The Budget Process to date:
Departments have entered their requests
Finance developed payroll budget
Revenue projections calculated and entered
Funds have been balanced
No unassigned fund balance (unrestricted reserves) used to balance General Fund
Budget Advisory Committee reviewed Budget with Department Heads
FY 2021 PROPOSED BUDGET
2
FY 2021 PROPOSED BUDGET
Two Budget Books:
Three Ring Book-”Detail” on all accounts by Fund:
Table of Contents
Revenues
Expenditures
Justification of Expenditures
Personnel Schedules
Table of Contents provides good detail if you are looking for a particular Fund and/or Department.
3
FY 2021 PROPOSED BUDGET
Two Budget Books:
Executive Summary-”Summarizing” of Detail
Budget book:
4
Executive Summary - Budget Message 4 to 15
Budget Process, Objectives, Guidelines etc 16 to 27
Total City Budget Numbers Combined 28 to 43
Personnel 44 to 50
Property Values, Millage Rates and Revenues 51 to 53
Debt Summary 54 to 55
General Fund Summary 56 to 69
Community Redevelopment Agency Fund Summary 70 to 76
Water-Sewer Fund Summary 77 to 86
Sanitation Fund Summary 87 to 93
Stormwater Fund Summary 94 to 100
Capital Improvement Program 101 to 126
PagesCategory
FY 2021 PROPOSED BUDGET
Two Budget Books:
Executive Summary-”Capital Improvement
Program” (CIP) provides detail on the following:
Five Year CIP Program and Capital Outlay:
5
Five Year CIP Summary 106 to 107
Five Year CIP by Fund:
Local Option Gas Tax 108
Police Impact 109
Fire Impact 110
Library Impact 111
Recreation Impact 112
General Government Impact 113
Transportation Impact 114
Capital Project Fund 115
One Cent Local Option Sales Tax Fund "Penny" 116
Sewer Impact 117
Water Impact 118
Stormwater Fund 119
Water -Sewer Fund 120 to 121
All Capital Requests 122 to 124
Capital Requests not in Budget on standby 125 to 126
Category Page or Pages
FY 2021 PROPOSED BUDGET
Total City Budget and Five Largest Funds:
6
FY 2021 Percent of FY 2020 Budget
Proposed FY 2021 Approved Increase Percent
8/13/2020 Budget Budget (Decrease) Changes
Total City 62,877,711$ 64,011,698$ (1,133,987)$ -1.77%
Five Largest Funds
General Fund 26,663,072$ 42.40% 26,014,325$ 648,747$ 2.49%
Water-Sewer Fund 18,861,736$ 30.00% 20,143,215$ (1,281,479)$ -6.36%
Sanitation Fund 6,246,927$ 9.94% 5,417,953$ 828,974$ 15.30%
Stormwater Fund 1,762,992$ 2.80% 3,631,088$ (1,868,096)$ -51.45%
Penny Fund 3,277,232$ 5.21% 2,441,977$ 835,255$ 34.20%
Total 56,811,959$ 90.35% 57,648,558$ (836,599)$
Total City Budget
FY 2021 PROPOSED BUDGET-ASSUMPTIONS
Pay Increases for all employees “funded” at 3%
Health Insurance Premium - 2% decrease
Dental Insurance Premium - 15.8% decrease
Pensions (Police and Fire) funded at actuarial required contribution; General Pension at 8.7% (no change).
Workers Compensation – Budgeted 10% increase, rate still to be determined.
Property Insurance – Budgeted 10% increase, rate still to be determined.
7
FY 2021 PROPOSED BUDGET-GENERAL FUND
8
FY 2021 FY 2020
Proposed Approved Percent Main Reason for
Budget Budget Increase Increase Increase
Total Budget 26,663,072$ 26,014,325$ 648,747$ 2.49% Pay Increase, Internal Auditor, Paramedics-Grant Expired
General Fund Budget
FY 2021 PROPOSED BUDGET-GENERAL FUND
REVENUES BY TYPE
9
Taxes,
14,540,060 , 54%
Permits & Fees,
2,377,841 , 9%
Intergovernmental, 2,877,790 , 11%
Charges for Services,
3,168,510 , 12%
Fines and Forfeitures,
147,611 , 1%
Interest,
140,456 , 0%
Miscellaneous,
820,496 , 3%
Transfers, Restricted Reserve, 2,590,308 ,
10%
General Fund Revenues by Type
FY 2021 PROPOSED BUDGET-GENERAL FUND
EXPENDITURES BY FUNCTION
10
General Government,
4,689,323 , 18%
Public Safety,
15,218,298 , 57%
Physical Environment,
1,439,837 , 5%
Transportation, 1,131,388 , 4%
Economic
Environment, 129,529 , 1%
Culture and Recreation,
4,054,697 , 15%
General Fund Expenditures by Function
FY 2021 PROPOSED BUDGET-GENERAL FUND
EXPENDITURES BY TYPE
11
Personnel
Services, 19,837,227 , 74%
Operating Services,
6,372,274 , 24%
Capital Outlay, 307,369 , 1%
Grants and Aids, 25,000 , 0%
Transfers/Other, 121,202 , 1%
General Fund Expenditures by Type
FY 2021 PROPOSED BUDGET – GENERAL FUND
General Fund Revenue Projections :
Property Taxes:
6.16% increase in taxable values
Millage rate maintained at 5.37
Total Property Tax revenues $10,232,123, 38% of
General Fund
12
FY 2021 PROPOSED BUDGET – GENERAL FUND
General Fund Revenue Projections (Continued):
Electric Utility Tax and Franchise Fee projected 2%
increase
EMS, Fire and School Officer Fees based on contracts
with Pinellas County and School Board
Sales Taxes, Projected 7.5% decrease
13
FY 2021 PROPOSED BUDGET-PROPERTY TAXES
14
1,938,896,972
1,298,345,335
2,034,725,396
1,000,000,000
1,200,000,000
1,400,000,000
1,600,000,000
1,800,000,000
2,000,000,000
2,200,000,000
2007 2008 2009 2010 2011 2012 2013 2014 2015 2016 2017 2018 2019 2020 2021
Taxable Values
Fiscal Year
4.3089
5.4500 5.4500 5.42005.3700 5.3700
4.0000
4.2500
4.5000
4.7500
5.0000
5.2500
5.5000
5.7500
6.0000
2007 2008 2009 2010 2011 2012 2013 2014 2015 2016 2017 2018 2019 2020 2021
Millage Rate
No millage increases since
2011 just decreases to 5.37
640 million loss in
Taxable Value
2008-2013
Revenue
Decrease
$1.5 mill
2008-2013
$8,123,557
$6,700,179
$10,232,123
$-
$2,000,000
$4,000,000
$6,000,000
$8,000,000
$10,000,000
$12,000,000
General Fund - Ad Valorem Revenue
Revenue
MILLAGE RATE COMPARISON FULL SERVICE
CITY’S POPULATION GREATER THAN 20,000
15
6.77
5.155
5.2139
5.5862
5.45
6.755
5.955
5.62
5.49
5.37
0 1 2 3 4 5 6 7 8
St. Petersburg
Clearwater
Largo
Pinellas Park
Tarpon Springs
Millage Rates ProposedPinellas County-Full Service City's Population Greater Than 20,000
Municipal Rate 2020 Municipal Rate 2014
CIP
16
FY 2021 PROPOSED BUDGET - CIP
17
CAPITAL IMPROVEMENTS PROGRAM (CIP)
PROJECT SUMMARY - by FUNCTION
FISCAL YEAR 2021 PROJECTS - $7,059,558
Public Safety, $1,034,558 , 15%
Physical Environment,
$4,875,000 , 69%
Transportation, $1,150,000 , 16%
$4.6 million is
Water-Sewer
Fund
FY 2021 PROPOSED BUDGET - CIP
Executive Summary Budget Book:
CIP Budget pages 101-126
Pages 106-107 has 5 Year CIP Summary $7.1 million.
Pages 108-121 has 5 Year Projections per Fund
Pages 122-124 has all Capital, including CIP and Capital Outlay, $9.9 million.
Pages 125-126 has all Capital not in Budget. To be prioritized if funding becomes available.
18
FY 2021 PROPOSED BUDGET - CIP
CIP for FY 2021 Totals $7.1 million
19
Budgeted
Water-Sewer Fund
Water Pipe Valve replacement 500,000$
Manhole and Sewer Lines 250,000$
Force Main Improvements 250,000$
Penny Fund
Roadway Reconfiguration Walmart/Huey-Grant Funded 750,000$
Police Vehicles 400,000$
Body Cameras 212,958$
Brick Street & Road Reconstruction 150,000$
Capital Project Fund
Annual Street Paving and Sidewalks 250,000$
Cost of above CIP Projects for FY 2021 2,762,958$
Major CIP Projects in FY 2021 Budget
CRA
20
FY 2021 PROPOSED BUDGET: CRA
Community Redevelopment Agency (CRA)
Created under Florida Statutes with City and County
Established 2001
Expires after 30 Years
Area Approx. - Alt 19 from Mere’s to Sponge Docks and 1 to 2 blocks east and west of Alt 19
Base Year 2000 Taxable Value 41,037,900
Taxable values over base year for City and County go into CRA, called Tax Increment Financing (TIF)
21
FY 2021 PROPOSED BUDGET: CRA
22
FY 2021 CRA Proposed Budget $558,900
City TIF,
$279,609 , 50%
County TIF, $279,291 , 50%
CRA Revenue FY 2021
FY 2021 PROPOSED BUDGET: CRA
23
Personnel Services,
$107,029 , 19%
Operating Expenditures, $71,566 , 13%
Grants, $64,768 , 12%
Loan Repayment, $100,000 , 18%
Reserve for
Capital, $215,537 , 38%
CRA Expenditures by Type FY 2021
Enterprise Funds
24
FY 2021 PROPOSED BUDGET: WATER-SEWER
The Water-Sewer Fund is the second largest
Fund in the City with a budget of $18.8 million
25
FY 2021 FY 2020
Proposed Approved Percent Main Reason for
Budget Budget Decrease Decrease Decrease
Total Budget 18,861,736$ 20,143,215$ (1,281,479)$ -6.36% Capital Requirements
Water-Sewer Fund Budget
FY 2020 had two large projects over $1 million each, one for new water wells
and the other for Seabreeze Drive Sewer
FY 2021 PROPOSED BUDGET: WATER-SEWER
REVENUES BY TYPE
26
Charges for Services,
17,560,330 , 93%
Interest, 100,000
, 1%
Non-Revenue-
Reserves, 1,201,406 , 6%
Water-Sewer Revenues by Type
Water and Sewer
Fees
FY 2021 PROPOSED BUDGET: WATER-SEWER
EXPENSES BY TYPE
27
Personnel
Services, 5,860,964 , 31%
Operating
Services, 4,815,932 , 26%
Capital Outlay,
4,718,765 , 25%
Debt Service,
2,045,563 , 11%
Transfers,
1,404,826 , 7%Other Uses, 15,686 , 0%
Water-Sewer Expenses by Type
FY 2021 PROPOSED BUDGET: SANITATION
The Sanitation Fund is the third largest Fund in
the City with a budget of $6.2 million.
28
FY 2021 FY 2020
Proposed Approved Percent Main Reason for
Budget Budget Increase Increase Increase
Total Budget 6,246,927$ 5,417,953$ 828,974$ 15.30% Contract Increase/Capital*
Sanitation Fund Budget
*New building for scale house and relocating scale with Mere’s Blvd connection
FY 2021 PROPOSED BUDGET: SANITATION
29
Refuse and
Recycling Fees
Charges for Services,
$5,929,187 , 95%
Interest, $21,000 , 0%
Non-Revenue-Reserves, $296,740 , 5%
Sanitation Fund Revenues by Type
FY 2021 PROPOSED BUDGET: SANITATION
30
Personnel Services,
$565,240 , 9%
Operating Services, $4,919,352 , 79%
Capital Outlay, $280,000 , 4%
Transfers, $474,335 , 8%
Other Uses, $8,000 , 0%
Sanitation Fund Expenses by Type
Majority is to
Contractor
FY 2021 PROPOSED BUDGET: STORMWATER
The Stormwater Fund is the fifth largest Fund in
the City with a budget of $1.8 million.
Sales
Stormwater Fees $1,741,828
Majority of expenses are for Personnel/Operating
31
FY 2021 PROPOSED BUDGET: GOLF COURSE
The Golf Course Fund has a budget of $1.4
million.
Golf Course fees pay for personnel and
operating costs of the golf course.
32
FY 2021 PROPOSED BUDGET: MARINA
The Marina Fund has a budget of $112,717.
Marina fees a majority of which are slip rentals
pay for personnel and operating costs of the
marina.
33
FY 2021 BUDGET PROCESS TIMETABLE
August 13, 2020 First Budget Workshop with BOC
August 18, 2020 Second Budget Workshop “BOC” if
necessary-tentative
August 24, 2020 Third Budget Workshop “BOC” if
necessary-tentative
August 24, 2020 TRIM notices mailed by Property
Appraiser
September 3, 2020 First Public Hearing on Tentative
Millage and Budget
September 15, 2020 Second and Final Public Hearing
October 1, 2020 First day of new Fiscal Year
34