphalt lifts.  Full Depth Mill asphalt and road gravels to 120mm depth. Proof roll subgrade and over excavate as required. Repave with 70mm, 50mm asphalt lifts.

60mm

to 90mm

60mm

90mm to

130mm

N/A

80mm to

110mm

Page 67: CITY OF NEW WESTMINSTER · Wally Carter P.Eng Address: WEB Engineering Ltd. 4173 Dawson Street, Burnaby, B.C. V5C 4B3 Phone: 604-294-8588 Fax: 604-294-8580 2.0 Tender Documents 2.1

City of New Westminster 2013 Capital Pavement Program

Contract NWIT-13-23

Appendix B – List of Projects

NWIT-13-23 SSP

ID# Street/ Intersection

Location Preliminary Strategy Existing A/C

Depth 232 6th Street : 10th Avenue to Sta. 1+140.6

Sta. 1+140.6 to Sta. 1+449.8 Sta 1+449.8 to 8th Avenue

Excavate road down 600mm. Rebuild road with 300mm thick sub-base gravel layer and 150mm thick base gravel layer. Repave with 100mm, 50mm asphalt lifts. Thru Lanes: Excavate road down 600mm. Rebuild road with 325mm thick sub-base gravel layer and 150mm thick base gravel layer. Repave with 75mm, 50mm asphalt lifts. Parking Lanes: Full Depth Mill asphalt and road gravels to 125mm depth. Proof roll subgrade and over excavate as required. Repave with 75mm, 50mm asphalt lifts. Excavate road down 600mm. Rebuild road with 300mm thick sub-base gravel layer and 150mm thick base gravel layer. Repave with 100mm, 50mm asphalt lifts.

65mm

65mm to

150mm

110mm

150mm

Page 68: CITY OF NEW WESTMINSTER · Wally Carter P.Eng Address: WEB Engineering Ltd. 4173 Dawson Street, Burnaby, B.C. V5C 4B3 Phone: 604-294-8588 Fax: 604-294-8580 2.0 Tender Documents 2.1

City of New Westminster 2013 Capital Pavement Program

Contract NWIT-13-23

Appendix C – Metro Testing Core Reports

NWIT-13-23 SSP

Page 69: CITY OF NEW WESTMINSTER · Wally Carter P.Eng Address: WEB Engineering Ltd. 4173 Dawson Street, Burnaby, B.C. V5C 4B3 Phone: 604-294-8588 Fax: 604-294-8580 2.0 Tender Documents 2.1
Page 70: CITY OF NEW WESTMINSTER · Wally Carter P.Eng Address: WEB Engineering Ltd. 4173 Dawson Street, Burnaby, B.C. V5C 4B3 Phone: 604-294-8588 Fax: 604-294-8580 2.0 Tender Documents 2.1
Page 71: CITY OF NEW WESTMINSTER · Wally Carter P.Eng Address: WEB Engineering Ltd. 4173 Dawson Street, Burnaby, B.C. V5C 4B3 Phone: 604-294-8588 Fax: 604-294-8580 2.0 Tender Documents 2.1
Page 72: CITY OF NEW WESTMINSTER · Wally Carter P.Eng Address: WEB Engineering Ltd. 4173 Dawson Street, Burnaby, B.C. V5C 4B3 Phone: 604-294-8588 Fax: 604-294-8580 2.0 Tender Documents 2.1
Page 73: CITY OF NEW WESTMINSTER · Wally Carter P.Eng Address: WEB Engineering Ltd. 4173 Dawson Street, Burnaby, B.C. V5C 4B3 Phone: 604-294-8588 Fax: 604-294-8580 2.0 Tender Documents 2.1
Page 74: CITY OF NEW WESTMINSTER · Wally Carter P.Eng Address: WEB Engineering Ltd. 4173 Dawson Street, Burnaby, B.C. V5C 4B3 Phone: 604-294-8588 Fax: 604-294-8580 2.0 Tender Documents 2.1
Page 75: CITY OF NEW WESTMINSTER · Wally Carter P.Eng Address: WEB Engineering Ltd. 4173 Dawson Street, Burnaby, B.C. V5C 4B3 Phone: 604-294-8588 Fax: 604-294-8580 2.0 Tender Documents 2.1
Page 76: CITY OF NEW WESTMINSTER · Wally Carter P.Eng Address: WEB Engineering Ltd. 4173 Dawson Street, Burnaby, B.C. V5C 4B3 Phone: 604-294-8588 Fax: 604-294-8580 2.0 Tender Documents 2.1
Page 77: CITY OF NEW WESTMINSTER · Wally Carter P.Eng Address: WEB Engineering Ltd. 4173 Dawson Street, Burnaby, B.C. V5C 4B3 Phone: 604-294-8588 Fax: 604-294-8580 2.0 Tender Documents 2.1
Page 78: CITY OF NEW WESTMINSTER · Wally Carter P.Eng Address: WEB Engineering Ltd. 4173 Dawson Street, Burnaby, B.C. V5C 4B3 Phone: 604-294-8588 Fax: 604-294-8580 2.0 Tender Documents 2.1
Page 79: CITY OF NEW WESTMINSTER · Wally Carter P.Eng Address: WEB Engineering Ltd. 4173 Dawson Street, Burnaby, B.C. V5C 4B3 Phone: 604-294-8588 Fax: 604-294-8580 2.0 Tender Documents 2.1
Page 80: CITY OF NEW WESTMINSTER · Wally Carter P.Eng Address: WEB Engineering Ltd. 4173 Dawson Street, Burnaby, B.C. V5C 4B3 Phone: 604-294-8588 Fax: 604-294-8580 2.0 Tender Documents 2.1
Page 81: CITY OF NEW WESTMINSTER · Wally Carter P.Eng Address: WEB Engineering Ltd. 4173 Dawson Street, Burnaby, B.C. V5C 4B3 Phone: 604-294-8588 Fax: 604-294-8580 2.0 Tender Documents 2.1
Page 82: CITY OF NEW WESTMINSTER · Wally Carter P.Eng Address: WEB Engineering Ltd. 4173 Dawson Street, Burnaby, B.C. V5C 4B3 Phone: 604-294-8588 Fax: 604-294-8580 2.0 Tender Documents 2.1
Page 83: CITY OF NEW WESTMINSTER · Wally Carter P.Eng Address: WEB Engineering Ltd. 4173 Dawson Street, Burnaby, B.C. V5C 4B3 Phone: 604-294-8588 Fax: 604-294-8580 2.0 Tender Documents 2.1
Page 84: CITY OF NEW WESTMINSTER · Wally Carter P.Eng Address: WEB Engineering Ltd. 4173 Dawson Street, Burnaby, B.C. V5C 4B3 Phone: 604-294-8588 Fax: 604-294-8580 2.0 Tender Documents 2.1
Page 85: CITY OF NEW WESTMINSTER · Wally Carter P.Eng Address: WEB Engineering Ltd. 4173 Dawson Street, Burnaby, B.C. V5C 4B3 Phone: 604-294-8588 Fax: 604-294-8580 2.0 Tender Documents 2.1
Page 86: CITY OF NEW WESTMINSTER · Wally Carter P.Eng Address: WEB Engineering Ltd. 4173 Dawson Street, Burnaby, B.C. V5C 4B3 Phone: 604-294-8588 Fax: 604-294-8580 2.0 Tender Documents 2.1
Page 87: CITY OF NEW WESTMINSTER · Wally Carter P.Eng Address: WEB Engineering Ltd. 4173 Dawson Street, Burnaby, B.C. V5C 4B3 Phone: 604-294-8588 Fax: 604-294-8580 2.0 Tender Documents 2.1
Page 88: CITY OF NEW WESTMINSTER · Wally Carter P.Eng Address: WEB Engineering Ltd. 4173 Dawson Street, Burnaby, B.C. V5C 4B3 Phone: 604-294-8588 Fax: 604-294-8580 2.0 Tender Documents 2.1
Page 89: CITY OF NEW WESTMINSTER · Wally Carter P.Eng Address: WEB Engineering Ltd. 4173 Dawson Street, Burnaby, B.C. V5C 4B3 Phone: 604-294-8588 Fax: 604-294-8580 2.0 Tender Documents 2.1
Page 90: CITY OF NEW WESTMINSTER · Wally Carter P.Eng Address: WEB Engineering Ltd. 4173 Dawson Street, Burnaby, B.C. V5C 4B3 Phone: 604-294-8588 Fax: 604-294-8580 2.0 Tender Documents 2.1